ANALISA HARGA SATUAN
PEKERJAAN PEMBANGUNAN RUMAH IBU INDRI
BREBES, JAWA TENGAH
TAHUN 2014
SNI 2013 PEKERJAAN PERSIAPAN
PS. 1 1.0000 m' Pengukuran dan Pemasangan Bouwplank
0.0120 m3 kayu 5/7x4m kayu hutan @ Rp 4,375,000.00 52,500.00
0.0200 kg paku biasa 2"-5" @ Rp 20,000.00 400.00
0.0070 m3 kayu papan 3/20 randu @ Rp 700,000.00 4,900.00
57,800.00
0.1000 OH tukang kayu @ Rp 65,000.00 6,500.00
0.1000 OH pekerja @ Rp 45,000.00 4,500.00
0.0100 OH kepala tukang @ Rp 75,000.00 750.00
0.0050 OH mandor @ Rp 85,000.00 425.00
12,175.00
69,975.00
SNI 2013 PEKERJAAN TANAH
T.1 1.0000 m3 Galian Tanah pondasi
0.7500 OH pekerja @ Rp 45,000.00 33,750.00
0.0250 OH mandor @ Rp 85,000.00 2,125.00
35,875.00
T.15 1.0000 m3 Urugan tanah
1.2000 m3 tanah urug @ Rp 120,000.00 144,000.00
0.2500 OH pekerja @ Rp 45,000.00 11,250.00
0.0250 OH mandor @ Rp 85,000.00 2,125.00
157,375.00
T.14 1.0000 m3 Urugan Pasir Hurug
1.2000 m3 pasir hurug @ Rp 140,000.00 168,000.00
0.3000 OH pekerja @ Rp 45,000.00 13,500.00
0.0100 OH mandor @ Rp 85,000.00 850.00
182,350.00
SNI 2013 PEKERJAAN PASANGAN DAN PLESTERAN
Pd.1 1.0000 m3 Pasang anstampeng batu belah
1.2000 m3 batu belah15/20 @ Rp 130,000.00 156,000.00
0.4320 m3 pasir hurug @ Rp 140,000.00 60,480.00
216,480.00
0.7800 OH pekerja @ Rp 45,000.00 35,100.00
0.3900 OH tukang batu @ Rp 60,000.00 23,400.00
0.0390 OH kepala tukang @ Rp 75,000.00 2,925.00
0.0390 OH mandor @ Rp 85,000.00 3,315.00
64,740.00
281,220.00
Pd.3 1.0000 m3 Pasang Pondasi Batu Kali
1.2000 m3 batu belah @ Rp 130,000.00 156,000.00
91.0000 kg semen / PC @ Rp 1,500.00 136,500.00
0.5840 m3 pasir pasang lokal @ Rp 170,000.00 99,280.00
391,780.00
1.5000 OH pekerja @ Rp 45,000.00 67,500.00
0.7500 OH tukang batu @ Rp 60,000.00 45,000.00
0.0750 OH kepala tukang @ Rp 75,000.00 5,625.00
0.0750 OH mandor @ Rp 85,000.00 6,375.00
124,500.00
516,280.00
PL.1 1.0000 m2 Plesteran dinding trasram 1 Pc : 3 Ps
6.5000 kg semen/PC @ Rp 1,500.00 9,750.00
0.0194 m3 pasir pasang @ Rp 170,000.00 3,298.00
13,048.00
0.4000 OH pekerja @ Rp 45,000.00 18,000.00
0.2000 OH tukang batu @ Rp 60,000.00 12,000.00
0.0200 OH kepala tukang @ Rp 75,000.00 1,500.00
0.0200 OH mandor @ Rp 85,000.00 1,700.00
33,200.00
46,248.00
D.5 1.0000 m2 Pasangan Batu Merah Tebal 1/2 bata, 1Pc : 8 Ps
75.0000 bh bata merah @ Rp 600.00 45,000.00
6.5000 kg semen / PC @ Rp 1,500.00 9,750.00
0.0500 m3 pasir pasang @ Rp 170,000.00 8,500.00
63,250.00
0.3000 OH pekerja @ Rp 45,000.00 13,500.00
0.1000 OH tukang batu @ Rp 60,000.00 6,000.00
0.0100 OH kepala tukang @ Rp 75,000.00 750.00
0.0150 OH mandor @ Rp 85,000.00 1,275.00
21,525.00
84,775.00
D.4 1.0000 m2 Pasangan Batu Merah Tebal 1/2 bata, 1Pc : 3 Ps
75.0000 bh bata merah @ Rp 600.00 45,000.00
14.3700 kg semen / PC @ Rp 1,500.00 21,555.00
0.0400 m3 pasir pasang @ Rp 170,000.00 6,800.00
73,355.00
0.3000 OH pekerja @ Rp 45,000.00 13,500.00
0.1000 OH tukang batu @ Rp 60,000.00 6,000.00
0.0100 OH kepala tukang @ Rp 75,000.00 750.00
0.0150 OH mandor @ Rp 85,000.00 1,275.00
21,525.00
94,880.00
D.5 1.0000 m2 Pasangan Batu alam
1.0000 m2 batu alam brownies @ Rp 130,000.00 130,000.00
14.3700 kg semen / PC @ Rp 1,500.00 21,555.00
0.0400 m3 pasir pasang @ Rp 170,000.00 6,800.00
158,355.00
0.3000 OH pekerja @ Rp 45,000.00 13,500.00
0.1000 OH tukang batu @ Rp 60,000.00 6,000.00
0.0100 OH kepala tukang @ Rp 75,000.00 750.00
0.0150 OH mandor @ Rp 85,000.00 1,275.00
21,525.00
179,880.00
PL.3 1.0000 m2 Plesteran dinding 1 Pc : 8 Ps
7.1860 kg semen/PC @ Rp 1,500.00 10,779.00
0.0280 m3 pasir pasang @ Rp 170,000.00 4,760.00
15,539.00
0.3000 OH pekerja @ Rp 45,000.00 13,500.00
0.1500 OH tukang batu @ Rp 60,000.00 9,000.00
0.0150 OH kepala tukang @ Rp 75,000.00 1,125.00
0.0150 OH mandor @ Rp 85,000.00 1,275.00
24,900.00
40,439.00
PL.2 1.0000 m2 Plesteran beton
6.5000 kg semen/PC @ Rp 1,500.00 9,750.00
0.0194 m3 pasir beton @ Rp 200,000.00 3,880.00
13,630.00
0.4000 OH pekerja @ Rp 45,000.00 18,000.00
0.2000 OH tukang batu @ Rp 60,000.00 12,000.00
0.0200 OH kepala tukang @ Rp 75,000.00 1,500.00
0.0200 OH mandor @ Rp 85,000.00 1,700.00
33,200.00
46,830.00
PL.4 1.0000 m2 Sponengan Sudut
0.0125 zak semen/PC @ Rp 1,500.00 18.75
0.0020 m3 pasir pasang @ Rp 170,000.00 340.00
358.75
0.0570 OH pekerja @ Rp 45,000.00 2,565.00
0.0380 OH tukang batu @ Rp 60,000.00 2,280.00
0.0038 OH kepala tukang @ Rp 75,000.00 285.00
0.0020 OH mandor @ Rp 85,000.00 170.00
5,300.00
5,658.75
SNI 2013 PEKERJAAN BETON BERTULANG
B.1 1.0000 m3 Beton 1pc : 3 ps : 5sp
0.8700 m3 batu pecah 2/3 @ Rp 130,000.00 113,100.00
5.4500 zak semen / PC @ Rp 1,500.00 8,175.00
0.5200 m3 pasir beton @ Rp 200,000.00 104,000.00
225,275.00
1.6500 OH pekerja @ Rp 45,000.00 74,250.00
0.2500 OH tukang batu @ Rp 60,000.00 15,000.00
0.0250 OH kepala tukang @ Rp 75,000.00 1,875.00
0.0800 OH mandor @ Rp 85,000.00 6,800.00
97,925.00
323,200.00
B.2 1.0000 m3 Beton 1pc : 2 ps : 3sp
0.8700 m3 batu pecah 1/2 @ Rp 140,000.00 121,800.00
