SlideShare a Scribd company logo
1 of 8
PMS Integration and Scheduling

       Initiative Status Report
Purpose of Initiative
• Improve methodology for entry of Ship’s Force
  PMS items into the shipyard scheduling
  database.
What problem are we trying to solve?
•   The current process duplicates the existing   •   For many PMS items, there is no value
    SF PMS management system.                         added to including them into the master
•    Current requirements result in significant       integrated schedule (MIS).
    churn in the SFZMs schedule.                  •   Expectations for entry of PMS items into
•   Volume of PMS items in the SFZMs                  the AWP to develop a line item/cu phase
    schedule creates a significant                    are inordinately cumbersome and require
    administrative burden to manage, taking           significant effort when work around
    time away from more critical items.               methods exist that would significantly
•   Mismanaged PMS items in the schedule              reduce the required effort.
    skew the graphs and make them poor            •   Shipboard Work Center Supervisors are
    management tools for senior leadership            unfamiliar with the work package during
    on the ship.                                      the initial stages of availability planning
•   Volume of PMS items entered significantly         and do not have access to or co-location
    adds to the load of the APT and takes their       with the shipyard which provides for a
    time away from more critical planning             significant challenge when asking them to
    aspects.                                          develop their PMS plan.
•   Artificial scheduling constraints remove
    the requisite flexibility for PMS item
    scheduling and accomplishment.
What won’t change?
• The intent of this proposal is not to remove the
  requirement for entry of SF PMS items into the
  Master Integrated Schedule (MIS).
• There is no intent to change the method for RPPY
  maintained PMS items entry into the BAWP.
• PMS Items to be accomplished by the shipyard
  will continue to be addressed via the BAWP or
  AWP.
• SF PMS items that meet specific criteria will be
  entered into the shipyard scheduling database.
Process Recommendations
• PMS items to be accomplished by Ship’s Force will not require a JSN
  (AWP Line Item) to be entered into the shipyard scheduling
  database. Some SF PMS actions will continue to require JSNs (e.g.
  requires parts, etc.). NOTE: Other more efficient methodology for
  accomplishing this task will be discussed below.
• Only those PMS items that meet specified criteria (identified below)
  will require entry into the shipyard scheduling database.
• The APT will assume the responsibility for initial review of the cyclic
  and quarterly schedules to identify which PMS actions meet the
  specified criteria.
• The Nuclear and Non-Nuclear Test codes will be provided a list of
  PMS items that were identified as not meeting the below criteria
  for a cursory review at the line item level.
Criteria for PMS Integration
• Requires a specific plant/ship’s condition. (e.g.
  accomplish in dry dock)
• Effects a major distributed system (e.g. CHT,
  Firemain, etc.)
• Is on a component or affects a component that
  has other work being performed on it.
• Is required to support a test program (e.g. startup
  PMS, pre-requisite item , etc.)
• PMS action cannot be fully completed (e.g. any
  retests that can’t be accomplished in conjunction
  with the PMS may require a test line item)
Pms integration and scheduling
Pms integration and scheduling

More Related Content

What's hot

Business Process Improvement
Business Process ImprovementBusiness Process Improvement
Business Process ImprovementSimon Gough
 
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_siesOm lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_siesvideoaakash15
 
Ps sap-pm maintenance-planning
Ps sap-pm maintenance-planningPs sap-pm maintenance-planning
Ps sap-pm maintenance-planningMansour Hineidi
 
Michael Smith Resume v5 with dates
Michael Smith Resume v5 with datesMichael Smith Resume v5 with dates
Michael Smith Resume v5 with datesMichael Smith
 
Cutover strategy in sap fico
Cutover strategy in sap ficoCutover strategy in sap fico
Cutover strategy in sap ficoBhushan Dhande
 
Production Planning and Control
Production Planning and ControlProduction Planning and Control
Production Planning and ControlAijaz Aryan
 
Process planning approaches
Process planning approaches Process planning approaches
Process planning approaches chethan kumar
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)Glen Alleman
 
1 page facility renewal snapshot
1 page facility renewal snapshot1 page facility renewal snapshot
1 page facility renewal snapshotBarry Lynch
 
Building tune ups for commercial buildings
Building tune ups for commercial buildingsBuilding tune ups for commercial buildings
Building tune ups for commercial buildingsBetterBricks
 
