SlideShare a Scribd company logo
1 of 69
ABB Power Transmission
The
Plug and Switch System
from
ABB
The new
generation !
PASS
ABB Power Transmission
The source of the name
AND SWITCH!
PLUG!PLUG!
ABB Power Transmission
ALL THE NECESSARY FUNCTIONS IN ONE MODULE
KEY FUNCTIONS SEALED TYPE
EASY INSTALLATION & FAST EXCHANGEABILITY
MAIN CONCEPTSPASS
Think different, think for
performance !
ABB Power Transmission
Introduction
The PASS Family
PASS M0 up to 170 kV
PASS M1 up to 300 kV
PASS M2 up to 550 kV
ABB Power Transmission
All bay functions in one module
Circuit breaker
Combined disconnector/
Earthing switch
Current measurement
Voltage measurement
Introduction
ABB Power Transmission
The PASS M0 ratings
Rated voltage kV 72.5 123 145 170
Rated frequency Hz 50/60
Rated current A 2500
Rated breaking current kA 40/31.5
Rated making current kA 100/80
Rated BIL kV 325 550 650 750
Temperature -30*°C / + 55 °C
* -25°C with pure SF6 for 750 kV BIL
Introduction
ABB Power Transmission
Where are your benefits from PASS M0?
Why PASS M0?
Price Performance
Layouts
Maintenance
Availability
Transport & Installation
Benefits
ABB Power Transmission
More bays on less space
Simple and innovative layouts
PASS M0 solution :
You can save 50 % of space in new PASS solution.
You can double your substation on the same AIS-footprint.
You can simplify your layouts keeping the same substation
functionality.
Why PASS M0?
Your challenges in substation engineering:
ABB Power Transmission
High substation availability through reliable
primary and secondary equipment
Planable maintenance and higher
transparency of installed equipment
Low operating costs
PASS M0 solution :
You decrease your unavailability compared to AIS by 90%.
Your maintenance efforts for PASS are only 40 % of AIS.
You switch to maintenance on demand.
Why PASS M0?
Your challenges in substation operation:
ABB Power Transmission
Short installation time
More bays in less space
Simple layouts
Highly competitive product
PASS M0 solution :
Your installation effort is only 20% of AIS.
You need only 1 compared to 14 days installation time for AIS.
You can double your substation on the same AIS-footprint.
Why PASS M0?
Your challenges as contractors:
ABB Power Transmission
Lowest initial investiment cost
Short installation time
PASS M0 solution :
Your initial costs for PASS and AIS substations are identical.
You reduce maintenance costs by 80%.
You reduce the total installation time for HV equipment to 1 day.
Why PASS M0?
Your challenges in substation purchasing:
ABB Power Transmission
Thank you !
for your interest in the
Plug and Switch System
from
ABB
ABB Power Transmission
Legend:
circuit breaker CB current transformer CT
voltage transformer VT line L
disconnector DS earthing switch ES
PASS M0 integrates several functions in one module:
SBB diagram
Conventional AIS PASS
BB L
DS/ES CB CT/VT
DS CB DS
CT VTES
LBB
Availability
ABB Power Transmission
PASS M0 single BusBar
ABB Power Transmission
All components are arranged in one enclosure:
CB Driver
Bushing
Circuit BreakerCombined current/
voltage sensor
Combined
Disconnector/
Earthing Switch
Availability
ABB Power Transmission
Circuit breaker
Higher availability through 10,000 times proven GIS chamber
Availability
ABB Power Transmission
L
Conventional AIS PASS
Legend:
circuit breaker CB current transformer CT
voltage transformer VT line L
disconnector DS earthing switch ES
BB 2
BB 1
DS/ES CB CT/VT
DS
CB DS
CT
VTES
L
DS
BB2
BB1
PASS M0 integrates several functions in one module:
DBB diagram
Availability
ABB Power Transmission
PASS M0 double BusBar
ABB Power Transmission
Simple and reliable operating mechanisms
CB Operating mechanism
(BLK222 or BLK82)
DS/ES Drive
Availability
ABB Power Transmission
Bushings
• silicon-fiberglass construction
• maintenance free
• self-cleaning surface
• better pollution and rain resistance
have higher availability through:
Availability
ABB Power Transmission
Conventional Current Transformer (ring type)
Availability
ABB Power Transmission
Combined I/U Sensor
• built-in PISA
• high accuracy and linearity
• local data processing
• optical output (no EMC
problems)
• no saturation
• no ferroresonance
• local data store for
disturbance data
Availability
ABB Power Transmission
• Oil free sensors:
no leakage / ageing problems
• insulating medium SF6 gas:
less solid insulation (ageing)
Further benefits:
• High accuracy
and linearity
• Large bandwidth
• No saturation
or ferroresonance
Sensors have higher availability through:
Rogowski coil
Capacitive ring
Availability
ABB Power Transmission
• Frequency 50Hz/60Hz
• Rated voltage range:
17.5kV/ 3 RMS…170kV/ 3 RMS
• Measurement accuracy:
• with SF6 density monitor installed:
– class 0.2% in range
80%…120% of rated voltage;
• without SF6 density monitor:
– class 1% in range
80%…120% of rated voltage.
• Frequency 50Hz/60Hz
• Rated current range:
100A....2500A
• Rated short circuit current:
40kA RMS at 50/60 Hz
(100kA/10ms, peak value).
• Measurement accuracy:
• with SF6 density monitor installed:
– class 0.2% in range
100A…2500A;
• without SF6 density monitor:
– class 1% in range 10A…2500A.
Voltage Current
Combined I/U Sensor
Availability
ABB Power Transmission
With PASS you decrease your unavailability compared
to AIS by 90%
minimum number of
components
all moving parts are
encapsulated
quick exchangeable
pole means
minimum down time
MTBF = 170 years
MTTR = 4 hours
proven GIS
contact system
one instead of
three motor drives
proven GIS
interrupting chamber
over 10000 chamber
into operation
mature drive
no oil
contained
SF6 or Air
instead of solid
insulation
CBDS/ES SwitchSYSTEM CP14/CT
Availability
ABB Power Transmission
C&P System architecture with combined I/U sensor
process bus process bus
Bay level:
Control, interlocking, line protection,
measurement and metering (option), event fault recording
Station level:
Control, event printing/plotting, alarm annuciator,
diagnostics
Process level:
PASS M0 with intelligent sensors and actuators
(PASS M0 with PISA)
Availability
ABB Power Transmission
C&P System architecture with conventional CT
Process level:
PASS M0 with wired interface
Bay level:
Control, interlocking, line protection,
measurement and metering (option), event fault recording
Station level:
Control, event printing/plotting, alarm annuciator,
diagnostics
Wired interfaceWired interface
Availability
ABB Power Transmission
AIS PASS
Long time unavailability: 23 min/y 1,4 min/y
With PASS M0 you decrease your unavailability
compared to AIS by 90 %
Single busbar arrangement
Component AIS PASS

