PROCUREMENT OF WORKS
(Highlight of PPA, 2007 & PPR, 2007, Contract type &
Standard bidding documents)
Prepared By:
Group Members (M.Sc. III Semester)
Ayush Joshi
Krishna Koirala
Milan Bhattarai
Sandeep Udash
Sarala Dahal
Procurement
“Procurement” means the acquisition by any
public entity of any goods, consultancy
services or other services, or executing or
causing to be executed any construction
works by such an entity. (PPA, 2007)
Construction works
The construction works means all activities
associated with the construction, reconstruction,
demolition, repair or renovation of a building,
structure or associated activities, such as site
preparation, excavation, erection, building,
installation of equipment or materials, decoration
and finishing.
Provisions Relating to Procurement of works
 Prior to procuring construction work, a public
body shall prepare a specification, plan,
drawing, design, special requirement or other
descriptions thereof.
 A public body shall prepare a cost estimate as
prescribed for any procurement whatsoever.
Provisions Relating to Procurement works
 A public entity shall approve the cost estimate.
Authority to approved cost estimate:
• Cost estimate upto 1 crore by Gazetted 3rd class chief of Office.
• Cost estimate upto 5 crore by Gazetted 2nd class chief of Office.
• Cost estimate upto 10 crore by Gazetted 1st class chief of Office.
• Cost estimate above 10 crore by the head of department.
Cost estimate once approved, such an amendment differs by more than
25% of the original cost estimate figure or the act of procurement gets
affected for the reason that the defective design has been made or abnormal
cost estimate has been prepared, the official who has prepared, examined or
approved such a design or cost estimate and the consultant who has been
involved in that act shall be liable to action under the prevailing law.
Provisions Relating to Procurement works
 A public entity should prepared Procurement plan.
(a) Master procurement plan : Project period exceeding 1
year (multiyear project) or in making an procurement of an
amount exceeding 10 crores a year.
(b) Annual procurement plan: Where a public entity is to
make procurement of an amount exceeding 10 lakhs a year.
 Each public entity should prepare separate standing list of
suppliers, construction entrepreneurs, consultants for
procurement to be made.
Procurement method
A public entity shall make procurement of works by applying
any of the following methods based on conditions and
purchase price:
1. Inviting international open bidding (ICB)
2. Inviting national open bidding (NCB)
3. Inviting sealed quotations
4. Direct procurement
5. Through participation of users' committee or beneficiary
group
6. Through a forced account
International Competitive bidding (ICB)
1. If the construction works as requisitioned by a public entity are not
available at the competitive price from more than one construction
entrepreneur within the State of Nepal,
2. If no bid has been submitted in response to an invitation to national
bidding for the procurement of construction works, and the same has to be
procured from abroad,
3. If construction works have to be procured through the foreign assistance
source pursuant to the agreement entered into with a donor party,
4. If it is certified by the public entity that the construction works, being of
complex and special nature, have to be procured through international
bidding.
5. If Project cost estimate exceed 1 Arab.
National Competitive bidding (NCB)
1. A construction work the cost estimate of which is above 20
lakh rupees but not exceeding 1 Arab rupees has to be
procured upon having competition between native bidders
only through the national open bidding, except in the
circumstances referred to in Section 15 of the Act.
2. Standard bidding procedure used as per procurement value:
• NCB, Single Stage Single Envelope (1S1E) – Procurement
value above 20 lakhs and upto 2 crores.
• NCB, Single Stage Two Envelope (1S2E) – Procurement
value above 2 crores.
Bidding Procedure for ICB/NCB…
Bid invitation
A notice for invitation to bids or pre-qualification proposals shall be published in
a daily newspaper of national circulation, and in the case of an international
bidding, it may also be published in any international communication media.
The notice shall be placed in the website of the entity or that of the Public
Procurement Monitoring Office i.e. www.bolpatra.gov.np/egp.
Period of a notice:
• For NCB or PQ proposal : Minimum 30 days
• For ICB or PQ Proposal : Minimum 45 days
•
Bidding Procedure for ICB/NCB…
 Fees for Bidding Documents
• 20 lakhs to 2 Crores Rupees : Rs 3000
• > 2 Crores to 10 Crores Rupees : Rs 5000
• >10 Crores to 25 Crores Rupees : Rs10,000
• > 25 Crores Rupees : Rs 20,000
 Withdrawal and Modification of Bid
• Within last submission date of bid in sealed envelop in case of bidder
who submits bid electronically
• Within 24 hour before the last submission date for other bidders
• Withdrawal or modification can be done at one time only.
Bidding Procedure for ICB/NCB
 Pre-bid meeting
• For NCB at least 10 days before of last submission date
• For ICB at least 15 days before of last submission date
• To be informed to bidders if any amendment within 5 days
pre bid meeting
 Bid Security
• 2 to 3 % of estimated amount
• Validity of bid security 30 days more than bid validity period
• Bid security amount shall be in form of a cash deposit or of a bid
security equal to that amount issued by a commercial bank or financial
institution.
Bidding Procedure for ICB/NCB
 Bid security will be forfeited if
• If requested for withdrawal or modification within the period of last bid
submission date and last date of bid validity.
If the bidder does not accept the correction of arithmetic error
• If the selected bidder rejects for agreement
• If the selected bidder fail to submit performance bond within due date
of contract agreement
• If clarification submitted by bidder makes substantial change to the bid
• If the bidder violates the code of conduct as per clause 62 of PPA.