5.8000 zak semen / PC @ Rp 1,500.00 8,700.00
0.5200 m3 pasir beton @ Rp 200,000.00 104,000.00
234,500.00
1.6500 OH pekerja @ Rp 45,000.00 74,250.00
0.2500 OH tukang batu @ Rp 60,000.00 15,000.00
0.0250 OH kepala tukang @ Rp 75,000.00 1,875.00
0.0800 OH mandor @ Rp 85,000.00 6,800.00
97,925.00
332,425.00
B.3 1.0000 m2 Begisting sloof
0.0360 m3 Kayu Bekisting @ Rp 1,500,000.00 54,000.00
0.3000 Kg Paku @ Rp 20,000.00 6,000.00
60,000.00
0.3000 OH Pekerja @ Rp 45,000.00 13,500.00
0.2600 OH Tukang Kayu @ Rp 65,000.00 16,900.00
0.0260 OH Kepala Tukang @ Rp 75,000.00 1,950.00
0.0050 OH Mandor @ Rp 85,000.00 425.00
32,775.00
92,775.00
B.4 1.0000 m2 Begisting Kolom + Steger
0.0380 m3 Kayu Bekisting @ Rp 1,500,000.00 57,000.00
0.4000 Kg Paku @ Rp 20,000.00 8,000.00
0.0175 m3 Kayu tahun @ Rp 2,200,000.00 38,500.00
2.0000 Btg. Dolken kayu tahun @ Rp 15,000.00 30,000.00
133,500.00
0.3000 OH Pekerja @ Rp 45,000.00 13,500.00
0.3300 OH Tukang Kayu @ Rp 65,000.00 21,450.00
0.0330 OH Kepala Tukang @ Rp 75,000.00 2,475.00
0.0060 OH Mandor @ Rp 85,000.00 510.00
37,935.00
171,435.00
B.5 1.0000 m2 Begisting Balok + Steger
0.0400 m3 Kayu Bekisting @ Rp 1,500,000.00 60,000.00
0.4000 Kg Paku @ Rp 20,000.00 8,000.00
0.0150 m3 Kayu tahun @ Rp 2,200,000.00 33,000.00
2.0000 Btg. Dolken kayu tahun @ Rp 15,000.00 30,000.00
131,000.00
0.3000 OH Pekerja @ Rp 45,000.00 13,500.00
0.3300 OH Tukang Kayu @ Rp 65,000.00 21,450.00
0.0330 OH Kepala Tukang @ Rp 75,000.00 2,475.00
0.0060 OH Mandor @ Rp 85,000.00 510.00
37,935.00
168,935.00
B.6 1.0000 m2 Begisting Plat Lantai + Steger
0.0360 m3 Kayu Bekisting @ Rp 1,500,000.00 54,000.00
0.4000 Kg Paku @ Rp 20,000.00 8,000.00
0.0100 m3 Kayu tahun @ Rp 2,200,000.00 22,000.00
2.5000 Btg. Dolken kayu tahun @ Rp 15,000.00 37,500.00
121,500.00
0.3000 OH Pekerja @ Rp 45,000.00 13,500.00
0.3300 OH Tukang Kayu @ Rp 65,000.00 21,450.00
0.0330 OH Kepala Tukang @ Rp 75,000.00 2,475.00
0.0060 OH Mandor @ Rp 85,000.00 510.00
37,935.00
159,435.00
B.7 1.0000 kg Pembesian
1.05 Kg Besi beton @ Rp 15,000.00 15,750.00
0.02 Kg Kawat Beton @ Rp 20,000.00 300.00
16,050.00
0.0070 OH Pekerja @ Rp 45,000.00 315.00
0.0070 OH Tukang Besi @ Rp 60,000.00 420.00
0.0007 OH Kepala Tukang @ Rp 75,000.00 52.50
0.0003 OH Mandor @ Rp 85,000.00 25.50
813.00
16,863.00
suppl. 1.0000 m3 Beton Footplat 80 x 80
1.0000 Beton 1:3:5 @ Rp 323,200.00 323,200.00
2.0000 Begesting @ Rp 92,775.00 185,550.00
156.0000 Pembesian @ Rp 16,863.00 2,630,628.00
3,139,378.00
suppl. 1.0000 m3 Beton Footplat 100 x 100
1.0000 Beton 1:3:5 @ Rp 323,200.00 323,200.00
3.0000 Begesting @ Rp 92,775.00 278,325.00
170.0000 Pembesian @ Rp 16,863.00 2,866,710.00
3,468,235.00
suppl. 1.0000 m3 Beton Footplat 120 x 120
1.0000 Beton 1:3:5 @ Rp 323,200.00 323,200.00
4.0000 Begesting @ Rp 92,775.00 371,100.00
180.0000 Pembesian @ Rp 16,863.00 3,035,340.00
3,729,640.00
suppl. 1.0000 m3 Beton Sloof 15 x 20
1.0000 Beton 1pc:2ps:3sp @ Rp 332,425.00 332,425.00
4.0000 Begesting sloof @ Rp 92,775.00 371,100.00
150.0000 Pembesian @ Rp 16,863.00 2,529,450.00
3,232,975.00
suppl. 1.0000 m3 Beton Sloof 15 x 30
1.0000 Beton 1pc:2ps:3sp @ Rp 332,425.00 332,425.00
6.0000 Begesting sloof @ Rp 92,775.00 556,650.00
160.0000 Pembesian @ Rp 16,863.00 2,698,080.00
3,587,155.00
suppl. 1.0000 m3 Beton Kolom 15 x 15
1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00
4.0000 Begesting + perancah @ Rp 171,435.00 685,740.00
129.0000 Pembesian @ Rp 16,863.00 2,175,327.00
3,193,492.00
suppl. 1.0000 m3 Beton Kolom 15 x 30
1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00
6.5000 Begesting + perancah @ Rp 171,435.00 1,114,327.50
150.0000 Pembesian @ Rp 16,863.00 2,529,450.00
3,976,202.50
suppl. 1.0000 m3 Beton Kolom 20 x 20
1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00
6.5000 Begesting + perancah @ Rp 171,435.00 1,114,327.50
140.0000 Pembesian @ Rp 16,863.00 2,360,820.00
3,807,572.50
suppl. 1.0000 m3 Beton Kolom 15 x 50
1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00
8.0000 Begesting + perancah @ Rp 171,435.00 1,371,480.00
180.0000 Pembesian @ Rp 16,863.00 3,035,340.00
4,739,245.00
suppl. 1.0000 m3 Beton Kolom 40 x 80
1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00
10.0000 Begesting + perancah @ Rp 171,435.00 1,714,350.00
200.0000 Pembesian @ Rp 16,863.00 3,372,600.00
5,419,375.00
suppl. 1.0000 m3 Beton Balok B1 15 x 50
1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00
9.0000 Begesting + steger @ Rp 168,935.00 1,520,415.00
175.0000 Pembesian @ Rp 16,863.00 2,951,025.00
4,803,865.00
suppl. 1.0000 m3 Beton Balok B2 15 x 30
1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00
7.0000 Begesting + steger @ Rp 168,935.00 1,182,545.00
160.0000 Pembesian @ Rp 16,863.00 2,698,080.00
4,213,050.00
suppl. 1.0000 m3 Beton Balok B3 15 x 40
1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00
8.0000 Begesting + steger @ Rp 168,935.00 1,351,480.00
