Dispelling the mystery around resource planning revc
1. Ken Delcol PMP, PEng
Project World Toronto 2012
Project World 2012 1
2. Attendees will leave with an alternative
approach for implementing resource planning
in their organization.
◦ Identify key areas that need to be addressed when
developing a resource plan
◦ Identify pitfalls to be avoided when developing a
resource planning process
Project World 2012 2
3. Learning Objectives
Introduction to Psion
Why resource planning is important
The Problem
The Journey
◦ First Pass
◦ Second Pass
A new Way
◦ How do we plan?
◦ Setting up to do resource planning
Recommendations
Take Away
Project World 2012 3
4. Omnii WORKABOUT PRO 3 IKÔN
Our most modular Flexible, adaptable Rugged PDA, ideal for
rugged product with Mobile Computer for a mobile delivery, field
dozens of flexible
variety of applications service and more
options
NEO 7535 7530
IP65, rugged mobile Ultra-rugged to operate
For light industrial, computer suited to in freezers and other
retail data collection the toughest extreme environments
environments
Project World 2012 4
5. 8515 8525 8530
Small form-factor
IP66 and hardened against extreme
computer for use where
temperatures, for use onboard fork trucks
space is an issue
any place from warehouses to ports and
beyond
8580 8590
Full PC Power running WindowsTM XP, with
the rugged reliability and flexibility of a
VMT
Project World 2012 5
6. Psion is a leading global manufacturer of Rugged Handheld and Vehicle-
Mounted Computers, with a rich history of mobile innovation
SUPPLY CHAIN & BUSINESS &
LOGISTICS ENTERPRISE MOBILITY
Including… Including…
Air, Ports & Rail Field Service &
Yards Asset Management
1980 Cold Chain 199 Courier & Postal
8
Warehouses & Retail & Direct Store
Distribution Delivery
Centers
…And Many More! …And Many More!
Project World 2012 6
7. Profits and growth are driven by new products
◦ The key is knowing when to commit to new projects
Standing Assumption
Psion is people constrained, not expense/capital
constrained
◦ Resource Planning Requires
Identification of resource supply and demand issues well
in advance
Clear, consistent, reliable
Cross-functional process for allocation of resources to
projects
Single, reliable and well-understood
Project World 2012 7
8. Executives were not confident they could start a
new project because
◦ No consistency in resource planning approach
Executives constantly changing the way they view the world
Project, project types, product, portfolio, program, etc
Functional managers with their own personal view towards
resource planning
Fiscal planning rate and hours varied across departments
Inconsistent definition of what work needs to be planned vs
not planned
◦ Multitasking of resources across various projects with no
Visibility
Clarity on priorities
Project World 2012 8
9. 2007 and earlier
◦ Solution Characteristics
Excel
Functional orientation
Challenges
◦ No cross-functional coordination
Reinforced “functional silo’s”
No single fully integrated plan for a project
◦ Spreadsheet nightmare
Everyone else’s spreadsheet is wrong!
Project estimates ≠ Functional estimates
No concept of supply and demand
People are allocated based on availability
Updating nightmare
Done once a year
Does not support changing business needs
Time to run a what if scenario – 5 to 7 days
Painful to set up
10. IT to the rescue with MS Project Server
◦ Common resource database and project definition!!
◦ Initial introduction of supply and demand
Challenges
◦ Batch operation – cube build time
◦ Updates take a long time
Individual projects hold the information
◦ What if scenarios both for budgeting and resources
still required Excel
◦ Product stability issues
◦ People are allocated based on availability rather
than demand
Project World 2012 10
11. Psion was no further ahead based on the first
two attempts
◦ General feeling was we did not have the right tool!
A new tool will solve everything!!!!
Sound familiar??