Bidding Procedure for ICB/NCB
 Bid validity Period
• Bid validity period is a period within which bidder’s rate are valid
• Contract agreement is done within bid validity period
• For bid having estimated cost within 10 Crores : 90 days
• For bid having estimated cost above 10 Crores: 120 days
• Period to be counted from last date of bid submission
• Can be increased with justified reasons
• Who agrees to extend bid validity shall extend validity of bid
security also
• Bid bond amount shall be returned to bidder if he disagrees to
extend bid validity
Bidding Procedure for ICB/NCB
 Bid Opening
• Immediately after last date and time of bid submission in presence of
bidders as far as possible (Absence of bidders does not disturb the
opening process)
• Then bid submitted electronically are opened first and then other bids
are opened
• Before opening bid, envelop of letter of withdrawn or modified bid
shall be opened and read
• Then remaining bids shall be opened and matters like bid security,
discount if any etc. shall be read, noted and signed
• No bid shall be rejected at the time of opening
Bidding Procedure for ICB/NCB
 Examination of completeness of bids
 Evaluation of bids:
 Technical Evaluation
 Financial Evaluation
 Special Evaluation
 Evaluation report
 Bid approval
• Upto 3 crores: gazetted third class chief of the office
• Upto 7 crores: gazetted second class chief of the office
• Upto 15 crores: gazetted first class chief of the office
• Above 15 crores: the head of department
Bidding Procedure for ICB/NCB
 Performance security
• To be taken to ensure due performance of contract
• 5% of Contract Value If bid price of the bidder selected for acceptance
is up to 15(fifteen) percent less than the approved cost estimate, the
performance security amount shall be 5 (five) percent of the bid price.
• For the bid price less than 15 percent of the cost estimate, the
performance security amount shall be determined as follows:
Performance Security Amount = (0.85 × Cost Estimate –
Bid Price) × 0.5 + 5% of Bid Price.
• The Bid Price and Cost Estimate shall be inclusive of Value
Added Tax
Bidding Procedure for ICB/NCB
 Contract award
• Letter of intent is issued within seven days of bid selection & information should be
given to other bidders also.
• If there is no complaint from other bidders within seven days, letter of acceptance is
issued to notify the successful bidder to come with performance security for contract
agreement within 15 days.
• If successful bidder fails to furnish the performance guarantee and to sign contract
within 15 days, then his bid security shall be forfeited and bid of next lowest
responsive bidder is accepted and called for agreement
If lowest evaluated bidder does not sign the agreement, in addition to forfeiture of bid
bond PPMO on the recommendation of PE blacklist the bidder.
• If any bidder requests for information on the reason for rejection of within 30 days
of issuing of letter of intent, the public entity shall communicate such information to
the bidder.
Bidding Procedure for ICB/NCB
 Rejection of tender or cancellation of procurement proceedings
• Where non of the tenders is substantial responsive
• Where the bid price of the lowest evaluated substantially responsive bid is
substantially higher than cost estimate
• Where construction works are no longer required.
No tender shall be rejected or re tendering shall be invited only by the
reason that only a few tenders or only one tender is substantial responsive.
A public entity shall communicate a notice along with the reason for the
rejection of tenders or the cancellation of procurement proceedings to all
bidders.
Sealed Quotation
 Procurement of works up to 20 lakhs can be carried out adopting
sealed quotation
 Procedure
Preparation of Sealed Quotation Document
Invitation: Notice in national or local newspaper with minimum
period of 15 days.
Sale and registration of Bid :Same as open bidding
Bid validity period : 45 day
 Bid security : same as open bidding (validity 75 days)
Withdrawal and Modification of Bid: Not allowed
Bid Evaluation & Bid Evaluation Report
Same as open bidding except if less than three sealed quotations
are submitted, it shall be cancelled and re-notice is published.
However for the second time less than three sealed quotations can
Sealed Quotation
 Selection for Award of Contract: Same as open bidding
Price of Bidding Documents: Rs. 1000
Performance security: Same as open bidding
Contract award
• The public entity shall accept the sealed quotation within 15
days of opening.
• Notice is issued to selected bidder within 7 days of acceptance
of the sealed quotation. Notice is issued to other bidders also.
• The sealed quotation bidder who receives the notice shall enter
into the procurement contract by furnishing the performance
guarantee within 7 days of date of receipt of such notice
Quotation
 Construction work may be procured by means of quotation
of works if the the value of work procurement up to 5 lakhs.
In this situation quotation shall be demanded with at least
three firms which are registered in the standing list of office.
Community Participation /User’s Committee
 This method is used for executing small labor intensive works
where the objective is to:
• Provide employment and income directly to persons living in the
project area.
• Increase the utilization of local know how, appropriate technologies
and materials
• Hand over the completed works for operation and maintenance
directly by persons living in the project area.
• When objective of project is to create employment which enhances
the economy, quality or substantiality of beneficiary community then
this method is used.
Works up to 1 crore (including VAT, contingencies & portion
of community) may be carried out by community participation.
Force Account
 Work such as repair and maintenance of ordinary nature, regular
petty work or sanitation may be executed by force account
 If a construction work is to be executed through force account
such a work may be caused to be executed through negotiation
after breaking it into pieces not exceeding 1 lakhs rupees or be
awarded on wage basis by making available the necessary
construction materials.
Types of contract for procurement of works
 A public entity may, in order to carry out a construction work, conclude any
one of the following contracts (Clause 22, Appendix 4 of the Public Procurement
Regulation):-
A. Unit Rate Contract
B. Lump-sum Contract
C. Cost Reimbursable Contract
D. Time and Material Rate Contract
E. Design and Build Contract
F. Management Contract
G. Performance Based Maintenance Management Contract
H. Piecework Contract
I. Build and maintenance contract
J. Turnkey contract
Unit Rate Contract:
 A unit rate contract may be concluded to execute a construction work the
quantity of which is not ascertained at the time of conclusion of the
