SlideShare a Scribd company logo
1 of 9
Project Management Diploma
Learn about the Activity Duration
Estimating in the Project Management
Diploma qualification.
The answer to the question ―How long will it take?
depends on the accuracy of the estimates, the consistency
of the work, and other variables within the project.
The best a project manager can do is create honest
estimates based on the information he’s been provided.
Until the schedule is finalised, no one will know the
duration of the project.
The tasks are first identified, the sequencing of the
activities takes place, resources are defined and then
durations are estimated. These activities are required to
complete the project schedule and the estimated project
duration. These four activities are iterated as more
information comes available. If the proposed schedule is
acceptable, the project can move forward.
If the proposed schedule takes too long, the scheduler
can use a few strategies to compress the project. We’ll
discuss the art of scheduling in a few moments. Activity
duration estimates, like the activity list and the WBS, don’t
come from the project manager—they come from the
people completing the work. They may also undergo
progressive elaboration.
The process of estimating schedule activity durations uses
information on schedule activity scope of work, required
resource types, estimated resource quantities, and
resource calendars with resource availabilities.
The inputs for the estimates of schedule activity duration
originate from the person or group on the project team
who is most familiar with the nature of the work content in
the specific schedule activity. The duration estimate is
progressively elaborated, and the process considers the
quality and availability of the input data.
For example, as the project engineering and
design work evolves, more detailed and precise data is
available, and the accuracy of the duration estimates
improves. Thus, the duration estimate can be assumed to
be progressively more accurate and of better quality.
The Activity Duration Estimating process requires that the
amount of work effort required to complete the schedule
activity is estimated, the assumed amount of resources to
be applied to complete the schedule activity is estimated,
and the number of work periods needed to complete the
schedule activity is determined.
All data and assumptions that support duration estimating
are documented for each activity duration estimate.
Estimating the number of work periods required to
complete a schedule activity can require consideration of
elapsed time as a requirement related to a specific type of
work.
Most project management software for scheduling will
handle this situation by using a project calendar and
alternative work-period resource calendars that are
usually identified by the resources that require specific
work periods.
The schedule activities will be worked according to the
project calendar, and the schedule activities to which the
resources are assigned will also be worked according to
the appropriate resource calendars. Overall project
duration is calculated as an output of the Schedule
Development process.
LMIT’s Diploma in Project Management is Now
Endorsed by AIPM – Get Your Diploma of PM and
You’ll Also Receive a Certificate from AIPM.
LMIT provides online training courses for
the Cert IV Project Management
BSB41507, the Certificate IV of Project
Management and the Diploma of Project
Management BSB51407 in Brisbane,
Sydney, Melbourne, Perth, Adelaide and
Canberra.

More Related Content

More from danieljohn810

More from danieljohn810 (19)

Cert IV OHS - WHS Responsibilities and Legislative Requirements
Cert IV OHS - WHS Responsibilities and Legislative RequirementsCert IV OHS - WHS Responsibilities and Legislative Requirements
Cert IV OHS - WHS Responsibilities and Legislative Requirements
 
Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)
 
Certificate IV OHS - Glossary of Common OHS Terms
Certificate IV OHS - Glossary of Common OHS TermsCertificate IV OHS - Glossary of Common OHS Terms
Certificate IV OHS - Glossary of Common OHS Terms
 
Writing Meeting Agendas - Business Writing Skills Training Courses
Writing Meeting Agendas - Business Writing Skills Training CoursesWriting Meeting Agendas - Business Writing Skills Training Courses
Writing Meeting Agendas - Business Writing Skills Training Courses
 
Diploma of Project Management - Activity Resource Estimating (Outputs)
Diploma of Project Management - Activity Resource Estimating (Outputs)Diploma of Project Management - Activity Resource Estimating (Outputs)
Diploma of Project Management - Activity Resource Estimating (Outputs)
 
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
 
Schedule Development - Diploma in Project Management
Schedule Development - Diploma in Project Management Schedule Development - Diploma in Project Management
Schedule Development - Diploma in Project Management
 
Occupational Health and Safety Training -The Role of Managers in WHS
Occupational Health and Safety Training -The Role of Managers in WHSOccupational Health and Safety Training -The Role of Managers in WHS
Occupational Health and Safety Training -The Role of Managers in WHS
 
Executive Assistant Training - Advanced PA Training
Executive Assistant Training - Advanced PA TrainingExecutive Assistant Training - Advanced PA Training
Executive Assistant Training - Advanced PA Training
 
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...
 
