Chapter 1 Let's Write a Program

Let's write a simple program for operating a conveyor.
CAUTION
Click the ladder program area to enable operation. The title bar will turn blue.
Key operations are not enabled when the title bar and menu items are grayed out.
1 Click [Edit Ladder] button on the remote control.
2 Only the 'END' symbol is displayed on the screen.
An 'END' rung at the top of the program signals that no other programming steps exist.
3 Let's input a program.
Place the cursor in the position shown below.

Press the [F5] key.
In the 'Enter symbol' dialog box, enter X24 and click [OK].
Press the [F7] key.
In the 'Enter symbol' dialog box, enter Y1 and click [OK].
The program should look like this. Make sure that yours is correct.

4 Let's convert the program you have written into a form the PLC can recognize.
Press the [F4] key.
The background of the program is changed from gray to white.
The program has been converted.
If the program has not been input properly, a conversion error message is displayed.
Chapter 2 Let's Write Another Program

1 This is how you write the program on the second line.
Place the cursor at the head of the second line.
Press the [F5] key.
1
In the 'Enter symbol' dialog box, enter X20 and click [OK].
Press the [F7] key.
In the 'Enter symbol' dialog box, enter Y0 and click [OK].
The program should look like this. Make sure that yours is correct.

2 Next, write the program on the third line.
Place the cursor at the head of the third line.
Press the [F5] key.
In the 'Enter symbol' dialog box, enter X21 and click [OK].
Press the [F7] key.
In the 'Enter symbol' dialog box, enter Y2 and click [OK].
The program should look like this. Make sure that yours is correct.

3 'Convert' this program as you converted the first line.
Press the [F4] key.
The background of the program is changed from gray to white.
The program has been converted.
If the program has not been input properly, a conversion error message is displayed.
Chapter 3 Program Transfer to PLC
2
Let's write the program you have created to the PLC.
An actual PLC is not required because a virtual FX Series PLC is already in your computer.
1 The program can be written to the PLC by selecting "Online" - "Write to PLC" in the ladder
program area.
2 When the message 'Write completed. The simulation will start.' is displayed, select [OK].
The PLC starts to operate.
The 'RUN' indicator lamp should be lit in the I/O monitor display area of the PLC.
If it is not lit, the PLC is not operating.
Next, let's simulate the program you have created.
Chapter 4 Machine Operation

Let's use your program to control a virtual machine.
If the guidance window blocks out the machine, click the tutor on the remote control to hide the
window.
Once you have confirmed the movement, click it again to display the guidance.
1 When [PB1] (X20) on the operation panel is pressed, a part is supplied to the conveyor.
(If multiple parts are supplied, they get crushed!)
2 When [SW1] (X24) on the operation panel is turned ON, the conveyor moves forward.
3 Press [PB1] (X20) to supply a part to the moving conveyor.

Chapter 5 Edit the Program

How is the movement of the conveyor and the part?
You see the part falling on the floor. Let's solve the problem as follows.
1 Click [Edit Ladder] button on the remote control.
2 Add this contact to the first program.

Press the [Shift] + [F5] key.
In the 'Enter symbol' dialog box, enter X0 and click [OK].

3
3 Press the [F4] key to convert the program.
4 Write the program to the PLC selecting "Online" - "Write to PLC".
5 Make sure 'RUN' is indicated on the remote control.
6 Press [PB1] (X20) to supply a part to the conveyer.
Turn ON [SW1] (X24) to start the conveyor.
7 Is the part stopped at Sensor (X0)?
• Stopped >> Good! Controlled as planned.
• Does not stop >> Check the program.
• Conveyor does not move >> Check the program.
• Part stops some time after passing the sensor
>> Select "Tools" - "Options" on the simulation window and lower the speed of the
conveyer.
8 After the part stops, press [PB2] (X21) to push it onto the tray.

As you can see, a three-line program can control something practical.
You have learned basic programs in the previous exercises.
As you proceed in the learning software, you will learn how to control more complex operations
using these basic concepts.