procurement contract or to provide the per unit activity of a construction work
at the rate referred to in the Bill of Quantities. In such a unit rate, the bidder
shall include the materials, labor and other things required to complete the
proposed construction work.
 Adopted when the quantities are difficult to be estimated precisely or they are
expected to vary
 In making payment for the work done pursuant to this contract, payment shall
be made of the amount to be found from computing the quantity of construction
work as ascertained from measurement of construction site by the per unit rate.
Lump sum contract:
 Provided that if the financial liability of the construction work is increased
for the reason that the public entity has ordered to make a change of any
type in the construction after the commencement of the construction work
upon conclusion of the procurement contract, the public entity shall bear
such contract.
 Adopted when quantities are fairly known (Eg. Superstructure of a Bridge)
or Difficult to Measure (Eg. Offshore Underwater Pipeline)
 lump sum contracts involve a fair amount of risk for contractors because
they don’t account for unexpected costs or delays after the project is
started.
Cost-reimbursement Contract:
 The cost-reimbursement contract may be concluded to execute a construction work nature of
which is high risky and unpredictable conditions of work and a construction entrepreneur does
not agree to execute or cannot execute it under the unit rate contract.
 In making payment to the construction entrepreneur for the construction work to be executed
by concluding this contract, payment may be made for the actual cost incurred in executing
such a construction work, overhead cost thereof, in addition to the profit as stated in the
approved cost estimate.
 In having a construction work executed by concluding this contract, the chief of the public
entity shall fix the maximum amount of cost-reimbursement and if an amount exceeding such
limit is to be paid, he or she shall obtain the prior approval of the head of department.
Different methods of reimbursement :
 Cost + percentage
 Cost + fixed fee
 Cost + fixed fee + profit-sharing clause.
Time and Material Rate Contract:
 The time and material rate contract may be concluded to carry out a work
by computing the labor on the basis of time and the materials as per the unit
rate due to unpredictability at the time of conclusion of the procurement
contract of the labor and materials required for the repair and maintenance
of a construction work.
 May be utilized for maintenance and repair services, and other situations
where it is difficult to predict the requirement of Labour and Material.
Design and Build Contract:
 The design and build contract may be concluded to have a design and
construction of a construction work to be executed by the same
construction entrepreneur.
 The public entity shall start the work under this contract only after causing
the design of construction work to be examined and approved by a
technician or a team of technicians.
 The technician or team of technicians who so examines the design shall
examine and approve such design, drawing and cost estimate by following
the procedure set forth in this Regulation for examination and approval.
Management contract:
 May be used in Project where there are Diverse Activities.
 Contractor takes the Legal and Contractual Responsibility
about Quality and Timely Completion.
 Payment for the work under this contract shall be made only to
the construction entrepreneur who has concluded the
procurement contract with the public entity.
Performance-based maintenance or management contract:
 The performance-based maintenance or management contract
may be concluded to execute a construction work without
mentioning the equipment required to maintain and manage
the construction work and item wise work and by mentioning
only the final performance.
 Used in Repair and Maintenance Projects.
 Payment based on Performance rather than Item-wise quantity.
 Penalty Provision if Performance Indicators not met.
Piecework Contract
 Used for small Repair and Maintenance works
 On As and When required basis.
 Contract Period generally not to be more than 1 year
Build and maintenance contract:
 The build and maintenance contract may be concluded to build
a big fast track, power plant with a big reservoir or pumping
station or turbine, ropeway, railway cable car or similar other
physical structure with sophisticated or complex technology,
conduct testing, give training, as required, to the employees of
the concerned public entity for operating such structure and
also to repair and maintain such structure.
Turnkey contract:
 The turnkey contract may be concluded to build a big fast
track, power plant with a big reservoir or pumping station or
turbine, ropeway, railway cable car, bridge or road with
sophisticate technology or similar other physical structure with
sophisticated or complex technology, conduct testing,
complete operation of such structure and hand it over to the
public entity.
Preparation of Bid Documents
 Bidding Documents should be prepared on the basis of Standard Bidding
Documents (SBDs) of PPMO, WB and ADB, etc. as the case may be. The
following step wise points to be followed to prepare Bid documents:
• Decide the SBD to be used;
• Finalize Cost Estimate;
• Collect the Scope of specialized works like pavement, Concrete, bridge etc;
• Finalize BoQ
• Discuss with authority on qualification criteria including financial capacity and
technical capacity to be applied;
• Prepare Qualification criteria in separate Excel sheet (for easy reference);
Preparation of Bid Documents
• Decide on whether to go for E-bidding or not;
• Prepare IFB providing all required information;
• Prepare Bidding Data Sheet as per project requirement and complexity;
• Prepare qualification requirements as per project requirement and complexity,
referring qualification criteria excel sheet prepared earlier;
• Prepare Contract Data/PCC as per project requirement and complexity;
• Take care of Price adjustment factor (whether for construction material only or
standard practice);
• Prepare Preamble for BoQ;
• Provide supplementary information, if any.
• Get NOL or approval of Bid document, as the case may be.
Outline of Bidding Documents
Invitation for Bids
Part I: Bidding Procedures
Section - I Instructions to Bidders
Section - II Bid Data Sheet
Section - III Evaluation and Qualification Criteria
Section – IV Bidding Forms
Part - II Requirements
Section - V Works Requirements
Section - VI Bill of Quantities
Part - III Conditions of Contract and Contract Forms
Section - VII General Conditions of Contract
Section - VIII Special Conditions of Contract
Section - IX Contract Forms
Thank you
for your kind attention
Your queries please !