Occupational Health and Safety Training - WHS Needs and Priorities
Occupational Health and Safety Training - WHS Needs and PrioritiesOccupational Health and Safety Training - WHS Needs and Priorities
Occupational Health and Safety Training - WHS Needs and Priorities
 
Office 365 Excel Essentials Training Course.pdf
Office 365 Excel Essentials Training Course.pdfOffice 365 Excel Essentials Training Course.pdf
Office 365 Excel Essentials Training Course.pdf
 
Glossary of OHS Terms - Diploma in Occupational Health and Safety
Glossary of OHS Terms - Diploma in Occupational Health and SafetyGlossary of OHS Terms - Diploma in Occupational Health and Safety
Glossary of OHS Terms - Diploma in Occupational Health and Safety
 
How to Measure the Relevance and Accuracy of OHS Information
How to Measure the Relevance and Accuracy of OHS InformationHow to Measure the Relevance and Accuracy of OHS Information
How to Measure the Relevance and Accuracy of OHS Information
 
Diploma Human Resources
Diploma Human ResourcesDiploma Human Resources
Diploma Human Resources
 
Diploma of Management - Three Basic Types of Human Communication
Diploma of Management - Three Basic Types of Human CommunicationDiploma of Management - Three Basic Types of Human Communication
Diploma of Management - Three Basic Types of Human Communication
 
Management Diploma Online - Seven Categories of Motivation
Management Diploma Online - Seven Categories of MotivationManagement Diploma Online - Seven Categories of Motivation
Management Diploma Online - Seven Categories of Motivation
 
Diploma of Management Training - Maslow’s Theory of Needs
Diploma of Management Training - Maslow’s Theory of NeedsDiploma of Management Training - Maslow’s Theory of Needs
Diploma of Management Training - Maslow’s Theory of Needs
 
Diploma in management
Diploma in managementDiploma in management
Diploma in management
 

Recently uploaded

WIOA Program Info Session | PMI Silver Spring Chapter | May 17, 2024
WIOA Program Info Session | PMI Silver Spring Chapter | May 17, 2024WIOA Program Info Session | PMI Silver Spring Chapter | May 17, 2024
WIOA Program Info Session | PMI Silver Spring Chapter | May 17, 2024
Hector Del Castillo, CPM, CPMM
 
Genaihelloallstudyjamheregetstartedwithai
GenaihelloallstudyjamheregetstartedwithaiGenaihelloallstudyjamheregetstartedwithai
Genaihelloallstudyjamheregetstartedwithai
joceko6768
 
Ralph - Project Presentation Enhancing System Security at Acme Flight Solutio...
Ralph - Project Presentation Enhancing System Security at Acme Flight Solutio...Ralph - Project Presentation Enhancing System Security at Acme Flight Solutio...
Ralph - Project Presentation Enhancing System Security at Acme Flight Solutio...
MasterG
 
unit-5-final-cn-unit-5-notes-important-questions.pdf
unit-5-final-cn-unit-5-notes-important-questions.pdfunit-5-final-cn-unit-5-notes-important-questions.pdf
unit-5-final-cn-unit-5-notes-important-questions.pdf
radheeshyam1176
 
toefl ibt practice test module download_1
toefl ibt practice test module download_1toefl ibt practice test module download_1
toefl ibt practice test module download_1
Aswar Amiruddin
 
કારકિર્દીના પંથે-2024 career guidance.pdf
કારકિર્દીના પંથે-2024 career guidance.pdfકારકિર્દીના પંથે-2024 career guidance.pdf
કારકિર્દીના પંથે-2024 career guidance.pdf
SAIYEDASAD2
 
B. A. (Prog.) Political Science 6th Semester 2019.pdf
B. A. (Prog.) Political Science 6th Semester 2019.pdfB. A. (Prog.) Political Science 6th Semester 2019.pdf
B. A. (Prog.) Political Science 6th Semester 2019.pdf
paraspiyush3
 

Recently uploaded (17)

WIOA Program Info Session | PMI Silver Spring Chapter | May 17, 2024
WIOA Program Info Session | PMI Silver Spring Chapter | May 17, 2024WIOA Program Info Session | PMI Silver Spring Chapter | May 17, 2024
WIOA Program Info Session | PMI Silver Spring Chapter | May 17, 2024
 
IG2 Risk Assessment.for any copany .docx
IG2 Risk Assessment.for any copany .docxIG2 Risk Assessment.for any copany .docx
IG2 Risk Assessment.for any copany .docx
 
Kathleen McBride Costume Design Resume.pdf
Kathleen McBride Costume Design Resume.pdfKathleen McBride Costume Design Resume.pdf
Kathleen McBride Costume Design Resume.pdf
 
Kathleen McBride ONLINE General Resume 2024.pdf
Kathleen McBride ONLINE General Resume 2024.pdfKathleen McBride ONLINE General Resume 2024.pdf
Kathleen McBride ONLINE General Resume 2024.pdf
 
Your 7-Step Job Application Checklist: Ace Your Next Career Move
Your 7-Step Job Application Checklist: Ace Your Next Career MoveYour 7-Step Job Application Checklist: Ace Your Next Career Move
Your 7-Step Job Application Checklist: Ace Your Next Career Move
 
Genaihelloallstudyjamheregetstartedwithai
GenaihelloallstudyjamheregetstartedwithaiGenaihelloallstudyjamheregetstartedwithai
Genaihelloallstudyjamheregetstartedwithai
 
Job Hunting - pick over this fishbone for telephone interviews!.pptx
Job Hunting - pick over this fishbone for telephone interviews!.pptxJob Hunting - pick over this fishbone for telephone interviews!.pptx
Job Hunting - pick over this fishbone for telephone interviews!.pptx
 