4

More Related Content

Similar to Li354 plc lab 0

Tizen-based Samsung TV Web Simulator
Tizen-based Samsung TV Web SimulatorTizen-based Samsung TV Web Simulator
Tizen-based Samsung TV Web Simulator
Ryo Jin
 
Steps to create_p_fstatus_e_waybill_report
Steps to create_p_fstatus_e_waybill_reportSteps to create_p_fstatus_e_waybill_report
Steps to create_p_fstatus_e_waybill_report
Lokesh Modem
 
Gui builder
Gui builderGui builder
Gui builder
learnt
 
Click cell C3 on the Summary Report worksheet This column w.pdf
Click cell C3 on the Summary Report worksheet This column w.pdfClick cell C3 on the Summary Report worksheet This column w.pdf
Click cell C3 on the Summary Report worksheet This column w.pdf
ABHISANJEET
 
infoPLC_net_Chapter2.pdf
infoPLC_net_Chapter2.pdfinfoPLC_net_Chapter2.pdf
infoPLC_net_Chapter2.pdf
waklinux
 

Similar to Li354 plc lab 0 (20)

Control precedence program
Control precedence programControl precedence program
Control precedence program
 
Zelio soft
Zelio softZelio soft
Zelio soft
 
Plc fatek
Plc fatekPlc fatek
Plc fatek
 
Autocad Training Delhi
Autocad Training DelhiAutocad Training Delhi
Autocad Training Delhi
 
Auto CAD - 2D
Auto CAD - 2DAuto CAD - 2D
Auto CAD - 2D
 
Tizen-based Samsung TV Web Simulator
Tizen-based Samsung TV Web SimulatorTizen-based Samsung TV Web Simulator
Tizen-based Samsung TV Web Simulator
 
Steps to create_p_fstatus_e_waybill_report
Steps to create_p_fstatus_e_waybill_reportSteps to create_p_fstatus_e_waybill_report
Steps to create_p_fstatus_e_waybill_report
 
Visual Basic Calculator
Visual Basic CalculatorVisual Basic Calculator
Visual Basic Calculator
 
Gui builder
Gui builderGui builder
Gui builder
 
plc slc 500.pptx
plc slc 500.pptxplc slc 500.pptx
plc slc 500.pptx
 
Visual Logic User Guide
Visual Logic User GuideVisual Logic User Guide
Visual Logic User Guide
 
Bd1 gantumur mon e 1
Bd1 gantumur mon e 1Bd1 gantumur mon e 1
Bd1 gantumur mon e 1
 
Bd1 gantumur mon e 1
Bd1 gantumur mon e 1Bd1 gantumur mon e 1
Bd1 gantumur mon e 1
 
How to operate blue elephant cnc machinery
How to operate blue elephant cnc machineryHow to operate blue elephant cnc machinery
How to operate blue elephant cnc machinery
 
Drv11 power flex 755 basic start
Drv11 power flex 755 basic startDrv11 power flex 755 basic start
Drv11 power flex 755 basic start
 
Manual LogixPro
Manual LogixProManual LogixPro
Manual LogixPro
 
Click cell C3 on the Summary Report worksheet This column w.pdf
Click cell C3 on the Summary Report worksheet This column w.pdfClick cell C3 on the Summary Report worksheet This column w.pdf
Click cell C3 on the Summary Report worksheet This column w.pdf
 
Plc trilogi5 purdue
Plc trilogi5 purduePlc trilogi5 purdue
Plc trilogi5 purdue
 
infoPLC_net_Chapter2.pdf
infoPLC_net_Chapter2.pdfinfoPLC_net_Chapter2.pdf
infoPLC_net_Chapter2.pdf
 
Lab
LabLab
Lab
 

More from Enhmandah Hemeelee (20)

Lab 02
Lab 02Lab 02
Lab 02
 
Bd 01
Bd 01Bd 01
Bd 01
 
Semenar 02
Semenar 02Semenar 02
Semenar 02
 
Li354 plc lects 2011a
Li354  plc lects 2011aLi354  plc lects 2011a
Li354 plc lects 2011a
 
111 120
111 120111 120
111 120
 
101 110
101 110101 110
101 110
 
91 100
91 10091 100
91 100
 
81 90
81 9081 90
81 90
 
61 70
61 7061 70
61 70
 
51 60
51 6051 60
51 60
 
41 50
41 5041 50
41 50
 
31 40
31 4031 40
31 40
 
21 30
21 3021 30
21 30
 
11 20
11 2011 20
11 20
 
1 10
1 101 10
1 10
 
1 10
1 101 10
1 10
 
Bd1 munkhbayar
Bd1 munkhbayarBd1 munkhbayar
Bd1 munkhbayar
 
Bd1 gantumur eng e 1
Bd1 gantumur eng e 1Bd1 gantumur eng e 1
Bd1 gantumur eng e 1
 
