SlideShare a Scribd company logo
1 of 22
Extension of Metro’sExtension of Metro’s
Purple LinePurple Line
Presented By:Presented By:
Eric ChristensonEric Christenson
Engineering Challenges andEngineering Challenges and
MitigationsMitigations
 Building a subway under a major cityBuilding a subway under a major city
that is already established.that is already established.
 Sustaining a tunnel through twoSustaining a tunnel through two
active fault zones.active fault zones.
 Most of construction is under theMost of construction is under the
ground water table.ground water table.
 Area has scattered natural depositsArea has scattered natural deposits
of tar, toxic gasses, and oil.of tar, toxic gasses, and oil.
First, Some Fun FactsFirst, Some Fun Facts
 Project started inProject started in
November 2014.November 2014.
 Largest public worksLargest public works
project and programproject and program
in the nation rightin the nation right
now.now.
 Already raised 1.2Already raised 1.2
billion for phase two.billion for phase two.
 To the right:To the right:
Hollywood andHollywood and
Highland station soHighland station so
far.far.
Construction of TunnelsConstruction of Tunnels
 Tunnels are 20’ inTunnels are 20’ in
diameter.diameter.
 They are parallelThey are parallel
and separatedand separated
about 20’ fromabout 20’ from
each other.each other.
 Varying depthsVarying depths
throughout projectthroughout project
from 50’ to 130’.from 50’ to 130’.
Tunnel Boring MachinesTunnel Boring Machines
 TBM’s are huge cylindricalTBM’s are huge cylindrical
machines that drill into themachines that drill into the
earth around 40’ per day.earth around 40’ per day.
 TBM’s on this project keepTBM’s on this project keep
pressure on the face and wallspressure on the face and walls
of the tunnel while installingof the tunnel while installing
tunnel liners to support thetunnel liners to support the
tunnel.tunnel.
 Different tunnel liners canDifferent tunnel liners can
accommodate specialaccommodate special
conditions.conditions.
 Under groundwater table thereUnder groundwater table there
will be secondary tunnel liners,will be secondary tunnel liners,
gaskets, and drainage systems.gaskets, and drainage systems.
Metro Tunnel DesignMetro Tunnel Design
 Metro design criteria uses two levels ofMetro design criteria uses two levels of
ground shaking hazard and fault offset:ground shaking hazard and fault offset:
the operating design earthquake (ODE),the operating design earthquake (ODE),
having a 50-percent probability ofhaving a 50-percent probability of
exceedance in 100 yearsexceedance in 100 years
 Maximum design earthquake (MDE),Maximum design earthquake (MDE),
having a 4-percent probability ofhaving a 4-percent probability of
exceedance in 100 yearsexceedance in 100 years
 Basically it is not feasible to design to lastBasically it is not feasible to design to last
over 100 years in this environment.over 100 years in this environment.
Through Two Active Fault Zones?Through Two Active Fault Zones?
 The tunnel alignment options in the CenturyThe tunnel alignment options in the Century
City/West Beverly Hills area cross two mappedCity/West Beverly Hills area cross two mapped
fault zones—the Santa Monica fault zone and thefault zones—the Santa Monica fault zone and the
West Beverly Hills Lineament (WBHL) fault zone.West Beverly Hills Lineament (WBHL) fault zone.
 Mitigate by minimizing area of tunnel thatMitigate by minimizing area of tunnel that
intersects faults.intersects faults.
 Make flexible tunnel liners and excavate a widerMake flexible tunnel liners and excavate a wider
tunnel by faults to allow for shear stress.tunnel by faults to allow for shear stress.
Exploration Plan Around Both Fault ZonesExploration Plan Around Both Fault Zones
 7 rotary-wash continuous core7 rotary-wash continuous core
boreholesboreholes
 49 hollow stem auger continuous49 hollow stem auger continuous
core boreholescore boreholes
 192 CPTs192 CPTs
 5 P-wave seismic reflection profiles5 P-wave seismic reflection profiles
 5 S-wave seismic reflection profiles5 S-wave seismic reflection profiles
 5 down hole suspension PS velocity5 down hole suspension PS velocity
measurementsmeasurements
Cannot Avoid FaultsCannot Avoid Faults
 The Santa Monica fault zone is capable ofThe Santa Monica fault zone is capable of
generating earthquakes in the magnitude rangegenerating earthquakes in the magnitude range
M6.9 to M7.2, with average surfaceM6.9 to M7.2, with average surface
displacements of approximately 3 to 6 feet.displacements of approximately 3 to 6 feet.
 A major event on the WBHL might be betweenA major event on the WBHL might be between
M6.4 (generally the lower end of the magnitudeM6.4 (generally the lower end of the magnitude
range for surface rupture) and M7.2, also withrange for surface rupture) and M7.2, also with
average surface displacements of up to 3 to 6average surface displacements of up to 3 to 6
feet, depending on the length of rupture on thefeet, depending on the length of rupture on the
northernmost portion of the Newport Inglewood-northernmost portion of the Newport Inglewood-
WBHL fault zone.WBHL fault zone.
 Designing for this maximum displacement wasDesigning for this maximum displacement was
not feasible, so the minimal cross sections arenot feasible, so the minimal cross sections are
crossing faults, repairs will be made when a faultcrossing faults, repairs will be made when a fault
ruptures.ruptures.
Liquefaction and SeismicLiquefaction and Seismic
SettlementSettlement
 Based on the magnitude of evaluatedBased on the magnitude of evaluated
liquefaction, a suitable mitigation will beliquefaction, a suitable mitigation will be
