SlideShare a Scribd company logo
1 of 19
Download to read offline
Project Portfolio
          for

     ALTARUM
     4401 Ford Ave
  Alexandria, VA. 22302




                          End Show
SCOPE OF SERVICE
   Phase 1
              PROJECT ORIENTATION
                         PROGRAMMING
                               SQUARE FOOTAGE FEASILBILITY STUDY
                                     BUDGET & SCHEDULE

        Phase 2
                   SPACE PLANNING
                              SCHEMATIC DESIGN
                                      DESIGN DEVELOPMENT

             Phase 3
                          INTERIOR FINISHES SPECIFICATIONS
                                    FURNITURE & FINISH SELECTION
                                           SIGNAGE


                   Phase 4
                                  CONSTRUCTION ADMINISTRATION
                                           CONSTRUCTION DRAWINGS


                       Phase 5
                                      SUPERVISION OF INTERIOR FINISH
                                       APPLICATIONS & FINAL WALK THROUGH
                                                                       End Show
PROPOSAL                                                                                   ARTICLE IV
    DEVELOPMENT                                                                            BASIC FEE SCHEDULE
                                                                                           In reviewing the project, FMG has arrived at the estimated design fee for the phases of the project set
                                                                                           forth below. The accuracy of these preliminary projected estimates is primarily dependent upon the
                                                                                           completeness of information provided by ALTARUM to FMG for the performance of design services at
                                                                                           this time. In particular, it is understood that changes in the scope of the project may increase the
                               ALTARUM                                                     amount of time necessary for the performance of the phases. In the event that this occurs, ALTARUM
                                                                                           will be notified of the change in fees required to complete this project. Additional work beyond the scope
                                                                                           of services detailed above shall be performed by Facility Matrix Group personnel at the rate of $65.00
                                                       Revised September 30, 2002
ARTICLE I                                                                                  per hour. Written authorization from ALTARUM shall be established prior to commencement of the
                                                                                           work.
INTRODUCTION
                                                                                           Please refer to Article II Basic Services for further description of the design phases.
This Professional Design Agreement ("Agreement") is made on March 14, 2002, at             Facility Matrix Group has estimated that the service identified above shall allow for the completion of
Bloomfield Hills, Michigan between Facility Matrix Group (FMG), a Michigan                 the project in the time required, based upon the following square foot costs:
corporation, and ALTARUM (“Client”), a Michigan corporation, for the request for               PHASE 1: Project Orientation @ $.06per square foot . . . . . . . . . . . . . . . . . . $2,867.00
the INTERIOR DESIGN for approximately 47,799 square feet of offices at three (3)               PHASE 2: Programming @ $.14 per square foot . . . . . . . . . . . . . . . . . . . . . . $6,691.00
floors (8th., 9th., 10th.) in the Transwestern Commercial Services Building 4401 Ford          PHASE 3: Space Planning @ $.16 per square foot . . . . . . . . . . . . . . . . . . . . . $7,647.00
Avenue, Alexandria, VA 22302 .                                                                 PHASE 4: Schematic Design @ $.12 per square foot . . . . . . . . . . . . . . . . . . . $ 5,735.00
                                                                                               PHASE 5: Design Development @ $.30 per square foot . . . . . . . . . . . . . . . . . $14,339.00
ARTICLE II                                                                                     PHASE 6: Interior Finish Specifications @ $.11per square foot . . . . . . . . . . . .     $5,257.00
                                                                                               PHASE 7: Supervision @ $.13 per square foot (approx. 90 hours) . . . . . . . . . .        $6,213.00
BASIC SERVICES                                                                                 PHASE 8: Signage @ $.04 per square foot . . . . . . . . . . . . . . . . . . . . . . . . . $1,911.00
                                                                                               PHASE 9: Proposed Furniture and finish Selection @ $.09 per square foot . . . . . . . $4,301.00
PHASE 1 – PROJECT ORIENTATION
                                                                                                                  Sub Total $ 54,961.00
FMG shall meet with ALTARUM and the Transwestern Commercial Services
Building’s designated representative(s) to discuss the general design theme and the        TOTAL COMPENSATION for services identified herein above shall be for an amount
desired project image. The project “Team” participants shall be established with             not to exceed: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $54,961.00
hierarchal authorizations identified.

FMG shall obtain, for their review and use, the building’s current subject architectural   PAYMENT SCHEDULE
drawings and specifications, landlord’s work letter, anticipated construction
“Estimate of Probable Cost”, and relevant facility constraints. The building’s subject     1st payment
floors will be toured by the participants to verify “As Built” conditions and              Due prior to the start of phase 1                                     12% of total compensation
parameters.                                                                                                                              $6,595.32
                                                                                           2nd payment
FMG shall discuss with ALTARUM and the Transwestern Commercial Services the                Due upon completion of phase 3                                        25% of total compensation
development of a preliminary project “Build-Out” completion schedule depicting the                                                       $13,740.25
design, selection, and documentation of interior materials and finishes, F.F. & E., and    3rd Payment
signage which reinforce the goals of the interior design solution.                         Due upon completion of phase 6                                        25% of total compensation
                                                                                                                                         $13,740.25
                                                                                           4th payment
PHASE 2 - PROGRAMMING                                                                      Due upon completion of phase 9                                        25% of total compensation
                                                                                                                                         $13,740.25
FMG shall meet with designated ALTARUM representative(s) to gather information             5th payment
via interviews conducted to ascertain individual and departmental adjacencies, needs       Due upon completion of the project            $7,144.93               13% of total compensation
and requirements, miscellaneous equipment and data / electrical requirements.
                                                                                           Total                  $54,961.00
FMG shall assimilate and compile the obtained data and produce a programming
report identifying the intra and inter departmental needs and requirements.                                                                                                                     End Show
PROJECT                                                          Altarum

     ORGANIZATION                                                        VP Finance
                 Altarum
                                                                          Phil Fazio               Altarum
Issued: 6/4/02
                                 Director of                                                                 IT Director
                                 Contracts


                    Altarum                                      Altarum                           Altarum

                      Contracts/Procurement                           Construction Lead                      Data/Phones
                                                                              s


                                                                 Altarum

                                                                        Project Lead
     Arch Project Manager                                                                                                   Building Manager



                                                                FMG

                           FMG                                     Project Director                  FMG

                           Exec. Management                             Bruce Tharp                   Account Executive
                             David Daugherty                                                                 Becky Peters
                                                        Communication              Communication


                                                Communication


                           HMI
                                                                FMG                                FMG

                       Account Manager                            Interior Designer                  Project Coordinator
                           June Smith Muranyi                                                                 Kay Webb

                                                                                                                                         End Show
PROGRAMMING
                                                                                                                              Programming Survey
        ALTARUM PROGRAMMING SURVEY                                                                                                     Area/Personnel Summary

                                                                 Project:                  Altarum                                                                           Issue Date: June 14, 2002
                                                                                        4401 Ford Ave
                                                                                     Arlington, VA. 22204                                                                    Revised: June 18, 2002

DIVISION: FACILITIES (SSV) 1/3                   DATE: 6/10/02
                                                                                                                                                                                   Total
PROJECT NO.: 10044                                                                                                         Personnel        Personnel           Total            Ancillary     Scenario A        Scenario B       Scenario C
                                                                    Abv                        Division                     Existing         Growth           Personnel           Areas           Sq Ft             Sq Ft            Sq Ft

STAFF AND GROWTH REQUIREMENTS                                      Ceer         Ceer                                             6                2                8                3             1,792            2,662              1,850
                                                                   MSV          Contracts & Procurements                         2                2                4                1              516             1,166               516
STAFF BELOW LEVEL 12                   TOTAL CURRENT STAFF 5        ED          Enterprise Development                           3                1                4                3              706             1,118               793
                                                                   ESD          Enterprise Solutions Development                46                15               61               12           10,305            20,020             10,926
GROWTH OVER NEXT TWO YEARS 5                                      HSD02         Health Solutions                                35                20               55               6             8,588            17,445             10,137
                                                                    SSV         Human Resources                                  3                1                4                2              754             1,404               754
TOTAL CURRENT STAFFAND GROWTH 5                                   SSV-NS        I.T.                                             6                0                6                3             2,691            3,503              2,691
                                                                   S SV         Publications                                     5                0                5                3             1,637            2,049              1,637
                                                                  SSV-Y3        Facilities                                       6                0                6                37            7,721            8,697              7,721

                                                                                                                               112                41              153               70           34,710           58,064              37,025
SUPPORT AREAS 400 SQ.FT.                                                                                          Total

                                                                 Summary
RECEPTION 1 (400 SQ.FT.)                                                                                                     Total            Total
                                                                                                                            Existing         Growth             Total              Total
HAVE AREA TO DISPLAY MARKETING MATERAL                                                           Item                      Personnel        Personnel         Personnel          Ancillary      Scenario A       Scenario B       Scenario C


•HEIGHT OF DESK SHOULD OBSCURE VIEW OF WORKSURFACE                                             Net Sq Ft / Qty Total
                                                                                      Building Total Sq Ft Available
                                                                                                                               112                41              153               70           34,710
                                                                                                                                                                                                 45,042
                                                                                                                                                                                                                   58,064
                                                                                                                                                                                                                   45,042
                                                                                                                                                                                                                                      37,025
                                                                                                                                                                                                                                      45,042
                                                                                                         Remainder                                                                               10,332           (13,022)            8,017
•STORE SECURITY BADGES                                           Circulation Sq Ft (Tot Net Sq Ft x Approx 31.026%)                                                                              10,771            18,021             11,490
                                                                                      Net Sq Ft Minus 45% Circ                                                                                   23,939            40,043             25,535
•SIGN IN BOOK                                                                             Personnel / Sq Ft Ratio
                                                                                                                                                  Programming Survey                              310               518                331


•WILL NOT HAVE SEPARATE WORKSTATION, NEEDS AREA TO PAY BILLS                                                                                           Department Requirements
                                                                   Notes:
                                                                                 Company: Altarum                                                                                 Issue Date: June 13, 2002
•MINIMAL FILING                                                             1
                                                                            2
                                                                                Assumes that for the primary purpose of this study, all workstations are 8' x 10' and all private offices are 12' x 16'.
                                                                                Scenario A: Totally Open Environment
                                                                            3
                                                                                 Department: Enterprise Development (ED)
                                                                                Scenario B: Totally Closed Environment
                                                                                                                                                                                  Revised: 6/14/02
•GUEST SEATING FOR 4                                                        4
                                                                            5
                                                                                Scenario C: Hybrid Environment
                                                                                ( ) = Negative Number
                                                                                                                                     Scenario A           Scenario B            Scenario C           Sq.   Ft. Total
                                                                                 FUNCTION                                              Open       Closed Open         Closed Open            Closed        A        B         C
•STORE PHONE BOOKS/ MENUS                                                       GRADE 15                                                      1                             1                     1        132     192        192
                                                                                GRADE 12 & ABOVE
•WILL HAVE PARKING METER TO STAMP GUEST TICKETS                                 GRADE BELOW 12                                                2                             2            2                 160     384        160
                                                                                                                             Growth:          1                             1            1                  80      80         80
PRINTER AREAS 6 @ 100 SQ.FT EA. - 600 SQ.FT.
                                                                            1   Conference Rooms (Exec)                                                 1                    -                    -        164           -        -
•2 PER FLOOR                                                                2   Enclaves (Exec)                                                         1                    -                    -        100           -        -
                                                                            3   Project Rooms
•STAND ALONE COPY                                                           4   Miscellaneous
                                                                            5   Hoteling                                                      1                             1                     1         48          48    48
•WORKTOP PRINTERS WITH STORAGE BELOW                                        6   Library (Shared w/HSD02)                                                                                                     -           -     -
                                                                            7   File Storage                                                  1                             1            1                  27          27    27
•FLIPPER UNITS ABOVE TO STORE INK CARTRIDGES, ETC.                          8   Fax Machine (Shared)                                          1                   1                      1                  40          40    40
                                                                                    (1/2 of 4' x 20' area)
•NEED TO STORE CASE OF PAPER AT LEAST IN EACH
                                                                                                                         Personnel            4         -         -         4            3        1     372         656       432     Net.Sq.Ft.
MAIN CONFERENCE ROOM 1 @ 540 SQ.FT - 540 SQ.FT.                                                                      Non Personnel            3         2         1         2            2        1     379         115       115     Net Sq.Ft.
                                                                                                                                                                                                        751         771       547     Net Total
•18’ X 30’                                                                                                                                                                                              338         347       246     45% Circ.
                                                                                                                                                                                                      1,089       1,118       793     Dept. Total
•EAST VIEW, SOUNDPROOFED                                                        Notes:
                                                                            1   Assumes that for the primary purpose of this study, all workstations are 8' x10' and all private offices are 12' x 16'.
•VIDEO TELECONFERECING                                                      2   Scenario A : Totally Open Environment
                                                                            3   Scenario B: Totally Closed Environment
•POLYCOM PHONE LINES, NETWORK, AND ANALOG LINES                             4   Scenario C: Hybrid Envirnoment