(1/y)
MTBF
(y)
MTTR
(h)
MF
(1/y)
MTTM
(h)

(F/y)
MTBF
(y)
MTTR
(h)
MF
(1/y)
MTTM
(h)
Current Transformer 0.0005 - 8 - -
Circuit breaker 0,0068 147 48 0.16 10
Disconnector 0,0047 212 8 0.5 4
Total 0.012 73 0,0059 170 4 0.1 41
Meanings  failure rate
MTBF Meantime between failure
MTTR Meantime to repair
MF Maintenance Frequency
MTTM Meantime to maintain
1
wiht spare part (w/o: 10 h)
data source: CIGRE' WG_13.06, June 1994 for AIS/CIGRE' WG_23.02 Brochure 2000 for GIS/CEA Report 93-97 for PASS bushing
Availability
ABB Power Transmission
SBB in transport position
fits into a standard container 20“
2500
37001950
Transport & Installation
ABB Power Transmission
DBB in transport position
fits into a standard container 20“
2500
45001950
Transport & Installation
ABB Power Transmission
transport unit
transport unit
disassembling
installation
on support
side poles
opening
operating
position
Installation on site
Transport & Installation
ABB Power Transmission
PASS M0
Look at the compactness fed through substation
Layouts
ABB Power Transmission
PASS M0 In-Out S/S
ABB Power Transmission
Fed through Substation (Top view)
30 m
15 m
MV switchboard
Power
Transformer
PASS M0
DBB
Single Line Diagram
Layouts
ABB Power Transmission
30 m
Fed through Substation (Section view)
Layouts
ABB Power Transmission
H configuration with transformer breaker
Layouts
ABB Power Transmission
44 m
20m
H configuration with transformer breaker
Layouts
ABB Power Transmission
PASS M0 doubleCB
ABB Power Transmission
PASS M0 : H configuration with doubleCB
ABB Power Transmission
Conventional AIS Double BusBar
62m
86 m
space requirements:
62 m * 86 m = 5300 m2
space requirements:
27 m * 62 m=1700 m2
27m
62 m
PASS M0 Double BusBar
PASS M0 saves 70 % of space in new substations:
Double BusBar configuration : 4 line bays, 2 trafo bays, 1 coupler
Layouts
ABB Power Transmission
38 m
Conventional AIS Double BusBar PASS M0 Double BusBar
18 m
Double BusBar configuration: line bay comparison
Space Savings
ABB Power Transmission
Layouts
H scheme with coupling bay
22 m
16 m
ABB Power Transmission
SBB with coupling bay (Top view)
16 m
54 m
Layouts
ABB Power Transmission
10 m
Trafo and Line bays (Section view)
6 m
Layouts
ABB Power Transmission
16 m
Coupling bay (Section view)
6 m
Layouts
ABB Power Transmission
145 kV S/S Le Grazie: retrofit of existing H scheme S/S
Layouts
ABB Power Transmission
transport operation
PASS M0 mobile
ABB Power Transmission
PASS M0 cable terminal
ABB Power Transmission
Installation on overhead line pole
Layouts
ABB Power Transmission
Comparison between AIS DBB and PASS M0 DBB:
AIS DBB
Numbers of bays 7
Numbers of foundations 100 %
Required space 100 %
Unavailability 100 %
Cost comparison 100 %
7
40%
32%
30%
70%
PASS M0 DBB
Example: 4 line bays, 2 trafo bays, 1 coupler
Layouts
ABB Power Transmission
Comparison between AIS and PASS substation:
Gantry foundations 4 4
Busbar foundations 16 16
Equipment foundations 65 17
Cable trenches for thousands of for 18 cables
cables
Engineering 100 % < 50 %
Total effort 100 % 60 %
AIS PASS
Example: 4 line bays, 2 trafo bays, 1 coupler
Layouts
ABB Power Transmission
Maintenance on demand is possible through real time
monitoring of:
…with PISA or with an additional unit
• CB operating time
• drive temperature
• accumulated I2T
• contact displacement
• motor running time
• self checking devices
• SF6 density
• etc. etc.
Maintenance
ABB Power Transmission
PISA = Process Interface for Sensors and Actuators
• data preprocessing at the switchgear
• self-checking electronics and drives
• continuous SF6 density monitoring
... lead to condition based maintenance
The PISA allows self-supervising operations
at the switchgear:
Maintenance
ABB Power Transmission
The PISA functions for the circuit breaker:
Spring Charger Control
Spring
Charger
Inductive
Sensor
Maintenance
ABB Power Transmission
The PISA functions for the combined DS/ES:
Process Bus
Maintenance
ABB Power Transmission
The PISA functions for the combined sensor:
Process Bus
I: Rogowsky coil,
U: Capacitive Divider
Maintenance
ABB Power Transmission
3 6 9 10 years
Transparency through trend analysis (example) :
Filling
pressure
First alarm
level
Blocking
pressure
Maintenance
on demand
SF6 gas density
620 kPa
600 kPa
680 kPa
550 kPa
750 kPa
Pressure
Years
Maintenance
ABB Power Transmission
Monitoring of Circuit Breaker: OLM
• Data acquisition unit for on-line
monitoring of HV circuit
breakers
• Date, time, temperature,
relevant data for each event
• 2 types: OLM1 (simpler) and
OLM2
• Compact: 212*210*50 mm
installed on site
• Communication with OLM-bus
(RS485, twisted pair, 115kbps)
• PC software for unit
configuration and data analysis
Monitoring & Diagnostic
ABB Power Transmission
Monitoring System Architecture
Travel
SF 6-Density
Temperature
Damping
Operating circuit
supervision
Spring charge time
r
Serial communication
Arc current
Stations PC
Step 2
Modem
RemotePC
Step 3
Modem
RS 485 or optical
RS 232
Laptop
Step 1
Alarm relay outputs
for conventional system
OLM
Monitoring & Diagnostic
ABB Power Transmission
OLM2 : monitored parameter
 Date and time
 Power voltage
 Heater currents
 SF6 gas density and temperature
 Contact status (I2t)
 Coil circuits, (O, C, T)
 Coil currents
 Number of operations
 Internal and external temperatures
 Motor charge time
 Mechanical travel Phase current
 Motor current
Monitoring & Diagnostic
ABB Power Transmission
Maintenance efforts for PASS M0 is only 40 % of AIS:
Scheduled inspection yes -
of all components
Scheduled maintenance yes -
of all components
Analysis of CT / VT oil yes -
Regular switching of yes -
disconnector and earthing
Cleaning of all components yes -
Greasing of drives yes -
Maintenance on demand - yes
AIS PASS
Maintenance
ABB Power Transmission
0%
50%
100%
150%
CONVENTIONAL PASS M0
Price performance
Cost comparison for AIS and PASS M0 S/S components:
EXAMPLE: RIGID "H" CONFIGURATION
120100
ABB Power Transmission
0%
20%
40%
60%
80%
100%
CONVENTIONAL PASS M0
Maintenance cost for AIS and PASS M0 (per year) :
EXAMPLE: RIGID "H" CONFIGURATION
33
100
Price performance
ABB Power Transmission
Life Cycle Cost for AIS and PASS M0 S/S:
EXAMPLE: RIGID "H" CONFIGURATION
0%
20%
40%
60%
80%
100%
CONVENTIONAL PASS M0
72
100
Price performance
ABB Power Transmission
Customer needs:
- feed energy to S/S A, B, C
- minimum space
- maximum availability on S/S B
- cost
A A1
B B1
C
Customer solution:
- conventional double busbar system
A A1 B B1 C
S/S A S/S B S/S C
S/S A S/S B S/S C
LCC (example from ) 145 kV, Generation S/S
ABB Power Transmission
1st Alternative solution:
- PASS M0, single busbar
A
A1
B
B1
C
A A1B B1 C
S/S A S/S B S/S CS/S A S/S B S/S C
- same functionalities
- reduced land occupation
- reduced cost
LCC (example from ) 145 kV, Generation S/S
ABB Power Transmission
2nd alternative solution:
- PASS M0 double circuit breaker, Single BusBar
B
A1
A
B1
C
A A1B B1 C
S/S A S/S B S/S CS/S A S/S B S/S C
- same functionalities
- further space reduction
- further cost reduction
LCC (example from ) 145 kV, Generation S/S
ABB Power Transmission
0.00
0.20
0.40
0.60
0.80
1.00
[h/y]
S/S A S/S B S/S C
CONV_DBB
PASS_SBB
PASS_DCB
Outage Frequency
0.00
0.02
0.04
0.06
0.08
0.10
0.12
[1/y]
S/S A S/S B S/S C
CONV_DBB
PASS_SBB
PASS_DCB
Outage Duration
Fed S/S UnavailabilityLCC (example from )
ABB Power Transmission
Lyfe Cycle Cost comparison
0%
20%
40%
60%
80%
100%
120%
140%
LCC INITIAL COST FIXED COST VARIABLE COST
CONV_DBB
PASS_SBB
PASS_DCB
INITIAL COST = engineering, civil works, components, secondary equipment, land acquisition, erection, spare part, etc.
FIXED COST = Operation & Maintenance
VARIABLE COST = repairing, power interruption, energy interruption
145 kV, Generation S/SLCC (example from )

