MANAGEMENT PROYEK
PROJECT
Developing Academic Information System of
SMAN 1 Benai
GUSFA LEO FIRNANDO
Program Studi S1 Sistem Informasi
Fakultas Sains dan Teknologi
Universitas Islam Sultan Syarif Kasim Riau
http://sif.uin-suska.ac.id/
http://fst.uin-suska.ac.id/
http://www.uin-suska.ac.id/
Project Chapter
Project Name : Establish Academic Information System of SMAN 1
Benai
Project Start Date : January 23, 2017
Completed Project Date : June 12, 2017
Project Manager : Misriadi
Analys : Gusfa Leo Firnando
Programmer : Arta, Affan Noer
1. INTRODUCTION
Project Objectives
build an academic information system at SMAN 1 Benai that can provide technology and
information related to academic at SMAN 1 Benai which includes new student enrollment,
teacher data storage, active student data storage and alumni students per force, and so forth.
Thus it can provide convenience and advantages for the school and also students / i. The project
starts with analyzing existing system processes, designing systems, designing computer network
architectures to be used, network testing, to system implementation. This project will be done for 5
months with estimated cost of Rp. 7,000,000.00, -
The following are some of the critical success factors of the project:
Determinants of Success
Commitment and support from the management.
The availability of human resources in accordance with
their respective competencies.
Commitment and support of the project team
Good cooperation of all parties in accordance with their
respective competencies
Continuity of project implementation.
Discipline implementation in accordance with the project work
plan.
Good and complete project documentation ..
The availability of all project support facilities is appropriate
and adequate.
Good cooperation of all parties in accordance with their respective competencies
Expected Benefits
From the school side:
 Provide wider and faster information access to students.
 Improve the quality of education in SMAN 1 Benai.
From student / i:
 Improve the effectiveness of learning from the circulation of knowledge of technology and
information.
 Supporting educational facilities for students of SMAN 1 Benai.
2. APPROACHES IN PROJECT MANAGEMENT
Stages of the Project Approach
o Analysis of the needs of computer users, hardware and software to be implemented.
o The design of computer network architecture.
o System development.
o Test computer network connectivity.
o Develop project cost estimation for implementation.
3. COVERAGE OF PROJECT
The academic information system project is a project to build an
academic information system and design a computer network
system in the environment of SMAN 1 Benai. The system to be
implemented is a LAN network system (Local Area Network).
a. Specification of Functional Requirements
From the analysis needs of SMAN 1 Benai and the use of computers, required a LAN network
system. Here in is a list of system functional requirements needed campus and also its users (server
computers, client computers).
Function Name Description
Server Computer
To manage all activities performed by the admin, where data is entered
issued will be stored and managed on the server computer.
Computer Client
For use by the user as a means of delivering information and teaching
learning by students / i.
b. Non-Functional Requirement Specification
The following is a list of non-functional requirements of academic information
system of SMAN 1 Benai:
No Non-Functional Needs
1
All applications required in learning activities must be provided
on every computer.
2 The computer used must be of the best quality and speck.
3 Network connectivity should be quickly accessible.
4 The computer used should be safe for use by the user.
Description of Project Scope
 The device that will be used in this project is hardware, and other supporting software in SMAN 1
Benai.
 The modules developed include: network connectivity, network architecture, and reports required
when there are additions or complaints from the modules we develop.
 The network model used by LAN network, so that all existing connections can only be used in the
environment of SMAN 1 Benai.
 Academic information system is built by using PHP, mysql and xampp programming languages.
Submission of Project
Outputs that will be included in this project are reports of system malfunction, network
performance decryption, and others.
Criteria for Project Acceptance
Team pegembang will perform network testing in the final stages, after the installation of
applications on the server computer or client is done. In addition to testing from the developer, this
final test will also be performed by the client in this case is the SMAN 1 Benai, and if everything is
considered sufficient and can be smoothly then it will be submitted to the SMAN 1 Benai.
Limitations
 The information system built is academic information system of SMAN 1 Benai.
 The features that will be displayed on the system is home, student enrollment / i, teacher
menu, student menu, alumni menu, about.
 Applications are built using PHP, mysql and xampp programming languages