selected, either structural design, orselected, either structural design, or
ground improvement (such as deep soilground improvement (such as deep soil
mixing) or deep foundations to nonmixing) or deep foundations to non
liquefiable soil (such as drilled piles).liquefiable soil (such as drilled piles).
 Most of the project will be under the layersMost of the project will be under the layers
of threatening liquefaction so this does notof threatening liquefaction so this does not
pose a big threat.pose a big threat.
Hazardous Subsurface GasHazardous Subsurface Gas
OperationsOperations
 Measures will include the following forMeasures will include the following for
both tunnel and station operation:both tunnel and station operation:
 High volume ventilation systems withHigh volume ventilation systems with
back-up power sources.back-up power sources.
 Gas detection systems with alarms.Gas detection systems with alarms.
 Emergency ventilation triggered by theEmergency ventilation triggered by the
gas detection systems.gas detection systems.
 Automatic equipment shut-off.Automatic equipment shut-off.
 Maintenance and operations personnelMaintenance and operations personnel
trainingtraining
Tar Sand DisposalTar Sand Disposal
 Based on results, tar sands may alsoBased on results, tar sands may also
be transported to a facility wherebe transported to a facility where
they can be re-cycled andthey can be re-cycled and
incorporated into the asphaltincorporated into the asphalt
pavement manufacturing process.pavement manufacturing process.
 If not recyclable, they will go toIf not recyclable, they will go to anan
appropriate waste manifest to a localappropriate waste manifest to a local
landfill that accepts petroleum-landfill that accepts petroleum-
impacted soils.impacted soils.
Beverly Hills High SchoolBeverly Hills High School
 1. Tunneling can be safely carried out beneath the Beverly1. Tunneling can be safely carried out beneath the Beverly
Hills High School (BHHS) campus;Hills High School (BHHS) campus;
 2. Tunneling would not prevent future development of the2. Tunneling would not prevent future development of the
BHHS campus;BHHS campus;
 3. Tunneling would not impact the use of the BHHS campus3. Tunneling would not impact the use of the BHHS campus
as an emergency evacuation center;as an emergency evacuation center;
 4. Vibration and noise levels are within the FTA4. Vibration and noise levels are within the FTA
requirements and tunnel operation is not anticipated torequirements and tunnel operation is not anticipated to
have adverse impacts. The tunnel construction may causehave adverse impacts. The tunnel construction may cause
some low levels of noise and vibration for a day or two;some low levels of noise and vibration for a day or two;
 5. Tunneling can be constructed and operated safely in5. Tunneling can be constructed and operated safely in
gassy ground;gassy ground;
 6. Oil wells do not pose an unmitigable risk to tunneling.6. Oil wells do not pose an unmitigable risk to tunneling.
Should they be encountered, procedures will be in place forShould they be encountered, procedures will be in place for
their safe removal and reabandonment;their safe removal and reabandonment;
Beverly Hills High SchoolBeverly Hills High School
 7. In Century City, Constellation Boulevard is a viable7. In Century City, Constellation Boulevard is a viable
option for a station location, but Santa Monica Boulevard isoption for a station location, but Santa Monica Boulevard is
not due to unacceptable seismic risk;not due to unacceptable seismic risk;
 8. Tunneling through fault zones can be done safely;8. Tunneling through fault zones can be done safely;
 9. MTA's approach to risk management is correct;9. MTA's approach to risk management is correct;
 10. Further site investigations will be conducted and10. Further site investigations will be conducted and
measures will be implemented to reduce risks to levels thatmeasures will be implemented to reduce risks to levels that
are as low as reasonably practicable;are as low as reasonably practicable;
 11. MTA and its engineering consultants have expertise11. MTA and its engineering consultants have expertise
designing and building tunnels and subway stations in Losdesigning and building tunnels and subway stations in Los
Angeles; andAngeles; and
 12. The Constellation Station will attract more riders than12. The Constellation Station will attract more riders than
the station locations along Santa Monica Boulevard.the station locations along Santa Monica Boulevard.
In Recent NewsIn Recent News
 As of late 2014 Beverly Hills is stillAs of late 2014 Beverly Hills is still
trying to appeal the decision totrying to appeal the decision to
tunnel under BHHS, recruitingtunnel under BHHS, recruiting
students to make anti metro subwaystudents to make anti metro subway
films...films...
 The current ruling still stands andThe current ruling still stands and
plans have been made to bore underplans have been made to bore under
the high school.the high school.
Possible Routs Through Century CityPossible Routs Through Century City
SourcesSources
 http://www.metro.net/projects/westside/http://www.metro.net/projects/westside/
#constructionimpacts#constructionimpacts
 http://thesource.metro.net/2011/10/19/ehttp://thesource.metro.net/2011/10/19/e
xperts-speak-to-metro-board-about-xperts-speak-to-metro-board-about-
westside-subway-extension-seismic-westside-subway-extension-seismic-
issues-in-century-city-a-constellation-issues-in-century-city-a-constellation-
station-is-recommended/station-is-recommended/
 http://media.metro.net/board/Items/2012/05http://media.metro.net/board/Items/2012/05_