More Related Content

What's hot

Cable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - ExampleCable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - ExampleLeonardo ENERGY
 
Sag tension calcs-ohl-tutorial
Sag tension calcs-ohl-tutorialSag tension calcs-ohl-tutorial
Sag tension calcs-ohl-tutorialAzira Muda
 
Power cables
Power cablesPower cables
Power cablescollege
 
02 - Fundamentals of Power Line Carrier.pdf
02 - Fundamentals of Power Line Carrier.pdf02 - Fundamentals of Power Line Carrier.pdf
02 - Fundamentals of Power Line Carrier.pdfkrishnabhardwaj15
 
MCC PANEL WIRING, GA and BOM Sample
MCC PANEL WIRING, GA and BOM SampleMCC PANEL WIRING, GA and BOM Sample
MCC PANEL WIRING, GA and BOM SampleShashi Kant
 
Webinar Sistemas de Puesta a Tierra
Webinar Sistemas de Puesta a TierraWebinar Sistemas de Puesta a Tierra
Webinar Sistemas de Puesta a TierraLeonardo ENERGY
 
Catalogogeneral unistrut(espanol)
Catalogogeneral unistrut(espanol)Catalogogeneral unistrut(espanol)
Catalogogeneral unistrut(espanol)Justhy Taquiri
 
5 centro de carga norma nema bticino tiven
5 centro de carga norma nema bticino tiven5 centro de carga norma nema bticino tiven
5 centro de carga norma nema bticino tivenJuan Marquez
 
Gis substation
Gis substationGis substation
Gis substationAsif Eqbal
 
Understanding and testing_the_abb_red670
Understanding and testing_the_abb_red670Understanding and testing_the_abb_red670
Understanding and testing_the_abb_red670طه محمد
 