 Network system built using LAN network system.
 Internet access is only provided around the environment of SMAN 1 Benai.
 Restrict access to excessive bandwidth usage that can harm the SMAN 1 Benai.
4. SCHEDULE OF PROJECT IMPLEMENTATION
Jadwal Tanggal
Mulai proyek 23 Januari 2017
Analisa sistem yang ada 25 Januari 2017
Project charter ditandatangani 27 Januari 2017
Proposal disetujui 27 Januari 2017
Perekrutan tim proyek 03 Februari 2017
Hasil analisa sistem disetujui 10 Februari 2017
Pembuatan laporan 28 Januari – 05 Juni 2017
Membangun sistem 15 Maret 2017
Penerapan instalasi jaringan komputer 17 April 2017
Penerapan Instalasi OS pada komputer server
dan client
02 Mei 2017
Testing jaringan 19 mei 2017
Seminar 10 Juni 2017
12 Juni 2017
5. CHANGE MANAGEMENT PLAN
In the course of a project, there is almost always a demand for change. To anticipate this, it is
necessary to prepare a procedure. The procedure for controlling changes in a project is often called the
Change Control Procedure.
Any approved modifications or changes to the project schedule and cost should refer to the following
procedures:
• Submission of changes may come from each team member when necessary, especially for changes
that will affect the schedule and scope of work.
• Approval on the change request form indicates approval of changes to the schedule.
Change Control Procedures
CONTINUE..
Submission of Changes
 A change can be submitted to the project manager through formal communication (regular meetings) or non-
formal (other communications).
 Fill out the change request form.
 Every change is recorded on the change request note.
Monitor Perubahan
 When the change request form has been approved, work can begin.
 The project manager will change the project schedule or work plan to accommodate the agreed changes and present
them in the project progress meeting for approval.
 Progress in change control will be reported in project meetings, the project manager must sign the change request form
if the change has been completed.
6. COMMUNICATION MANAGEMENT PLAN
Communicating Planning
Communication planning outlines the need for regular communication
among team members involved in the construction of the academic
information system development project of SMAN 1 Benai. Communication
should not be done formally, communication can be done openly and
informally to facilitate knowledge transfer between all parties involved /
interested
Preparation for the Meeting
Distributing the agenda of the meeting, at least one day before the meeting,
discussion of topics in order of importance begins with easy topics and each topic is
allocated time.
 Distributing meeting materials, agenda, as well as location and time information.
 Each member of the project team is responsible for preparing, attending and
participating actively in meetings.
 Leaders of meetings and facilitators ensure meetings are on track and effective, so
meeting objectives can be achieved.
 The meeting leader will appoint a notary to make the meeting documentation and
distribute appropriately.
Continue....
The meeting discussed at least the following topks:
 Activities that will soon be done
 Review of change controls
7. PROJECT TEAM DIRECTORY
Nama Posisi Email Telephone
Misriadi Project Manajer adipangean1@gmail.com 082144991000
Gusfa Leo
Firnando
Analisa Perancangan
dan training operator
Gusfaleo13@gmail.com 085216422219
1. Arta Utama
2. Affan Noer
Konfigurasi server,
setting router, switch
dan hub
1. Artautama23@gmail.com
2. Akagami767@gmail.com
1. 082384455454
2. 085296780785
8. MANAGEMENT PLAN COST
The project will use accepted value metrics to track and manage costs and the cost basis provides the
basis for reporting, tracking, and managing costs. The cost breakdown for the project to build the
academic information system of SMAN 1 Benai covers all budgeted costs for the successful completion of
the project. The details of the cost as follows:
Jenis Pengerjaan max Type Fee
Base
Calender
Project Manajer 100% Work 90.000/hari
Analisa Perancangan dan
Training Operator 100% Work 80.000/hari
Konfigurasi server, Setting
Router, Switch dan Hub 100% Work 75.000/hari
9. MANAGEMENT PLAN CREATION PROJECT
Project scope management is the management of processes for defining and
controlling what is included and not included in the project. Implementation of the project
and all stakeholders should have the same perception of the outcome of the project and
the process that will be undertaken in making the project outcome. Project scope
management processes include:
Continue ..
1. Project initiation: the initial process of the project or the transition from one stage to the
next.
2. Planning coverage: the creation of documents to be used as the basis for decision making
in project implementation.
3. Screen definition: details of the final project result into smaller and more manageable
component parts
4. Verification of coverage: a formal process of approval of project coverage
5. Control of coverage changes: process control over changes in project scope.
COMPLETE
THANK YOU

