SlideShare a Scribd company logo
1 of 6
Download to read offline
BI-WEEKLY REPORT
- - Ebbin Daniel
OCT 17 - OCT 31
Electrical Engineer
CONTENTS:
1. Maintenance and troubleshooting
a. Replacing new HMI panel in the batch machine of the block plant.
b. Troubleshooting the wrapper machine of the block plant.
c. Troubleshooting the pallet stacker
d. Obtaining proper scaled value in the aggregate bins.
e. Replacing the Load cell on the color machine.
f. Replacing broken safety photo eyes on the pallet transfer cart.
g. Troubleshooting Cuber malfunction.
2. Future Projects
a. Height adjustment for pavers on wet side.
b. Installing cable ladder and cable tray system on the paver plant.
c. Rewiring the Cuber UP/ down control wires.
d. Adjustment of the height sensor on the Hopper 1.
A.Replacing new HMI panel in the batch machine of the
block plant.
Cause of the Problem:
 No power at the panel.
 Possible loss of the program.
 Setup not running.
 Not able to automatically add color as panel was down.
Troubleshooting:
 The power was restored.
 It was rebooted and the setup was run.
 The setup was not able to run as the program was cleared.
 Therefore new panels were ordered and installed.
B. Troubleshooting the wrapper machine of the block plant.
Cause of the Problem:
 Conveyor does not start.
 Blocks not able to pass forward.
 NO power in the SLC power card.
 Delay in production cycle.
Troubleshooting:
 A broken fuse was found and was replaced.
 The SLC power card was reinstalled and a new was ordered.
 The SLC processor was reinstalled with the Current program and rebooted.
 The conveyor started running.
 However wrapper is still waiting on a part after which it could be used in the process.
C.Troubleshooting the pallet stacker
Cause of the Problem:
 Pallet stacker shows unusual behavior.
 Sometimes it just comes down with just 2 or three boards.
Troubleshooting:
 The sensor in the middle which is responsible for the number of boards was loose.
 Repositioned the sensor.
 Adjusted the sensor for the number of boards.
 Pallet stacker working fine
D. Obtaining proper scaled value in the aggregate bins.
Cause of the Problem:
 Desired Agg bin weight was different than the value obtained.
 Caused differences in the product made.
Troubleshooting:
 The small jog and the large jog values were altered with the help of Mr. Joe.
 Difference in the jog time was also altered.
 The exact value was obtained and noted down.
E.Replacing the Load cell on the color machine.
Cause of the Problem:
 The weight of color in the color panel was showing as constant.
 There was no difference with any color.
 Resetting the color program had no effect either.
Troubleshooting:
 Any loose wire connection was found out. All wires were intact.
 The Load cell had no control voltage between the green and the black wires.
 The load cell had incoming voltage to it.
 This confirmed that the load cell was bad.
 The load cell was replaced and was calibrated through the software.
F. Replacing broken safety photo eyes on the pallet transfer cart.
Cause of the Problem:
 Broken photo eye
 The transfer car sometimes stops in between.
 Connection problem with the receiver.
Troubleshooting:
 Both the Transmitter and the receiver was replaced and a new set was ordered.
 They were aligned to get the maximum signal.
 They were all fitted and started with operation.
G. Troubleshooting Cuber malfunction.
Cause of the Problem:
 Cuber not going up and down.
 Manual/ auto operation cannot perform.
 Delay in dry side production.
Troubleshooting:
 A loose wire was found which was tied up together.
 Eventually the fuse had also blown which was also replaced.
 The wire is very tight so did come off twice.
 New wires are ordered and will be rewired by Wednesday.

More Related Content

Viewers also liked

Viewers also liked (6)

Noon conference
Noon conferenceNoon conference
Noon conference
 
Problems1
Problems1Problems1
Problems1
 
Περιοδικό «Δύσκολος Δρόμος» τεύχος 3
Περιοδικό «Δύσκολος Δρόμος» τεύχος 3Περιοδικό «Δύσκολος Δρόμος» τεύχος 3
Περιοδικό «Δύσκολος Δρόμος» τεύχος 3
 
Περιοδικό Γέφυρα τεύχος 7
Περιοδικό Γέφυρα τεύχος 7Περιοδικό Γέφυρα τεύχος 7
Περιοδικό Γέφυρα τεύχος 7
 
Rheumatoid Arthritis
Rheumatoid ArthritisRheumatoid Arthritis
Rheumatoid Arthritis
 
Idiom flashcard (7)time
Idiom flashcard (7)timeIdiom flashcard (7)time
Idiom flashcard (7)time
 