More Related Content

What's hot

BIDDING PROCEDURES AND UPDATES.pptx
BIDDING PROCEDURES AND UPDATES.pptxBIDDING PROCEDURES AND UPDATES.pptx
BIDDING PROCEDURES AND UPDATES.pptxbenito procia
 
Fidic contract
Fidic contract Fidic contract
Fidic contract Yash Patel
 
Tender Management
Tender ManagementTender Management
Tender ManagementAwais Tahir
 
Topic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptxTopic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptxVanJasperCastillo
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spceirkportal
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractAvinash Kumar Gupta
 
Procurement of services ppt
Procurement of services pptProcurement of services ppt
Procurement of services pptparibeshtimsina1
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessPrateek Kashyap
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tenderingvvsasane
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftMuneesh Methwani
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 

What's hot (20)

BIDDING PROCEDURES AND UPDATES.pptx
BIDDING PROCEDURES AND UPDATES.pptxBIDDING PROCEDURES AND UPDATES.pptx
BIDDING PROCEDURES AND UPDATES.pptx
 
Tendering presenation
Tendering presenationTendering presenation
Tendering presenation
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
Fidic contract
Fidic contract Fidic contract
Fidic contract
 
Fidic
FidicFidic
Fidic
 
Tenders, their types and process
Tenders, their types and processTenders, their types and process
Tenders, their types and process
 