•PAM WOULD LIKE IT TO BE FLEXIBLE, BUT NOT “TO FLEXIBLE”
                                                                                                                                                                                                                                                   End Show
SQUARE FOOTAGE                                                                          EConclusion
                                                                                        The Feasibility Study was developed in order to assist ALTARUM in determining the most desirable solution

    FEASIBILITY STUDY                                                                   for the configuration of its new multi-floored offices in Alexandria, VA.
                                                                                        Compilation of current programming information obtained by FMG in conjunction with data provided by
                                                                                        ALTARAM has resulted in a recommendation of use by comparing three different scenarios:

                                                                                        Scenario “A”: Totally open office environment with no personnel in enclosed offices.
                                                                                        Scenario “B”: Totally enclosed office environment with all personnel in enclosed offices.
                                     ALTARUM                                            Scenario “C”: A hybrid of “A & B” scenarios with only E.C. personnel in enclosed offices and all other
                                                                                        personnel in open office environment.

Executive Summary                                                                       Facility Matrix Group recommends pursuing the hybrid Scenario “C” in order to maintain the maximum in
                                                                                        flexibility for future reconfigurations and additions for the following reasons:
A. Background to Feasibility Study. This report has been prepared in
response to ALTARUM’s requirements, which authorizes FMG to conduct management                                              END     OF SUMMARY
programming to determine a square footage feasibility study.

Primary Objectives:
·   Comparative analysis of open office environment vs. totally enclosed environment.
·   Compilation of square footage requirements, plus anticipated growth.
·   Determination of the optimum solution utilizing maximum flexibility.

Review Undertaken:
·   Assimilation of previous programming effort.
·   Review of previous test fit efforts.
·   Departmental Interviews.
·   Tour of leased space and meeting with Building Mgrs. Office.

Key Assumptions:
·   Open environment crucial in order to accommodate change.
·   Minimal accumulation of primary circulation square footage.
·   Identification of potential duplicity in ancillary elements.

Unresolved Issues:
·   Future acquisitions and growth ramifications thereof.



B. Adjacency Matrix.
The bubble diagrams have been prepared based on the following general assumptions:
·   Total number of employees (existing + Growth).
·   Accounting of all ancillary elements.
·   Conclusive square footage calculations.
·   Intra – Departmental adjacencies prioritization.                                                                                                                                    End Show
Furniture, Fixtures & Equipment
SCHEDULE & BUDGET                            Description of Work
                                         8th Floor - Revised 7/23/02
                                                    Hoteling Workstations 8x8
                                                                                    U of M QT Y

                                                                                     Ea       2
                                                                                                      Unit Rate

                                                                                                  $ 4,700.00          $
                                                                                                                            Sub-T otal

                                                                                                                                    9,400.00    $
                                                                                                                                                      Labor

                                                                                                                                                          658.00   $
                                                                                                                                                                       Grand T otal

                                                                                                                                                                           10,058.00
                                                                                                                                                                                         Actual Product $

                                                                                                                                                                                         $            -
                                                      Staff Workstations 8x10        Ea      19   $ 5,500.00          $           104,500.00    $       7,315.00   $       111,815.00    $            -
                                                Copy/Print Workstations 8x10         Ea       1   $ 4,700.00          $             4,700.00    $         329.00   $         5,029.00    $            -
                                                 Executive Workstations 12x14        Ea       1   $ 8,000.00          $             8,000.00    $         560.00   $         8,560.00    $            -
                                                            Systems Furniture        Lot     23   $       -           $                  -      $            -     $              -      $     125,667.49
                                                  Miscellaneous Files & Storage      Ea      49   $    550.00         $            26,950.00    $       1,886.50   $       28,836.50     $      15,738.54
                                                 Workstation Conference Areas        Ea       4   $ 1,400.00          $             5,600.00    $         392.00   $         5,992.00    $       4,263.86
                                                            Conference Rooms         Ea       4   $ 18,500.00         $            74,000.00    $       5,180.00   $       79,180.00     $      69,738.76
                                                               Reception Area        Lot      1   $ 5,000.00          $             5,000.00    $         350.00   $         5,350.00    $            -
                                                                          Lobby      Ea       1   $ 10,000.00         $            10,000.00    $        700.00    $       10,700.00     $      29,769.02
                                                             Enclaves 80 Sq Ft       Ea       5   $ 2,500.00          $            12,500.00    $         875.00   $       13,375.00     $       9,260.40
                                     Publication Work Area/Central Copy/Mail         Ea       1   $ 5,500.00          $             5,500.00    $         385.00   $         5,885.00    $      15,260.86
                                                    Coffee Lounge/Kitchenette        Ea       1   $ 3,700.00          $             3,700.00    $         259.00   $         3,959.00    $       2,037.00
                                                                      File Room      Ea       1   $ 2,000.00          $             2,000.00    $         140.00   $         2,140.00    $            -
                                                                Copy / Printer       Ea       4   $    550.00         $             2,200.00    $         154.00   $         2,354.00    $       1,696.00
                                                                     IT Storage      Ea       1   $ 2,000.00          $             2,000.00    $         140.00   $         2,140.00
                                                                           SCCR      Ea       1   $ 3,500.00          $             3,500.00    $         245.00   $         3,745.00
                                                                      IT Server      Ea       1   $ 10,500.00         $            10,500.00    $         735.00   $        11,235.00
                                                                   Misc Seating      Lot      1   $       -           $                  -      $            -     $              -      $         727.20
                                                                                                  Sub-Total           $     290,050.00          $ 20,303.50        $    310,353.50       $   273,431.93

                                         9th Floor - Revised 7/23/02
                                                 Hoteling Workstations 8x8           Ea      4    $     4,700.00 $              18,800.00 $           1,316.00     $        20,116.00    $             -
                                                   Staff Workstations 8x10           Ea     52    $     5,500.00 $            286,000.00 $          20,020.00      $      306,020.00     $             -
                                              Executive Workstations 12x14           Ea      3    $     8,000.00     $         24,000.00 $           1,680.00      $       25,680.00     $             -
                                                         Systems Furniture           Lot    59    $           -      $                 -     $             -       $              -      $     308,401.04
                                                                  Budget Summary
                                                           Coffee / Lounge           Ea      1    $     3,700.00 $               3,700.00 $             259.00     $         3,959.00    $        1,645.20
               Professional Fees                             Coffee Station          Ea      1    $           -      $                 -     $             -       $              -      $             -
                    Description of Work         U of M       QT Y Library            Ea      1
                                                                                     Unit Rate    $     5,600.00 $
                                                                                                              T otal             5,600.00 m$
                                                                                                                                       Com ents         392.00     $         5,992.00    $        3,681.48
                                Interior Design SQ FT Enclaves 80 Sq $
                                                            47799        Ft          Ea      4 1.78
                                                                                                  $      $      85,082.22
                                                                                                        2,500.00 $           FMG10,000.00 $             700.00     $       10,700.00     $       8,235.68
                                 Architectural Executive Conference Rooms
                                                SQ FT       47799        $           Ea      2 1.21
                                                                                                  $      $      57,836.79
                                                                                                       15,000.00 $           DBI
                                                                                                                               30,000.00 $           2,100.00      $       32,100.00     $       5,245.68
                     Mechanical & Engineering SQ FT Project Work Room
                                                            47799        $           Ea      5 0.90
                                                                                                  $      $      43,019.10
                                                                                                        4,700.00 $           EK23,500.00 $
                                                                                                                                 Fox                  1,645.00     $        25,145.00    $       21,105.18
                           General Contractor Miscellaneous47799 Storage
                                                SQ FT       Files &      $           Ea     35 - $       $ 550.00 $   -      Included in Construction 1,347.50
                                                                                                                                19,250.00    $        $            $       20,597.50     $      14,975.69
                              Furniture Lease      %           File/Storage          Ea      1    $      $    296,724.38
                                                                                                        2,000.00 $           25%2,000.00 $ Budget 140.00
                                                                                                                                  Of Furniture                     $         2,140.00    $          815.92
                                    Legal Fees    Lot        Copy / Printer          Ea      4    $      $ 550.00 $   -          2,200.00 $             154.00     $         2,354.00    $       3,392.00
                                    Insurance     Lot                                             Sub-Total           $     425,050.00          $    29,753.50     $    454,803.50       $   367,497.87
                                                                                           Sub-Total    $    185,938.11
                                        10th Floor - Revised 7/23/02
               Construction                     Hoteling Workstations 8x8             Ea     4   $      4,700.00 $             18,800.00 $            1,316.00     $       20,116.00     $            -
                      Description of Work      U of M         QT Y                    Produ ct              I nstallation                 T otal
                                                  Staff Workstations 8x10             Ea    50   $      5,500.00 $            275,000.00 $         19,250.00       $      294,250.00     $            -
                                    8th Floor    Lot                                                                                        *
                                            Executive Workstations 12x14              Ea     0   $      8,000.00 $                     -      $            -       $               -     $            -
                                    9th Floor    Lot
                                                         Systems Furniture           Lot    54   $              -      $               -      $            -       $               -     $     262,307.81
                                   10th Floor    Lot
                                              Miscellaneous Files & Storage           Ea    27   $         550.00      $       14,850.00 $           1,039.50      $       15,889.50     $            -
                                   Sub-Total                                                                                $                    762,940.00
                                              Executive Conference Rooms              Ea     1   $      2,500.00 $               2,500.00 $             175.00     $         2,675.00    $       2,622.84
                                                              Copy / Printer          Ea     2   $         550.00 $               1,100.00    $          77.00     $          1,177.00   $       2,544.00
                                       ME&P                                                                                 $                    325,640.00
                                                       Project Work Room              Ea     4   $      6,200.00 $             24,800.00 $           1,736.00      $       26,536.00     $      18,027.44
                                                          Enclaves 80 Sq Ft           Ea     3   $      2,500.00 $               7,500.00 $             525.00     $         8,025.00    $       7,414.85
                                                                                                                Sub-Total $                   1,088,580.00
                                                                    Storage           Ea     2   $      2,000.00 $               4,000.00 $            280.00      $         4,280.00    $      12,727.12
                                                                 Safe Room            Ea     1   $      2,000.00 $               2,000.00     $         140.00     $         2,140.00    $            -
               FF&E                                                     Lab           Ea     1   $      6,500.00 $               6,500.00 $             455.00     $         6,955.00    $            -
                   Description of Work         U of M         QT Y                    Produ ct              I nstallation                 T otal
                                                        Lunchroom Booths              Ea     1   $     15,000.00 $             15,000.00 $           1,050.00      $       16,050.00     $            -
                                    8th Floor    Lot                      $             290,050.00       $       20,303.50 $                     310,353.50
                                                     Classified Work Room             Ea     1   $     11,400.00 $              11,400.00 $             798.00     $        12,198.00    $            -
                                    9th Floor    Lot                      $             425,050.00       $        29,753.50 $                    454,803.50
                                                                    Kitchen           Ea     1   $      1,500.00       $         1,500.00     $         105.00     $         1,605.00    $            -
                                   10th Floor    Lot                      $             394,150.00       $        27,590.50 $                    421,740.50
                                                                   Cafeteria          Ea     1   $      5,500.00 $               5,500.00 $             385.00     $         5,885.00    $       9,592.00
                                                               Coffee Lounge          Ea     1   $      3,700.00 $               3,700.00 $             259.00     $         3,959.00    $         924.00
                                                             Sub-Total $             1,109,250.00        $     77,647.50    $                 1,186,897.50
                                                               Coffee Station         Ea     1   $              -      $               -      $            -       $               -     $            -
                                                                                                  Sub-Total           $      394,150.00         $    27,590.50     $    421,740.50       $   316,160.06
               Misc
                      Description of Work    Miscellaneous FurnitureY Floors
                                                   U of M       QT All               Lot    1
                                                                                     Produ ct               I nstallation                  T otal                                        $    41,024.64
                             Move Management         Lot                      $            47,799.00 $      3,345.00 $                                51,144.00
                                 AV Equipment        Lot    Incl. in Const. $ $
                                                                     Installation    Lot       1 -     $         -   $                                      -                            $    81,000.00
                              Tele/Data Cabling      Lot                      $            95,598.00 $      6,691.86 $                               102,289.86
                                Security System      Lot                      $                  -     $         -   $                                      -
                                                                                                   Grand Total $ 1,109,250.00                   $     77,647.50    $ 1,186,897.50        $ 1,079,114.50
                                   Card Reader       Lot                      $                  -     $         -   $                                      -
                       Artwork And Accessories       Lot                      $                  -     $         -   $                                      -
                                         Signage     Lot                      $            15,200.00 $      1,064.00 $                                16,264.00
                              Vending Machines       Lot         NIC          $                  -     $         -   $                                      -
                             Kitchen Equipment       Lot         NIC          $                  -     $         -   $                                      -
                              Coffee Equipment       Lot         NIC          $                  -     $         -   $                                      -
                       Furniture Refurbishment       Lot         NIC          $                  -     $         -   $                                      -