More Related Content

Viewers also liked

YOTG Hamburg - Hayley Ard - Dissolving Demographics
YOTG Hamburg - Hayley Ard - Dissolving DemographicsYOTG Hamburg - Hayley Ard - Dissolving Demographics
YOTG Hamburg - Hayley Ard - Dissolving DemographicsYear of the X
 
Robots & Robotics
Robots & RoboticsRobots & Robotics
Robots & RoboticsRajiv Manna
 
anti-virus
anti-virusanti-virus
anti-virusnandocas
 
How to maximize smart city & energy efficiency replication potential - commun...
How to maximize smart city & energy efficiency replication potential - commun...How to maximize smart city & energy efficiency replication potential - commun...
How to maximize smart city & energy efficiency replication potential - commun...Alec Walker-Love
 
Dignóstico de hepatites virais
Dignóstico de  hepatites viraisDignóstico de  hepatites virais
Dignóstico de hepatites viraisVitor Obara
 
Exercícios nova ortografia
Exercícios nova ortografia Exercícios nova ortografia
Exercícios nova ortografia Leticia Olivera
 
Doenças Auto Imunes - Imunologia
Doenças Auto Imunes - ImunologiaDoenças Auto Imunes - Imunologia
Doenças Auto Imunes - ImunologiaFisio Unipampa
 
Age loc me-science
Age loc me-scienceAge loc me-science
Age loc me-scienceLi Li
 
Emballage og transport beretning 2015
Emballage og transport   beretning 2015Emballage og transport   beretning 2015
Emballage og transport beretning 2015Helle Antvorskov
 
Tr collection 2017 1
Tr collection 2017 1Tr collection 2017 1
Tr collection 2017 1Şule Özaran
 