Public Procurement and Contract - Theory and practice in Nepal_2013
Public Procurement and Contract - Theory and practice in Nepal_2013Public Procurement and Contract - Theory and practice in Nepal_2013
Public Procurement and Contract - Theory and practice in Nepal_2013
 
Tender Management
Tender ManagementTender Management
Tender Management
 
Procurement of services
Procurement of  servicesProcurement of  services
Procurement of services
 
Topic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptxTopic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptx
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spce
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction Contract
 
Procurement of services ppt
Procurement of services pptProcurement of services ppt
Procurement of services ppt
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award Process
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 
Construction Bidding Step-by-Step
Construction Bidding Step-by-StepConstruction Bidding Step-by-Step
Construction Bidding Step-by-Step
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 

Similar to Procurement of works

Procurement Management
Procurement ManagementProcurement Management
Procurement Managementlearnafren
 
Types of tenders & stages for successful tendering
Types of tenders & stages for successful tenderingTypes of tenders & stages for successful tendering
Types of tenders & stages for successful tenderingAditya Sanyal
 
2. Project Procurement Process.pptx
2. Project Procurement Process.pptx2. Project Procurement Process.pptx
2. Project Procurement Process.pptxDoctorOkelloBen
 
Public Issue Rules, 2015
Public Issue Rules, 2015Public Issue Rules, 2015
Public Issue Rules, 2015Suman Kundu
 
governmentprocurementactww-180625195256.pptx
governmentprocurementactww-180625195256.pptxgovernmentprocurementactww-180625195256.pptx
governmentprocurementactww-180625195256.pptxJeesseJadulco
 
governmentprocurementactww-180625195256.pdf
governmentprocurementactww-180625195256.pdfgovernmentprocurementactww-180625195256.pdf
governmentprocurementactww-180625195256.pdfRalph Vasquez, CIE
 
Tendering procedures
Tendering proceduresTendering procedures
Tendering proceduresRotich Kimaru
 
Government procurement Act RA 9184
Government procurement Act  RA 9184Government procurement Act  RA 9184
Government procurement Act RA 9184SQSY
 
tamil nadu tenders act.pptx
tamil nadu tenders act.pptxtamil nadu tenders act.pptx
tamil nadu tenders act.pptxPradeep513562
 
Purchase procedure 9thJuly 2019 at iitb
Purchase procedure 9thJuly 2019 at iitbPurchase procedure 9thJuly 2019 at iitb
Purchase procedure 9thJuly 2019 at iitbGanesh Bhorkade
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTVISHNU VIJAYAN
 
Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...Mauricio Portugal Ribeiro
 
Ethiopian tender practice
Ethiopian tender practiceEthiopian tender practice
Ethiopian tender practiceEyob Ahmed
 
Tender & its process.pptx
Tender & its process.pptxTender & its process.pptx
Tender & its process.pptx2ke21cv405
 

Similar to Procurement of works (20)

Procurement Management
Procurement ManagementProcurement Management
Procurement Management
 
Procurement
ProcurementProcurement
Procurement
 
Types of tenders & stages for successful tendering
Types of tenders & stages for successful tenderingTypes of tenders & stages for successful tendering
Types of tenders & stages for successful tendering
 
2. Project Procurement Process.pptx
2. Project Procurement Process.pptx2. Project Procurement Process.pptx
2. Project Procurement Process.pptx
 
Public Issue Rules, 2015
Public Issue Rules, 2015Public Issue Rules, 2015
Public Issue Rules, 2015
 
Tanmay presentation
Tanmay presentationTanmay presentation
Tanmay presentation
 
governmentprocurementactww-180625195256.pptx
governmentprocurementactww-180625195256.pptxgovernmentprocurementactww-180625195256.pptx
governmentprocurementactww-180625195256.pptx
 
governmentprocurementactww-180625195256.pdf
governmentprocurementactww-180625195256.pdfgovernmentprocurementactww-180625195256.pdf
governmentprocurementactww-180625195256.pdf
 
Tenders for construction
Tenders for constructionTenders for construction
Tenders for construction
 
Qsct tendering dr_clj
Qsct tendering dr_cljQsct tendering dr_clj
Qsct tendering dr_clj
 
Tendering procedures
Tendering proceduresTendering procedures
Tendering procedures
 
Government procurement Act RA 9184
Government procurement Act  RA 9184Government procurement Act  RA 9184
Government procurement Act RA 9184
 
tamil nadu tenders act.pptx
tamil nadu tenders act.pptxtamil nadu tenders act.pptx
tamil nadu tenders act.pptx
 
Purchase procedure 9thJuly 2019 at iitb
Purchase procedure 9thJuly 2019 at iitbPurchase procedure 9thJuly 2019 at iitb
Purchase procedure 9thJuly 2019 at iitb
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACT
 
Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Chapter -Two (3).pdf
Chapter -Two (3).pdfChapter -Two (3).pdf
Chapter -Two (3).pdf
 
Ethiopian tender practice
Ethiopian tender practiceEthiopian tender practice
Ethiopian tender practice
 
Tender & its process.pptx
Tender & its process.pptxTender & its process.pptx
Tender & its process.pptx
 

Recently uploaded

EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 

Recently uploaded (20)

EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 

Procurement of works

  • 1. PROCUREMENT OF WORKS (Highlight of PPA, 2007 & PPR, 2007, Contract type & Standard bidding documents) Prepared By: Group Members (M.Sc. III Semester) Ayush Joshi Krishna Koirala Milan Bhattarai Sandeep Udash Sarala Dahal
  • 2. Procurement “Procurement” means the acquisition by any public entity of any goods, consultancy services or other services, or executing or causing to be executed any construction works by such an entity. (PPA, 2007)
  • 3. Construction works The construction works means all activities associated with the construction, reconstruction, demolition, repair or renovation of a building, structure or associated activities, such as site preparation, excavation, erection, building, installation of equipment or materials, decoration and finishing.
  • 4. Provisions Relating to Procurement of works  Prior to procuring construction work, a public body shall prepare a specification, plan, drawing, design, special requirement or other descriptions thereof.  A public body shall prepare a cost estimate as prescribed for any procurement whatsoever.
  • 5. Provisions Relating to Procurement works  A public entity shall approve the cost estimate. Authority to approved cost estimate: • Cost estimate upto 1 crore by Gazetted 3rd class chief of Office. • Cost estimate upto 5 crore by Gazetted 2nd class chief of Office. • Cost estimate upto 10 crore by Gazetted 1st class chief of Office. • Cost estimate above 10 crore by the head of department. Cost estimate once approved, such an amendment differs by more than 25% of the original cost estimate figure or the act of procurement gets affected for the reason that the defective design has been made or abnormal cost estimate has been prepared, the official who has prepared, examined or approved such a design or cost estimate and the consultant who has been involved in that act shall be liable to action under the prevailing law.
  • 6. Provisions Relating to Procurement works  A public entity should prepared Procurement plan. (a) Master procurement plan : Project period exceeding 1 year (multiyear project) or in making an procurement of an amount exceeding 10 crores a year. (b) Annual procurement plan: Where a public entity is to make procurement of an amount exceeding 10 lakhs a year.  Each public entity should prepare separate standing list of suppliers, construction entrepreneurs, consultants for procurement to be made.
  • 7. Procurement method A public entity shall make procurement of works by applying any of the following methods based on conditions and purchase price: 1. Inviting international open bidding (ICB) 2. Inviting national open bidding (NCB) 3. Inviting sealed quotations 4. Direct procurement 5. Through participation of users' committee or beneficiary group 6. Through a forced account
  • 8. International Competitive bidding (ICB) 1. If the construction works as requisitioned by a public entity are not available at the competitive price from more than one construction entrepreneur within the State of Nepal, 2. If no bid has been submitted in response to an invitation to national bidding for the procurement of construction works, and the same has to be procured from abroad, 3. If construction works have to be procured through the foreign assistance source pursuant to the agreement entered into with a donor party, 4. If it is certified by the public entity that the construction works, being of complex and special nature, have to be procured through international bidding. 5. If Project cost estimate exceed 1 Arab.
  • 9. National Competitive bidding (NCB) 1. A construction work the cost estimate of which is above 20 lakh rupees but not exceeding 1 Arab rupees has to be procured upon having competition between native bidders only through the national open bidding, except in the circumstances referred to in Section 15 of the Act. 2. Standard bidding procedure used as per procurement value: • NCB, Single Stage Single Envelope (1S1E) – Procurement value above 20 lakhs and upto 2 crores. • NCB, Single Stage Two Envelope (1S2E) – Procurement value above 2 crores.
  • 10. Bidding Procedure for ICB/NCB… Bid invitation A notice for invitation to bids or pre-qualification proposals shall be published in a daily newspaper of national circulation, and in the case of an international bidding, it may also be published in any international communication media. The notice shall be placed in the website of the entity or that of the Public Procurement Monitoring Office i.e. www.bolpatra.gov.np/egp. Period of a notice: • For NCB or PQ proposal : Minimum 30 days • For ICB or PQ Proposal : Minimum 45 days •
  • 11. Bidding Procedure for ICB/NCB…  Fees for Bidding Documents • 20 lakhs to 2 Crores Rupees : Rs 3000 • > 2 Crores to 10 Crores Rupees : Rs 5000 • >10 Crores to 25 Crores Rupees : Rs10,000 • > 25 Crores Rupees : Rs 20,000  Withdrawal and Modification of Bid • Within last submission date of bid in sealed envelop in case of bidder who submits bid electronically • Within 24 hour before the last submission date for other bidders • Withdrawal or modification can be done at one time only.