◦ A third attempt was to be made …
◦ However a decision was made to view the problem
from a different perspective
Project World 2012 11
12. Split the solution to resource
planning into three areas
◦ Key Goal: simplicity in execution and
maintenance
Easy to solve Tool Selection
Touched on briefly in this presentation
Tool Configuration/Set Up
Tool and organization dependent
Topic of interest for this presentation
Most difficult to solve
How are you going to use the tool
People and process dependent
Tool Independent
Topic of interest for this presentation
12
Project World 2012
13. Three solution areas
◦ 1) Tool Selection
A common resource and project pool that is shared
across all projects with live data
No files, no separation, no batch manipulation of data!
Its all about the tool’s features
This is where everyone spends their time and money
◦ 2) Tool Configuration/Set Up
How the organization fundamentally structures work and
resources
A necessary evil of a tool
People want to minimize the time and the money spent here
This is for the IT gurus not for the real people doing work!
This attitude is what gets the organization into trouble.
Project World 2012 13
14. Three solution areas (Continued)
◦ 3) How are you going to use the tool
How the organization plans resources i.e. a common
lexicon, level of detail, and approach
The tool can help to support once the process is understood.
Nobody wants to spend time here since its about getting
agreements on how to do work!!
Project World 2012
14
15. Integrated Database Solution
◦ P6 v7.8 has the capability with real time results
Major Concern
◦ How do we use P6 without creating a monster!
Drive for simplicity1 and clarity of process and data
Psion does not have an army of planners!
◦ Psion company characteristics
Functional Managers like to be in control
Make things complex
Stress the uniqueness of their function over others
1 Einstein: “Everything should be made as simple as possible …
but no simpler.”
15
Project World 2012
16. Started with how you fundamentally organize
your projects when doing work and NOT how
you want to analyze them
◦ Structure is repeated over and over across other
systems
◦ Core to the business
Allows for easier maintenance
For Psion work is organized by the product and then the
projects
◦ How you analyze your projects will constantly evolve!
◦ Organizing structure in P6 is called the EPS node
Project World 2012 16
17. Overview of EPS Node New Product
Development
Projects
Resource-Constrained
(non-development)
Projects
High-level multi-year
portfolio / project view
Project World 2012 17
18. How do you want to analyze your projects?
◦ Set project characteristics at the project level
Project characteristics flow down to the resources and the tasks
Avoids specialized resource groups and task classifications
Slice and dice the projects for analysis
Highly configurable
◦ P6 Solution are Project Codes
Limited the number – total 9
Focused on the key ways the business is analyzed
Code headings include
Project Status
Product Type that the project is associated with
Project Type
Project Complexity
Business Line
Estimate Accuracy
Project Scope
Time Collection Enable Flag
Project World 2012 18
19. Resource Structure
◦ Goal: create a common structure for all functional
groups
◦ Roles
Starting with job titles and pay bands
Psion had 96 roles for 191 people
Reduced to 14 roles across Engineering, Operations and
Marketing
Five core roles of – Manger, Specialist, Functional Lead,
Management, Generic
Introduce generic planning role
Used for medium- and long- term planning
Project World 2012 19
20. Functional Grp ABC Functional Generic
Manager – FG.ABC
Functional-Role
Group Lead – FG.ABC Generic
Joe
Sue
Specialist– FG. ABC
Karen
Frank Resource
Bob
Specific
Deb
21. Resource Structure
◦ Goal: create a common structure for all functional
groups
Identify resource characteristics that are used to
analyze/group people independent of project and
functional group e.g. locations, company, etc
Highly configurable
◦ P6 Solution - Resource Codes
Used in place of roles
Reduces the number of roles by avoiding specialized groups
Allows for classifications to be introduced
Provides cross-functional group analysis
Project World 2012 21
22. Overview of Resource Role + Codes
Role
(Primary)
Resource Codes
Project World 2012 22