Tr collection012017 screen_01
Tr collection012017 screen_01Tr collection012017 screen_01
Tr collection012017 screen_01Gökhan TEKİN
 
Livrodemedicamentos 130205180446-phpapp02
Livrodemedicamentos 130205180446-phpapp02Livrodemedicamentos 130205180446-phpapp02
Livrodemedicamentos 130205180446-phpapp02Giovanna Fernandes
 

Viewers also liked (17)

YOTG Hamburg - Hayley Ard - Dissolving Demographics
YOTG Hamburg - Hayley Ard - Dissolving DemographicsYOTG Hamburg - Hayley Ard - Dissolving Demographics
YOTG Hamburg - Hayley Ard - Dissolving Demographics
 
Robots & Robotics
Robots & RoboticsRobots & Robotics
Robots & Robotics
 
anti-virus
anti-virusanti-virus
anti-virus
 
How to maximize smart city & energy efficiency replication potential - commun...
How to maximize smart city & energy efficiency replication potential - commun...How to maximize smart city & energy efficiency replication potential - commun...
How to maximize smart city & energy efficiency replication potential - commun...
 
Dignóstico de hepatites virais
Dignóstico de  hepatites viraisDignóstico de  hepatites virais
Dignóstico de hepatites virais
 
Exercícios nova ortografia
Exercícios nova ortografia Exercícios nova ortografia
Exercícios nova ortografia
 
Infix to postfix
Infix to postfixInfix to postfix
Infix to postfix
 
Doenças Auto Imunes - Imunologia
Doenças Auto Imunes - ImunologiaDoenças Auto Imunes - Imunologia
Doenças Auto Imunes - Imunologia
 
Age loc me-science
Age loc me-scienceAge loc me-science
Age loc me-science
 
cooking methods
cooking methodscooking methods
cooking methods
 
Emballage og transport beretning 2015
Emballage og transport   beretning 2015Emballage og transport   beretning 2015
Emballage og transport beretning 2015
 
Chap 11
Chap 11Chap 11
Chap 11
 
Food processing
Food processingFood processing
Food processing
 
Tr collection 2017 1
Tr collection 2017 1Tr collection 2017 1
Tr collection 2017 1
 
Tr collection012017 screen_01
Tr collection012017 screen_01Tr collection012017 screen_01
Tr collection012017 screen_01
 
Livrodemedicamentos 130205180446-phpapp02
Livrodemedicamentos 130205180446-phpapp02Livrodemedicamentos 130205180446-phpapp02
Livrodemedicamentos 130205180446-phpapp02
 
David schmidt port
David schmidt portDavid schmidt port
David schmidt port
 

Similar to Extension of Metro's Purple line.

Deep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over viewDeep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over viewR K DHIMAN
 
Copy of homeowner concerns regarding verizon data communications tower at 4...
Copy of homeowner concerns  regarding verizon data communications tower  at 4...Copy of homeowner concerns  regarding verizon data communications tower  at 4...
Copy of homeowner concerns regarding verizon data communications tower at 4...Avia Moon
 
Pillar design - a case study
Pillar design - a case studyPillar design - a case study
Pillar design - a case studyTIKESHWAR MAHTO
 
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...Make Mannan
 
A preview of soil behavior
A preview of soil behaviorA preview of soil behavior
A preview of soil behaviorShumei Zhou
 
Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016Travis Smith
 
"Factors Affecting the Design and Construction of High Capacity Minipiles"
"Factors Affecting the Design and Construction of High Capacity Minipiles""Factors Affecting the Design and Construction of High Capacity Minipiles"
"Factors Affecting the Design and Construction of High Capacity Minipiles"Remedy Geotechnics Ltd
 
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.Emeka Ngwobia
 
Pile foundation -sunil kumar mohapatra
Pile foundation -sunil kumar mohapatraPile foundation -sunil kumar mohapatra
Pile foundation -sunil kumar mohapatraSUNIL KUMAR MOHAPATRA
 
Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Abner Silva
 
SSCS Track Record
SSCS Track RecordSSCS Track Record
SSCS Track RecordAdam Tucker
 
Excavation eschenasy
Excavation eschenasyExcavation eschenasy
Excavation eschenasyq q
 

Similar to Extension of Metro's Purple line. (20)

Deep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over viewDeep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over view
 
Pillar design
Pillar designPillar design
Pillar design
 
Pillar design
Pillar designPillar design
Pillar design
 
Copy of homeowner concerns regarding verizon data communications tower at 4...
Copy of homeowner concerns  regarding verizon data communications tower  at 4...Copy of homeowner concerns  regarding verizon data communications tower  at 4...
Copy of homeowner concerns regarding verizon data communications tower at 4...
 