Similar to oct17

Joseph Machine CNC Saw Kaizen and Repair1
Joseph Machine CNC Saw Kaizen and Repair1Joseph Machine CNC Saw Kaizen and Repair1
Joseph Machine CNC Saw Kaizen and Repair1Eric Mosley
 
2nd cycle experiments.docx
2nd cycle experiments.docx2nd cycle experiments.docx
2nd cycle experiments.docxatiulla001
 
Case Studies Ii
Case Studies IiCase Studies Ii
Case Studies Iijfjohnson6
 
Last Rev. August 2014 Calibration and Temperature Measurement.docx
Last Rev. August 2014 Calibration and Temperature Measurement.docxLast Rev. August 2014 Calibration and Temperature Measurement.docx
Last Rev. August 2014 Calibration and Temperature Measurement.docxsmile790243
 
Thermocharger 2018
Thermocharger 2018Thermocharger 2018
Thermocharger 2018Regina Sung
 
Solar poweredleadacidbatterycharger
Solar poweredleadacidbatterychargerSolar poweredleadacidbatterycharger
Solar poweredleadacidbatterychargerReynold Reegan
 
Wireless Charging Proposal
Wireless Charging Proposal Wireless Charging Proposal
Wireless Charging Proposal Nadeem Qandeel
 
wind turbine _ battery recharge controller
wind turbine _ battery recharge controller wind turbine _ battery recharge controller
wind turbine _ battery recharge controller mussa_000
 
Ni project presentation version 3
Ni project presentation version 3Ni project presentation version 3
Ni project presentation version 3Ahmed Zahid
 
ECET 402 Entire Course NEW
ECET 402 Entire Course NEWECET 402 Entire Course NEW
ECET 402 Entire Course NEWshyamuopuop
 
4th periodic test final
4th periodic test final4th periodic test final
4th periodic test finalGagha BeeCee
 
Wirless Charging Progress Presentation
Wirless Charging Progress PresentationWirless Charging Progress Presentation
Wirless Charging Progress PresentationNadeem Qandeel
 
Digital Energy Meter Project Report
Digital Energy Meter Project ReportDigital Energy Meter Project Report
Digital Energy Meter Project ReportVijayananda Mohire
 

Similar to oct17 (20)

Ebbin_oct3
Ebbin_oct3Ebbin_oct3
Ebbin_oct3
 
Joseph Machine CNC Saw Kaizen and Repair1
Joseph Machine CNC Saw Kaizen and Repair1Joseph Machine CNC Saw Kaizen and Repair1
Joseph Machine CNC Saw Kaizen and Repair1
 
Quizbank quiz buzzer
Quizbank quiz buzzer Quizbank quiz buzzer
Quizbank quiz buzzer
 
2nd cycle experiments.docx
2nd cycle experiments.docx2nd cycle experiments.docx
2nd cycle experiments.docx
 
WHO final
WHO  finalWHO  final
WHO final
 
Final Results Memo
Final Results MemoFinal Results Memo
Final Results Memo
 
Case Studies Ii
Case Studies IiCase Studies Ii
Case Studies Ii
 
Last Rev. August 2014 Calibration and Temperature Measurement.docx
Last Rev. August 2014 Calibration and Temperature Measurement.docxLast Rev. August 2014 Calibration and Temperature Measurement.docx
Last Rev. August 2014 Calibration and Temperature Measurement.docx
 
Electrotherm_Report
Electrotherm_ReportElectrotherm_Report
Electrotherm_Report
 
Thermocharger 2018
Thermocharger 2018Thermocharger 2018
Thermocharger 2018
 
Solar poweredleadacidbatterycharger
Solar poweredleadacidbatterychargerSolar poweredleadacidbatterycharger
Solar poweredleadacidbatterycharger
 
Wireless Charging Proposal
Wireless Charging Proposal Wireless Charging Proposal
Wireless Charging Proposal
 
Digital Weight Scale
Digital Weight ScaleDigital Weight Scale
Digital Weight Scale
 
wind turbine _ battery recharge controller
wind turbine _ battery recharge controller wind turbine _ battery recharge controller
wind turbine _ battery recharge controller
 
Ni project presentation version 3
Ni project presentation version 3Ni project presentation version 3
Ni project presentation version 3
 
A battery charger is a device that can restore the charger to a battery
A battery charger is a device that can restore the charger to a batteryA battery charger is a device that can restore the charger to a battery
A battery charger is a device that can restore the charger to a battery
 
ECET 402 Entire Course NEW
ECET 402 Entire Course NEWECET 402 Entire Course NEW
ECET 402 Entire Course NEW
 
4th periodic test final
4th periodic test final4th periodic test final
4th periodic test final
 