23. Provide standard views and reports to promote
consistency
◦ Overview
Overload and under-load reports
◦ Assignment
Functional
Person, Project
Project, Person
Project
Function, Person
◦ Key Message
Everybody uses the same views and reports for resource
allocations, over/under loading
PMO creates custom reports on as needed basis
Project World 2012 23
28. Calendars
◦ Global vs Project vs Resource
Provide a board suite of global calendars
Avoid project and resource specific calendars
Too much maintenance work
Time
◦ Need to understand the number of hours in a year,
week, month and its impact when calculating FTEs
Project Settings
◦ Agree on how progress is tracked when using
resources
Project World 2012 28
31. Goal
◦ Define resource demand at the appropriate levels of
detail through the life-cycle of a project
◦ Describe resources in the supply pool to enable
matching of supply to demand most effectively
Approach
◦ Develop a rolling wave planning philosophy for
resources - labour, expense and capital
◦ Foster collaborative planning – force the
discussions
Clear communication of demand/supply
requirements and status
Project World 2012 31
32. Planning Horizon
Today +3 mths +6 +9 +12 +15 +18 +21 > 24 mths
Projects
Active
Legend
Functional Generic
Function-Role Generic
+ Resource Specific
Resource Specific
Projects
Planned
Active Projects:
BudgetaryProjects: in progress
Planned Projects are
Projects:
Projects Short-term (0-3PDV Resource demand
are included in mths)
Projects are approved to proceed
Budgetary
budgetary expressed as Resource Specific
is not yet not yet
Projects
but have plans – started
approved to proceed
Resource demand estimated toResource demand
Longer-term (>3 mths)
Resourceis planned at Functional-Role Generic
Functional-Role Generic level,
demand estimated to
Functional Generic level Resourcethe Resource
and, selectively toselectively at
level, and, the
Specific level level
Specific
Project World 2012 32
33. Step 1: Project Managers …
Step 2: Functional Managers …
review and confirm resource
demand review and confirm resources
for Planning Horizon; planned for all Projects in
Planning Horizon;
identify supply issues in Planning
Horizon
November Planning Horizon
Week-1 Week-2 Week-3 Week-4 Dec Jan Feb
Step 3: PMO …
Step 4: PMO …
identifies Resource Management Step 5: PMO …
planning issues during Planning convenes meeting to
Horizon: resolve Resource transfer timesheet
Management planning actuals into planning
Generic resources not assigned; and scheduling tool
issues identified in
Specific resources over- Step 3.
assigned.
communicates these issues to PM’s
and FM’s
34. What about non-development project work?
◦ Solution
Level of Effort and/or Constrained project
Overhead
R&D – floating time lines
Sustaining – capped with designated specific resources
Few people are actually allocated to the projects
Anyone can charge to the project for unplanned work
How do you show long term demand??
◦ Generic Resource
What about unplanned work in a project?
◦ Activity to capture the hours between time reports
Adjust schedules once identified
Project World 2012 34
36. High-level Resource Demand vs. Supply view
Department shows planned
available capacity
Department shows planned
over-allocation of resources
36
Project World 2012
40. Need to take your time and think about
◦ How resources are planned and tracked
Independent of your tool
◦ How the organization is fundamentally organized
to do project work
Then look at how projects are analyzed
◦ How resources are structured
◦ How subtleties are going to be dealt with
Need a consistent and simple approach when dealing
with exceptions
◦ Selecting a tool that gives access to live data
NO batch operations
◦ Always keeping it simple
Project World 2012 40
41. Attendees will leave with an alternative
approach for implementing resource planning
in their organization.
◦ Identify key areas that need to be addressed when
developing a resource plan
◦ Identify pitfalls to be avoided when developing a
resource planning process
Project World 2012 41
42. This presentation has focused at dispelling
the misguided belief in a be-all-and-end-all
technical solution.
◦ Rather you were provided an alterative approach
that is based on:
Balancing human processes/behaviours vs. tool-based
capabilities, and
Built on a foundation of simplicity and clarity.
Project World 2012 42