Pillar design
Pillar designPillar design
Pillar design
 
Pillar design - a case study
Pillar design - a case studyPillar design - a case study
Pillar design - a case study
 
Blast Design-2.pdf
Blast Design-2.pdfBlast Design-2.pdf
Blast Design-2.pdf
 
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
Soil exploration/Investigation method, purpose depth of exploration (Usefulse...
 
A preview of soil behavior
A preview of soil behaviorA preview of soil behavior
A preview of soil behavior
 
MINING AND HARD ROCK
MINING AND HARD ROCKMINING AND HARD ROCK
MINING AND HARD ROCK
 
Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016
 
"Factors Affecting the Design and Construction of High Capacity Minipiles"
"Factors Affecting the Design and Construction of High Capacity Minipiles""Factors Affecting the Design and Construction of High Capacity Minipiles"
"Factors Affecting the Design and Construction of High Capacity Minipiles"
 
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.
 
Pile foundation -sunil kumar mohapatra
Pile foundation -sunil kumar mohapatraPile foundation -sunil kumar mohapatra
Pile foundation -sunil kumar mohapatra
 
Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015Hybrid epb tunnelling in rio de janeiro 2015
Hybrid epb tunnelling in rio de janeiro 2015
 
Pillar design
Pillar designPillar design
Pillar design
 
SSCS Track Record
SSCS Track RecordSSCS Track Record
SSCS Track Record
 
Foundations seminar
Foundations seminarFoundations seminar
Foundations seminar
 
Excavation eschenasy
Excavation eschenasyExcavation eschenasy
Excavation eschenasy
 
Foundation Design of a Fixed Fuel Station (Case Study; Niger Delta Region of ...
Foundation Design of a Fixed Fuel Station (Case Study; Niger Delta Region of ...Foundation Design of a Fixed Fuel Station (Case Study; Niger Delta Region of ...
Foundation Design of a Fixed Fuel Station (Case Study; Niger Delta Region of ...
 

Recently uploaded

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 

Recently uploaded (20)

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 

Extension of Metro's Purple line.