                                                             Sub-Total        $       158,597.00        $      11,100.86      $                     118,553.86


                                                                                    Estimated Project Budget                  $                2,579,969.47
                                                                                                                                                                                             End Show
SPACE PLANNING




                 North View




                              End Show
DESIGN DEVELOPMENT

     ALTARUM




                                              8th Floor Conference Room


 8th Floor Lobby




                   10th Floor Coffee Lounge
                                                                          End Show
ARCHITECTURAL MATERIAL SELECTION

                                                                                                                                                                                                                   ALTARUM




Carpet
CPT-1     Shaw            Mode # 50885               Balanced                 Multi level- Patterned Loop 100%        8th Floor Lobby
          Contract                                   #85712                   Solution Dyed Ultron VIP
                                                                              BCP Nylon 6.6, 12' Broadloom
                                                                              Repeat: 18"W X 10"L

CPT-2     Durkan          Two-Steppe                 TWS-401                  Patterned Loop                          8th Floor Overall
                                                     Ballet                Paint
                                                                             Solutia Ultra VIP Nylon 6.6
                                                                              32 oz., 12' Broadloom
                                                                           P-1Repeat: 18" W X 36"L
                                                                                         Sherwin           Gauntlet                     SW7019             (Dark Gray)                  8th Floor Lobby
                                                                                         Williams          Gray                                            Satin Finish                 Overall
CPT-3     Durkan          Delano                     DLO-401                  Patterned Loop                         9th Floor Overall
                                                     The Romance           P-2Solutia Ultra VIP Nylon 6.6 Tourchlight
                                                                                         Sherwin                                      SW6374               (Vibrant Orange              8th Floor Lobby
                                                                                         Williams
                                                                              32 oz., 12' Broadloom                                                        Yellow)                      10th Floor Coffee Lounge
                                                                              Repeat: 18" W X 12 3/4"L                                                     Satin Finish
         Ceiling
CPT-4     Durkan                                                         P-3Patterned Sherwin           Retreat                   SW6207                    (Dark Gray
         ACT-1       USGHot Lights Astro ClimaPlus HLS-401     #8223                    Loop 2'
                                                                                       Williams x 5/8" Panel size
                                                                                          2' x                    10th Floor Overall
                                                                                                                              Workrooms, Enclaves,          Green)
                                   (SLT)           High Speed White         Solutia Ultra SLT Nylon 6.6
                                                                                          VIP Edge                            Enclosed Staff areas, Mail, Satin Finish
                                                                            32 oz., 12' Broadloom15/16" Grid - White
                                                                                          Donn DX                             Central Copy
                                                                            Repeat: 18" W X 36"L
                                                                         P-4           Sherwin          Moonraker                 SW6701                    (Bright Yellow              Coffee Stations
         ACT-2       USG           Orion 270                   #66271                  Williams x 3/4"Vinyl Tile Lobby
                                                                                          2' x 2'      Panel size             Open office                   Green)                      Paint behind backsplash
CPT-5     Bentley       Kings Road                  519                     Dense Cut Pile
                                   ClimaPlus (SL)                                         SL Edge                             Executive Conferences         Satin Finish
                                                   Black Pearl              Dupont Antron Legacy Nylon            Coffee Stations
                                                                                          Donn DX 15/16" Grid - White
                                                                            Dura Tech Soil Treatment  VCT-1       Mannington      Designer                         280 Lapis      Size: 12"X12", Gauge:1/8"        10th Floor Coffee Lounge
                                                                         P-512' Broadloom
                                                                                       Sherwin          Rejunenate                SW6620
                                                                                                                                  Essentials                (Vibrant Orange)              Kitchen Paint
                                                                                                                                                                                  Vinyl Composition Tile           10th Floor Lunch Room
         ACT-3       USG           Panz                        Panz 002                Williams                               Reception                     Satin Finish
                                                                            Repeat: No                                                                                            (Bright behind Backsplash
                                                                                                                                                                                          Blue)
                                   Perforated Panel #D500      Silver Satin finish                                            Note: Provide USG Compasso
                                   W/ Acoustibond              w/ Fineline Edge                                               edge profile 2'-4"H w/ finish
                                                               install in USG Fineline                VCT-2       Mannington to match silver satin
                                                                                                                                  Designer                         220 Horizon    Size: 12"X12", Gauge:1/8"        10th Floor Coffee Lounge
                                                                                                                                  Essentials                                      Vinyl Compostion Tile            10th Floor Lunch Room
Plastic Laminate                                               Edge 9/16" (DXF)
                                                                    Suspension Grid                                                                                               (Dark Dusty Blue)
PL-1      Avonite         Frosted Glass              K3-8480                 Translucent Solid                        8th Floor Recepton
          Solid Surface                              Satin Finish also in silver satin
                                                                              Surface                                 Transaction Top
                                                                                                      VCT-3           Mannington      Designer                   130 Wedge wood   Size: 12"X12", Gauge:1/8"        10th Floor Coffee Lounge
PL-2      Avonite         Sky Glass                  K3-8465                  Translucent Solid                                       Essentials
                                                                                                                      10th Floor Coffee Lounge                                    Vinyl Composition Tile           10th Floor Lunch Room
          Solid Surface                              Satin Finish             Surface                                 Rotating Transaction Top                                    (Light Dusty Blue)

PL-3      Nevamar         Silver Alu Metalx          MXT-003T                 Plastic Laminate        VCT-4           Mannington        Designer
                                                                                                                      All millwork countertops                   263 Sunflower    Size: 12" x 12", Gauge:1/8"      10th Floor Coffee Lounge
          ARP Plus        Textured                                                                                    All millwork upperEssentials
                                                                                                                                         cabinets                                 Vinyl Composition Tile           10th Floor Lunch Room
                                                                                                                                                                                  (Yellow)
PL-4      Nevamar         Wrought Iron               S-6-54T                  Plastic Laminate                        All millwork
          ARP Plus        Textured                                                                    VCT-5           Lower Cabinets Designer
                                                                                                                      Mannington                                 273 Spectrum     Size: 12" x 12", Gauge:1/8"      10th Floor Coffee Lounge
                                                                                                                                       Essentials                Orange           Vinyl Composition Tile           10th Floor Lunch Room
PL-5      Chemetal     Pewter Wave                   #244S                    Metal Dark Gray                         Coffee Stations Backsplash                                  (Orange)
          800-807-7341                                                        Wave Laminate                           on all levels
                                                                                                                                                                                                                                              End Show
FURNISHINGS SELECTION




                        End Show
CONSTRUCTION DRAWINGS




   DBI Architects, P.C.




                          End Show
BID DOCUMENTS
                 Contractor Request for Proposal                                                        NEW FURNITURE INSTALLATION WORK