More Related Content

Similar to Management project

(Project Charter )V 2.0Project Sc.docx
 (Project Charter )V 2.0Project Sc.docx (Project Charter )V 2.0Project Sc.docx
(Project Charter )V 2.0Project Sc.docxaryan532920
 
Implementation evaluation and maintenance of the mis
Implementation evaluation and maintenance of the misImplementation evaluation and maintenance of the mis
Implementation evaluation and maintenance of the misSneha Autade
 
Project Information System
Project Information SystemProject Information System
Project Information SystemSaurabhAdhau1
 
Ignou MCA mini project report
Ignou MCA mini project reportIgnou MCA mini project report
Ignou MCA mini project reportHitesh Jangid
 
Team 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docxTeam 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docxmattinsonjanel
 
E 5 development-of_a_data_management_system_for_stud
E 5 development-of_a_data_management_system_for_studE 5 development-of_a_data_management_system_for_stud
E 5 development-of_a_data_management_system_for_studEdress Oryakhail
 
Project Review Management System
Project Review Management SystemProject Review Management System
Project Review Management SystemIRJET Journal
 
SCHOOL_MANAGEMENT_SYSTEM_This_Report_Pre.doc
SCHOOL_MANAGEMENT_SYSTEM_This_Report_Pre.docSCHOOL_MANAGEMENT_SYSTEM_This_Report_Pre.doc
SCHOOL_MANAGEMENT_SYSTEM_This_Report_Pre.docbosed0737
 
Attendance management system project report.
Attendance management system project report.Attendance management system project report.
Attendance management system project report.Manoj Kumar
 
Online Examination system mini project -1.ppt
Online Examination system mini project -1.pptOnline Examination system mini project -1.ppt
Online Examination system mini project -1.pptParvatiRathod1
 
OS Password-Manager-Report.docx
OS Password-Manager-Report.docxOS Password-Manager-Report.docx
OS Password-Manager-Report.docxrinim85726
 
Assignment 8.14.docx
Assignment 8.14.docxAssignment 8.14.docx
Assignment 8.14.docxssuser562afc1
 
School admission process management system (Documention)
School admission process management system (Documention)School admission process management system (Documention)
School admission process management system (Documention)Shital Kat
 
Student database management system
Student database management systemStudent database management system
Student database management systemSnehal Raut
 

Similar to Management project (20)

Assignment no 1se
Assignment no 1seAssignment no 1se
Assignment no 1se
 
(Project Charter )V 2.0Project Sc.docx
 (Project Charter )V 2.0Project Sc.docx (Project Charter )V 2.0Project Sc.docx
(Project Charter )V 2.0Project Sc.docx
 
Implementation evaluation and maintenance of the mis
Implementation evaluation and maintenance of the misImplementation evaluation and maintenance of the mis
Implementation evaluation and maintenance of the mis
 
Project Information System
Project Information SystemProject Information System
Project Information System
 
Ignou MCA mini project report
Ignou MCA mini project reportIgnou MCA mini project report
Ignou MCA mini project report
 
Team 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docxTeam 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docx
 
E 5 development-of_a_data_management_system_for_stud
E 5 development-of_a_data_management_system_for_studE 5 development-of_a_data_management_system_for_stud
E 5 development-of_a_data_management_system_for_stud
 
Final project se
Final project seFinal project se
Final project se
 
Project Review Management System
Project Review Management SystemProject Review Management System
Project Review Management System
 
Tony_CV New
Tony_CV NewTony_CV New
Tony_CV New
 
SCHOOL_MANAGEMENT_SYSTEM_This_Report_Pre.doc
SCHOOL_MANAGEMENT_SYSTEM_This_Report_Pre.docSCHOOL_MANAGEMENT_SYSTEM_This_Report_Pre.doc
SCHOOL_MANAGEMENT_SYSTEM_This_Report_Pre.doc
 
Attendance management system project report.
Attendance management system project report.Attendance management system project report.
Attendance management system project report.
 
Online Examination system mini project -1.ppt
Online Examination system mini project -1.pptOnline Examination system mini project -1.ppt
Online Examination system mini project -1.ppt
 
Lecture 3.pptx
Lecture 3.pptxLecture 3.pptx
Lecture 3.pptx
 
OS Password-Manager-Report.docx
OS Password-Manager-Report.docxOS Password-Manager-Report.docx
OS Password-Manager-Report.docx
 
Project scheduler doc
Project scheduler docProject scheduler doc
Project scheduler doc
 
Assignment 8.14.docx
Assignment 8.14.docxAssignment 8.14.docx
Assignment 8.14.docx
 
School admission process management system (Documention)
School admission process management system (Documention)School admission process management system (Documention)
School admission process management system (Documention)
 
Project Plan - Docweb
Project Plan - DocwebProject Plan - Docweb
Project Plan - Docweb
 
