2. Short description
The project reflects the development
of a 3D game.
The phases of the game include the
creation of the game and the story and
characters definition
Being an android application, time is
also an issue. The whole process
should not take longer than a few
months
3. Resources (1)
We have a team of nine competent people.
=> A few team member swill have multiple roles.
Software Roles:
Project manager: Indy
Game designers: Garry, Gwen
Artist: Ariana
Programmers: Peter, Penny, Perry, Garry
Technical director: Gwen
Testers: Tweak, Peter, Penny
Animator: Andrew
4. Resources (2)
Work hour costs in normal conditions:
Wages: 7-9$ / hr
The project manager and Game
designers earn more
Work hour costs in case of overtime:
For everyone: 9$ / hr
5. Constrains & Risks
There are two major constrains:
most important: money
constrain: time
The planning will be done by the
project manager. He will try to reduce
the cost to a minimum.
=> No overtime!
• Overtime is only for special
situations and it has to be agreed
by the project manager and
person in issue.
6. Project phases:
Concept
Planning and design
Development (pre-alpha)
Testing (alpha)
Release
Maintenance and bug fixes
12. Conclusions
We have used Microsoft Project to manage
our android application.
We chose it because it allowed us to enter
the tasks in a list, to schedule them, to assign
resources to these tasks, and to enter costs
for all the phases and resources while
tracking the changes.
Microsoft Project is useful from the very first
step since it supplies some templates that we
can use for a specific kind of project