Ralph - Project Presentation Enhancing System Security at Acme Flight Solutio...
Ralph - Project Presentation Enhancing System Security at Acme Flight Solutio...Ralph - Project Presentation Enhancing System Security at Acme Flight Solutio...
Ralph - Project Presentation Enhancing System Security at Acme Flight Solutio...
 
unit-5-final-cn-unit-5-notes-important-questions.pdf
unit-5-final-cn-unit-5-notes-important-questions.pdfunit-5-final-cn-unit-5-notes-important-questions.pdf
unit-5-final-cn-unit-5-notes-important-questions.pdf
 
Day care leadership document it helps to a person who needs caring children
Day care leadership document it helps to a person who needs caring childrenDay care leadership document it helps to a person who needs caring children
Day care leadership document it helps to a person who needs caring children
 
5CL-ADBA,5cladba, the best supplier in China
5CL-ADBA,5cladba, the best supplier in China5CL-ADBA,5cladba, the best supplier in China
5CL-ADBA,5cladba, the best supplier in China
 
Navigating the Tech Industry Journey GDSC UNIDEB
Navigating the Tech Industry Journey GDSC UNIDEBNavigating the Tech Industry Journey GDSC UNIDEB
Navigating the Tech Industry Journey GDSC UNIDEB
 
toefl ibt practice test module download_1
toefl ibt practice test module download_1toefl ibt practice test module download_1
toefl ibt practice test module download_1
 
129. Reviewer Certificate in BioNature [2024]
129. Reviewer Certificate in BioNature [2024]129. Reviewer Certificate in BioNature [2024]
129. Reviewer Certificate in BioNature [2024]
 
કારકિર્દીના પંથે-2024 career guidance.pdf
કારકિર્દીના પંથે-2024 career guidance.pdfકારકિર્દીના પંથે-2024 career guidance.pdf
કારકિર્દીના પંથે-2024 career guidance.pdf
 
Master SEO in 2024 The Complete Beginner's Guide
Master SEO in 2024 The Complete Beginner's GuideMaster SEO in 2024 The Complete Beginner's Guide
Master SEO in 2024 The Complete Beginner's Guide
 
B. A. (Prog.) Political Science 6th Semester 2019.pdf
B. A. (Prog.) Political Science 6th Semester 2019.pdfB. A. (Prog.) Political Science 6th Semester 2019.pdf
B. A. (Prog.) Political Science 6th Semester 2019.pdf
 

Project Management Diploma - Activity Duration Estimating

  • 2. Learn about the Activity Duration Estimating in the Project Management Diploma qualification.
  • 3. The answer to the question ―How long will it take? depends on the accuracy of the estimates, the consistency of the work, and other variables within the project. The best a project manager can do is create honest estimates based on the information he’s been provided. Until the schedule is finalised, no one will know the duration of the project.
  • 4. The tasks are first identified, the sequencing of the activities takes place, resources are defined and then durations are estimated. These activities are required to complete the project schedule and the estimated project duration. These four activities are iterated as more information comes available. If the proposed schedule is acceptable, the project can move forward. If the proposed schedule takes too long, the scheduler can use a few strategies to compress the project. We’ll discuss the art of scheduling in a few moments. Activity duration estimates, like the activity list and the WBS, don’t come from the project manager—they come from the people completing the work. They may also undergo progressive elaboration.
  • 5. The process of estimating schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities. The inputs for the estimates of schedule activity duration originate from the person or group on the project team who is most familiar with the nature of the work content in the specific schedule activity. The duration estimate is progressively elaborated, and the process considers the quality and availability of the input data.
  • 6. For example, as the project engineering and design work evolves, more detailed and precise data is available, and the accuracy of the duration estimates improves. Thus, the duration estimate can be assumed to be progressively more accurate and of better quality. The Activity Duration Estimating process requires that the amount of work effort required to complete the schedule activity is estimated, the assumed amount of resources to be applied to complete the schedule activity is estimated, and the number of work periods needed to complete the schedule activity is determined.
  • 7. All data and assumptions that support duration estimating are documented for each activity duration estimate. Estimating the number of work periods required to complete a schedule activity can require consideration of elapsed time as a requirement related to a specific type of work. Most project management software for scheduling will handle this situation by using a project calendar and alternative work-period resource calendars that are usually identified by the resources that require specific work periods.
  • 8. The schedule activities will be worked according to the project calendar, and the schedule activities to which the resources are assigned will also be worked according to the appropriate resource calendars. Overall project duration is calculated as an output of the Schedule Development process. LMIT’s Diploma in Project Management is Now Endorsed by AIPM – Get Your Diploma of PM and You’ll Also Receive a Certificate from AIPM.
  • 9. LMIT provides online training courses for the Cert IV Project Management BSB41507, the Certificate IV of Project Management and the Diploma of Project Management BSB51407 in Brisbane, Sydney, Melbourne, Perth, Adelaide and Canberra.