 I. REQUEST FOR PROPOSAL                                                                                                           FOR
 Transwestern Commercial Services, on behalf of Transwestern Park                                                                        IV.   General Conditions
 Center II, LLC, is soliciting bids for the tenant renovations for Altarum. The                                             Alt a r u mPre-Installation:  The Contractor will be responsible
 space consists of approximately 47,799 square feet of tenant build-out at                                                              for field measuring the space, attending Project
                                                                                                                                        Coordination meetings, working around field
 Park Center II, 4401 Ford Avenue, Suite 800, Alexandria, Virginia 22302.                                                  Park Centerconditions and coordination of
                                                                                                                                         II
 This bid package consists of the following sections:                                                                                   furniture/construction, furniture/building electrical
                                                                                                                         4401 Ford Avenue
                                                                                                                                        and furniture/voice & data interface. Clearances
  I.           Request for Proposal                                                                                  Alexandria, Virginia 22302
                                                                                                                                        and egress aisles are critical to the project, and
 II.           Building Rules and Regulations                                                                                           shall not be compromised or reduced.
 III.          Bid Forms, Long Lead Items, Alternates Form &                                                                            •The project will require straight time non-union
                                                                                                                            V. Scope of Work services.
                                                                                                                        FMG JOB NO. 10044
                                                                                                                                        installation
               Subcontractor List
                                                                                                                             The work to which this pertains generally consists of
                                                                                                                                        •All electrical components associated with the
 IV.           Retainage Release Form
                                                                                                                        September 20, systems furniture shall be VA. (FMG's Job
                                                                                                                            the Altarum, located in Alexandria, connected by the
                                                                                                                                        2002
 V.            Drawing Inventory                                                                                            No. 10044) furniture installers. The hard-wire connection of the
                                                                                                                                         Drawings are intended to include
                                                                                                                            everything building to the systems furniturecompletion
                                                                                                                                         obviously necessary for proper will be performed
  The following items constitute the bid requirements and instructions:
                                                                                                                            of the work.
                                                                                                                                        by an electrician supplied by the Contractor.
  PRE-BID &Park Center II, 4401 Ford Avenue, Alexandria, Virginia 22302
            CONTACTS
                                                                                                                             The work consists of, but is not limited to,
                                                                                                                                        •The contractor will be required to coordinate with
  1. Questions and clarifications regarding the construction documents
           II. Building Rules theRegulationsPark, DBI Architects,
                                    & attention of Jin                                                                      Confirmations of field conditions, providingTeam, the General
                                                                                                                                        the FMG, Project Management all field
             should be directed to
                                                                                                                            measuring Contractors’ Electrical Subcontractor and the
                                                                                                                                        as required
           BUILDING STANDARD CONFORMANCE -toThecopied to
             via facsimile 703.847.9336. All inquiries are be Contractor must be                                                        Communications Subcontractor.
           certain thatPerucci, Transwestern Commercial Serviceshardware conform
             Maribeth all ceiling tiles, Venetian blinds, and door via                                                      Delivery, installation and set up of all new workstations
           tofacsimile 703/845-8042. Door locks should be keyed to the building
               the building standards.                                                                                      and new freestanding furniture
  2. DBI Architects will issuethe floor addressing the Building Manager should be
           master and to addenda master. The contractors’                                                                     VII. Lump Sum
                                                                                                                            Removal of all furniture related debris; building
           consulted beforeclarifications as necessary. The addenda will
             questions and ordering these items.                                                                            dumpster is not to be used unless specific materials, is
                                                                                                                              We hereby propose to furnish all labor, permission
             PROTECTIONall of the participating contractors..
               be issued to OF NON-CONSTRUCTION AREAS - The Contractor                                                      provided by building contractor at no furniture work
                                                                                                                              tools, and will provide and install all cost to Owner
             shall protect all walls, floors, carpet, furniture and fixtures and shall repair                               Develop and maintain an installation New Office in
                                                                                                                               required to complete the Altarum schedule
             or replace damaged propertyThe undersignedthe Owner. Masonite (or
                                                 without cost to as bidder, declares that only the interested                  accordance with all new Contract Documents
             plywood) must be placed asperson or parties interested in this Bid as principals are those
                                                 a walkway on the public corridors from                                     After installation, furniture orientation for the Owner
                                                                                                                               supplied for the following lump sum amount which
             freight elevator to the construction site and to thehe visited the site ofto project described by
                                               named herein. That Public Restrooms the
                                                                                                                            Provide a punch list for insurance, and all applicable
                                                                                                                               includes applicable each phase of new furniture
             protect the carpet from drywallthe bidetc. Common area carpet protection
                                                 dust, documents and has reviewed completely such documents                 installation State, and local taxes of whatever
                                                                                                                               Federal,
             is to be removed daily and the and agrees that he will provide all necessary labor, materials,
                                                carpet vacuumed daily.                                                         character and description.
                                               trade work and supervision required to complete the project for the          All furniture related permits
                                               stipulated sum and in the stated number of business days from
                                               written notice to proceed. The contractor understands all terms                 _                                      ______Dollars
                                               and conditions of the bid documents and written criteria. The
                                               contractor understands that this Bid must remain valid for a period             (Enter amount in writing)
                                               of thirty (30) calendar days from submission.
            DBI Architects, P.C.                                                                                               $_________________________Lump sum
                                                                 Stipulated Lump Sum of:                                       (Enter amount numerically)
                                                                $______________________

                                                                                                                                                                                        End Show
BID ANALYSIS                                                                                                                                                                                                                                                                                             Corbett Construction

                                                                                                                                                                                                                                                                                                  Interior Construction           ME&P

                                                                                                                                                                                                                                                                                                  $            30,195.00
                                                                                                                                                                                                                                                                                                  $               600.00
                                                                                                                                                                                                                                                              Rand Construction
                                                  8/30/02 FMG
                                                                                                                                                                                                                                                     Interior Construction          ME&P
               Description                        Estimate WO                     BCMI Construction                                               BCMI Revised 9/10/02                                                                                                                            $             1,800.00
                                                      ME&P                                                                                                                                                Tripp Contracting, LLC                     $            28,000.00                       $            83,857.00
                                                                                                                                                                                                                                                                                                  $               900.00
                                                                         Interior Construction            ME&P              Interior Construction               ME&P                 Delta
                                                                                                                                                                                                                                                     $             1,500.00
General Scope of Work                                                                                                                                                                                 Interior Construction           ME&P                                                        $            29,560.00
                                                                                                                                                                                                                                                     $             3,000.00
General Conditions                                                   $                 36,830.00                        $                    36,830.00                           $           -                                                                                                    $            28,504.00
Demolition                                                           $                    950.00                                                                                 $       (950.00)     $             43,935.00                                                                     $            95,000.00
Site Work                                                                                                                                                                                             $                500.00                                                                     $            95,000.00
                                                                                                                                                                                                                                                     $            96,339.00
Concrete X-Ray                                                       $                  5,200.00                        $                     5,690.00                           $           490.00                                                  $             6,745.00                       $           132,052.00
Metals                                                                                                                                                                                                $              1,850.00
                                                                                                                                                                                                                                                                                                  $            33,920.00
Flash Patching Allowance (Floor Prep)                                                                                                                                                                                                                $            24,750.00
Carpentry/Millwork                           $          99,258.30    $                 92,641.00                        $                    86,370.00                           $     (6,271.00)                                                    $            20,300.00
                                                                                                                                                                                                      $             82,115.00                        $            79,697.00
Rough Carpentry                                                      $                  6,214.00                        $                     6,214.00                           $           -                                                                                                    $             7,756.00
                                                                                                                                                                                                      $              4,789.00                        $           105,679.00
Moisture Control
                                                                                                                                                                                                                                                     $           125,052.00
Doors/Frames & Hardware                      $          49,180.00    $                 25,891.00                        $                   25,891.00                            $           -        $            27,057.00
Glass/Glazing                                $          20,587.00    $                  5,030.00                        $                   15,700.00                            $     10,670.00      $            17,162.00                         $            30,125.00
Drywall                                      $         105,065.00    $                 66,538.00                        $                   66,538.00                            $           -        $            82,697.00                                                                                               $       204,400.00
Acoustical/Ceiling                           $         224,697.40    $                125,644.00                        $                  125,644.00                            $           -        $           108,679.00                         $               938.98
Carpet/Base/VCT                              $          83,918.04    $                129,283.00                        $                  131,783.00                            $      2,500.00      $           134,000.00
                                                                                                                                                                                                                                                                                                                           $        39,762.00
Skim Perimeter Walls                         $          21,883.20    $                  8,200.00                        $                    8,200.00                            $           -                                                       $            25,012.00
                                                                                                                                                                                                                                                                                                                           $       179,000.00
Paint                                        $          35,499.25    $                 28,975.00                        $                   43,675.00                            $     14,700.00      $             33,253.00
Wallcovering                                 $           7,991.94                                                       $                    2,500.00                            $      2,500.00                                                                                                  $             6,800.00
Signage                                      $           8,047.50                                                                                                                                     $                939.00                                                 $      169,500.00
Appliances                                   $           5,643.00    $                  5,902.00                        $                     5,902.00                           $              -                                                                             $       32,500.00             tbd
Furnishings/Equipment                                                                                                                                                                                 $              8,100.00                                                                     $            13,830.00
                                                                                                                                                                                                      $             10,461.00                                                 $       27,895.00
Special Construction
                                                                                                                                                                                                                                                                              $      227,800.00
Light Fixtures                               $          88,927.00
                                                                                                                                                                                                                                  $    187,900.00                                                 $            24,114.00
Mechanical                                                                                          $      179,900.00                                     $       179,900.00     $              -
                                                                                                                                                                                                                                  $     18,750.00                                                 $           583,888.00   $       423,162.00
Plumbing                                                                                            $       17,640.00                                     $        17,640.00     $              -
                                                                                                                                                                                                                                                                                                  $                              1,007,050.00
Sinks & Faucets                              $           8,334.40                                                                                                                                                                 $     30,895.00    $            18,715.00
Fire Protection                                                                                     $       31,500.00                                     $        31,500.00     $           -                                    $    189,750.00                                                 $                                 18,115.00
Electrical                                                                                          $      189,740.00                                     $       190,900.00     $      1,160.00
Roofing                                                                                             $        1,150.00                                     $         1,150.00     $           -                                                                                                    $                              1,025,165.00
Banquette Seating                                                                                                                                                                                                                                    $            30,144.99
Misc. Folding Partition                      $           7,616.00    $                 10,461.00                        $                    10,461.00                           $           -        $             14,450.00                        $           595,997.97   $      457,695.00
8th Flr Blackout Shades                                                                                                 $                    10,307.00                           $     10,307.00      $             45,508.00                        $                             1,053,692.97       Included in Above
Projector Lift & Screens                                                                                                                                                                                                                             $                                25,873.00
Equip. Schedule (Rev. Alternate Form)                                                                                   $                    38,360.00                           $     38,360.00                                                                                                  $                1,800.00 (1) Ambassador ?
Building Standard Mini Blinds                                                                                           $                    20,874.00                           $     20,874.00      $            30,850.00                                                                             Not Included
                                                                                                                                                                                                                                                     $                             1,079,565.97
                                                                                                                                                                                                      $           646,345.00 $          427,295.00                                                       Not Included
Fee (OH&P)                                                           $                 24,192.23                        $                    26,551.00                           $      2,358.77
                                                                                                                                                                                                      $                               1,073,640.00                                                $              10,461.00
                                                        Sub-Total    $              571,951.23 $          419,930.00    $                667,490.00 $           421,090.00                                                                                                                                    tbd
                                                             Total   $                                  991,881.23      $                                 1,088,580.00           $ 96,698.77          $                                 41,513.00        Included in Above                            Included in Above
                                                                                                                                                                                                                                                                                                  $                8,800.00
                   Estimated Contractor Adds (No Addendums)          $                                     55,771.00    Included in Above (Per Bid Clarification Dated 9/9/02)                        $                               1,115,153.00   $               1,067.00 (4) Ambassador      $                9,315.00
                                                                                                                                                                                                                                                            Not Included                          $             (14,728.00)
                                                                                                                                                                                                                                                            Not Included                          $               (9,100.00)
                                                    Adjusted Total                                  $ 1,047,652.23                                                                                    $              (6,975.00)                                                                   $               (5,200.00)
                                                                                                                                                                                                                                                         Included in Above
Add/Deducts & Alternates                                                                                                                                                                                  Included in Above                          $              18,715.00                     $               (4,250.00)
Minus Permits                                                                                                                                                                                                                                            Included in Above                        $               (4,200.00)
                                                                                                                                                                                                      $             1,000.00 (4) Ambassador          $               2,618.00                     $               (1,100.00)
Draper - Micro Projector Lift                 $         13,848.00    $                 13,300.00                              Included in Above
                                                                                                                                                                                                           Not Included                                  Included in Above
DA-Lite - Electric Projector Screen 8'x8'     $          3,275.80                                                                  Alternate
                                                                                                                                                                                                           Not Included                              $              (5,499.00)                    $       1,025,165.00
(1) DA-Lite - Electric Projector Screen 8'10' $          3,495.80    $                   1,645.00 (1) Electrol                     Alternate
                                                                                                                                                                                                        Included in Above                            $                 (35.00)
(1) Mitsubishi Projector                                             $                   4,595.00                             Included in Above
                                                                                                                                                                                                      $           14,450.00                          $              (7,066.00)                                     47799 Sq FT
Scamp Noise Distortion System                 $          1,350.00             Not Included                                       Not Included
                                                                                                                                                                                                        Included in Above                            $              (3,187.50)
Misc. Folding Partition                                                    Included in Above                                  Included in Above                                                       $             8,800.00                         $              (5,889.60)
8th Flr Blackout Shades                                              $                  10,307.00                             Included in Above                                                         Included in Above                            $              (1,260.00)                    $               21.45
8th Floor Recept Floor Core                                          $                     490.00                             Included in Above                                                       $          (11,200.00)
Upgrade to (9) 2x4 Luna Lights                                       $                   8,800.00                             Included in Above                                                       $              (245.00)                        $       1,079,565.97
Add Screenwall - Detail 1/A-502                                            Included in Above                                  Included in Above                                                       $            (8,783.00)
Delete Storefront Glass /Replace with Drywall                              Included in Above                                  Included in Above                                                       $            (4,010.00)
                                                                                                                                                                                                                                                                      47799 Sq FT
Delete Paint to Have 1 Paint Selection                                                                                                NIC                                                             $            (9,069.00)
Delete Wallcovering / Replace with Paint                                                                                              NIC                                                                       NC
Delete Carpet Cutouts                                                $                 (2,500.00)                             Included in Above                                                                                                      $               22.59
Delete Drywall Soffits                                                                                                                NIC                                                             $ 1,115,153.00
Replace Seating Booth Fabric with Vinyl                                                                                               NIC
                                                        Sub-Total                                                                                                                                                     47799 Sq FT
                             Grand Total $ 788,617.63
                                                                                                                                                                                                      $               23.33                                                                                                End Show
Altarum DC Presentation
Altarum DC Presentation
Altarum DC Presentation
Altarum DC Presentation
Altarum DC Presentation