165.0000 Pembesian @ Rp 16,863.00 2,782,395.00
4,466,300.00
suppl. 1.0000 m3 Beton Balok Bbd 15 x 30
1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00
7.0000 Begesting + steger @ Rp 168,935.00 1,182,545.00
165.0000 Pembesian @ Rp 16,863.00 2,782,395.00
4,297,365.00
suppl. 1.0000 m3 Beton Balok 15 x 20
1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00
4.0000 Begesting + steger @ Rp 168,935.00 675,740.00
140.0000 Pembesian @ Rp 16,863.00 2,360,820.00
3,368,985.00
suppl. 1.0000 m3 Beton Balok Lateu 15 x 15
1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00
4.0000 Begesting + perancah @ Rp 168,935.00 675,740.00
129.0000 Pembesian @ Rp 16,863.00 2,175,327.00
3,183,492.00
suppl. 1.0000 m3 Plat Lantai
1.0000 Beton 1:3:5 @ Rp 323,200.00 323,200.00
8.0000 Begesting + steger @ Rp 159,435.00 1,275,480.00
156.0000 Pembesian @ Rp 16,863.00 2,630,628.00
4,229,308.00
suppl. 1.0000 m3 Plat Tangga
1.0000 Beton 1:3:5 @ Rp 323,200.00 323,200.00
8.0000 Begesting + steger @ Rp 159,435.00 1,275,480.00
153.0000 Pembesian @ Rp 16,863.00 2,580,039.00
4,178,719.00
suppl. 1.0000 m3 Sun Shading
1.0000 Beton 1:3:5 @ Rp 323,200.00 323,200.00
5.0000 Begesting + steger @ Rp 159,435.00 797,175.00
120.0000 Pembesian @ Rp 16,863.00 2,023,560.00
3,143,935.00
SNI 2013 PEKERJAAN PLAFOND
LL.1 1.0000 m2 Pekerjaan Plafond Gypsum board, rangka metal furing
0.3810 lbr Gypsum board 9mm @ Rp 60,000.00 22,860.00
3.0000 m' metal furing 4x4 @ Rp 7,500.00 22,500.00
2.0000 m' kawat penggantung @ Rp 1,500.00 3,000.00
48,360.00
0.1800 OH Pekerja @ Rp 45,000.00 8,100.00
0.3200 OH Tukang Kayu @ Rp 65,000.00 20,800.00
0.0320 OH Kepala Tukang @ Rp 75,000.00 2,400.00
0.0765 OH Mandor @ Rp 85,000.00 6,502.50
37,802.50
86,162.50
LL.2 1.0000 m2 Pekerjaan Plafond kalsiboard, rangka metal furing
0.3810 lbr Kalciboard 4mm @ Rp 58,000.00 22,098.00
3.0000 m' metal furing 4x4 @ Rp 7,500.00 22,500.00
2.0000 m' kawat penggantung @ Rp 1,500.00 3,000.00
47,598.00
0.1800 OH Pekerja @ Rp 45,000.00 8,100.00
0.3200 OH Tukang Kayu @ Rp 65,000.00 20,800.00
0.0320 OH Kepala Tukang @ Rp 75,000.00 2,400.00
0.0765 OH Mandor @ Rp 85,000.00 6,502.50
37,802.50
85,400.50
LL.3 1.0000 m' Pasang List Profil Gypsum
1.0500 m' List profil gypsum 5 cm @ Rp 19,000.00 19,950.00
0.0100 Kg Paku @ Rp 20,000.00 200.00
20,150.00
0.0500 OH Pekerja @ Rp 45,000.00 2,250.00
0.0500 OH Tukang Kayu @ Rp 65,000.00 3,250.00
0.0050 OH Kepala Tukang @ Rp 75,000.00 375.00
0.0030 OH Mandor @ Rp 85,000.00 255.00
6,130.00
26,280.00
SNI 2013 PEKERJAAN ATAP
PA.1 1.0000 m2 Pasang Atap Genteng Keramik
9.0000 bh Genteng keramik M-Class @ Rp 9,000.00 81,000.00
0.1200 OH Pekerja @ Rp 45,000.00 5,400.00
0.0600 OH Tukang Kayu @ Rp 65,000.00 3,900.00
0.0060 OH Kepala Tukang @ Rp 75,000.00 450.00
0.0060 OH Mandor @ Rp 85,000.00 510.00
91,260.00
91,260.00
PA.2 1.0000 m' Pasang Listplank
1.0000 m' Listplank Kalsiplank @ Rp 12,000.00 12,000.00
0.0200 Kg Paku @ Rp 20,000.00 400.00
12,400.00
0.0500 OH Pekerja @ Rp 45,000.00 2,250.00
0.0500 OH Tukang Kayu @ Rp 65,000.00 3,250.00
0.0050 OH Kepala Tukang @ Rp 75,000.00 375.00
0.0030 OH Mandor @ Rp 85,000.00 255.00
6,130.00
18,530.00
SNI 2013 PEKERJAAN LANTAI DAN DINDING
L.1 1.0000 m2 Pasang Lantai Granite 60x60
1.0000 m2 Granite 60x60 @ Rp 420,500.00 420,500.00
9.8000 kg Semen PC @ Rp 1,500.00 14,700.00
0.0450 m3 Pasir pasang @ Rp 170,000.00 7,650.00
1.0000 kg Semen warna @ Rp 2,500.00 2,500.00
445,350.00
0.2500 OH Pekerja @ Rp 45,000.00 11,250.00
0.1200 OH Tukang Batu @ Rp 60,000.00 7,200.00
0.0120 OH Kepala Tukang @ Rp 75,000.00 900.00
0.0125 OH Mandor @ Rp 85,000.00 1,062.50
20,412.50
465,762.50
L.2 1.0000 m2 Pasang Lantai Keramik 60x60
3.5000 bh Keramik 60x60 @ Rp 21,000.00 73,500.00
9.8000 kg Semen PC @ Rp 1,500.00 14,700.00
0.0450 m3 Pasir pasang @ Rp 170,000.00 7,650.00
1.0000 kg Semen warna @ Rp 2,500.00 2,500.00
98,350.00
0.2500 OH Pekerja @ Rp 45,000.00 11,250.00
0.1200 OH Tukang Batu @ Rp 60,000.00 7,200.00
0.0120 OH Kepala Tukang @ Rp 75,000.00 900.00
0.0125 OH Mandor @ Rp 85,000.00 1,062.50
20,412.50
118,762.50
L.3 1.0000 m2 Pasang Lantai Keramik 30x30 rustic
25.0000 bh Keramik 30x30 rustic @ Rp 4,100.00 102,500.00
10.4000 kg Semen PC @ Rp 1,500.00 15,600.00
0.0450 m3 Pasir pasang @ Rp 170,000.00 7,650.00
1.6200 kg Semen warna @ Rp 2,500.00 4,050.00
129,800.00
0.2500 OH Pekerja @ Rp 45,000.00 11,250.00
0.1200 OH Tukang Batu @ Rp 60,000.00 7,200.00
0.0120 OH Kepala Tukang @ Rp 75,000.00 900.00
0.0125 OH Mandor @ Rp 85,000.00 1,062.50
20,412.50
150,212.50
L.4 1.0000 m2 Pasang Dinding Keramik 30x40
20.0000 bh Keramik 30x40 @ Rp 9,000.00 180,000.00
10.4000 kg Semen PC @ Rp 1,500.00 15,600.00
0.0450 m3 Pasir pasang @ Rp 170,000.00 7,650.00
1.4000 kg Semen warna @ Rp 2,500.00 3,500.00
206,750.00
0.2500 OH Pekerja @ Rp 45,000.00 11,250.00
0.1200 OH Tukang Batu @ Rp 60,000.00 7,200.00
0.0120 OH Kepala Tukang @ Rp 75,000.00 900.00