Student database management system
Student database management systemStudent database management system
Student database management system
 

Recently uploaded

Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc.../:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...lizamodels9
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedKaiNexus
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCRsoniya singh
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfmuskan1121w
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCRsoniya singh
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Serviceankitnayak356677
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckHajeJanKamps
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...lizamodels9
 

Recently uploaded (20)

Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc.../:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
 

Management project

  • 1. MANAGEMENT PROYEK PROJECT Developing Academic Information System of SMAN 1 Benai GUSFA LEO FIRNANDO Program Studi S1 Sistem Informasi Fakultas Sains dan Teknologi Universitas Islam Sultan Syarif Kasim Riau http://sif.uin-suska.ac.id/ http://fst.uin-suska.ac.id/ http://www.uin-suska.ac.id/
  • 2. Project Chapter Project Name : Establish Academic Information System of SMAN 1 Benai Project Start Date : January 23, 2017 Completed Project Date : June 12, 2017 Project Manager : Misriadi Analys : Gusfa Leo Firnando Programmer : Arta, Affan Noer 1. INTRODUCTION
  • 3. Project Objectives build an academic information system at SMAN 1 Benai that can provide technology and information related to academic at SMAN 1 Benai which includes new student enrollment, teacher data storage, active student data storage and alumni students per force, and so forth. Thus it can provide convenience and advantages for the school and also students / i. The project starts with analyzing existing system processes, designing systems, designing computer network architectures to be used, network testing, to system implementation. This project will be done for 5 months with estimated cost of Rp. 7,000,000.00, -
  • 4. The following are some of the critical success factors of the project: Determinants of Success Commitment and support from the management. The availability of human resources in accordance with their respective competencies. Commitment and support of the project team Good cooperation of all parties in accordance with their respective competencies Continuity of project implementation. Discipline implementation in accordance with the project work plan. Good and complete project documentation .. The availability of all project support facilities is appropriate and adequate. Good cooperation of all parties in accordance with their respective competencies
  • 5. Expected Benefits From the school side:  Provide wider and faster information access to students.  Improve the quality of education in SMAN 1 Benai. From student / i:  Improve the effectiveness of learning from the circulation of knowledge of technology and information.  Supporting educational facilities for students of SMAN 1 Benai.
  • 6. 2. APPROACHES IN PROJECT MANAGEMENT Stages of the Project Approach o Analysis of the needs of computer users, hardware and software to be implemented. o The design of computer network architecture. o System development. o Test computer network connectivity. o Develop project cost estimation for implementation.
  • 7. 3. COVERAGE OF PROJECT The academic information system project is a project to build an academic information system and design a computer network system in the environment of SMAN 1 Benai. The system to be implemented is a LAN network system (Local Area Network).
  • 8. a. Specification of Functional Requirements From the analysis needs of SMAN 1 Benai and the use of computers, required a LAN network system. Here in is a list of system functional requirements needed campus and also its users (server computers, client computers). Function Name Description Server Computer To manage all activities performed by the admin, where data is entered issued will be stored and managed on the server computer. Computer Client For use by the user as a means of delivering information and teaching learning by students / i.
  • 9. b. Non-Functional Requirement Specification The following is a list of non-functional requirements of academic information system of SMAN 1 Benai: No Non-Functional Needs 1 All applications required in learning activities must be provided on every computer. 2 The computer used must be of the best quality and speck. 3 Network connectivity should be quickly accessible. 4 The computer used should be safe for use by the user.
  • 10. Description of Project Scope  The device that will be used in this project is hardware, and other supporting software in SMAN 1 Benai.  The modules developed include: network connectivity, network architecture, and reports required when there are additions or complaints from the modules we develop.  The network model used by LAN network, so that all existing connections can only be used in the environment of SMAN 1 Benai.  Academic information system is built by using PHP, mysql and xampp programming languages.
  • 11. Submission of Project Outputs that will be included in this project are reports of system malfunction, network performance decryption, and others. Criteria for Project Acceptance Team pegembang will perform network testing in the final stages, after the installation of applications on the server computer or client is done. In addition to testing from the developer, this final test will also be performed by the client in this case is the SMAN 1 Benai, and if everything is considered sufficient and can be smoothly then it will be submitted to the SMAN 1 Benai.