  • 1. Extension of Metro’sExtension of Metro’s Purple LinePurple Line Presented By:Presented By: Eric ChristensonEric Christenson
  • 2. Engineering Challenges andEngineering Challenges and MitigationsMitigations  Building a subway under a major cityBuilding a subway under a major city that is already established.that is already established.  Sustaining a tunnel through twoSustaining a tunnel through two active fault zones.active fault zones.  Most of construction is under theMost of construction is under the ground water table.ground water table.  Area has scattered natural depositsArea has scattered natural deposits of tar, toxic gasses, and oil.of tar, toxic gasses, and oil.
  • 3.
  • 4. First, Some Fun FactsFirst, Some Fun Facts  Project started inProject started in November 2014.November 2014.  Largest public worksLargest public works project and programproject and program in the nation rightin the nation right now.now.  Already raised 1.2Already raised 1.2 billion for phase two.billion for phase two.  To the right:To the right: Hollywood andHollywood and Highland station soHighland station so far.far.
  • 5. Construction of TunnelsConstruction of Tunnels  Tunnels are 20’ inTunnels are 20’ in diameter.diameter.  They are parallelThey are parallel and separatedand separated about 20’ fromabout 20’ from each other.each other.  Varying depthsVarying depths throughout projectthroughout project from 50’ to 130’.from 50’ to 130’.
  • 6. Tunnel Boring MachinesTunnel Boring Machines  TBM’s are huge cylindricalTBM’s are huge cylindrical machines that drill into themachines that drill into the earth around 40’ per day.earth around 40’ per day.  TBM’s on this project keepTBM’s on this project keep pressure on the face and wallspressure on the face and walls of the tunnel while installingof the tunnel while installing tunnel liners to support thetunnel liners to support the tunnel.tunnel.  Different tunnel liners canDifferent tunnel liners can accommodate specialaccommodate special conditions.conditions.  Under groundwater table thereUnder groundwater table there will be secondary tunnel liners,will be secondary tunnel liners, gaskets, and drainage systems.gaskets, and drainage systems.
  • 7. Metro Tunnel DesignMetro Tunnel Design  Metro design criteria uses two levels ofMetro design criteria uses two levels of ground shaking hazard and fault offset:ground shaking hazard and fault offset: the operating design earthquake (ODE),the operating design earthquake (ODE), having a 50-percent probability ofhaving a 50-percent probability of exceedance in 100 yearsexceedance in 100 years  Maximum design earthquake (MDE),Maximum design earthquake (MDE), having a 4-percent probability ofhaving a 4-percent probability of exceedance in 100 yearsexceedance in 100 years  Basically it is not feasible to design to lastBasically it is not feasible to design to last over 100 years in this environment.over 100 years in this environment.
  • 8. Through Two Active Fault Zones?Through Two Active Fault Zones?  The tunnel alignment options in the CenturyThe tunnel alignment options in the Century City/West Beverly Hills area cross two mappedCity/West Beverly Hills area cross two mapped fault zones—the Santa Monica fault zone and thefault zones—the Santa Monica fault zone and the West Beverly Hills Lineament (WBHL) fault zone.West Beverly Hills Lineament (WBHL) fault zone.  Mitigate by minimizing area of tunnel thatMitigate by minimizing area of tunnel that intersects faults.intersects faults.  Make flexible tunnel liners and excavate a widerMake flexible tunnel liners and excavate a wider tunnel by faults to allow for shear stress.tunnel by faults to allow for shear stress.
  • 9.
  • 10. Exploration Plan Around Both Fault ZonesExploration Plan Around Both Fault Zones  7 rotary-wash continuous core7 rotary-wash continuous core boreholesboreholes  49 hollow stem auger continuous49 hollow stem auger continuous core boreholescore boreholes  192 CPTs192 CPTs  5 P-wave seismic reflection profiles5 P-wave seismic reflection profiles  5 S-wave seismic reflection profiles5 S-wave seismic reflection profiles  5 down hole suspension PS velocity5 down hole suspension PS velocity measurementsmeasurements
  • 11. Cannot Avoid FaultsCannot Avoid Faults  The Santa Monica fault zone is capable ofThe Santa Monica fault zone is capable of generating earthquakes in the magnitude rangegenerating earthquakes in the magnitude range M6.9 to M7.2, with average surfaceM6.9 to M7.2, with average surface displacements of approximately 3 to 6 feet.displacements of approximately 3 to 6 feet.  A major event on the WBHL might be betweenA major event on the WBHL might be between M6.4 (generally the lower end of the magnitudeM6.4 (generally the lower end of the magnitude range for surface rupture) and M7.2, also withrange for surface rupture) and M7.2, also with average surface displacements of up to 3 to 6average surface displacements of up to 3 to 6 feet, depending on the length of rupture on thefeet, depending on the length of rupture on the northernmost portion of the Newport Inglewood-northernmost portion of the Newport Inglewood- WBHL fault zone.WBHL fault zone.  Designing for this maximum displacement wasDesigning for this maximum displacement was not feasible, so the minimal cross sections arenot feasible, so the minimal cross sections are crossing faults, repairs will be made when a faultcrossing faults, repairs will be made when a fault ruptures.ruptures.