Orchuulga
OrchuulgaOrchuulga
Orchuulga
 
бие даалт 1,2 бат өлзий
бие даалт 1,2  бат өлзийбие даалт 1,2  бат өлзий
бие даалт 1,2 бат өлзий
 

Recently uploaded

Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Victor Rentea
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 

Recently uploaded (20)

TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with Milvus
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Vector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxVector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptx
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 

Li354 plc lab 0

  • 1. Chapter 1 Let's Write a Program Let's write a simple program for operating a conveyor. CAUTION Click the ladder program area to enable operation. The title bar will turn blue. Key operations are not enabled when the title bar and menu items are grayed out. 1 Click [Edit Ladder] button on the remote control. 2 Only the 'END' symbol is displayed on the screen. An 'END' rung at the top of the program signals that no other programming steps exist. 3 Let's input a program. Place the cursor in the position shown below. Press the [F5] key. In the 'Enter symbol' dialog box, enter X24 and click [OK]. Press the [F7] key. In the 'Enter symbol' dialog box, enter Y1 and click [OK]. The program should look like this. Make sure that yours is correct. 4 Let's convert the program you have written into a form the PLC can recognize. Press the [F4] key. The background of the program is changed from gray to white. The program has been converted. If the program has not been input properly, a conversion error message is displayed. Chapter 2 Let's Write Another Program 1 This is how you write the program on the second line. Place the cursor at the head of the second line. Press the [F5] key. 1
  • 2. In the 'Enter symbol' dialog box, enter X20 and click [OK]. Press the [F7] key. In the 'Enter symbol' dialog box, enter Y0 and click [OK]. The program should look like this. Make sure that yours is correct. 2 Next, write the program on the third line. Place the cursor at the head of the third line. Press the [F5] key. In the 'Enter symbol' dialog box, enter X21 and click [OK]. Press the [F7] key. In the 'Enter symbol' dialog box, enter Y2 and click [OK]. The program should look like this. Make sure that yours is correct. 3 'Convert' this program as you converted the first line. Press the [F4] key. The background of the program is changed from gray to white. The program has been converted. If the program has not been input properly, a conversion error message is displayed. Chapter 3 Program Transfer to PLC 2
  • 3. Let's write the program you have created to the PLC. An actual PLC is not required because a virtual FX Series PLC is already in your computer. 1 The program can be written to the PLC by selecting "Online" - "Write to PLC" in the ladder program area. 2 When the message 'Write completed. The simulation will start.' is displayed, select [OK]. The PLC starts to operate. The 'RUN' indicator lamp should be lit in the I/O monitor display area of the PLC. If it is not lit, the PLC is not operating. Next, let's simulate the program you have created. Chapter 4 Machine Operation Let's use your program to control a virtual machine. If the guidance window blocks out the machine, click the tutor on the remote control to hide the window. Once you have confirmed the movement, click it again to display the guidance. 1 When [PB1] (X20) on the operation panel is pressed, a part is supplied to the conveyor. (If multiple parts are supplied, they get crushed!) 2 When [SW1] (X24) on the operation panel is turned ON, the conveyor moves forward. 3 Press [PB1] (X20) to supply a part to the moving conveyor. Chapter 5 Edit the Program How is the movement of the conveyor and the part? You see the part falling on the floor. Let's solve the problem as follows. 1 Click [Edit Ladder] button on the remote control. 2 Add this contact to the first program. Press the [Shift] + [F5] key. In the 'Enter symbol' dialog box, enter X0 and click [OK]. 3
  • 4. 3 Press the [F4] key to convert the program. 4 Write the program to the PLC selecting "Online" - "Write to PLC". 5 Make sure 'RUN' is indicated on the remote control. 6 Press [PB1] (X20) to supply a part to the conveyer. Turn ON [SW1] (X24) to start the conveyor. 7 Is the part stopped at Sensor (X0)? • Stopped >> Good! Controlled as planned. • Does not stop >> Check the program. • Conveyor does not move >> Check the program. • Part stops some time after passing the sensor >> Select "Tools" - "Options" on the simulation window and lower the speed of the conveyer. 8 After the part stops, press [PB2] (X21) to push it onto the tray. As you can see, a three-line program can control something practical. You have learned basic programs in the previous exercises. As you proceed in the learning software, you will learn how to control more complex operations using these basic concepts. 4