Functions of production planning and control 2
Functions of production planning and control 2Functions of production planning and control 2
Functions of production planning and control 2Vignesh Jayakumar
 
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2GreenData.IO
 
CAPP , JIT, FMS
CAPP , JIT, FMSCAPP , JIT, FMS
CAPP , JIT, FMSDenny John
 

What's hot (19)

Scheduling
SchedulingScheduling
Scheduling
 
Business Process Improvement
Business Process ImprovementBusiness Process Improvement
Business Process Improvement
 
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_siesOm lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
Om lect 05_a(r0-aug-08)_manufacturing planning & scheduling_mms_sies
 
Scheduling
SchedulingScheduling
Scheduling
 
Ps sap-pm maintenance-planning
Ps sap-pm maintenance-planningPs sap-pm maintenance-planning
Ps sap-pm maintenance-planning
 
Michael Smith Resume v5 with dates
Michael Smith Resume v5 with datesMichael Smith Resume v5 with dates
Michael Smith Resume v5 with dates
 
Cutover strategy in sap fico
Cutover strategy in sap ficoCutover strategy in sap fico
Cutover strategy in sap fico
 
Capp
CappCapp
Capp
 
Production Planning and Control
Production Planning and ControlProduction Planning and Control
Production Planning and Control
 
Process planning approaches
Process planning approaches Process planning approaches
Process planning approaches
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Leave Time A3
Leave Time A3Leave Time A3
Leave Time A3
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
 
1 page facility renewal snapshot
1 page facility renewal snapshot1 page facility renewal snapshot
1 page facility renewal snapshot
 
Building tune ups for commercial buildings
Building tune ups for commercial buildingsBuilding tune ups for commercial buildings
Building tune ups for commercial buildings
 
Functions of production planning and control 2
Functions of production planning and control 2Functions of production planning and control 2
Functions of production planning and control 2
 
FINAL CHARTER
FINAL CHARTERFINAL CHARTER
FINAL CHARTER
 
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2
 
CAPP , JIT, FMS
CAPP , JIT, FMSCAPP , JIT, FMS
CAPP , JIT, FMS
 

Similar to Pms integration and scheduling

Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROLUnit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROLMohanumar S
 
PRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROLPRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROLSIVASHANKAR N
 
Ppc unit-4-production scheduling
Ppc   unit-4-production schedulingPpc   unit-4-production scheduling
Ppc unit-4-production schedulingkarthi keyan
 
PRODUCTION PLANNING AND CONTROL-Unit 4
PRODUCTION PLANNING AND CONTROL-Unit 4PRODUCTION PLANNING AND CONTROL-Unit 4
PRODUCTION PLANNING AND CONTROL-Unit 4prakash0712
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Manish 13 mrp2
Manish 13 mrp2Manish 13 mrp2
Manish 13 mrp2samjune
 
Operational Readiness and Importance of Operator Training
Operational Readiness and Importance of Operator TrainingOperational Readiness and Importance of Operator Training
Operational Readiness and Importance of Operator TrainingJuan Jorge
 
Hyperspring Implementation of BWROG EP/SAG CONTE 2019
Hyperspring Implementation of BWROG EP/SAG CONTE 2019Hyperspring Implementation of BWROG EP/SAG CONTE 2019
Hyperspring Implementation of BWROG EP/SAG CONTE 2019GSE Systems, Inc.
 
Mba ii pmom_unit-4.2 shop floor planning and control a
Mba ii pmom_unit-4.2 shop floor planning and control aMba ii pmom_unit-4.2 shop floor planning and control a
Mba ii pmom_unit-4.2 shop floor planning and control aRai University
 
Price.rick
Price.rickPrice.rick
Price.rickNASAPMC
 
Price.rick
Price.rickPrice.rick
Price.rickNASAPMC
 

Similar to Pms integration and scheduling (20)

Unit 4
Unit 4Unit 4
Unit 4
 
Unit 4
Unit 4Unit 4
Unit 4
 
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROLUnit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
Unit 4-IE6605 & PRODUCTION PLANNING AND CONTROL
 
PRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROLPRODUCTION PLANNING AND CONTROL
PRODUCTION PLANNING AND CONTROL
 
unit 4.ppt
unit 4.pptunit 4.ppt
unit 4.ppt
 
Unit 4 PPC
Unit 4 PPCUnit 4 PPC
Unit 4 PPC
 
Unit 4
Unit 4Unit 4
Unit 4
 
Ppc unit-4-production scheduling
Ppc   unit-4-production schedulingPpc   unit-4-production scheduling
Ppc unit-4-production scheduling
 