More Related Content

Viewers also liked

Product Procurement
Product ProcurementProduct Procurement
Product Procurementbtharp
 
Relocation Managment
Relocation ManagmentRelocation Managment
Relocation Managmentbtharp
 
GM San Francisco, CA
GM San Francisco, CAGM San Francisco, CA
GM San Francisco, CAbtharp
 
Program Management
Program ManagementProgram Management
Program Managementbtharp
 
คู่มือ SketchUp
คู่มือ SketchUpคู่มือ SketchUp
คู่มือ SketchUpPiyaboon Nilkaew
 
Navidad en las conchas
Navidad en las conchasNavidad en las conchas
Navidad en las conchasbpsalamanca
 

Viewers also liked (9)

Product Procurement
Product ProcurementProduct Procurement
Product Procurement
 
Relocation Managment
Relocation ManagmentRelocation Managment
Relocation Managment
 
GM San Francisco, CA
GM San Francisco, CAGM San Francisco, CA
GM San Francisco, CA
 
Cáncer de mama
Cáncer de mamaCáncer de mama
Cáncer de mama
 
Pie diabético
Pie diabéticoPie diabético
Pie diabético
 
Cáncer de mama
Cáncer de mamaCáncer de mama
Cáncer de mama
 
Program Management
Program ManagementProgram Management
Program Management
 
คู่มือ SketchUp
คู่มือ SketchUpคู่มือ SketchUp
คู่มือ SketchUp
 
Navidad en las conchas
Navidad en las conchasNavidad en las conchas
Navidad en las conchas
 

Similar to Altarum DC Presentation

Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeffNASAPMC
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Antonio Coladarce
 
Project Management Services
Project Management ServicesProject Management Services
Project Management ServicesBruce Tharp
 
Project+brief presentation july
Project+brief presentation julyProject+brief presentation july
Project+brief presentation julygiap0083
 
Comments on Glass Big Push II & III.pdf
Comments on Glass Big Push II & III.pdfComments on Glass Big Push II & III.pdf
Comments on Glass Big Push II & III.pdfBrij Consulting, LLC
 
Infrastructure project and responsibility break down
Infrastructure project and responsibility break downInfrastructure project and responsibility break down
Infrastructure project and responsibility break downBhim Upadhyaya
 
Engineering
EngineeringEngineering
EngineeringHaDeGo
 
Feed report
Feed report Feed report
Feed report jadamsm
 
ARC_SBIR_TechInvestments_Handbook_2012
ARC_SBIR_TechInvestments_Handbook_2012ARC_SBIR_TechInvestments_Handbook_2012
ARC_SBIR_TechInvestments_Handbook_2012Matthew F. Reyes
 
[AgileCMMI] Practical Experience Report: Application of Project Management ar...
[AgileCMMI] Practical Experience Report: Application of Project Management ar...[AgileCMMI] Practical Experience Report: Application of Project Management ar...
[AgileCMMI] Practical Experience Report: Application of Project Management ar...davidobama
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve Satish Yadavalli
 
Buildings construction-mgt-1
Buildings construction-mgt-1Buildings construction-mgt-1
Buildings construction-mgt-1Qs. Nahinga David
 
Tecnologias de informacion aplicados en la ingenieria civil costos y presupu...
Tecnologias  de informacion aplicados en la ingenieria civil costos y presupu...Tecnologias  de informacion aplicados en la ingenieria civil costos y presupu...
Tecnologias de informacion aplicados en la ingenieria civil costos y presupu...CritciaLuceraSalazar
 
Real 'E' State, Your Cloud Based Assets
Real 'E' State, Your Cloud Based AssetsReal 'E' State, Your Cloud Based Assets
Real 'E' State, Your Cloud Based AssetsBrij Consulting, LLC
 
Competitive Bid Process
Competitive Bid ProcessCompetitive Bid Process
Competitive Bid Processxulxin2009
 

Similar to Altarum DC Presentation (20)

Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeff
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Project Management Services
Project Management ServicesProject Management Services
Project Management Services
 
Project+brief presentation july
Project+brief presentation julyProject+brief presentation july
Project+brief presentation july
 
Comments on Glass Big Push II & III.pdf
Comments on Glass Big Push II & III.pdfComments on Glass Big Push II & III.pdf
Comments on Glass Big Push II & III.pdf
 
Glass Big Push Part II (III).pdf
Glass Big Push  Part II  (III).pdfGlass Big Push  Part II  (III).pdf
Glass Big Push Part II (III).pdf
 
Infrastructure project and responsibility break down
Infrastructure project and responsibility break downInfrastructure project and responsibility break down
Infrastructure project and responsibility break down
 
Engineering
EngineeringEngineering
Engineering
 
Feed report
Feed report Feed report
Feed report
 
Article final ivan f
Article final ivan fArticle final ivan f
Article final ivan f
 
ARC_SBIR_TechInvestments_Handbook_2012
ARC_SBIR_TechInvestments_Handbook_2012ARC_SBIR_TechInvestments_Handbook_2012
ARC_SBIR_TechInvestments_Handbook_2012
 
Quality plan
Quality planQuality plan
Quality plan
 
[AgileCMMI] Practical Experience Report: Application of Project Management ar...
[AgileCMMI] Practical Experience Report: Application of Project Management ar...[AgileCMMI] Practical Experience Report: Application of Project Management ar...
[AgileCMMI] Practical Experience Report: Application of Project Management ar...
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
 
Buildings construction-mgt-1
Buildings construction-mgt-1Buildings construction-mgt-1
Buildings construction-mgt-1
 
Stages in construction
Stages in constructionStages in construction
Stages in construction
 
Tecnologias de informacion aplicados en la ingenieria civil costos y presupu...
Tecnologias  de informacion aplicados en la ingenieria civil costos y presupu...Tecnologias  de informacion aplicados en la ingenieria civil costos y presupu...
Tecnologias de informacion aplicados en la ingenieria civil costos y presupu...
 
Real 'E' State, Your Cloud Based Assets
Real 'E' State, Your Cloud Based AssetsReal 'E' State, Your Cloud Based Assets
Real 'E' State, Your Cloud Based Assets
 
Sow p9
Sow p9Sow p9
Sow p9
 
Competitive Bid Process
Competitive Bid ProcessCompetitive Bid Process
Competitive Bid Process
 