0.0125 OH Mandor @ Rp 85,000.00 1,062.50
20,412.50
227,162.50
L.5 1.0000 m' Pasang Border Keramik 10x30
5.0000 bh Keramik 10x30 @ Rp 10,000.00 50,000.00
3.0000 kg Semen PC @ Rp 1,500.00 4,500.00
0.0210 m3 Pasir pasang @ Rp 170,000.00 3,570.00
0.5000 kg Semen warna @ Rp 2,500.00 1,250.00
59,320.00
0.0500 OH Pekerja @ Rp 45,000.00 2,250.00
0.0500 OH Tukang Batu @ Rp 60,000.00 3,000.00
0.0050 OH Kepala Tukang @ Rp 75,000.00 375.00
0.0050 OH Mandor @ Rp 85,000.00 425.00
6,050.00
65,370.00
L.6 1.0000 m2 Pasang Lantai Keramik 30x30
25.0000 bh Keramik 20x20 @ Rp 4,000.00 100,000.00
10.4000 kg Semen PC @ Rp 1,500.00 15,600.00
0.0450 m3 Pasir pasang @ Rp 170,000.00 7,650.00
1.6200 kg Semen warna @ Rp 2,500.00 4,050.00
127,300.00
0.2500 OH Pekerja @ Rp 45,000.00 11,250.00
0.1200 OH Tukang Batu @ Rp 60,000.00 7,200.00
0.0120 OH Kepala Tukang @ Rp 75,000.00 900.00
0.0125 OH Mandor @ Rp 85,000.00 1,062.50
20,412.50
147,712.50
L.7 1.0000 m' Plint keramik 10x60
1.6667 bh Plint granite 10x60 @ Rp 15,000.00 25,000.50
3.0000 kg Semen PC @ Rp 1,500.00 4,500.00
0.0210 m3 Pasir pasang @ Rp 170,000.00 3,570.00
0.5000 kg Semen warna @ Rp 2,500.00 1,250.00
34,320.50
0.0500 OH Pekerja @ Rp 45,000.00 2,250.00
0.0500 OH Tukang Batu @ Rp 60,000.00 3,000.00
0.0050 OH Kepala Tukang @ Rp 75,000.00 375.00
0.0050 OH Mandor @ Rp 85,000.00 425.00
6,050.00
40,370.50
L.8 1.0000 m3 Rabat beton di bawah lantai & keliling bangunan
9.3000 kg Semen PC @ Rp 1,500.00 13,950.00
1.2000 m3 Pasir Pasang @ Rp 170,000.00 204,000.00
217,950.00
0.4000 OH Pekerja @ Rp 45,000.00 18,000.00
0.1500 OH Tukang Batu @ Rp 60,000.00 9,000.00
0.0150 OH Kepala Tukang @ Rp 75,000.00 1,125.00
0.0200 OH Mandor @ Rp 85,000.00 1,700.00
29,825.00
247,775.00
L.9 1.0000 m3 Rabat beton Carport
9.3000 kg Semen PC @ Rp 1,500.00 13,950.00
1.2000 m3 Pasir Pasang @ Rp 170,000.00 204,000.00
10.0000 kg Koral Warna @ Rp 4,500.00 45,000.00
262,950.00
0.4000 OH Pekerja @ Rp 45,000.00 18,000.00
0.1500 OH Tukang Batu @ Rp 60,000.00 9,000.00
0.0150 OH Kepala Tukang @ Rp 75,000.00 1,125.00
0.0200 OH Mandor @ Rp 85,000.00 1,700.00
29,825.00
292,775.00
L.9 1.0000 m2 Pasang Batu Candi 60x60
1.2000 m3 Pasir Pasang @ Rp 170,000.00 204,000.00
1.0000 m2 Batu Candi 60x60 @ Rp 4,500.00 4,500.00
208,500.00
0.4000 OH Pekerja @ Rp 45,000.00 18,000.00
0.1500 OH Tukang Batu @ Rp 60,000.00 9,000.00
0.0150 OH Kepala Tukang @ Rp 75,000.00 1,125.00
0.0200 OH Mandor @ Rp 85,000.00 1,700.00
29,825.00
238,325.00
L.10 1.0000 m' Pasang Stepnoizing tangga 10 x 20 cm
5.0000 bh keramik 10/20 @ Rp 10,300.00 51,500.00
9.8000 kg pc @ Rp 1,500.00 14,700.00
0.0450 m3 pasir pasang @ Rp 170,000.00 7,650.00
1.3000 kg semen warna @ Rp 2,500.00 3,250.00
77,100.00
0.2500 OH pekerja @ Rp 45,000.00 11,250.00
0.1200 OH tukang batu @ Rp 60,000.00 7,200.00
0.0120 OH kepala tukang @ Rp 75,000.00 900.00
0.0125 OH mandor @ Rp 85,000.00 1,062.50
20,412.50
97,512.50
SNI 2013 PEKERJAAN SANITAIR DAN PEMIPAAN
SA.1 1.0000 m' Pasang saluran Got U diameter 30cm
1.0000 bh Got U 30cm @ Rp 55,000.00 55,000.00
0.2300 m3 Galian tanah @ Rp 35,875.00 8,251.25
0.0500 m3 Pasir urug @ Rp 140,000.00 7,000.00
0.0308 m3 Pas. Bt. Bata rollag @ Rp 75,000.00 2,310.00
0.1000 m2 Pas. bt.belah 1:6 @ Rp 516,280.00 51,628.00
0.0360 m3 Beton tutup @ Rp 4,229,308.00 152,255.09
0.0750 upah meletakkan got @ Rp 45,000.00 3,375.00
279,819.34
SNI 2013 PEKERJAAN PENGECATAN
C.1 1.0000 m2 Mengecat tembok luar ruangan
0.3500 kg cat tembok eksterior @ Rp 100,000.00 35,000.00
0.2250 kg plamur @ Rp 12,000.00 2,700.00
0.2500 lbr amplas @ Rp 3,000.00 750.00
0.0750 OH tukang cat @ Rp 60,000.00 4,500.00
0.0075 OH tukang kepala @ Rp 75,000.00 562.50
0.0500 OH pekerja @ Rp 45,000.00 2,250.00
0.0025 OH mandor @ Rp 85,000.00 212.50
45,975.00
C.2 1.0000 m2 Mengecat tembok dalam ruangan
0.3500 kg cat tembok interior @ Rp 20,000.00 7,000.00
0.2250 kg plamur @ Rp 12,000.00 2,700.00
0.2500 lbr amplas @ Rp 3,000.00 750.00
0.0750 OH tukang cat @ Rp 60,000.00 4,500.00
0.0075 OH tukang kepala @ Rp 75,000.00 562.50
0.0500 OH pekerja @ Rp 45,000.00 2,250.00
0.0025 OH mandor @ Rp 85,000.00 212.50
17,975.00
C.3 1.0000 m2 Mengecat Plafond
0.3600 Kg Cat Tembok interior @ Rp 20,000.00 7,200.00
0.0200 OH Pekerja @ Rp 45,000.00 900.00
0.0630 OH Tukang Cat @ Rp 60,000.00 3,780.00
0.0063 OH Kepala Tukang @ Rp 75,000.00 472.50
0.0025 OH Mandor @ Rp 85,000.00 212.50
12,565.00
C.4 1.0000 m2 Melitur Kayu 3x
0.3600 ltr Plitur Kayu @ Rp 39,000.00 14,040.00
0.0200 OH Pekerja @ Rp 45,000.00 900.00
0.0630 OH Tukang Cat @ Rp 60,000.00 3,780.00
0.0063 OH Kepala Tukang @ Rp 75,000.00 472.50
0.0025 OH Mandor @ Rp 85,000.00 212.50
19,405.00
C.5 1.0000 m2 Waterprofing atap dag beton
0.3600 Kg waterprofing No Drop @ Rp 35,000.00 12,600.00
0.0200 OH Pekerja @ Rp 45,000.00 900.00
0.0630 OH Tukang Cat @ Rp 60,000.00 3,780.00
0.0063 OH Kepala Tukang @ Rp 75,000.00 472.50
0.0025 OH Mandor @ Rp 85,000.00 212.50
17,965.00