  • 12. Bidding Procedure for ICB/NCB  Pre-bid meeting • For NCB at least 10 days before of last submission date • For ICB at least 15 days before of last submission date • To be informed to bidders if any amendment within 5 days pre bid meeting  Bid Security • 2 to 3 % of estimated amount • Validity of bid security 30 days more than bid validity period • Bid security amount shall be in form of a cash deposit or of a bid security equal to that amount issued by a commercial bank or financial institution.
  • 13. Bidding Procedure for ICB/NCB  Bid security will be forfeited if • If requested for withdrawal or modification within the period of last bid submission date and last date of bid validity. If the bidder does not accept the correction of arithmetic error • If the selected bidder rejects for agreement • If the selected bidder fail to submit performance bond within due date of contract agreement • If clarification submitted by bidder makes substantial change to the bid • If the bidder violates the code of conduct as per clause 62 of PPA. 
  • 14. Bidding Procedure for ICB/NCB  Bid validity Period • Bid validity period is a period within which bidder’s rate are valid • Contract agreement is done within bid validity period • For bid having estimated cost within 10 Crores : 90 days • For bid having estimated cost above 10 Crores: 120 days • Period to be counted from last date of bid submission • Can be increased with justified reasons • Who agrees to extend bid validity shall extend validity of bid security also • Bid bond amount shall be returned to bidder if he disagrees to extend bid validity
  • 15. Bidding Procedure for ICB/NCB  Bid Opening • Immediately after last date and time of bid submission in presence of bidders as far as possible (Absence of bidders does not disturb the opening process) • Then bid submitted electronically are opened first and then other bids are opened • Before opening bid, envelop of letter of withdrawn or modified bid shall be opened and read • Then remaining bids shall be opened and matters like bid security, discount if any etc. shall be read, noted and signed • No bid shall be rejected at the time of opening
  • 16. Bidding Procedure for ICB/NCB  Examination of completeness of bids  Evaluation of bids:  Technical Evaluation  Financial Evaluation  Special Evaluation  Evaluation report  Bid approval • Upto 3 crores: gazetted third class chief of the office • Upto 7 crores: gazetted second class chief of the office • Upto 15 crores: gazetted first class chief of the office • Above 15 crores: the head of department
  • 17. Bidding Procedure for ICB/NCB  Performance security • To be taken to ensure due performance of contract • 5% of Contract Value If bid price of the bidder selected for acceptance is up to 15(fifteen) percent less than the approved cost estimate, the performance security amount shall be 5 (five) percent of the bid price. • For the bid price less than 15 percent of the cost estimate, the performance security amount shall be determined as follows: Performance Security Amount = (0.85 × Cost Estimate – Bid Price) × 0.5 + 5% of Bid Price. • The Bid Price and Cost Estimate shall be inclusive of Value Added Tax
  • 18. Bidding Procedure for ICB/NCB  Contract award • Letter of intent is issued within seven days of bid selection & information should be given to other bidders also. • If there is no complaint from other bidders within seven days, letter of acceptance is issued to notify the successful bidder to come with performance security for contract agreement within 15 days. • If successful bidder fails to furnish the performance guarantee and to sign contract within 15 days, then his bid security shall be forfeited and bid of next lowest responsive bidder is accepted and called for agreement If lowest evaluated bidder does not sign the agreement, in addition to forfeiture of bid bond PPMO on the recommendation of PE blacklist the bidder. • If any bidder requests for information on the reason for rejection of within 30 days of issuing of letter of intent, the public entity shall communicate such information to the bidder.
  • 19. Bidding Procedure for ICB/NCB  Rejection of tender or cancellation of procurement proceedings • Where non of the tenders is substantial responsive • Where the bid price of the lowest evaluated substantially responsive bid is substantially higher than cost estimate • Where construction works are no longer required. No tender shall be rejected or re tendering shall be invited only by the reason that only a few tenders or only one tender is substantial responsive. A public entity shall communicate a notice along with the reason for the rejection of tenders or the cancellation of procurement proceedings to all bidders.
  • 20. Sealed Quotation  Procurement of works up to 20 lakhs can be carried out adopting sealed quotation  Procedure Preparation of Sealed Quotation Document Invitation: Notice in national or local newspaper with minimum period of 15 days. Sale and registration of Bid :Same as open bidding Bid validity period : 45 day  Bid security : same as open bidding (validity 75 days) Withdrawal and Modification of Bid: Not allowed Bid Evaluation & Bid Evaluation Report Same as open bidding except if less than three sealed quotations are submitted, it shall be cancelled and re-notice is published. However for the second time less than three sealed quotations can