ETAP - coordinación de protecciones (star)
ETAP -  coordinación de protecciones (star)ETAP -  coordinación de protecciones (star)
ETAP - coordinación de protecciones (star)Himmelstern
 

What's hot (20)

Catálogo ABB MyAt
Catálogo ABB MyAtCatálogo ABB MyAt
Catálogo ABB MyAt
 
Abb dcb
Abb dcbAbb dcb
Abb dcb
 
Introduction to mv switchgear
Introduction to mv switchgearIntroduction to mv switchgear
Introduction to mv switchgear
 
Cable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - ExampleCable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - Example
 
Sag tension calcs-ohl-tutorial
Sag tension calcs-ohl-tutorialSag tension calcs-ohl-tutorial
Sag tension calcs-ohl-tutorial
 
Power cables
Power cablesPower cables
Power cables
 
02 - Fundamentals of Power Line Carrier.pdf
02 - Fundamentals of Power Line Carrier.pdf02 - Fundamentals of Power Line Carrier.pdf
02 - Fundamentals of Power Line Carrier.pdf
 
HYpact brochure EN
HYpact brochure ENHYpact brochure EN
HYpact brochure EN
 
MCC PANEL WIRING, GA and BOM Sample
MCC PANEL WIRING, GA and BOM SampleMCC PANEL WIRING, GA and BOM Sample
MCC PANEL WIRING, GA and BOM Sample
 
Webinar Sistemas de Puesta a Tierra
Webinar Sistemas de Puesta a TierraWebinar Sistemas de Puesta a Tierra
Webinar Sistemas de Puesta a Tierra
 
Catalogogeneral unistrut(espanol)
Catalogogeneral unistrut(espanol)Catalogogeneral unistrut(espanol)
Catalogogeneral unistrut(espanol)
 
5 centro de carga norma nema bticino tiven
5 centro de carga norma nema bticino tiven5 centro de carga norma nema bticino tiven
5 centro de carga norma nema bticino tiven
 
RETIE APLICADO A CELDAS DE MEDIA TENSIÓN
RETIE APLICADO A CELDAS DE MEDIA TENSIÓNRETIE APLICADO A CELDAS DE MEDIA TENSIÓN
RETIE APLICADO A CELDAS DE MEDIA TENSIÓN
 
Productos schneider 2
Productos schneider 2Productos schneider 2
Productos schneider 2
 
Gis substation
Gis substationGis substation
Gis substation
 
Understanding and testing_the_abb_red670
Understanding and testing_the_abb_red670Understanding and testing_the_abb_red670
Understanding and testing_the_abb_red670
 
Busbar configuarations
Busbar configuarationsBusbar configuarations
Busbar configuarations
 
ETAP - coordinación de protecciones (star)
ETAP -  coordinación de protecciones (star)ETAP -  coordinación de protecciones (star)
ETAP - coordinación de protecciones (star)
 
20432718 sistemas-de-puesta-a-tierra
20432718 sistemas-de-puesta-a-tierra20432718 sistemas-de-puesta-a-tierra
20432718 sistemas-de-puesta-a-tierra
 
Sld for pmcc
Sld for pmccSld for pmcc
Sld for pmcc
 

Similar to Passm0 r0500

Datasheet Fluke A40B. Hubungi PT. Siwali Swantika 021-45850618
Datasheet Fluke A40B. Hubungi PT. Siwali Swantika 021-45850618Datasheet Fluke A40B. Hubungi PT. Siwali Swantika 021-45850618
Datasheet Fluke A40B. Hubungi PT. Siwali Swantika 021-45850618PT. Siwali Swantika
 
Power Quality Systems and Power Factor Correction Presentation
Power Quality Systems and Power Factor Correction PresentationPower Quality Systems and Power Factor Correction Presentation
Power Quality Systems and Power Factor Correction PresentationMircea Gingu
 
Weg automation-drives-and-controls-usa804-brochure-english
Weg automation-drives-and-controls-usa804-brochure-englishWeg automation-drives-and-controls-usa804-brochure-english
Weg automation-drives-and-controls-usa804-brochure-englishDaniel García
 
ABB+Power+Quality+Filters.pdf
ABB+Power+Quality+Filters.pdfABB+Power+Quality+Filters.pdf
ABB+Power+Quality+Filters.pdfssuser5b27192
 
KIKUSUI PBZ Series Intelligent Bi-Polar Power Supplies
KIKUSUI PBZ Series Intelligent Bi-Polar Power Supplies KIKUSUI PBZ Series Intelligent Bi-Polar Power Supplies
KIKUSUI PBZ Series Intelligent Bi-Polar Power Supplies NIHON DENKEI SINGAPORE
 
Kikusui Bipolar Power Supply PBZ series
Kikusui Bipolar Power Supply PBZ seriesKikusui Bipolar Power Supply PBZ series
Kikusui Bipolar Power Supply PBZ seriesNIHON DENKEI SINGAPORE
 
120216 -saia_-_data_sheet_awd3_-_26-496_en_ds_energy_meter-awd3-s0
120216  -saia_-_data_sheet_awd3_-_26-496_en_ds_energy_meter-awd3-s0120216  -saia_-_data_sheet_awd3_-_26-496_en_ds_energy_meter-awd3-s0
120216 -saia_-_data_sheet_awd3_-_26-496_en_ds_energy_meter-awd3-s0Benny Padly
 
1 sbc100192c0201 main_catalog_motor_protection_and_control
1 sbc100192c0201 main_catalog_motor_protection_and_control1 sbc100192c0201 main_catalog_motor_protection_and_control
1 sbc100192c0201 main_catalog_motor_protection_and_controlLuis Antonio González Mederos
 
Powersines presentation (lec)
Powersines presentation (lec)Powersines presentation (lec)
Powersines presentation (lec)greenacquisition
 
Powersines presentation (lec)
Powersines presentation (lec)Powersines presentation (lec)
Powersines presentation (lec)greenacquisition
 