More Related Content

Similar to Analisa

Similar to Analisa (7)

Daftarbahanbangunan
Daftarbahanbangunan Daftarbahanbangunan
Daftarbahanbangunan
 
Harga satuan maluku
Harga satuan malukuHarga satuan maluku
Harga satuan maluku
 
Rehab kantor pariwsata
Rehab kantor pariwsataRehab kantor pariwsata
Rehab kantor pariwsata
 
Data penawaran subur jaya
Data penawaran subur jayaData penawaran subur jaya
Data penawaran subur jaya
 
Tugas
TugasTugas
Tugas
 
BQ RSJ TAHAP 1 TA 2022 Revisi 21 Februari 2022.pdf
BQ RSJ  TAHAP 1 TA 2022 Revisi  21 Februari 2022.pdfBQ RSJ  TAHAP 1 TA 2022 Revisi  21 Februari 2022.pdf
BQ RSJ TAHAP 1 TA 2022 Revisi 21 Februari 2022.pdf
 
7. m. darul ikhsan pematang duku oe
7. m. darul ikhsan pematang duku oe7. m. darul ikhsan pematang duku oe
7. m. darul ikhsan pematang duku oe
 

Recently uploaded

Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Recently uploaded (20)

UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 

Analisa

  • 1. ANALISA HARGA SATUAN PEKERJAAN PEMBANGUNAN RUMAH IBU INDRI BREBES, JAWA TENGAH TAHUN 2014 SNI 2013 PEKERJAAN PERSIAPAN PS. 1 1.0000 m' Pengukuran dan Pemasangan Bouwplank 0.0120 m3 kayu 5/7x4m kayu hutan @ Rp 4,375,000.00 52,500.00 0.0200 kg paku biasa 2"-5" @ Rp 20,000.00 400.00 0.0070 m3 kayu papan 3/20 randu @ Rp 700,000.00 4,900.00 57,800.00 0.1000 OH tukang kayu @ Rp 65,000.00 6,500.00 0.1000 OH pekerja @ Rp 45,000.00 4,500.00 0.0100 OH kepala tukang @ Rp 75,000.00 750.00 0.0050 OH mandor @ Rp 85,000.00 425.00 12,175.00 69,975.00 SNI 2013 PEKERJAAN TANAH T.1 1.0000 m3 Galian Tanah pondasi 0.7500 OH pekerja @ Rp 45,000.00 33,750.00 0.0250 OH mandor @ Rp 85,000.00 2,125.00 35,875.00 T.15 1.0000 m3 Urugan tanah 1.2000 m3 tanah urug @ Rp 120,000.00 144,000.00 0.2500 OH pekerja @ Rp 45,000.00 11,250.00 0.0250 OH mandor @ Rp 85,000.00 2,125.00 157,375.00 T.14 1.0000 m3 Urugan Pasir Hurug 1.2000 m3 pasir hurug @ Rp 140,000.00 168,000.00 0.3000 OH pekerja @ Rp 45,000.00 13,500.00 0.0100 OH mandor @ Rp 85,000.00 850.00 182,350.00 SNI 2013 PEKERJAAN PASANGAN DAN PLESTERAN Pd.1 1.0000 m3 Pasang anstampeng batu belah 1.2000 m3 batu belah15/20 @ Rp 130,000.00 156,000.00 0.4320 m3 pasir hurug @ Rp 140,000.00 60,480.00 216,480.00 0.7800 OH pekerja @ Rp 45,000.00 35,100.00 0.3900 OH tukang batu @ Rp 60,000.00 23,400.00 0.0390 OH kepala tukang @ Rp 75,000.00 2,925.00 0.0390 OH mandor @ Rp 85,000.00 3,315.00 64,740.00 281,220.00 Pd.3 1.0000 m3 Pasang Pondasi Batu Kali 1.2000 m3 batu belah @ Rp 130,000.00 156,000.00 91.0000 kg semen / PC @ Rp 1,500.00 136,500.00 0.5840 m3 pasir pasang lokal @ Rp 170,000.00 99,280.00 391,780.00 1.5000 OH pekerja @ Rp 45,000.00 67,500.00 0.7500 OH tukang batu @ Rp 60,000.00 45,000.00 0.0750 OH kepala tukang @ Rp 75,000.00 5,625.00 0.0750 OH mandor @ Rp 85,000.00 6,375.00 124,500.00 516,280.00 PL.1 1.0000 m2 Plesteran dinding trasram 1 Pc : 3 Ps 6.5000 kg semen/PC @ Rp 1,500.00 9,750.00 0.0194 m3 pasir pasang @ Rp 170,000.00 3,298.00 13,048.00 0.4000 OH pekerja @ Rp 45,000.00 18,000.00 0.2000 OH tukang batu @ Rp 60,000.00 12,000.00
  • 2. 0.0200 OH kepala tukang @ Rp 75,000.00 1,500.00 0.0200 OH mandor @ Rp 85,000.00 1,700.00 33,200.00 46,248.00 D.5 1.0000 m2 Pasangan Batu Merah Tebal 1/2 bata, 1Pc : 8 Ps 75.0000 bh bata merah @ Rp 600.00 45,000.00 6.5000 kg semen / PC @ Rp 1,500.00 9,750.00 0.0500 m3 pasir pasang @ Rp 170,000.00 8,500.00 63,250.00 0.3000 OH pekerja @ Rp 45,000.00 13,500.00 0.1000 OH tukang batu @ Rp 60,000.00 6,000.00 0.0100 OH kepala tukang @ Rp 75,000.00 750.00 0.0150 OH mandor @ Rp 85,000.00 1,275.00 21,525.00 84,775.00 D.4 1.0000 m2 Pasangan Batu Merah Tebal 1/2 bata, 1Pc : 3 Ps 75.0000 bh bata merah @ Rp 600.00 45,000.00 14.3700 kg semen / PC @ Rp 1,500.00 21,555.00 0.0400 m3 pasir pasang @ Rp 170,000.00 6,800.00 73,355.00 0.3000 OH pekerja @ Rp 45,000.00 13,500.00 0.1000 OH tukang batu @ Rp 60,000.00 6,000.00 0.0100 OH kepala tukang @ Rp 75,000.00 750.00 0.0150 OH mandor @ Rp 85,000.00 1,275.00 21,525.00 94,880.00 D.5 1.0000 m2 Pasangan Batu alam 1.0000 m2 batu alam brownies @ Rp 130,000.00 130,000.00 14.3700 kg semen / PC @ Rp 1,500.00 21,555.00 0.0400 m3 pasir pasang @ Rp 170,000.00 6,800.00 158,355.00 0.3000 OH pekerja @ Rp 45,000.00 13,500.00 0.1000 OH tukang batu @ Rp 60,000.00 6,000.00 0.0100 OH kepala tukang @ Rp 75,000.00 750.00 0.0150 OH mandor @ Rp 85,000.00 1,275.00 21,525.00 179,880.00 PL.3 1.0000 m2 Plesteran dinding 1 Pc : 8 Ps 7.1860 kg semen/PC @ Rp 1,500.00 10,779.00 0.0280 m3 pasir pasang @ Rp 170,000.00 4,760.00 15,539.00 0.3000 OH pekerja @ Rp 45,000.00 13,500.00 0.1500 OH tukang batu @ Rp 60,000.00 9,000.00 0.0150 OH kepala tukang @ Rp 75,000.00 1,125.00 0.0150 OH mandor @ Rp 85,000.00 1,275.00 24,900.00 40,439.00 PL.2 1.0000 m2 Plesteran beton 6.5000 kg semen/PC @ Rp 1,500.00 9,750.00 0.0194 m3 pasir beton @ Rp 200,000.00 3,880.00 13,630.00 0.4000 OH pekerja @ Rp 45,000.00 18,000.00 0.2000 OH tukang batu @ Rp 60,000.00 12,000.00 0.0200 OH kepala tukang @ Rp 75,000.00 1,500.00 0.0200 OH mandor @ Rp 85,000.00 1,700.00 33,200.00 46,830.00 PL.4 1.0000 m2 Sponengan Sudut 0.0125 zak semen/PC @ Rp 1,500.00 18.75 0.0020 m3 pasir pasang @ Rp 170,000.00 340.00 358.75 0.0570 OH pekerja @ Rp 45,000.00 2,565.00 0.0380 OH tukang batu @ Rp 60,000.00 2,280.00 0.0038 OH kepala tukang @ Rp 75,000.00 285.00 0.0020 OH mandor @ Rp 85,000.00 170.00