Wirless Charging Progress Presentation
Wirless Charging Progress PresentationWirless Charging Progress Presentation
Wirless Charging Progress Presentation
 
Digital Energy Meter Project Report
Digital Energy Meter Project ReportDigital Energy Meter Project Report
Digital Energy Meter Project Report
 

More from ebbin daniel

More from ebbin daniel (8)

New Microsoft PowerPoint Presentation
New Microsoft PowerPoint PresentationNew Microsoft PowerPoint Presentation
New Microsoft PowerPoint Presentation
 
TCIL_PROJECT
TCIL_PROJECTTCIL_PROJECT
TCIL_PROJECT
 
POWER ELECTRONICS
POWER ELECTRONICSPOWER ELECTRONICS
POWER ELECTRONICS
 
DFIG_report
DFIG_reportDFIG_report
DFIG_report
 
Presentation1
Presentation1Presentation1
Presentation1
 
EDS_REPORT_FINAL
EDS_REPORT_FINALEDS_REPORT_FINAL
EDS_REPORT_FINAL
 
tremron_ebbin
tremron_ebbintremron_ebbin
tremron_ebbin
 
TREMRON_PROJECT_summer
TREMRON_PROJECT_summerTREMRON_PROJECT_summer
TREMRON_PROJECT_summer
 

oct17

  • 1. BI-WEEKLY REPORT - - Ebbin Daniel OCT 17 - OCT 31 Electrical Engineer
  • 2. CONTENTS: 1. Maintenance and troubleshooting a. Replacing new HMI panel in the batch machine of the block plant. b. Troubleshooting the wrapper machine of the block plant. c. Troubleshooting the pallet stacker d. Obtaining proper scaled value in the aggregate bins. e. Replacing the Load cell on the color machine. f. Replacing broken safety photo eyes on the pallet transfer cart. g. Troubleshooting Cuber malfunction. 2. Future Projects a. Height adjustment for pavers on wet side. b. Installing cable ladder and cable tray system on the paver plant. c. Rewiring the Cuber UP/ down control wires. d. Adjustment of the height sensor on the Hopper 1.
  • 3. A.Replacing new HMI panel in the batch machine of the block plant. Cause of the Problem:  No power at the panel.  Possible loss of the program.  Setup not running.  Not able to automatically add color as panel was down. Troubleshooting:  The power was restored.  It was rebooted and the setup was run.  The setup was not able to run as the program was cleared.  Therefore new panels were ordered and installed. B. Troubleshooting the wrapper machine of the block plant. Cause of the Problem:  Conveyor does not start.  Blocks not able to pass forward.  NO power in the SLC power card.  Delay in production cycle. Troubleshooting:  A broken fuse was found and was replaced.  The SLC power card was reinstalled and a new was ordered.  The SLC processor was reinstalled with the Current program and rebooted.  The conveyor started running.  However wrapper is still waiting on a part after which it could be used in the process.
  • 4. C.Troubleshooting the pallet stacker Cause of the Problem:  Pallet stacker shows unusual behavior.  Sometimes it just comes down with just 2 or three boards. Troubleshooting:  The sensor in the middle which is responsible for the number of boards was loose.  Repositioned the sensor.  Adjusted the sensor for the number of boards.  Pallet stacker working fine D. Obtaining proper scaled value in the aggregate bins. Cause of the Problem:  Desired Agg bin weight was different than the value obtained.  Caused differences in the product made. Troubleshooting:  The small jog and the large jog values were altered with the help of Mr. Joe.  Difference in the jog time was also altered.  The exact value was obtained and noted down. E.Replacing the Load cell on the color machine. Cause of the Problem:  The weight of color in the color panel was showing as constant.  There was no difference with any color.  Resetting the color program had no effect either.
  • 5. Troubleshooting:  Any loose wire connection was found out. All wires were intact.  The Load cell had no control voltage between the green and the black wires.  The load cell had incoming voltage to it.  This confirmed that the load cell was bad.  The load cell was replaced and was calibrated through the software. F. Replacing broken safety photo eyes on the pallet transfer cart. Cause of the Problem:  Broken photo eye  The transfer car sometimes stops in between.  Connection problem with the receiver. Troubleshooting:  Both the Transmitter and the receiver was replaced and a new set was ordered.  They were aligned to get the maximum signal.  They were all fitted and started with operation.
  • 6. G. Troubleshooting Cuber malfunction. Cause of the Problem:  Cuber not going up and down.  Manual/ auto operation cannot perform.  Delay in dry side production. Troubleshooting:  A loose wire was found which was tied up together.  Eventually the fuse had also blown which was also replaced.  The wire is very tight so did come off twice.  New wires are ordered and will be rewired by Wednesday.