Altarum DC Presentation

  • 1. Project Portfolio for ALTARUM 4401 Ford Ave Alexandria, VA. 22302 End Show
  • 2. SCOPE OF SERVICE Phase 1  PROJECT ORIENTATION  PROGRAMMING  SQUARE FOOTAGE FEASILBILITY STUDY  BUDGET & SCHEDULE Phase 2  SPACE PLANNING  SCHEMATIC DESIGN  DESIGN DEVELOPMENT Phase 3  INTERIOR FINISHES SPECIFICATIONS  FURNITURE & FINISH SELECTION  SIGNAGE Phase 4  CONSTRUCTION ADMINISTRATION  CONSTRUCTION DRAWINGS Phase 5  SUPERVISION OF INTERIOR FINISH APPLICATIONS & FINAL WALK THROUGH End Show
  • 3. PROPOSAL ARTICLE IV DEVELOPMENT BASIC FEE SCHEDULE In reviewing the project, FMG has arrived at the estimated design fee for the phases of the project set forth below. The accuracy of these preliminary projected estimates is primarily dependent upon the completeness of information provided by ALTARUM to FMG for the performance of design services at this time. In particular, it is understood that changes in the scope of the project may increase the ALTARUM amount of time necessary for the performance of the phases. In the event that this occurs, ALTARUM will be notified of the change in fees required to complete this project. Additional work beyond the scope of services detailed above shall be performed by Facility Matrix Group personnel at the rate of $65.00 Revised September 30, 2002 ARTICLE I per hour. Written authorization from ALTARUM shall be established prior to commencement of the work. INTRODUCTION Please refer to Article II Basic Services for further description of the design phases. This Professional Design Agreement ("Agreement") is made on March 14, 2002, at Facility Matrix Group has estimated that the service identified above shall allow for the completion of Bloomfield Hills, Michigan between Facility Matrix Group (FMG), a Michigan the project in the time required, based upon the following square foot costs: corporation, and ALTARUM (“Client”), a Michigan corporation, for the request for PHASE 1: Project Orientation @ $.06per square foot . . . . . . . . . . . . . . . . . . $2,867.00 the INTERIOR DESIGN for approximately 47,799 square feet of offices at three (3) PHASE 2: Programming @ $.14 per square foot . . . . . . . . . . . . . . . . . . . . . . $6,691.00 floors (8th., 9th., 10th.) in the Transwestern Commercial Services Building 4401 Ford PHASE 3: Space Planning @ $.16 per square foot . . . . . . . . . . . . . . . . . . . . . $7,647.00 Avenue, Alexandria, VA 22302 . PHASE 4: Schematic Design @ $.12 per square foot . . . . . . . . . . . . . . . . . . . $ 5,735.00 PHASE 5: Design Development @ $.30 per square foot . . . . . . . . . . . . . . . . . $14,339.00 ARTICLE II PHASE 6: Interior Finish Specifications @ $.11per square foot . . . . . . . . . . . . $5,257.00 PHASE 7: Supervision @ $.13 per square foot (approx. 90 hours) . . . . . . . . . . $6,213.00 BASIC SERVICES PHASE 8: Signage @ $.04 per square foot . . . . . . . . . . . . . . . . . . . . . . . . . $1,911.00 PHASE 9: Proposed Furniture and finish Selection @ $.09 per square foot . . . . . . . $4,301.00 PHASE 1 – PROJECT ORIENTATION Sub Total $ 54,961.00 FMG shall meet with ALTARUM and the Transwestern Commercial Services Building’s designated representative(s) to discuss the general design theme and the TOTAL COMPENSATION for services identified herein above shall be for an amount desired project image. The project “Team” participants shall be established with not to exceed: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $54,961.00 hierarchal authorizations identified. FMG shall obtain, for their review and use, the building’s current subject architectural PAYMENT SCHEDULE drawings and specifications, landlord’s work letter, anticipated construction “Estimate of Probable Cost”, and relevant facility constraints. The building’s subject 1st payment floors will be toured by the participants to verify “As Built” conditions and Due prior to the start of phase 1 12% of total compensation parameters. $6,595.32 2nd payment FMG shall discuss with ALTARUM and the Transwestern Commercial Services the Due upon completion of phase 3 25% of total compensation development of a preliminary project “Build-Out” completion schedule depicting the $13,740.25 design, selection, and documentation of interior materials and finishes, F.F. & E., and 3rd Payment signage which reinforce the goals of the interior design solution. Due upon completion of phase 6 25% of total compensation $13,740.25 4th payment PHASE 2 - PROGRAMMING Due upon completion of phase 9 25% of total compensation $13,740.25 FMG shall meet with designated ALTARUM representative(s) to gather information 5th payment via interviews conducted to ascertain individual and departmental adjacencies, needs Due upon completion of the project $7,144.93 13% of total compensation and requirements, miscellaneous equipment and data / electrical requirements. Total $54,961.00 FMG shall assimilate and compile the obtained data and produce a programming report identifying the intra and inter departmental needs and requirements. End Show
  • 4. PROJECT Altarum ORGANIZATION VP Finance Altarum Phil Fazio Altarum Issued: 6/4/02 Director of IT Director Contracts Altarum Altarum Altarum Contracts/Procurement Construction Lead Data/Phones s Altarum Project Lead Arch Project Manager Building Manager FMG FMG Project Director FMG Exec. Management Bruce Tharp Account Executive David Daugherty Becky Peters Communication Communication Communication HMI FMG FMG Account Manager Interior Designer Project Coordinator June Smith Muranyi Kay Webb End Show
  • 5. PROGRAMMING Programming Survey ALTARUM PROGRAMMING SURVEY Area/Personnel Summary Project: Altarum Issue Date: June 14, 2002 4401 Ford Ave Arlington, VA. 22204 Revised: June 18, 2002 DIVISION: FACILITIES (SSV) 1/3 DATE: 6/10/02 Total PROJECT NO.: 10044 Personnel Personnel Total Ancillary Scenario A Scenario B Scenario C Abv Division Existing Growth Personnel Areas Sq Ft Sq Ft Sq Ft STAFF AND GROWTH REQUIREMENTS Ceer Ceer 6 2 8 3 1,792 2,662 1,850 MSV Contracts & Procurements 2 2 4 1 516 1,166 516 STAFF BELOW LEVEL 12 TOTAL CURRENT STAFF 5 ED Enterprise Development 3 1 4 3 706 1,118 793 ESD Enterprise Solutions Development 46 15 61 12 10,305 20,020 10,926 GROWTH OVER NEXT TWO YEARS 5 HSD02 Health Solutions 35 20 55 6 8,588 17,445 10,137 SSV Human Resources 3 1 4 2 754 1,404 754 TOTAL CURRENT STAFFAND GROWTH 5 SSV-NS I.T. 6 0 6 3 2,691 3,503 2,691 S SV Publications 5 0 5 3 1,637 2,049 1,637 SSV-Y3 Facilities 6 0 6 37 7,721 8,697 7,721 112 41 153 70 34,710 58,064 37,025 SUPPORT AREAS 400 SQ.FT. Total Summary RECEPTION 1 (400 SQ.FT.) Total Total Existing Growth Total Total HAVE AREA TO DISPLAY MARKETING MATERAL Item Personnel Personnel Personnel Ancillary Scenario A Scenario B Scenario C •HEIGHT OF DESK SHOULD OBSCURE VIEW OF WORKSURFACE Net Sq Ft / Qty Total Building Total Sq Ft Available 112 41 153 70 34,710 45,042 58,064 45,042 37,025 45,042 Remainder 10,332 (13,022) 8,017 •STORE SECURITY BADGES Circulation Sq Ft (Tot Net Sq Ft x Approx 31.026%) 10,771 18,021 11,490 Net Sq Ft Minus 45% Circ 23,939 40,043 25,535 •SIGN IN BOOK Personnel / Sq Ft Ratio Programming Survey 310 518 331 •WILL NOT HAVE SEPARATE WORKSTATION, NEEDS AREA TO PAY BILLS Department Requirements Notes: Company: Altarum Issue Date: June 13, 2002 •MINIMAL FILING 1 2 Assumes that for the primary purpose of this study, all workstations are 8' x 10' and all private offices are 12' x 16'. Scenario A: Totally Open Environment 3 Department: Enterprise Development (ED) Scenario B: Totally Closed Environment Revised: 6/14/02 •GUEST SEATING FOR 4 4 5 Scenario C: Hybrid Environment ( ) = Negative Number Scenario A Scenario B Scenario C Sq. Ft. Total FUNCTION Open Closed Open Closed Open Closed A B C •STORE PHONE BOOKS/ MENUS GRADE 15 1 1 1 132 192 192 GRADE 12 & ABOVE •WILL HAVE PARKING METER TO STAMP GUEST TICKETS GRADE BELOW 12 2 2 2 160 384 160 Growth: 1 1 1 80 80 80 PRINTER AREAS 6 @ 100 SQ.FT EA. - 600 SQ.FT. 1 Conference Rooms (Exec) 1 - - 164 - - •2 PER FLOOR 2 Enclaves (Exec) 1 - - 100 - - 3 Project Rooms •STAND ALONE COPY 4 Miscellaneous 5 Hoteling 1 1 1 48 48 48 •WORKTOP PRINTERS WITH STORAGE BELOW 6 Library (Shared w/HSD02) - - - 7 File Storage 1 1 1 27 27 27 •FLIPPER UNITS ABOVE TO STORE INK CARTRIDGES, ETC. 8 Fax Machine (Shared) 1 1 1 40 40 40 (1/2 of 4' x 20' area) •NEED TO STORE CASE OF PAPER AT LEAST IN EACH Personnel 4 - - 4 3 1 372 656 432 Net.Sq.Ft. MAIN CONFERENCE ROOM 1 @ 540 SQ.FT - 540 SQ.FT. Non Personnel 3 2 1 2 2 1 379 115 115 Net Sq.Ft. 751 771 547 Net Total •18’ X 30’ 338 347 246 45% Circ. 1,089 1,118 793 Dept. Total •EAST VIEW, SOUNDPROOFED Notes: 1 Assumes that for the primary purpose of this study, all workstations are 8' x10' and all private offices are 12' x 16'. •VIDEO TELECONFERECING 2 Scenario A : Totally Open Environment 3 Scenario B: Totally Closed Environment •POLYCOM PHONE LINES, NETWORK, AND ANALOG LINES 4 Scenario C: Hybrid Envirnoment •PAM WOULD LIKE IT TO BE FLEXIBLE, BUT NOT “TO FLEXIBLE” End Show