  • 3. 5,300.00 5,658.75 SNI 2013 PEKERJAAN BETON BERTULANG B.1 1.0000 m3 Beton 1pc : 3 ps : 5sp 0.8700 m3 batu pecah 2/3 @ Rp 130,000.00 113,100.00 5.4500 zak semen / PC @ Rp 1,500.00 8,175.00 0.5200 m3 pasir beton @ Rp 200,000.00 104,000.00 225,275.00 1.6500 OH pekerja @ Rp 45,000.00 74,250.00 0.2500 OH tukang batu @ Rp 60,000.00 15,000.00 0.0250 OH kepala tukang @ Rp 75,000.00 1,875.00 0.0800 OH mandor @ Rp 85,000.00 6,800.00 97,925.00 323,200.00 B.2 1.0000 m3 Beton 1pc : 2 ps : 3sp 0.8700 m3 batu pecah 1/2 @ Rp 140,000.00 121,800.00 5.8000 zak semen / PC @ Rp 1,500.00 8,700.00 0.5200 m3 pasir beton @ Rp 200,000.00 104,000.00 234,500.00 1.6500 OH pekerja @ Rp 45,000.00 74,250.00 0.2500 OH tukang batu @ Rp 60,000.00 15,000.00 0.0250 OH kepala tukang @ Rp 75,000.00 1,875.00 0.0800 OH mandor @ Rp 85,000.00 6,800.00 97,925.00 332,425.00 B.3 1.0000 m2 Begisting sloof 0.0360 m3 Kayu Bekisting @ Rp 1,500,000.00 54,000.00 0.3000 Kg Paku @ Rp 20,000.00 6,000.00 60,000.00 0.3000 OH Pekerja @ Rp 45,000.00 13,500.00 0.2600 OH Tukang Kayu @ Rp 65,000.00 16,900.00 0.0260 OH Kepala Tukang @ Rp 75,000.00 1,950.00 0.0050 OH Mandor @ Rp 85,000.00 425.00 32,775.00 92,775.00 B.4 1.0000 m2 Begisting Kolom + Steger 0.0380 m3 Kayu Bekisting @ Rp 1,500,000.00 57,000.00 0.4000 Kg Paku @ Rp 20,000.00 8,000.00 0.0175 m3 Kayu tahun @ Rp 2,200,000.00 38,500.00 2.0000 Btg. Dolken kayu tahun @ Rp 15,000.00 30,000.00 133,500.00 0.3000 OH Pekerja @ Rp 45,000.00 13,500.00 0.3300 OH Tukang Kayu @ Rp 65,000.00 21,450.00 0.0330 OH Kepala Tukang @ Rp 75,000.00 2,475.00 0.0060 OH Mandor @ Rp 85,000.00 510.00 37,935.00 171,435.00 B.5 1.0000 m2 Begisting Balok + Steger 0.0400 m3 Kayu Bekisting @ Rp 1,500,000.00 60,000.00 0.4000 Kg Paku @ Rp 20,000.00 8,000.00 0.0150 m3 Kayu tahun @ Rp 2,200,000.00 33,000.00 2.0000 Btg. Dolken kayu tahun @ Rp 15,000.00 30,000.00 131,000.00 0.3000 OH Pekerja @ Rp 45,000.00 13,500.00 0.3300 OH Tukang Kayu @ Rp 65,000.00 21,450.00 0.0330 OH Kepala Tukang @ Rp 75,000.00 2,475.00 0.0060 OH Mandor @ Rp 85,000.00 510.00 37,935.00 168,935.00 B.6 1.0000 m2 Begisting Plat Lantai + Steger 0.0360 m3 Kayu Bekisting @ Rp 1,500,000.00 54,000.00 0.4000 Kg Paku @ Rp 20,000.00 8,000.00 0.0100 m3 Kayu tahun @ Rp 2,200,000.00 22,000.00
  • 4. 2.5000 Btg. Dolken kayu tahun @ Rp 15,000.00 37,500.00 121,500.00 0.3000 OH Pekerja @ Rp 45,000.00 13,500.00 0.3300 OH Tukang Kayu @ Rp 65,000.00 21,450.00 0.0330 OH Kepala Tukang @ Rp 75,000.00 2,475.00 0.0060 OH Mandor @ Rp 85,000.00 510.00 37,935.00 159,435.00 B.7 1.0000 kg Pembesian 1.05 Kg Besi beton @ Rp 15,000.00 15,750.00 0.02 Kg Kawat Beton @ Rp 20,000.00 300.00 16,050.00 0.0070 OH Pekerja @ Rp 45,000.00 315.00 0.0070 OH Tukang Besi @ Rp 60,000.00 420.00 0.0007 OH Kepala Tukang @ Rp 75,000.00 52.50 0.0003 OH Mandor @ Rp 85,000.00 25.50 813.00 16,863.00 suppl. 1.0000 m3 Beton Footplat 80 x 80 1.0000 Beton 1:3:5 @ Rp 323,200.00 323,200.00 2.0000 Begesting @ Rp 92,775.00 185,550.00 156.0000 Pembesian @ Rp 16,863.00 2,630,628.00 3,139,378.00 suppl. 1.0000 m3 Beton Footplat 100 x 100 1.0000 Beton 1:3:5 @ Rp 323,200.00 323,200.00 3.0000 Begesting @ Rp 92,775.00 278,325.00 170.0000 Pembesian @ Rp 16,863.00 2,866,710.00 3,468,235.00 suppl. 1.0000 m3 Beton Footplat 120 x 120 1.0000 Beton 1:3:5 @ Rp 323,200.00 323,200.00 4.0000 Begesting @ Rp 92,775.00 371,100.00 180.0000 Pembesian @ Rp 16,863.00 3,035,340.00 3,729,640.00 suppl. 1.0000 m3 Beton Sloof 15 x 20 1.0000 Beton 1pc:2ps:3sp @ Rp 332,425.00 332,425.00 4.0000 Begesting sloof @ Rp 92,775.00 371,100.00 150.0000 Pembesian @ Rp 16,863.00 2,529,450.00 3,232,975.00 suppl. 1.0000 m3 Beton Sloof 15 x 30 1.0000 Beton 1pc:2ps:3sp @ Rp 332,425.00 332,425.00 6.0000 Begesting sloof @ Rp 92,775.00 556,650.00 160.0000 Pembesian @ Rp 16,863.00 2,698,080.00 3,587,155.00 suppl. 1.0000 m3 Beton Kolom 15 x 15 1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00 4.0000 Begesting + perancah @ Rp 171,435.00 685,740.00 129.0000 Pembesian @ Rp 16,863.00 2,175,327.00 3,193,492.00 suppl. 1.0000 m3 Beton Kolom 15 x 30 1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00 6.5000 Begesting + perancah @ Rp 171,435.00 1,114,327.50 150.0000 Pembesian @ Rp 16,863.00 2,529,450.00 3,976,202.50 suppl. 1.0000 m3 Beton Kolom 20 x 20 1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00 6.5000 Begesting + perancah @ Rp 171,435.00 1,114,327.50 140.0000 Pembesian @ Rp 16,863.00 2,360,820.00 3,807,572.50 suppl. 1.0000 m3 Beton Kolom 15 x 50 1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00 8.0000 Begesting + perancah @ Rp 171,435.00 1,371,480.00
