DEVELOPMENT OF THE NETWORK DIAGRAM AND CRITICAL PATH Acknowledgement - A Practical Introduction to Management Science 4 th edition
BUILDING A HOUSE THE NETWORK DIAGRAM IS ABOUT CREATING RELATIONSHIPSBETWEEN ACTIVITIES
BUILDING A HOUSE RELATIONSHIPS ARE ALSO REFERRED TO AS DEPENDENCIES – THE MOST BASIC IS “FINISH TO START”
BUILDING A HOUSE THUS THE BASIC QUESTION IS WHICH ACTIVITIES MUST BE FINISHED BEFORE WHICH ACTIVITIES CAN START
BUILDING A HOUSE THE USE OF AN ARROW (SPECIFICALLY IN THE NOTATION USED IN THIS EXAMPLE) SHOWS THIS RELATIONSHIP Activity A Must Be Finished Before B Can Start A B
BUILDING A HOUSE THE USE OF AN ARROW (SPECIFICALLY IN THE NOTATION USED IN THIS EXAMPLE) SHOWS THIS RELATIONSHIP But Activity E, F and G Don’t Have to Wait for Each Other D E F G Frame HVAC Rough Electric H Sheet Rock
BUILDING A HOUSE THE USE OF AN ARROW (SPECIFICALLY IN THE NOTATION USED IN THIS EXAMPLE) SHOWS THIS RELATIONSHIP Note That E, F and G Don’t Have to Start and Finish At The Same Time D E F G Frame HVAC Rough Electric H Sheet Rock
BUILDING A HOUSE THE USE OF AN ARROW (SPECIFICALLY IN THE NOTATION USED IN THIS EXAMPLE) SHOWS THIS RELATIONSHIP TheY However Need to Be Finished Before H Can Start D E F G Frame HVAC Rough Electric H Sheet Rock
Task 1 Is to Create These Dependencies By Indicating the Predecessors For Each Activity
SUMMARY OF ACTIVITIES Time Immediate Required Predecessor Activity Description (in days) Activities A Excavate B Lay foundation C Rough plumbing D Frame E Finish exterior F Install HVAC G Rough electric H Sheet rock I Install cabinets J Paint K Final plumbing L Final electric M Install flooring
SUMMARY OF ACTIVITIES Time Immediate Required Predecessor Activity Description (in days) Activities A Excavate -- B Lay foundation A C Rough plumbing B D Frame B E Finish exterior D F Install HVAC D G Rough electric D H Sheet rock C, E, F, G I Install cabinets H J Paint H K Final plumbing I L Final electric J M Install flooring K, L
Task 2 TEST THE LOGIC BY CONSTRUCTING THE NETWORK DIAGRAM
An Activity-On-Node (AON) Network Install Cabinets A B C D E F G H I J K L M Excavate Lay Foundation Rough Plumbing Frame Finish Exterior HVAC Rough Electric Sheet Rock Paint Final Plumbing Final Electric Install Flooring
SUMMARY OF ACTIVITIES Time Immediate Required Predecessor Activity Description (in days) Activities A Excavate 3 -- B Lay foundation 4 A C Rough plumbing 3 B D Frame 10 B E Finish exterior 8 D F Install HVAC 4 D G Rough electric 6 D H Sheet rock 8 C, E, F, G I Install cabinets 5 H J Paint 5 H K Final plumbing 4 I L Final electric 2 J M Install flooring 4 K, L
Information Recorded for Each Node t i = DURATION required to perform activity i EST i = earliest possible start for activity i EFT i = earliest possible finish for activity i LST i = latest possible start for activity i LFT i = latest possible finish for activity i i t i EST i EFT i LST i LFT i
Results of the Forward Pass 25 33 8 33 38 5 0 3 3 7 17 10 3 7 4 Note: EST H =MAX(EFT C ,EFT E ,EFT F ,EFT G )=25 H E 17 25 8 J 33 38 5 I K 38 42 4 L 38 40 2 M 42 46 4 A F 17 21 4 G 17 23 6 D C 7 10 3 B
Results of the Backward Pass Note: LFT H =MIN(LST I ,LST J )=33 LFT D =MIN(LST E ,LST F ,LST G )=17 LFT B =MIN(LST C ,LST D )=7 25 33 8 0 3 3 7 17 10 3 7 4 0 3 3 7 22 25 17 7 17 25 21 25 25 19 25 33 33 38 35 40 42 42 40 42 46 38 3 H E 17 25 8 J 33 38 5 I 33 38 5 K 38 42 4 L 38 40 2 M 42 46 4 A F 17 21 4 G 17 23 6 D C 7 10 3 B