PRODUCTION PLANNING AND CONTROL-Unit 4
PRODUCTION PLANNING AND CONTROL-Unit 4PRODUCTION PLANNING AND CONTROL-Unit 4
PRODUCTION PLANNING AND CONTROL-Unit 4
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Manish 13 mrp2
Manish 13 mrp2Manish 13 mrp2
Manish 13 mrp2
 
Operational Readiness and Importance of Operator Training
Operational Readiness and Importance of Operator TrainingOperational Readiness and Importance of Operator Training
Operational Readiness and Importance of Operator Training
 
Hyperspring Implementation of BWROG EP/SAG CONTE 2019
Hyperspring Implementation of BWROG EP/SAG CONTE 2019Hyperspring Implementation of BWROG EP/SAG CONTE 2019
Hyperspring Implementation of BWROG EP/SAG CONTE 2019
 
Rccp report
Rccp reportRccp report
Rccp report
 
Mba ii pmom_unit-4.2 shop floor planning and control a
Mba ii pmom_unit-4.2 shop floor planning and control aMba ii pmom_unit-4.2 shop floor planning and control a
Mba ii pmom_unit-4.2 shop floor planning and control a
 
Rough cut planning
Rough cut planningRough cut planning
Rough cut planning
 
Manish 13 mrp2
Manish 13 mrp2Manish 13 mrp2
Manish 13 mrp2
 
Price.rick
Price.rickPrice.rick
Price.rick
 
Price.rick
Price.rickPrice.rick
Price.rick
 

Pms integration and scheduling

  • 1. PMS Integration and Scheduling Initiative Status Report
  • 2. Purpose of Initiative • Improve methodology for entry of Ship’s Force PMS items into the shipyard scheduling database.
  • 3. What problem are we trying to solve? • The current process duplicates the existing • For many PMS items, there is no value SF PMS management system. added to including them into the master • Current requirements result in significant integrated schedule (MIS). churn in the SFZMs schedule. • Expectations for entry of PMS items into • Volume of PMS items in the SFZMs the AWP to develop a line item/cu phase schedule creates a significant are inordinately cumbersome and require administrative burden to manage, taking significant effort when work around time away from more critical items. methods exist that would significantly • Mismanaged PMS items in the schedule reduce the required effort. skew the graphs and make them poor • Shipboard Work Center Supervisors are management tools for senior leadership unfamiliar with the work package during on the ship. the initial stages of availability planning • Volume of PMS items entered significantly and do not have access to or co-location adds to the load of the APT and takes their with the shipyard which provides for a time away from more critical planning significant challenge when asking them to aspects. develop their PMS plan. • Artificial scheduling constraints remove the requisite flexibility for PMS item scheduling and accomplishment.
  • 4. What won’t change? • The intent of this proposal is not to remove the requirement for entry of SF PMS items into the Master Integrated Schedule (MIS). • There is no intent to change the method for RPPY maintained PMS items entry into the BAWP. • PMS Items to be accomplished by the shipyard will continue to be addressed via the BAWP or AWP. • SF PMS items that meet specific criteria will be entered into the shipyard scheduling database.
  • 5. Process Recommendations • PMS items to be accomplished by Ship’s Force will not require a JSN (AWP Line Item) to be entered into the shipyard scheduling database. Some SF PMS actions will continue to require JSNs (e.g. requires parts, etc.). NOTE: Other more efficient methodology for accomplishing this task will be discussed below. • Only those PMS items that meet specified criteria (identified below) will require entry into the shipyard scheduling database. • The APT will assume the responsibility for initial review of the cyclic and quarterly schedules to identify which PMS actions meet the specified criteria. • The Nuclear and Non-Nuclear Test codes will be provided a list of PMS items that were identified as not meeting the below criteria for a cursory review at the line item level.
  • 6. Criteria for PMS Integration • Requires a specific plant/ship’s condition. (e.g. accomplish in dry dock) • Effects a major distributed system (e.g. CHT, Firemain, etc.) • Is on a component or affects a component that has other work being performed on it. • Is required to support a test program (e.g. startup PMS, pre-requisite item , etc.) • PMS action cannot be fully completed (e.g. any retests that can’t be accomplished in conjunction with the PMS may require a test line item)