  • 5. 180.0000 Pembesian @ Rp 16,863.00 3,035,340.00 4,739,245.00 suppl. 1.0000 m3 Beton Kolom 40 x 80 1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00 10.0000 Begesting + perancah @ Rp 171,435.00 1,714,350.00 200.0000 Pembesian @ Rp 16,863.00 3,372,600.00 5,419,375.00 suppl. 1.0000 m3 Beton Balok B1 15 x 50 1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00 9.0000 Begesting + steger @ Rp 168,935.00 1,520,415.00 175.0000 Pembesian @ Rp 16,863.00 2,951,025.00 4,803,865.00 suppl. 1.0000 m3 Beton Balok B2 15 x 30 1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00 7.0000 Begesting + steger @ Rp 168,935.00 1,182,545.00 160.0000 Pembesian @ Rp 16,863.00 2,698,080.00 4,213,050.00 suppl. 1.0000 m3 Beton Balok B3 15 x 40 1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00 8.0000 Begesting + steger @ Rp 168,935.00 1,351,480.00 165.0000 Pembesian @ Rp 16,863.00 2,782,395.00 4,466,300.00 suppl. 1.0000 m3 Beton Balok Bbd 15 x 30 1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00 7.0000 Begesting + steger @ Rp 168,935.00 1,182,545.00 165.0000 Pembesian @ Rp 16,863.00 2,782,395.00 4,297,365.00 suppl. 1.0000 m3 Beton Balok 15 x 20 1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00 4.0000 Begesting + steger @ Rp 168,935.00 675,740.00 140.0000 Pembesian @ Rp 16,863.00 2,360,820.00 3,368,985.00 suppl. 1.0000 m3 Beton Balok Lateu 15 x 15 1.0000 Beton 1:2:3 @ Rp 332,425.00 332,425.00 4.0000 Begesting + perancah @ Rp 168,935.00 675,740.00 129.0000 Pembesian @ Rp 16,863.00 2,175,327.00 3,183,492.00 suppl. 1.0000 m3 Plat Lantai 1.0000 Beton 1:3:5 @ Rp 323,200.00 323,200.00 8.0000 Begesting + steger @ Rp 159,435.00 1,275,480.00 156.0000 Pembesian @ Rp 16,863.00 2,630,628.00 4,229,308.00 suppl. 1.0000 m3 Plat Tangga 1.0000 Beton 1:3:5 @ Rp 323,200.00 323,200.00 8.0000 Begesting + steger @ Rp 159,435.00 1,275,480.00 153.0000 Pembesian @ Rp 16,863.00 2,580,039.00 4,178,719.00 suppl. 1.0000 m3 Sun Shading 1.0000 Beton 1:3:5 @ Rp 323,200.00 323,200.00 5.0000 Begesting + steger @ Rp 159,435.00 797,175.00 120.0000 Pembesian @ Rp 16,863.00 2,023,560.00 3,143,935.00 SNI 2013 PEKERJAAN PLAFOND LL.1 1.0000 m2 Pekerjaan Plafond Gypsum board, rangka metal furing 0.3810 lbr Gypsum board 9mm @ Rp 60,000.00 22,860.00 3.0000 m' metal furing 4x4 @ Rp 7,500.00 22,500.00 2.0000 m' kawat penggantung @ Rp 1,500.00 3,000.00 48,360.00
  • 6. 0.1800 OH Pekerja @ Rp 45,000.00 8,100.00 0.3200 OH Tukang Kayu @ Rp 65,000.00 20,800.00 0.0320 OH Kepala Tukang @ Rp 75,000.00 2,400.00 0.0765 OH Mandor @ Rp 85,000.00 6,502.50 37,802.50 86,162.50 LL.2 1.0000 m2 Pekerjaan Plafond kalsiboard, rangka metal furing 0.3810 lbr Kalciboard 4mm @ Rp 58,000.00 22,098.00 3.0000 m' metal furing 4x4 @ Rp 7,500.00 22,500.00 2.0000 m' kawat penggantung @ Rp 1,500.00 3,000.00 47,598.00 0.1800 OH Pekerja @ Rp 45,000.00 8,100.00 0.3200 OH Tukang Kayu @ Rp 65,000.00 20,800.00 0.0320 OH Kepala Tukang @ Rp 75,000.00 2,400.00 0.0765 OH Mandor @ Rp 85,000.00 6,502.50 37,802.50 85,400.50 LL.3 1.0000 m' Pasang List Profil Gypsum 1.0500 m' List profil gypsum 5 cm @ Rp 19,000.00 19,950.00 0.0100 Kg Paku @ Rp 20,000.00 200.00 20,150.00 0.0500 OH Pekerja @ Rp 45,000.00 2,250.00 0.0500 OH Tukang Kayu @ Rp 65,000.00 3,250.00 0.0050 OH Kepala Tukang @ Rp 75,000.00 375.00 0.0030 OH Mandor @ Rp 85,000.00 255.00 6,130.00 26,280.00 SNI 2013 PEKERJAAN ATAP PA.1 1.0000 m2 Pasang Atap Genteng Keramik 9.0000 bh Genteng keramik M-Class @ Rp 9,000.00 81,000.00 0.1200 OH Pekerja @ Rp 45,000.00 5,400.00 0.0600 OH Tukang Kayu @ Rp 65,000.00 3,900.00 0.0060 OH Kepala Tukang @ Rp 75,000.00 450.00 0.0060 OH Mandor @ Rp 85,000.00 510.00 91,260.00 91,260.00 PA.2 1.0000 m' Pasang Listplank 1.0000 m' Listplank Kalsiplank @ Rp 12,000.00 12,000.00 0.0200 Kg Paku @ Rp 20,000.00 400.00 12,400.00 0.0500 OH Pekerja @ Rp 45,000.00 2,250.00 0.0500 OH Tukang Kayu @ Rp 65,000.00 3,250.00 0.0050 OH Kepala Tukang @ Rp 75,000.00 375.00 0.0030 OH Mandor @ Rp 85,000.00 255.00 6,130.00 18,530.00 SNI 2013 PEKERJAAN LANTAI DAN DINDING L.1 1.0000 m2 Pasang Lantai Granite 60x60 1.0000 m2 Granite 60x60 @ Rp 420,500.00 420,500.00 9.8000 kg Semen PC @ Rp 1,500.00 14,700.00 0.0450 m3 Pasir pasang @ Rp 170,000.00 7,650.00 1.0000 kg Semen warna @ Rp 2,500.00 2,500.00 445,350.00 0.2500 OH Pekerja @ Rp 45,000.00 11,250.00 0.1200 OH Tukang Batu @ Rp 60,000.00 7,200.00 0.0120 OH Kepala Tukang @ Rp 75,000.00 900.00 0.0125 OH Mandor @ Rp 85,000.00 1,062.50 20,412.50 465,762.50 L.2 1.0000 m2 Pasang Lantai Keramik 60x60 3.5000 bh Keramik 60x60 @ Rp 21,000.00 73,500.00
  • 7. 9.8000 kg Semen PC @ Rp 1,500.00 14,700.00 0.0450 m3 Pasir pasang @ Rp 170,000.00 7,650.00 1.0000 kg Semen warna @ Rp 2,500.00 2,500.00 98,350.00 0.2500 OH Pekerja @ Rp 45,000.00 11,250.00 0.1200 OH Tukang Batu @ Rp 60,000.00 7,200.00 0.0120 OH Kepala Tukang @ Rp 75,000.00 900.00 0.0125 OH Mandor @ Rp 85,000.00 1,062.50 20,412.50 118,762.50 L.3 1.0000 m2 Pasang Lantai Keramik 30x30 rustic 25.0000 bh Keramik 30x30 rustic @ Rp 4,100.00 102,500.00 10.4000 kg Semen PC @ Rp 1,500.00 15,600.00 0.0450 m3 Pasir pasang @ Rp 170,000.00 7,650.00 1.6200 kg Semen warna @ Rp 2,500.00 4,050.00 129,800.00 0.2500 OH Pekerja @ Rp 45,000.00 11,250.00 0.1200 OH Tukang Batu @ Rp 60,000.00 7,200.00 0.0120 OH Kepala Tukang @ Rp 75,000.00 900.00 0.0125 OH Mandor @ Rp 85,000.00 1,062.50 20,412.50 150,212.50 L.4 1.0000 m2 Pasang Dinding Keramik 30x40 20.0000 bh Keramik 30x40 @ Rp 9,000.00 180,000.00 10.4000 kg Semen PC @ Rp 1,500.00 15,600.00 0.0450 