Icu real time monitoring project status report 201109
1. HCIS Project Management Office
ICU Real Time Monitoring Project Status Report
FOR THE MONTH OF SEPTEMBER, 2011
HCIS Project Management Office Project Status Report
Project Name: ICU Real Time Monitoring Project Reporting Period: September, 2011
Project Sponsor: Dr. Schmidt PM/PL: Curtis Chung/Denise Grafft AC/TL: Teresa Franklin/Brian Hegland
Project Life Cycle/Phases
Phase 1 Phase 2 Phase 3 Phase 4 Phase 5 Phase 6 Phase 7
Planning Hardware/Walk-throughs Reports Build & Test Monitor Parallel Testing Training Go-Live Closure
7/17/11 – 10/15/11 8/8/11 – 1/30/12 10/17/11 – 12/16/11 12/15/ 11 – 1/30/12 1/4/12 – 1/30/12 2/5/12 – 3/15/12 2/15/12 – 3/15/12
Green Green Planned Planned Planned Planned Planned
Executive Summary
OVERALL STATUS Planned Project Start Date Actual Project Start Date Planned Project Completion Date Actual Project Completion date
32% Complete 7/17/2011 8/1/2011 3/30/12
The overall project status is Green, based on our current project schedule and scope.
The team will meet early next week to confirm the scope and finalize the number of monitors, monitor locations, and
other associated costs.
Reports have been identified, documented, categorized and prioritized. The Respiratory Report widget is 90% build
and is currently on Epic Support for preliminary review. The initial list of report to be built includes, but not limited
Overall
Green to: Respiratory, Infectious Disease, Hemodynamic, I/Os and LDA/Hines Days. Thank you for completing Homework
Status
assignment #1.
Hardware/equipment walk-throughs are completed.
The monitor application software setup & configuration planning activities are currently underway.
We have extended Phase 2 end date from 12/30/11 to 1/30/12. This schedule change will not impact our planned Go-
Live date.
Schedule Green On-schedule
Budget Yellow Currently working with the team to determine the overall project cost and the HCIS project team work hour estimates.
Risks Green None.
Issues
Green None.
Concerns
Phase 1 – Planning
STATUS Planned Project Start Date Actual Project Start Date Planned Project Completion Date Actual Project Completion date
Green 7/15/11 7/17/11 9/30/11
Project share point website.
Summary
Collected and listed the reports’ recommendations. Homework1 compiled.
Accomplishments for
Built the Respiratory report’s widget.
This Period
Scheduled a meeting with Epic to discuss and plan the monitor application software configuration activities.
Complete and baseline project schedule and timeline.
Work Planned for
Finalize the project scope. (Reports/hardware/locations)
Next Period/
Confirm and signoff on initial reports’ list & scope.
Upcoming Milestones
Complete the project cost estimates.
Matters for
Management None at this time.
Attention
Phase 2 – Hardware & Software Installation
STATUS Planned Project Start Date Actual Project Start Date Planned Project Completion Date Actual Project Completion date
Green 8/14/11 8/14/11 1/30/12
Summary Conducted touchscreen monitor review sessions.
Accomplishments for Selected top touchscreen monitor identified by staff.
This Period Completed the walk-throughs (NICU, PICU, MICU, SICU and Burn).
STATUS KEY
Green Yellow Red N/A
On Track Warning Not on Track Not applicable
-1-
2. HCIS Project Management Office
ICU Real Time Monitoring Project Status Report
FOR THE MONTH OF SEPTEMBER, 2011
Setup and install a test touchscreen monitor.
Work Planned for
Confirm hardware & equipment scope, location and placement.
Next Period/
Submit touchscreen monitor bid and place initial order.
Upcoming Milestones
Begin touchscreen monitor installation activity.
Matters for
Management None at this time.
Attention
STATUS KEY
Green Yellow Red N/A
On Track Warning Not on Track Not applicable
-2-