  • 6. SQUARE FOOTAGE EConclusion The Feasibility Study was developed in order to assist ALTARUM in determining the most desirable solution FEASIBILITY STUDY for the configuration of its new multi-floored offices in Alexandria, VA. Compilation of current programming information obtained by FMG in conjunction with data provided by ALTARAM has resulted in a recommendation of use by comparing three different scenarios: Scenario “A”: Totally open office environment with no personnel in enclosed offices. Scenario “B”: Totally enclosed office environment with all personnel in enclosed offices. ALTARUM Scenario “C”: A hybrid of “A & B” scenarios with only E.C. personnel in enclosed offices and all other personnel in open office environment. Executive Summary Facility Matrix Group recommends pursuing the hybrid Scenario “C” in order to maintain the maximum in flexibility for future reconfigurations and additions for the following reasons: A. Background to Feasibility Study. This report has been prepared in response to ALTARUM’s requirements, which authorizes FMG to conduct management  END OF SUMMARY programming to determine a square footage feasibility study. Primary Objectives: · Comparative analysis of open office environment vs. totally enclosed environment. · Compilation of square footage requirements, plus anticipated growth. · Determination of the optimum solution utilizing maximum flexibility. Review Undertaken: · Assimilation of previous programming effort. · Review of previous test fit efforts. · Departmental Interviews. · Tour of leased space and meeting with Building Mgrs. Office. Key Assumptions: · Open environment crucial in order to accommodate change. · Minimal accumulation of primary circulation square footage. · Identification of potential duplicity in ancillary elements. Unresolved Issues: · Future acquisitions and growth ramifications thereof. B. Adjacency Matrix. The bubble diagrams have been prepared based on the following general assumptions: · Total number of employees (existing + Growth). · Accounting of all ancillary elements. · Conclusive square footage calculations. · Intra – Departmental adjacencies prioritization. End Show
  • 7. Furniture, Fixtures & Equipment SCHEDULE & BUDGET Description of Work 8th Floor - Revised 7/23/02 Hoteling Workstations 8x8 U of M QT Y Ea 2 Unit Rate $ 4,700.00 $ Sub-T otal 9,400.00 $ Labor 658.00 $ Grand T otal 10,058.00 Actual Product $ $ - Staff Workstations 8x10 Ea 19 $ 5,500.00 $ 104,500.00 $ 7,315.00 $ 111,815.00 $ - Copy/Print Workstations 8x10 Ea 1 $ 4,700.00 $ 4,700.00 $ 329.00 $ 5,029.00 $ - Executive Workstations 12x14 Ea 1 $ 8,000.00 $ 8,000.00 $ 560.00 $ 8,560.00 $ - Systems Furniture Lot 23 $ - $ - $ - $ - $ 125,667.49 Miscellaneous Files & Storage Ea 49 $ 550.00 $ 26,950.00 $ 1,886.50 $ 28,836.50 $ 15,738.54 Workstation Conference Areas Ea 4 $ 1,400.00 $ 5,600.00 $ 392.00 $ 5,992.00 $ 4,263.86 Conference Rooms Ea 4 $ 18,500.00 $ 74,000.00 $ 5,180.00 $ 79,180.00 $ 69,738.76 Reception Area Lot 1 $ 5,000.00 $ 5,000.00 $ 350.00 $ 5,350.00 $ - Lobby Ea 1 $ 10,000.00 $ 10,000.00 $ 700.00 $ 10,700.00 $ 29,769.02 Enclaves 80 Sq Ft Ea 5 $ 2,500.00 $ 12,500.00 $ 875.00 $ 13,375.00 $ 9,260.40 Publication Work Area/Central Copy/Mail Ea 1 $ 5,500.00 $ 5,500.00 $ 385.00 $ 5,885.00 $ 15,260.86 Coffee Lounge/Kitchenette Ea 1 $ 3,700.00 $ 3,700.00 $ 259.00 $ 3,959.00 $ 2,037.00 File Room Ea 1 $ 2,000.00 $ 2,000.00 $ 140.00 $ 2,140.00 $ - Copy / Printer Ea 4 $ 550.00 $ 2,200.00 $ 154.00 $ 2,354.00 $ 1,696.00 IT Storage Ea 1 $ 2,000.00 $ 2,000.00 $ 140.00 $ 2,140.00 SCCR Ea 1 $ 3,500.00 $ 3,500.00 $ 245.00 $ 3,745.00 IT Server Ea 1 $ 10,500.00 $ 10,500.00 $ 735.00 $ 11,235.00 Misc Seating Lot 1 $ - $ - $ - $ - $ 727.20 Sub-Total $ 290,050.00 $ 20,303.50 $ 310,353.50 $ 273,431.93 9th Floor - Revised 7/23/02 Hoteling Workstations 8x8 Ea 4 $ 4,700.00 $ 18,800.00 $ 1,316.00 $ 20,116.00 $ - Staff Workstations 8x10 Ea 52 $ 5,500.00 $ 286,000.00 $ 20,020.00 $ 306,020.00 $ - Executive Workstations 12x14 Ea 3 $ 8,000.00 $ 24,000.00 $ 1,680.00 $ 25,680.00 $ - Systems Furniture Lot 59 $ - $ - $ - $ - $ 308,401.04 Budget Summary Coffee / Lounge Ea 1 $ 3,700.00 $ 3,700.00 $ 259.00 $ 3,959.00 $ 1,645.20 Professional Fees Coffee Station Ea 1 $ - $ - $ - $ - $ - Description of Work U of M QT Y Library Ea 1 Unit Rate $ 5,600.00 $ T otal 5,600.00 m$ Com ents 392.00 $ 5,992.00 $ 3,681.48 Interior Design SQ FT Enclaves 80 Sq $ 47799 Ft Ea 4 1.78 $ $ 85,082.22 2,500.00 $ FMG10,000.00 $ 700.00 $ 10,700.00 $ 8,235.68 Architectural Executive Conference Rooms SQ FT 47799 $ Ea 2 1.21 $ $ 57,836.79 15,000.00 $ DBI 30,000.00 $ 2,100.00 $ 32,100.00 $ 5,245.68 Mechanical & Engineering SQ FT Project Work Room 47799 $ Ea 5 0.90 $ $ 43,019.10 4,700.00 $ EK23,500.00 $ Fox 1,645.00 $ 25,145.00 $ 21,105.18 General Contractor Miscellaneous47799 Storage SQ FT Files & $ Ea 35 - $ $ 550.00 $ - Included in Construction 1,347.50 19,250.00 $ $ $ 20,597.50 $ 14,975.69 Furniture Lease % File/Storage Ea 1 $ $ 296,724.38 2,000.00 $ 25%2,000.00 $ Budget 140.00 Of Furniture $ 2,140.00 $ 815.92 Legal Fees Lot Copy / Printer Ea 4 $ $ 550.00 $ - 2,200.00 $ 154.00 $ 2,354.00 $ 3,392.00 Insurance Lot Sub-Total $ 425,050.00 $ 29,753.50 $ 454,803.50 $ 367,497.87 Sub-Total $ 185,938.11 10th Floor - Revised 7/23/02 Construction Hoteling Workstations 8x8 Ea 4 $ 4,700.00 $ 18,800.00 $ 1,316.00 $ 20,116.00 $ - Description of Work U of M QT Y Produ ct I nstallation T otal Staff Workstations 8x10 Ea 50 $ 5,500.00 $ 275,000.00 $ 19,250.00 $ 294,250.00 $ - 8th Floor Lot * Executive Workstations 12x14 Ea 0 $ 8,000.00 $ - $ - $ - $ - 9th Floor Lot Systems Furniture Lot 54 $ - $ - $ - $ - $ 262,307.81 10th Floor Lot Miscellaneous Files & Storage Ea 27 $ 550.00 $ 14,850.00 $ 1,039.50 $ 15,889.50 $ - Sub-Total $ 762,940.00 Executive Conference Rooms Ea 1 $ 2,500.00 $ 2,500.00 $ 175.00 $ 2,675.00 $ 2,622.84 Copy / Printer Ea 2 $ 550.00 $ 1,100.00 $ 77.00 $ 1,177.00 $ 2,544.00 ME&P $ 325,640.00 Project Work Room Ea 4 $ 6,200.00 $ 24,800.00 $ 1,736.00 $ 26,536.00 $ 18,027.44 Enclaves 80 Sq Ft Ea 3 $ 2,500.00 $ 7,500.00 $ 525.00 $ 8,025.00 $ 7,414.85 Sub-Total $ 1,088,580.00 Storage Ea 2 $ 2,000.00 $ 4,000.00 $ 280.00 $ 4,280.00 $ 12,727.12 Safe Room Ea 1 $ 2,000.00 $ 2,000.00 $ 140.00 $ 2,140.00 $ - FF&E Lab Ea 1 $ 6,500.00 $ 6,500.00 $ 455.00 $ 6,955.00 $ - Description of Work U of M QT Y Produ ct I nstallation T otal Lunchroom Booths Ea 1 $ 15,000.00 $ 15,000.00 $ 1,050.00 $ 16,050.00 $ - 8th Floor Lot $ 290,050.00 $ 20,303.50 $ 310,353.50 Classified Work Room Ea 1 $ 11,400.00 $ 11,400.00 $ 798.00 $ 12,198.00 $ - 9th Floor Lot $ 425,050.00 $ 29,753.50 $ 454,803.50 Kitchen Ea 1 $ 1,500.00 $ 1,500.00 $ 105.00 $ 1,605.00 $ - 10th Floor Lot $ 394,150.00 $ 27,590.50 $ 421,740.50 Cafeteria Ea 1 $ 5,500.00 $ 5,500.00 $ 385.00 $ 5,885.00 $ 9,592.00 Coffee Lounge Ea 1 $ 3,700.00 $ 3,700.00 $ 259.00 $ 3,959.00 $ 924.00 Sub-Total $ 1,109,250.00 $ 77,647.50 $ 1,186,897.50 Coffee Station Ea 1 $ - $ - $ - $ - $ - Sub-Total $ 394,150.00 $ 27,590.50 $ 421,740.50 $ 316,160.06 Misc Description of Work Miscellaneous FurnitureY Floors U of M QT All Lot 1 Produ ct I nstallation T otal $ 41,024.64 Move Management Lot $ 47,799.00 $ 3,345.00 $ 51,144.00 AV Equipment Lot Incl. in Const. $ $ Installation Lot 1 - $ - $ - $ 81,000.00 Tele/Data Cabling Lot $ 95,598.00 $ 6,691.86 $ 102,289.86 Security System Lot $ - $ - $ - Grand Total $ 1,109,250.00 $ 77,647.50 $ 1,186,897.50 $ 1,079,114.50 Card Reader Lot $ - $ - $ - Artwork And Accessories Lot $ - $ - $ - Signage Lot $ 15,200.00 $ 1,064.00 $ 16,264.00 Vending Machines Lot NIC $ - $ - $ - Kitchen Equipment Lot NIC $ - $ - $ - Coffee Equipment Lot NIC $ - $ - $ - Furniture Refurbishment Lot NIC $ - $ - $ - Sub-Total $ 158,597.00 $ 11,100.86 $ 118,553.86 Estimated Project Budget $ 2,579,969.47 End Show
  • 8. SPACE PLANNING North View End Show
  • 9. DESIGN DEVELOPMENT ALTARUM 8th Floor Conference Room 8th Floor Lobby 10th Floor Coffee Lounge End Show
  • 10. ARCHITECTURAL MATERIAL SELECTION ALTARUM Carpet CPT-1 Shaw Mode # 50885 Balanced Multi level- Patterned Loop 100% 8th Floor Lobby Contract #85712 Solution Dyed Ultron VIP BCP Nylon 6.6, 12' Broadloom Repeat: 18"W X 10"L CPT-2 Durkan Two-Steppe TWS-401 Patterned Loop 8th Floor Overall Ballet Paint Solutia Ultra VIP Nylon 6.6 32 oz., 12' Broadloom P-1Repeat: 18" W X 36"L Sherwin Gauntlet SW7019 (Dark Gray) 8th Floor Lobby Williams Gray Satin Finish Overall CPT-3 Durkan Delano DLO-401 Patterned Loop 9th Floor Overall The Romance P-2Solutia Ultra VIP Nylon 6.6 Tourchlight Sherwin SW6374 (Vibrant Orange 8th Floor Lobby Williams 32 oz., 12' Broadloom Yellow) 10th Floor Coffee Lounge Repeat: 18" W X 12 3/4"L Satin Finish Ceiling CPT-4 Durkan P-3Patterned Sherwin Retreat SW6207 (Dark Gray ACT-1 USGHot Lights Astro ClimaPlus HLS-401 #8223 Loop 2' Williams x 5/8" Panel size 2' x 10th Floor Overall Workrooms, Enclaves, Green) (SLT) High Speed White Solutia Ultra SLT Nylon 6.6 VIP Edge Enclosed Staff areas, Mail, Satin Finish 32 oz., 12' Broadloom15/16" Grid - White Donn DX Central Copy Repeat: 18" W X 36"L P-4 Sherwin Moonraker SW6701 (Bright Yellow Coffee Stations ACT-2 USG Orion 270 #66271 Williams x 3/4"Vinyl Tile Lobby 2' x 2' Panel size Open office Green) Paint behind backsplash CPT-5 Bentley Kings Road 519 Dense Cut Pile ClimaPlus (SL) SL Edge Executive Conferences Satin Finish Black Pearl Dupont Antron Legacy Nylon Coffee Stations Donn DX 15/16" Grid - White Dura Tech Soil Treatment VCT-1 Mannington Designer 280 Lapis Size: 12"X12", Gauge:1/8" 10th Floor Coffee Lounge P-512' Broadloom Sherwin Rejunenate SW6620 Essentials (Vibrant Orange) Kitchen Paint Vinyl Composition Tile 10th Floor Lunch Room ACT-3 USG Panz Panz 002 Williams Reception Satin Finish Repeat: No (Bright behind Backsplash Blue) Perforated Panel #D500 Silver Satin finish Note: Provide USG Compasso W/ Acoustibond w/ Fineline Edge edge profile 2'-4"H w/ finish install in USG Fineline VCT-2 Mannington to match silver satin Designer 220 Horizon Size: 12"X12", Gauge:1/8" 10th Floor Coffee Lounge Essentials Vinyl Compostion Tile 10th Floor Lunch Room Plastic Laminate Edge 9/16" (DXF) Suspension Grid (Dark Dusty Blue) PL-1 Avonite Frosted Glass K3-8480 Translucent Solid 8th Floor Recepton Solid Surface Satin Finish also in silver satin Surface Transaction Top VCT-3 Mannington Designer 130 Wedge wood Size: 12"X12", Gauge:1/8" 10th Floor Coffee Lounge PL-2 Avonite Sky Glass K3-8465 Translucent Solid Essentials 10th Floor Coffee Lounge Vinyl Composition Tile 10th Floor Lunch Room Solid Surface Satin Finish Surface Rotating Transaction Top (Light Dusty Blue) PL-3 Nevamar Silver Alu Metalx MXT-003T Plastic Laminate VCT-4 Mannington Designer All millwork countertops 263 Sunflower Size: 12" x 12", Gauge:1/8" 10th Floor Coffee Lounge ARP Plus Textured All millwork upperEssentials cabinets Vinyl Composition Tile 10th Floor Lunch Room (Yellow) PL-4 Nevamar Wrought Iron S-6-54T Plastic Laminate All millwork ARP Plus Textured VCT-5 Lower Cabinets Designer Mannington 273 Spectrum Size: 12" x 12", Gauge:1/8" 10th Floor Coffee Lounge Essentials Orange Vinyl Composition Tile 10th Floor Lunch Room PL-5 Chemetal Pewter Wave #244S Metal Dark Gray Coffee Stations Backsplash (Orange) 800-807-7341 Wave Laminate on all levels End Show