  • 12. Liquefaction and SeismicLiquefaction and Seismic SettlementSettlement  Based on the magnitude of evaluatedBased on the magnitude of evaluated liquefaction, a suitable mitigation will beliquefaction, a suitable mitigation will be selected, either structural design, orselected, either structural design, or ground improvement (such as deep soilground improvement (such as deep soil mixing) or deep foundations to nonmixing) or deep foundations to non liquefiable soil (such as drilled piles).liquefiable soil (such as drilled piles).  Most of the project will be under the layersMost of the project will be under the layers of threatening liquefaction so this does notof threatening liquefaction so this does not pose a big threat.pose a big threat.
  • 13. Hazardous Subsurface GasHazardous Subsurface Gas OperationsOperations  Measures will include the following forMeasures will include the following for both tunnel and station operation:both tunnel and station operation:  High volume ventilation systems withHigh volume ventilation systems with back-up power sources.back-up power sources.  Gas detection systems with alarms.Gas detection systems with alarms.  Emergency ventilation triggered by theEmergency ventilation triggered by the gas detection systems.gas detection systems.  Automatic equipment shut-off.Automatic equipment shut-off.  Maintenance and operations personnelMaintenance and operations personnel trainingtraining
  • 14. Tar Sand DisposalTar Sand Disposal  Based on results, tar sands may alsoBased on results, tar sands may also be transported to a facility wherebe transported to a facility where they can be re-cycled andthey can be re-cycled and incorporated into the asphaltincorporated into the asphalt pavement manufacturing process.pavement manufacturing process.  If not recyclable, they will go toIf not recyclable, they will go to anan appropriate waste manifest to a localappropriate waste manifest to a local landfill that accepts petroleum-landfill that accepts petroleum- impacted soils.impacted soils.
  • 15.
  • 16.
  • 17. Beverly Hills High SchoolBeverly Hills High School  1. Tunneling can be safely carried out beneath the Beverly1. Tunneling can be safely carried out beneath the Beverly Hills High School (BHHS) campus;Hills High School (BHHS) campus;  2. Tunneling would not prevent future development of the2. Tunneling would not prevent future development of the BHHS campus;BHHS campus;  3. Tunneling would not impact the use of the BHHS campus3. Tunneling would not impact the use of the BHHS campus as an emergency evacuation center;as an emergency evacuation center;  4. Vibration and noise levels are within the FTA4. Vibration and noise levels are within the FTA requirements and tunnel operation is not anticipated torequirements and tunnel operation is not anticipated to have adverse impacts. The tunnel construction may causehave adverse impacts. The tunnel construction may cause some low levels of noise and vibration for a day or two;some low levels of noise and vibration for a day or two;  5. Tunneling can be constructed and operated safely in5. Tunneling can be constructed and operated safely in gassy ground;gassy ground;  6. Oil wells do not pose an unmitigable risk to tunneling.6. Oil wells do not pose an unmitigable risk to tunneling. Should they be encountered, procedures will be in place forShould they be encountered, procedures will be in place for their safe removal and reabandonment;their safe removal and reabandonment;
  • 18. Beverly Hills High SchoolBeverly Hills High School  7. In Century City, Constellation Boulevard is a viable7. In Century City, Constellation Boulevard is a viable option for a station location, but Santa Monica Boulevard isoption for a station location, but Santa Monica Boulevard is not due to unacceptable seismic risk;not due to unacceptable seismic risk;  8. Tunneling through fault zones can be done safely;8. Tunneling through fault zones can be done safely;  9. MTA's approach to risk management is correct;9. MTA's approach to risk management is correct;  10. Further site investigations will be conducted and10. Further site investigations will be conducted and measures will be implemented to reduce risks to levels thatmeasures will be implemented to reduce risks to levels that are as low as reasonably practicable;are as low as reasonably practicable;  11. MTA and its engineering consultants have expertise11. MTA and its engineering consultants have expertise designing and building tunnels and subway stations in Losdesigning and building tunnels and subway stations in Los Angeles; andAngeles; and  12. The Constellation Station will attract more riders than12. The Constellation Station will attract more riders than the station locations along Santa Monica Boulevard.the station locations along Santa Monica Boulevard.
  • 19. In Recent NewsIn Recent News  As of late 2014 Beverly Hills is stillAs of late 2014 Beverly Hills is still trying to appeal the decision totrying to appeal the decision to tunnel under BHHS, recruitingtunnel under BHHS, recruiting students to make anti metro subwaystudents to make anti metro subway films...films...  The current ruling still stands andThe current ruling still stands and plans have been made to bore underplans have been made to bore under the high school.the high school.
  • 20. Possible Routs Through Century CityPossible Routs Through Century City
  • 21.