Advanced motion controls ab250a060
Advanced motion controls ab250a060Advanced motion controls ab250a060
Advanced motion controls ab250a060Electromate
 
Manufacturers of Load Cell Amplifiers in India - Canopus Instruments
Manufacturers of Load Cell Amplifiers in India - Canopus InstrumentsManufacturers of Load Cell Amplifiers in India - Canopus Instruments
Manufacturers of Load Cell Amplifiers in India - Canopus Instrumentssmita_kale
 
Introducing ten ksolar rais inverter bus 130809
Introducing ten ksolar rais inverter bus 130809Introducing ten ksolar rais inverter bus 130809
Introducing ten ksolar rais inverter bus 130809Timothy Johnson
 
Introducing ten ksolar rais inverter bus 130809
Introducing ten ksolar rais inverter bus 130809Introducing ten ksolar rais inverter bus 130809
Introducing ten ksolar rais inverter bus 130809Timothy Johnson
 

Similar to Passm0 r0500 (20)

Datasheet Fluke A40B. Hubungi PT. Siwali Swantika 021-45850618
Datasheet Fluke A40B. Hubungi PT. Siwali Swantika 021-45850618Datasheet Fluke A40B. Hubungi PT. Siwali Swantika 021-45850618
Datasheet Fluke A40B. Hubungi PT. Siwali Swantika 021-45850618
 
Power Quality Systems and Power Factor Correction Presentation
Power Quality Systems and Power Factor Correction PresentationPower Quality Systems and Power Factor Correction Presentation
Power Quality Systems and Power Factor Correction Presentation
 
Weg automation-drives-and-controls-usa804-brochure-english
Weg automation-drives-and-controls-usa804-brochure-englishWeg automation-drives-and-controls-usa804-brochure-english
Weg automation-drives-and-controls-usa804-brochure-english
 
Abb ethernet-expansion-board
Abb ethernet-expansion-boardAbb ethernet-expansion-board
Abb ethernet-expansion-board
 
ABB+Power+Quality+Filters.pdf
ABB+Power+Quality+Filters.pdfABB+Power+Quality+Filters.pdf
ABB+Power+Quality+Filters.pdf
 
slup343.pdf
slup343.pdfslup343.pdf
slup343.pdf
 
KIKUSUI PBZ Series Intelligent Bi-Polar Power Supplies
KIKUSUI PBZ Series Intelligent Bi-Polar Power Supplies KIKUSUI PBZ Series Intelligent Bi-Polar Power Supplies
KIKUSUI PBZ Series Intelligent Bi-Polar Power Supplies
 
Kikusui Bipolar Power Supply PBZ series
Kikusui Bipolar Power Supply PBZ seriesKikusui Bipolar Power Supply PBZ series
Kikusui Bipolar Power Supply PBZ series
 
Contactores ABB
Contactores ABBContactores ABB
Contactores ABB
 
CWB Contactors
CWB ContactorsCWB Contactors
CWB Contactors
 
ADCMT 7352 Series Digital Multimeter
ADCMT 7352 Series Digital MultimeterADCMT 7352 Series Digital Multimeter
ADCMT 7352 Series Digital Multimeter
 
120216 -saia_-_data_sheet_awd3_-_26-496_en_ds_energy_meter-awd3-s0
120216  -saia_-_data_sheet_awd3_-_26-496_en_ds_energy_meter-awd3-s0120216  -saia_-_data_sheet_awd3_-_26-496_en_ds_energy_meter-awd3-s0
120216 -saia_-_data_sheet_awd3_-_26-496_en_ds_energy_meter-awd3-s0
 
1 sbc100192c0201 main_catalog_motor_protection_and_control
1 sbc100192c0201 main_catalog_motor_protection_and_control1 sbc100192c0201 main_catalog_motor_protection_and_control
1 sbc100192c0201 main_catalog_motor_protection_and_control
 
Kikusui dcps pat_denkei
Kikusui dcps pat_denkeiKikusui dcps pat_denkei
Kikusui dcps pat_denkei
 
Powersines presentation (lec)
Powersines presentation (lec)Powersines presentation (lec)
Powersines presentation (lec)
 
Powersines presentation (lec)
Powersines presentation (lec)Powersines presentation (lec)
Powersines presentation (lec)
 
Advanced motion controls ab250a060
Advanced motion controls ab250a060Advanced motion controls ab250a060
Advanced motion controls ab250a060
 
Manufacturers of Load Cell Amplifiers in India - Canopus Instruments
Manufacturers of Load Cell Amplifiers in India - Canopus InstrumentsManufacturers of Load Cell Amplifiers in India - Canopus Instruments
Manufacturers of Load Cell Amplifiers in India - Canopus Instruments
 
Introducing ten ksolar rais inverter bus 130809
Introducing ten ksolar rais inverter bus 130809Introducing ten ksolar rais inverter bus 130809
Introducing ten ksolar rais inverter bus 130809
 
Introducing ten ksolar rais inverter bus 130809
Introducing ten ksolar rais inverter bus 130809Introducing ten ksolar rais inverter bus 130809
Introducing ten ksolar rais inverter bus 130809
 

Recently uploaded

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 

Recently uploaded (20)