  • 12. CONSTRUCTION DRAWINGS DBI Architects, P.C. End Show
  • 13. BID DOCUMENTS Contractor Request for Proposal NEW FURNITURE INSTALLATION WORK I. REQUEST FOR PROPOSAL FOR Transwestern Commercial Services, on behalf of Transwestern Park IV. General Conditions Center II, LLC, is soliciting bids for the tenant renovations for Altarum. The Alt a r u mPre-Installation: The Contractor will be responsible space consists of approximately 47,799 square feet of tenant build-out at for field measuring the space, attending Project Coordination meetings, working around field Park Center II, 4401 Ford Avenue, Suite 800, Alexandria, Virginia 22302. Park Centerconditions and coordination of II This bid package consists of the following sections: furniture/construction, furniture/building electrical 4401 Ford Avenue and furniture/voice & data interface. Clearances I. Request for Proposal Alexandria, Virginia 22302 and egress aisles are critical to the project, and II. Building Rules and Regulations shall not be compromised or reduced. III. Bid Forms, Long Lead Items, Alternates Form & •The project will require straight time non-union V. Scope of Work services. FMG JOB NO. 10044 installation Subcontractor List The work to which this pertains generally consists of •All electrical components associated with the IV. Retainage Release Form September 20, systems furniture shall be VA. (FMG's Job the Altarum, located in Alexandria, connected by the 2002 V. Drawing Inventory No. 10044) furniture installers. The hard-wire connection of the Drawings are intended to include everything building to the systems furniturecompletion obviously necessary for proper will be performed The following items constitute the bid requirements and instructions: of the work. by an electrician supplied by the Contractor. PRE-BID &Park Center II, 4401 Ford Avenue, Alexandria, Virginia 22302 CONTACTS The work consists of, but is not limited to, •The contractor will be required to coordinate with 1. Questions and clarifications regarding the construction documents II. Building Rules theRegulationsPark, DBI Architects, & attention of Jin Confirmations of field conditions, providingTeam, the General the FMG, Project Management all field should be directed to measuring Contractors’ Electrical Subcontractor and the as required BUILDING STANDARD CONFORMANCE -toThecopied to via facsimile 703.847.9336. All inquiries are be Contractor must be Communications Subcontractor. certain thatPerucci, Transwestern Commercial Serviceshardware conform Maribeth all ceiling tiles, Venetian blinds, and door via Delivery, installation and set up of all new workstations tofacsimile 703/845-8042. Door locks should be keyed to the building the building standards. and new freestanding furniture 2. DBI Architects will issuethe floor addressing the Building Manager should be master and to addenda master. The contractors’ VII. Lump Sum Removal of all furniture related debris; building consulted beforeclarifications as necessary. The addenda will questions and ordering these items. dumpster is not to be used unless specific materials, is We hereby propose to furnish all labor, permission PROTECTIONall of the participating contractors.. be issued to OF NON-CONSTRUCTION AREAS - The Contractor provided by building contractor at no furniture work tools, and will provide and install all cost to Owner shall protect all walls, floors, carpet, furniture and fixtures and shall repair Develop and maintain an installation New Office in required to complete the Altarum schedule or replace damaged propertyThe undersignedthe Owner. Masonite (or without cost to as bidder, declares that only the interested accordance with all new Contract Documents plywood) must be placed asperson or parties interested in this Bid as principals are those a walkway on the public corridors from After installation, furniture orientation for the Owner supplied for the following lump sum amount which freight elevator to the construction site and to thehe visited the site ofto project described by named herein. That Public Restrooms the Provide a punch list for insurance, and all applicable includes applicable each phase of new furniture protect the carpet from drywallthe bidetc. Common area carpet protection dust, documents and has reviewed completely such documents installation State, and local taxes of whatever Federal, is to be removed daily and the and agrees that he will provide all necessary labor, materials, carpet vacuumed daily. character and description. trade work and supervision required to complete the project for the All furniture related permits stipulated sum and in the stated number of business days from written notice to proceed. The contractor understands all terms _ ______Dollars and conditions of the bid documents and written criteria. The contractor understands that this Bid must remain valid for a period (Enter amount in writing) of thirty (30) calendar days from submission. DBI Architects, P.C. $_________________________Lump sum Stipulated Lump Sum of: (Enter amount numerically) $______________________ End Show
  • 14. BID ANALYSIS Corbett Construction Interior Construction ME&P $ 30,195.00 $ 600.00 Rand Construction 8/30/02 FMG Interior Construction ME&P Description Estimate WO BCMI Construction BCMI Revised 9/10/02 $ 1,800.00 ME&P Tripp Contracting, LLC $ 28,000.00 $ 83,857.00 $ 900.00 Interior Construction ME&P Interior Construction ME&P Delta $ 1,500.00 General Scope of Work Interior Construction ME&P $ 29,560.00 $ 3,000.00 General Conditions $ 36,830.00 $ 36,830.00 $ - $ 28,504.00 Demolition $ 950.00 $ (950.00) $ 43,935.00 $ 95,000.00 Site Work $ 500.00 $ 95,000.00 $ 96,339.00 Concrete X-Ray $ 5,200.00 $ 5,690.00 $ 490.00 $ 6,745.00 $ 132,052.00 Metals $ 1,850.00 $ 33,920.00 Flash Patching Allowance (Floor Prep) $ 24,750.00 Carpentry/Millwork $ 99,258.30 $ 92,641.00 $ 86,370.00 $ (6,271.00) $ 20,300.00 $ 82,115.00 $ 79,697.00 Rough Carpentry $ 6,214.00 $ 6,214.00 $ - $ 7,756.00 $ 4,789.00 $ 105,679.00 Moisture Control $ 125,052.00 Doors/Frames & Hardware $ 49,180.00 $ 25,891.00 $ 25,891.00 $ - $ 27,057.00 Glass/Glazing $ 20,587.00 $ 5,030.00 $ 15,700.00 $ 10,670.00 $ 17,162.00 $ 30,125.00 Drywall $ 105,065.00 $ 66,538.00 $ 66,538.00 $ - $ 82,697.00 $ 204,400.00 Acoustical/Ceiling $ 224,697.40 $ 125,644.00 $ 125,644.00 $ - $ 108,679.00 $ 938.98 Carpet/Base/VCT $ 83,918.04 $ 129,283.00 $ 131,783.00 $ 2,500.00 $ 134,000.00 $ 39,762.00 Skim Perimeter Walls $ 21,883.20 $ 8,200.00 $ 8,200.00 $ - $ 25,012.00 $ 179,000.00 Paint $ 35,499.25 $ 28,975.00 $ 43,675.00 $ 14,700.00 $ 33,253.00 Wallcovering $ 7,991.94 $ 2,500.00 $ 2,500.00 $ 6,800.00 Signage $ 8,047.50 $ 939.00 $ 169,500.00 Appliances $ 5,643.00 $ 5,902.00 $ 5,902.00 $ - $ 32,500.00 tbd Furnishings/Equipment $ 8,100.00 $ 13,830.00 $ 10,461.00 $ 27,895.00 Special Construction $ 227,800.00 Light Fixtures $ 88,927.00 $ 187,900.00 $ 24,114.00 Mechanical $ 179,900.00 $ 179,900.00 $ - $ 18,750.00 $ 583,888.00 $ 423,162.00 Plumbing $ 17,640.00 $ 17,640.00 $ - $ 1,007,050.00 Sinks & Faucets $ 8,334.40 $ 30,895.00 $ 18,715.00 Fire Protection $ 31,500.00 $ 31,500.00 $ - $ 189,750.00 $ 18,115.00 Electrical $ 189,740.00 $ 190,900.00 $ 1,160.00 Roofing $ 1,150.00 $ 1,150.00 $ - $ 1,025,165.00 Banquette Seating $ 30,144.99 Misc. Folding Partition $ 7,616.00 $ 10,461.00 $ 10,461.00 $ - $ 14,450.00 $ 595,997.97 $ 457,695.00 8th Flr Blackout Shades $ 10,307.00 $ 10,307.00 $ 45,508.00 $ 1,053,692.97 Included in Above Projector Lift & Screens $ 25,873.00 Equip. Schedule (Rev. Alternate Form) $ 38,360.00 $ 38,360.00 $ 1,800.00 (1) Ambassador ? Building Standard Mini Blinds $ 20,874.00 $ 20,874.00 $ 30,850.00 Not Included $ 1,079,565.97 $ 646,345.00 $ 427,295.00 Not Included Fee (OH&P) $ 24,192.23 $ 26,551.00 $ 2,358.77 $ 1,073,640.00 $ 10,461.00 Sub-Total $ 571,951.23 $ 419,930.00 $ 667,490.00 $ 421,090.00 tbd Total $ 991,881.23 $ 1,088,580.00 $ 96,698.77 $ 41,513.00 Included in Above Included in Above $ 8,800.00 Estimated Contractor Adds (No Addendums) $ 55,771.00 Included in Above (Per Bid Clarification Dated 9/9/02) $ 1,115,153.00 $ 1,067.00 (4) Ambassador $ 9,315.00 Not Included $ (14,728.00) Not Included $ (9,100.00) Adjusted Total $ 1,047,652.23 $ (6,975.00) $ (5,200.00) Included in Above Add/Deducts & Alternates Included in Above $ 18,715.00 $ (4,250.00) Minus Permits Included in Above $ (4,200.00) $ 1,000.00 (4) Ambassador $ 2,618.00 $ (1,100.00) Draper - Micro Projector Lift $ 13,848.00 $ 13,300.00 Included in Above Not Included Included in Above DA-Lite - Electric Projector Screen 8'x8' $ 3,275.80 Alternate Not Included $ (5,499.00) $ 1,025,165.00 (1) DA-Lite - Electric Projector Screen 8'10' $ 3,495.80 $ 1,645.00 (1) Electrol Alternate Included in Above $ (35.00) (1) Mitsubishi Projector $ 4,595.00 Included in Above $ 14,450.00 $ (7,066.00) 47799 Sq FT Scamp Noise Distortion System $ 1,350.00 Not Included Not Included Included in Above $ (3,187.50) Misc. Folding Partition Included in Above Included in Above $ 8,800.00 $ (5,889.60) 8th Flr Blackout Shades $ 10,307.00 Included in Above Included in Above $ (1,260.00) $ 21.45 8th Floor Recept Floor Core $ 490.00 Included in Above $ (11,200.00) Upgrade to (9) 2x4 Luna Lights $ 8,800.00 Included in Above $ (245.00) $ 1,079,565.97 Add Screenwall - Detail 1/A-502 Included in Above Included in Above $ (8,783.00) Delete Storefront Glass /Replace with Drywall Included in Above Included in Above $ (4,010.00) 47799 Sq FT Delete Paint to Have 1 Paint Selection NIC $ (9,069.00) Delete Wallcovering / Replace with Paint NIC NC Delete Carpet Cutouts $ (2,500.00) Included in Above $ 22.59 Delete Drywall Soffits NIC $ 1,115,153.00 Replace Seating Booth Fabric with Vinyl NIC Sub-Total 47799 Sq FT Grand Total $ 788,617.63 $ 23.33 End Show