  • 12. Limitations  The information system built is academic information system of SMAN 1 Benai.  The features that will be displayed on the system is home, student enrollment / i, teacher menu, student menu, alumni menu, about.  Applications are built using PHP, mysql and xampp programming languages  Network system built using LAN network system.  Internet access is only provided around the environment of SMAN 1 Benai.  Restrict access to excessive bandwidth usage that can harm the SMAN 1 Benai.
  • 13. 4. SCHEDULE OF PROJECT IMPLEMENTATION Jadwal Tanggal Mulai proyek 23 Januari 2017 Analisa sistem yang ada 25 Januari 2017 Project charter ditandatangani 27 Januari 2017 Proposal disetujui 27 Januari 2017 Perekrutan tim proyek 03 Februari 2017 Hasil analisa sistem disetujui 10 Februari 2017 Pembuatan laporan 28 Januari – 05 Juni 2017 Membangun sistem 15 Maret 2017 Penerapan instalasi jaringan komputer 17 April 2017 Penerapan Instalasi OS pada komputer server dan client 02 Mei 2017 Testing jaringan 19 mei 2017 Seminar 10 Juni 2017 12 Juni 2017
  • 14. 5. CHANGE MANAGEMENT PLAN In the course of a project, there is almost always a demand for change. To anticipate this, it is necessary to prepare a procedure. The procedure for controlling changes in a project is often called the Change Control Procedure. Any approved modifications or changes to the project schedule and cost should refer to the following procedures: • Submission of changes may come from each team member when necessary, especially for changes that will affect the schedule and scope of work. • Approval on the change request form indicates approval of changes to the schedule. Change Control Procedures
  • 15. CONTINUE.. Submission of Changes  A change can be submitted to the project manager through formal communication (regular meetings) or non- formal (other communications).  Fill out the change request form.  Every change is recorded on the change request note. Monitor Perubahan  When the change request form has been approved, work can begin.  The project manager will change the project schedule or work plan to accommodate the agreed changes and present them in the project progress meeting for approval.  Progress in change control will be reported in project meetings, the project manager must sign the change request form if the change has been completed.
  • 16. 6. COMMUNICATION MANAGEMENT PLAN Communicating Planning Communication planning outlines the need for regular communication among team members involved in the construction of the academic information system development project of SMAN 1 Benai. Communication should not be done formally, communication can be done openly and informally to facilitate knowledge transfer between all parties involved / interested
  • 17. Preparation for the Meeting Distributing the agenda of the meeting, at least one day before the meeting, discussion of topics in order of importance begins with easy topics and each topic is allocated time.  Distributing meeting materials, agenda, as well as location and time information.  Each member of the project team is responsible for preparing, attending and participating actively in meetings.  Leaders of meetings and facilitators ensure meetings are on track and effective, so meeting objectives can be achieved.  The meeting leader will appoint a notary to make the meeting documentation and distribute appropriately.
  • 18. Continue.... The meeting discussed at least the following topks:  Activities that will soon be done  Review of change controls
  • 19. 7. PROJECT TEAM DIRECTORY Nama Posisi Email Telephone Misriadi Project Manajer adipangean1@gmail.com 082144991000 Gusfa Leo Firnando Analisa Perancangan dan training operator Gusfaleo13@gmail.com 085216422219 1. Arta Utama 2. Affan Noer Konfigurasi server, setting router, switch dan hub 1. Artautama23@gmail.com 2. Akagami767@gmail.com 1. 082384455454 2. 085296780785
  • 20. 8. MANAGEMENT PLAN COST The project will use accepted value metrics to track and manage costs and the cost basis provides the basis for reporting, tracking, and managing costs. The cost breakdown for the project to build the academic information system of SMAN 1 Benai covers all budgeted costs for the successful completion of the project. The details of the cost as follows: Jenis Pengerjaan max Type Fee Base Calender Project Manajer 100% Work 90.000/hari Analisa Perancangan dan Training Operator 100% Work 80.000/hari Konfigurasi server, Setting Router, Switch dan Hub 100% Work 75.000/hari
  • 21. 9. MANAGEMENT PLAN CREATION PROJECT Project scope management is the management of processes for defining and controlling what is included and not included in the project. Implementation of the project and all stakeholders should have the same perception of the outcome of the project and the process that will be undertaken in making the project outcome. Project scope management processes include:
  • 22. Continue .. 1. Project initiation: the initial process of the project or the transition from one stage to the next. 2. Planning coverage: the creation of documents to be used as the basis for decision making in project implementation. 3. Screen definition: details of the final project result into smaller and more manageable component parts 4. Verification of coverage: a formal process of approval of project coverage 5. Control of coverage changes: process control over changes in project scope.