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 

Passm0 r0500

  • 1. ABB Power Transmission The Plug and Switch System from ABB The new generation ! PASS
  • 2. ABB Power Transmission The source of the name AND SWITCH! PLUG!PLUG!
  • 3. ABB Power Transmission ALL THE NECESSARY FUNCTIONS IN ONE MODULE KEY FUNCTIONS SEALED TYPE EASY INSTALLATION & FAST EXCHANGEABILITY MAIN CONCEPTSPASS Think different, think for performance !
  • 4. ABB Power Transmission Introduction The PASS Family PASS M0 up to 170 kV PASS M1 up to 300 kV PASS M2 up to 550 kV
  • 5. ABB Power Transmission All bay functions in one module Circuit breaker Combined disconnector/ Earthing switch Current measurement Voltage measurement Introduction
  • 6. ABB Power Transmission The PASS M0 ratings Rated voltage kV 72.5 123 145 170 Rated frequency Hz 50/60 Rated current A 2500 Rated breaking current kA 40/31.5 Rated making current kA 100/80 Rated BIL kV 325 550 650 750 Temperature -30*°C / + 55 °C * -25°C with pure SF6 for 750 kV BIL Introduction
  • 7. ABB Power Transmission Where are your benefits from PASS M0? Why PASS M0? Price Performance Layouts Maintenance Availability Transport & Installation Benefits
  • 8. ABB Power Transmission More bays on less space Simple and innovative layouts PASS M0 solution : You can save 50 % of space in new PASS solution. You can double your substation on the same AIS-footprint. You can simplify your layouts keeping the same substation functionality. Why PASS M0? Your challenges in substation engineering:
  • 9. ABB Power Transmission High substation availability through reliable primary and secondary equipment Planable maintenance and higher transparency of installed equipment Low operating costs PASS M0 solution : You decrease your unavailability compared to AIS by 90%. Your maintenance efforts for PASS are only 40 % of AIS. You switch to maintenance on demand. Why PASS M0? Your challenges in substation operation:
  • 10. ABB Power Transmission Short installation time More bays in less space Simple layouts Highly competitive product PASS M0 solution : Your installation effort is only 20% of AIS. You need only 1 compared to 14 days installation time for AIS. You can double your substation on the same AIS-footprint. Why PASS M0? Your challenges as contractors:
  • 11. ABB Power Transmission Lowest initial investiment cost Short installation time PASS M0 solution : Your initial costs for PASS and AIS substations are identical. You reduce maintenance costs by 80%. You reduce the total installation time for HV equipment to 1 day. Why PASS M0? Your challenges in substation purchasing:
  • 12. ABB Power Transmission Thank you ! for your interest in the Plug and Switch System from ABB
  • 13. ABB Power Transmission Legend: circuit breaker CB current transformer CT voltage transformer VT line L disconnector DS earthing switch ES PASS M0 integrates several functions in one module: SBB diagram Conventional AIS PASS BB L DS/ES CB CT/VT DS CB DS CT VTES LBB Availability
  • 14. ABB Power Transmission PASS M0 single BusBar
  • 15. ABB Power Transmission All components are arranged in one enclosure: CB Driver Bushing Circuit BreakerCombined current/ voltage sensor Combined Disconnector/ Earthing Switch Availability
  • 16. ABB Power Transmission Circuit breaker Higher availability through 10,000 times proven GIS chamber Availability
  • 17. ABB Power Transmission L Conventional AIS PASS Legend: circuit breaker CB current transformer CT voltage transformer VT line L disconnector DS earthing switch ES BB 2 BB 1 DS/ES CB CT/VT DS CB DS CT VTES L DS BB2 BB1 PASS M0 integrates several functions in one module: DBB diagram Availability
  • 18. ABB Power Transmission PASS M0 double BusBar
  • 19. ABB Power Transmission Simple and reliable operating mechanisms CB Operating mechanism (BLK222 or BLK82) DS/ES Drive Availability
  • 20. ABB Power Transmission Bushings • silicon-fiberglass construction • maintenance free • self-cleaning surface • better pollution and rain resistance have higher availability through: Availability
  • 21. ABB Power Transmission Conventional Current Transformer (ring type) Availability
  • 22. ABB Power Transmission Combined I/U Sensor • built-in PISA • high accuracy and linearity • local data processing • optical output (no EMC problems) • no saturation • no ferroresonance • local data store for disturbance data Availability
  • 23. ABB Power Transmission • Oil free sensors: no leakage / ageing problems • insulating medium SF6 gas: less solid insulation (ageing) Further benefits: • High accuracy and linearity • Large bandwidth • No saturation or ferroresonance Sensors have higher availability through: Rogowski coil Capacitive ring Availability
  • 24. ABB Power Transmission • Frequency 50Hz/60Hz • Rated voltage range: 17.5kV/ 3 RMS…170kV/ 3 RMS • Measurement accuracy: • with SF6 density monitor installed: – class 0.2% in range 80%…120% of rated voltage; • without SF6 density monitor: – class 1% in range 80%…120% of rated voltage. • Frequency 50Hz/60Hz • Rated current range: 100A....2500A • Rated short circuit current: 40kA RMS at 50/60 Hz (100kA/10ms, peak value). • Measurement accuracy: • with SF6 density monitor installed: – class 0.2% in range 100A…2500A; • without SF6 density monitor: – class 1% in range 10A…2500A. Voltage Current Combined I/U Sensor Availability
  • 25. ABB Power Transmission With PASS you decrease your unavailability compared to AIS by 90% minimum number of components all moving parts are encapsulated quick exchangeable pole means minimum down time MTBF = 170 years MTTR = 4 hours proven GIS contact system one instead of three motor drives proven GIS interrupting chamber over 10000 chamber into operation mature drive no oil contained SF6 or Air instead of solid insulation CBDS/ES SwitchSYSTEM CP14/CT Availability
  • 26. ABB Power Transmission C&P System architecture with combined I/U sensor process bus process bus Bay level: Control, interlocking, line protection, measurement and metering (option), event fault recording Station level: Control, event printing/plotting, alarm annuciator, diagnostics Process level: PASS M0 with intelligent sensors and actuators (PASS M0 with PISA) Availability
  • 27. ABB Power Transmission C&P System architecture with conventional CT Process level: PASS M0 with wired interface Bay level: Control, interlocking, line protection, measurement and metering (option), event fault recording Station level: Control, event printing/plotting, alarm annuciator, diagnostics Wired interfaceWired interface Availability
  • 28. ABB Power Transmission AIS PASS Long time unavailability: 23 min/y 1,4 min/y With PASS M0 you decrease your unavailability compared to AIS by 90 % Single busbar arrangement Component AIS PASS  (1/y) MTBF (y) MTTR (h) MF (1/y) MTTM (h)  (F/y) MTBF (y) MTTR (h) MF (1/y) MTTM (h) Current Transformer 0.0005 - 8 - - Circuit breaker 0,0068 147 48 0.16 10 Disconnector 0,0047 212 8 0.5 4 Total 0.012 73 0,0059 170 4 0.1 41 Meanings  failure rate MTBF Meantime between failure MTTR Meantime to repair MF Maintenance Frequency MTTM Meantime to maintain 1 wiht spare part (w/o: 10 h) data source: CIGRE' WG_13.06, June 1994 for AIS/CIGRE' WG_23.02 Brochure 2000 for GIS/CEA Report 93-97 for PASS bushing Availability