m3 Pasir pasang @ Rp 170,000.00 7,650.00 1.4000 kg Semen warna @ Rp 2,500.00 3,500.00 206,750.00 0.2500 OH Pekerja @ Rp 45,000.00 11,250.00 0.1200 OH Tukang Batu @ Rp 60,000.00 7,200.00 0.0120 OH Kepala Tukang @ Rp 75,000.00 900.00 0.0125 OH Mandor @ Rp 85,000.00 1,062.50 20,412.50 227,162.50 L.5 1.0000 m' Pasang Border Keramik 10x30 5.0000 bh Keramik 10x30 @ Rp 10,000.00 50,000.00 3.0000 kg Semen PC @ Rp 1,500.00 4,500.00 0.0210 m3 Pasir pasang @ Rp 170,000.00 3,570.00 0.5000 kg Semen warna @ Rp 2,500.00 1,250.00 59,320.00 0.0500 OH Pekerja @ Rp 45,000.00 2,250.00 0.0500 OH Tukang Batu @ Rp 60,000.00 3,000.00 0.0050 OH Kepala Tukang @ Rp 75,000.00 375.00 0.0050 OH Mandor @ Rp 85,000.00 425.00 6,050.00 65,370.00 L.6 1.0000 m2 Pasang Lantai Keramik 30x30 25.0000 bh Keramik 20x20 @ Rp 4,000.00 100,000.00 10.4000 kg Semen PC @ Rp 1,500.00 15,600.00 0.0450 m3 Pasir pasang @ Rp 170,000.00 7,650.00 1.6200 kg Semen warna @ Rp 2,500.00 4,050.00 127,300.00 0.2500 OH Pekerja @ Rp 45,000.00 11,250.00 0.1200 OH Tukang Batu @ Rp 60,000.00 7,200.00 0.0120 OH Kepala Tukang @ Rp 75,000.00 900.00 0.0125 OH Mandor @ Rp 85,000.00 1,062.50 20,412.50 147,712.50 L.7 1.0000 m' Plint keramik 10x60 1.6667 bh Plint granite 10x60 @ Rp 15,000.00 25,000.50 3.0000 kg Semen PC @ Rp 1,500.00 4,500.00 0.0210 m3 Pasir pasang @ Rp 170,000.00 3,570.00 0.5000 kg Semen warna @ Rp 2,500.00 1,250.00 34,320.50 0.0500 OH Pekerja @ Rp 45,000.00 2,250.00 0.0500 OH Tukang Batu @ Rp 60,000.00 3,000.00
  • 8. 0.0050 OH Kepala Tukang @ Rp 75,000.00 375.00 0.0050 OH Mandor @ Rp 85,000.00 425.00 6,050.00 40,370.50 L.8 1.0000 m3 Rabat beton di bawah lantai & keliling bangunan 9.3000 kg Semen PC @ Rp 1,500.00 13,950.00 1.2000 m3 Pasir Pasang @ Rp 170,000.00 204,000.00 217,950.00 0.4000 OH Pekerja @ Rp 45,000.00 18,000.00 0.1500 OH Tukang Batu @ Rp 60,000.00 9,000.00 0.0150 OH Kepala Tukang @ Rp 75,000.00 1,125.00 0.0200 OH Mandor @ Rp 85,000.00 1,700.00 29,825.00 247,775.00 L.9 1.0000 m3 Rabat beton Carport 9.3000 kg Semen PC @ Rp 1,500.00 13,950.00 1.2000 m3 Pasir Pasang @ Rp 170,000.00 204,000.00 10.0000 kg Koral Warna @ Rp 4,500.00 45,000.00 262,950.00 0.4000 OH Pekerja @ Rp 45,000.00 18,000.00 0.1500 OH Tukang Batu @ Rp 60,000.00 9,000.00 0.0150 OH Kepala Tukang @ Rp 75,000.00 1,125.00 0.0200 OH Mandor @ Rp 85,000.00 1,700.00 29,825.00 292,775.00 L.9 1.0000 m2 Pasang Batu Candi 60x60 1.2000 m3 Pasir Pasang @ Rp 170,000.00 204,000.00 1.0000 m2 Batu Candi 60x60 @ Rp 4,500.00 4,500.00 208,500.00 0.4000 OH Pekerja @ Rp 45,000.00 18,000.00 0.1500 OH Tukang Batu @ Rp 60,000.00 9,000.00 0.0150 OH Kepala Tukang @ Rp 75,000.00 1,125.00 0.0200 OH Mandor @ Rp 85,000.00 1,700.00 29,825.00 238,325.00 L.10 1.0000 m' Pasang Stepnoizing tangga 10 x 20 cm 5.0000 bh keramik 10/20 @ Rp 10,300.00 51,500.00 9.8000 kg pc @ Rp 1,500.00 14,700.00 0.0450 m3 pasir pasang @ Rp 170,000.00 7,650.00 1.3000 kg semen warna @ Rp 2,500.00 3,250.00 77,100.00 0.2500 OH pekerja @ Rp 45,000.00 11,250.00 0.1200 OH tukang batu @ Rp 60,000.00 7,200.00 0.0120 OH kepala tukang @ Rp 75,000.00 900.00 0.0125 OH mandor @ Rp 85,000.00 1,062.50 20,412.50 97,512.50 SNI 2013 PEKERJAAN SANITAIR DAN PEMIPAAN SA.1 1.0000 m' Pasang saluran Got U diameter 30cm 1.0000 bh Got U 30cm @ Rp 55,000.00 55,000.00 0.2300 m3 Galian tanah @ Rp 35,875.00 8,251.25 0.0500 m3 Pasir urug @ Rp 140,000.00 7,000.00 0.0308 m3 Pas. Bt. Bata rollag @ Rp 75,000.00 2,310.00 0.1000 m2 Pas. bt.belah 1:6 @ Rp 516,280.00 51,628.00 0.0360 m3 Beton tutup @ Rp 4,229,308.00 152,255.09 0.0750 upah meletakkan got @ Rp 45,000.00 3,375.00 279,819.34 SNI 2013 PEKERJAAN PENGECATAN C.1 1.0000 m2 Mengecat tembok luar ruangan 0.3500 kg cat tembok eksterior @ Rp 100,000.00 35,000.00 0.2250 kg plamur @ Rp 12,000.00 2,700.00 0.2500 lbr amplas @ Rp 3,000.00 750.00
  • 9. 0.0750 OH tukang cat @ Rp 60,000.00 4,500.00 0.0075 OH tukang kepala @ Rp 75,000.00 562.50 0.0500 OH pekerja @ Rp 45,000.00 2,250.00 0.0025 OH mandor @ Rp 85,000.00 212.50 45,975.00 C.2 1.0000 m2 Mengecat tembok dalam ruangan 0.3500 kg cat tembok interior @ Rp 20,000.00 7,000.00 0.2250 kg plamur @ Rp 12,000.00 2,700.00 0.2500 lbr amplas @ Rp 3,000.00 750.00 0.0750 OH tukang cat @ Rp 60,000.00 4,500.00 0.0075 OH tukang kepala @ Rp 75,000.00 562.50 0.0500 OH pekerja @ Rp 45,000.00 2,250.00 0.0025 OH mandor @ Rp 85,000.00 212.50 17,975.00 C.3 1.0000 m2 Mengecat Plafond 0.3600 Kg Cat Tembok interior @ Rp 20,000.00 7,200.00 0.0200 OH Pekerja @ Rp 45,000.00 900.00 0.0630 OH Tukang Cat @ Rp 60,000.00 3,780.00 0.0063 OH Kepala Tukang @ Rp 75,000.00 472.50 0.0025 OH Mandor @ Rp 85,000.00 212.50 12,565.00 C.4 1.0000 m2 Melitur Kayu 3x 0.3600 ltr Plitur Kayu @ Rp 39,000.00 14,040.00 0.0200 OH Pekerja @ Rp 45,000.00 900.00 0.0630 OH Tukang Cat @ Rp 60,000.00 3,780.00 0.0063 OH Kepala Tukang @ Rp 75,000.00 472.50 0.0025 OH Mandor @ Rp 85,000.00 212.50 19,405.00 C.5 1.0000 m2 Waterprofing atap dag beton 0.3600 Kg waterprofing No Drop @ Rp 35,000.00 12,600.00 0.0200 OH Pekerja @ Rp 45,000.00 900.00 0.0630 OH Tukang Cat @ Rp 60,000.00 3,780.00 0.0063 OH Kepala Tukang @ Rp 75,000.00 472.50 0.0025 OH Mandor @ Rp 85,000.00 212.50 17,965.00