  • 29. ABB Power Transmission SBB in transport position fits into a standard container 20“ 2500 37001950 Transport & Installation
  • 30. ABB Power Transmission DBB in transport position fits into a standard container 20“ 2500 45001950 Transport & Installation
  • 31. ABB Power Transmission transport unit transport unit disassembling installation on support side poles opening operating position Installation on site Transport & Installation
  • 32. ABB Power Transmission PASS M0 Look at the compactness fed through substation Layouts
  • 34. ABB Power Transmission Fed through Substation (Top view) 30 m 15 m MV switchboard Power Transformer PASS M0 DBB Single Line Diagram Layouts
  • 35. ABB Power Transmission 30 m Fed through Substation (Section view) Layouts
  • 36. ABB Power Transmission H configuration with transformer breaker Layouts
  • 37. ABB Power Transmission 44 m 20m H configuration with transformer breaker Layouts
  • 39. ABB Power Transmission PASS M0 : H configuration with doubleCB
  • 40. ABB Power Transmission Conventional AIS Double BusBar 62m 86 m space requirements: 62 m * 86 m = 5300 m2 space requirements: 27 m * 62 m=1700 m2 27m 62 m PASS M0 Double BusBar PASS M0 saves 70 % of space in new substations: Double BusBar configuration : 4 line bays, 2 trafo bays, 1 coupler Layouts
  • 41. ABB Power Transmission 38 m Conventional AIS Double BusBar PASS M0 Double BusBar 18 m Double BusBar configuration: line bay comparison Space Savings
  • 42. ABB Power Transmission Layouts H scheme with coupling bay 22 m 16 m
  • 43. ABB Power Transmission SBB with coupling bay (Top view) 16 m 54 m Layouts
  • 44. ABB Power Transmission 10 m Trafo and Line bays (Section view) 6 m Layouts
  • 45. ABB Power Transmission 16 m Coupling bay (Section view) 6 m Layouts
  • 46. ABB Power Transmission 145 kV S/S Le Grazie: retrofit of existing H scheme S/S Layouts
  • 47. ABB Power Transmission transport operation PASS M0 mobile
  • 48. ABB Power Transmission PASS M0 cable terminal
  • 49. ABB Power Transmission Installation on overhead line pole Layouts
  • 50. ABB Power Transmission Comparison between AIS DBB and PASS M0 DBB: AIS DBB Numbers of bays 7 Numbers of foundations 100 % Required space 100 % Unavailability 100 % Cost comparison 100 % 7 40% 32% 30% 70% PASS M0 DBB Example: 4 line bays, 2 trafo bays, 1 coupler Layouts
  • 51. ABB Power Transmission Comparison between AIS and PASS substation: Gantry foundations 4 4 Busbar foundations 16 16 Equipment foundations 65 17 Cable trenches for thousands of for 18 cables cables Engineering 100 % < 50 % Total effort 100 % 60 % AIS PASS Example: 4 line bays, 2 trafo bays, 1 coupler Layouts
  • 52. ABB Power Transmission Maintenance on demand is possible through real time monitoring of: …with PISA or with an additional unit • CB operating time • drive temperature • accumulated I2T • contact displacement • motor running time • self checking devices • SF6 density • etc. etc. Maintenance
  • 53. ABB Power Transmission PISA = Process Interface for Sensors and Actuators • data preprocessing at the switchgear • self-checking electronics and drives • continuous SF6 density monitoring ... lead to condition based maintenance The PISA allows self-supervising operations at the switchgear: Maintenance
  • 54. ABB Power Transmission The PISA functions for the circuit breaker: Spring Charger Control Spring Charger Inductive Sensor Maintenance
  • 55. ABB Power Transmission The PISA functions for the combined DS/ES: Process Bus Maintenance
  • 56. ABB Power Transmission The PISA functions for the combined sensor: Process Bus I: Rogowsky coil, U: Capacitive Divider Maintenance
  • 57. ABB Power Transmission 3 6 9 10 years Transparency through trend analysis (example) : Filling pressure First alarm level Blocking pressure Maintenance on demand SF6 gas density 620 kPa 600 kPa 680 kPa 550 kPa 750 kPa Pressure Years Maintenance
  • 58. ABB Power Transmission Monitoring of Circuit Breaker: OLM • Data acquisition unit for on-line monitoring of HV circuit breakers • Date, time, temperature, relevant data for each event • 2 types: OLM1 (simpler) and OLM2 • Compact: 212*210*50 mm installed on site • Communication with OLM-bus (RS485, twisted pair, 115kbps) • PC software for unit configuration and data analysis Monitoring & Diagnostic
  • 59. ABB Power Transmission Monitoring System Architecture Travel SF 6-Density Temperature Damping Operating circuit supervision Spring charge time r Serial communication Arc current Stations PC Step 2 Modem RemotePC Step 3 Modem RS 485 or optical RS 232 Laptop Step 1 Alarm relay outputs for conventional system OLM Monitoring & Diagnostic
  • 60. ABB Power Transmission OLM2 : monitored parameter  Date and time  Power voltage  Heater currents  SF6 gas density and temperature  Contact status (I2t)  Coil circuits, (O, C, T)  Coil currents  Number of operations  Internal and external temperatures  Motor charge time  Mechanical travel Phase current  Motor current Monitoring & Diagnostic
  • 61. ABB Power Transmission Maintenance efforts for PASS M0 is only 40 % of AIS: Scheduled inspection yes - of all components Scheduled maintenance yes - of all components Analysis of CT / VT oil yes - Regular switching of yes - disconnector and earthing Cleaning of all components yes - Greasing of drives yes - Maintenance on demand - yes AIS PASS Maintenance
  • 62. ABB Power Transmission 0% 50% 100% 150% CONVENTIONAL PASS M0 Price performance Cost comparison for AIS and PASS M0 S/S components: EXAMPLE: RIGID "H" CONFIGURATION 120100
  • 63. ABB Power Transmission 0% 20% 40% 60% 80% 100% CONVENTIONAL PASS M0 Maintenance cost for AIS and PASS M0 (per year) : EXAMPLE: RIGID "H" CONFIGURATION 33 100 Price performance
  • 64. ABB Power Transmission Life Cycle Cost for AIS and PASS M0 S/S: EXAMPLE: RIGID "H" CONFIGURATION 0% 20% 40% 60% 80% 100% CONVENTIONAL PASS M0 72 100 Price performance
  • 65. ABB Power Transmission Customer needs: - feed energy to S/S A, B, C - minimum space - maximum availability on S/S B - cost A A1 B B1 C Customer solution: - conventional double busbar system A A1 B B1 C S/S A S/S B S/S C S/S A S/S B S/S C LCC (example from ) 145 kV, Generation S/S
  • 66. ABB Power Transmission 1st Alternative solution: - PASS M0, single busbar A A1 B B1 C A A1B B1 C S/S A S/S B S/S CS/S A S/S B S/S C - same functionalities - reduced land occupation - reduced cost LCC (example from ) 145 kV, Generation S/S
  • 67. ABB Power Transmission 2nd alternative solution: - PASS M0 double circuit breaker, Single BusBar B A1 A B1 C A A1B B1 C S/S A S/S B S/S CS/S A S/S B S/S C - same functionalities - further space reduction - further cost reduction LCC (example from ) 145 kV, Generation S/S
  • 68. ABB Power Transmission 0.00 0.20 0.40 0.60 0.80 1.00 [h/y] S/S A S/S B S/S C CONV_DBB PASS_SBB PASS_DCB Outage Frequency 0.00 0.02 0.04 0.06 0.08 0.10 0.12 [1/y] S/S A S/S B S/S C CONV_DBB PASS_SBB PASS_DCB Outage Duration Fed S/S UnavailabilityLCC (example from )
  • 69. ABB Power Transmission Lyfe Cycle Cost comparison 0% 20% 40% 60% 80% 100% 120% 140% LCC INITIAL COST FIXED COST VARIABLE COST CONV_DBB PASS_SBB PASS_DCB INITIAL COST = engineering, civil works, components, secondary equipment, land acquisition, erection, spare part, etc. FIXED COST = Operation & Maintenance VARIABLE COST = repairing, power interruption, energy interruption 145 kV, Generation S/SLCC (example from )

Editor's Notes

  1. MTBF = Mean Time Between Failure MTTR = Mean Time To Repair, Note: The PASS concept considers the time needed for replacing the pole or of the module instead of repairing it on site
  2. The example is referred to a double busbar bay made with conventional component and with PASS M0 DBB
  3. In the present case only the line and transformer bay have been replaced by PASS M0. The coupling, the busbar, the voltage transformer and the cable bushing belong to the existing substation.
  4. The module can be provided with disconnectors only
  5. Unavailability means the outage time for the bay due to maintenance and repair
  6. EXAMPLE REFERRED TO A SUBSTATION WITH RIGID H CONFIGURATION: COST OF THE COMPONENTS ONLY
  7. LIFE CYCLE COST MEANS THE TOTAL COST OF OWNERSHIP AND INCLUDES THE FOLLOWING ITEMS : - INITIAL COST FOR BUILD UP THE SUBSTATION (C&P, ENGINEERING, COMPONENTS, CIVIL WORKS, ETC) - OPERATION & MAINTENANCE COSTS, CONSIDERING AN AVERAGE S/S LIFE OF 20 YEARS - REPAIRING COST AS ABOVE
  8. THE EXAMPLE IS APPLICABLE TO THIS SPECIFIC SUBSTATION; IT WILL BE PRESENTED AT THE NEXT CIGRE' 2000. IT IS REFERRED TO A PROPOSED S/S SOLUTION, NOT SIMPLY LIMITED TO A SALE OF COMPONENTS: NOTE: - CUSTOMER NEEDS means the customer's requirements listed according to the customer priorities: VERY IMPORTANT: the customer core business is to sell energy. - CUSTOMER SOLUTION means the solution proposed by the customer, based on its experience.
  9. ABB SOLUTION: - SINGLE BUSBAR SYSTEM WITH PASS M0 ASSURING THE SAME FUNCTIONALITIES; - IMPORTANT: the feeders are connected according to the need of maximum availability on S/S B; note that S/S B can experience an outage only if the bay B1 and B or both couplers experience an outage contemporary.
  10. IInd ABB SOLUTION The proposed solution makes use of PASS M0 double circuit breaker. As before, the solution assures the same functionalities and a further space reduction. Also in the present case, the maximum availability results on S/S B
  11. COMPARISON OF FEEDED SUBSTATIONS UNAVAILABILITY DUE TO CONVENTIONAL AND PASS M0 PROPOSED SOLUTIONS: - the comparison between conventional and PASS M0 solution shows a higher S/S (A, B, C) unavailability if feeded by the conventional solution (CONV_DBB, double busbar system) in respect to PASS M0 solutions (single busbar PASS_SBB and double circuit breaker PASS_DCB).
  12. Life Cycle Cost comparison of the customer S/S solution (CONV_DBB), and ABB proposed solutions with PASS ( PASS_SBB and PASS_DCB). Life Cycle Cost means the total cost of ownership and includes the following items : - initial cost for build up the substation (c&p, engineering, components, civil works, etc) - operation & maintenance costs, considering an average s/s life of 20 years - repairing cost and cost of power and energy interruption (1 USD/kW and 0.2 USD/kWh)