  • 21. Sealed Quotation  Selection for Award of Contract: Same as open bidding Price of Bidding Documents: Rs. 1000 Performance security: Same as open bidding Contract award • The public entity shall accept the sealed quotation within 15 days of opening. • Notice is issued to selected bidder within 7 days of acceptance of the sealed quotation. Notice is issued to other bidders also. • The sealed quotation bidder who receives the notice shall enter into the procurement contract by furnishing the performance guarantee within 7 days of date of receipt of such notice
  • 22. Quotation  Construction work may be procured by means of quotation of works if the the value of work procurement up to 5 lakhs. In this situation quotation shall be demanded with at least three firms which are registered in the standing list of office.
  • 23. Community Participation /User’s Committee  This method is used for executing small labor intensive works where the objective is to: • Provide employment and income directly to persons living in the project area. • Increase the utilization of local know how, appropriate technologies and materials • Hand over the completed works for operation and maintenance directly by persons living in the project area. • When objective of project is to create employment which enhances the economy, quality or substantiality of beneficiary community then this method is used. Works up to 1 crore (including VAT, contingencies & portion of community) may be carried out by community participation.
  • 24. Force Account  Work such as repair and maintenance of ordinary nature, regular petty work or sanitation may be executed by force account  If a construction work is to be executed through force account such a work may be caused to be executed through negotiation after breaking it into pieces not exceeding 1 lakhs rupees or be awarded on wage basis by making available the necessary construction materials.
  • 25. Types of contract for procurement of works  A public entity may, in order to carry out a construction work, conclude any one of the following contracts (Clause 22, Appendix 4 of the Public Procurement Regulation):- A. Unit Rate Contract B. Lump-sum Contract C. Cost Reimbursable Contract D. Time and Material Rate Contract E. Design and Build Contract F. Management Contract G. Performance Based Maintenance Management Contract H. Piecework Contract I. Build and maintenance contract J. Turnkey contract
  • 26. Unit Rate Contract:  A unit rate contract may be concluded to execute a construction work the quantity of which is not ascertained at the time of conclusion of the procurement contract or to provide the per unit activity of a construction work at the rate referred to in the Bill of Quantities. In such a unit rate, the bidder shall include the materials, labor and other things required to complete the proposed construction work.  Adopted when the quantities are difficult to be estimated precisely or they are expected to vary  In making payment for the work done pursuant to this contract, payment shall be made of the amount to be found from computing the quantity of construction work as ascertained from measurement of construction site by the per unit rate.
  • 27. Lump sum contract:  Provided that if the financial liability of the construction work is increased for the reason that the public entity has ordered to make a change of any type in the construction after the commencement of the construction work upon conclusion of the procurement contract, the public entity shall bear such contract.  Adopted when quantities are fairly known (Eg. Superstructure of a Bridge) or Difficult to Measure (Eg. Offshore Underwater Pipeline)  lump sum contracts involve a fair amount of risk for contractors because they don’t account for unexpected costs or delays after the project is started.
  • 28. Cost-reimbursement Contract:  The cost-reimbursement contract may be concluded to execute a construction work nature of which is high risky and unpredictable conditions of work and a construction entrepreneur does not agree to execute or cannot execute it under the unit rate contract.  In making payment to the construction entrepreneur for the construction work to be executed by concluding this contract, payment may be made for the actual cost incurred in executing such a construction work, overhead cost thereof, in addition to the profit as stated in the approved cost estimate.  In having a construction work executed by concluding this contract, the chief of the public entity shall fix the maximum amount of cost-reimbursement and if an amount exceeding such limit is to be paid, he or she shall obtain the prior approval of the head of department. Different methods of reimbursement :  Cost + percentage  Cost + fixed fee  Cost + fixed fee + profit-sharing clause.
  • 29. Time and Material Rate Contract:  The time and material rate contract may be concluded to carry out a work by computing the labor on the basis of time and the materials as per the unit rate due to unpredictability at the time of conclusion of the procurement contract of the labor and materials required for the repair and maintenance of a construction work.  May be utilized for maintenance and repair services, and other situations where it is difficult to predict the requirement of Labour and Material.
  • 30. Design and Build Contract:  The design and build contract may be concluded to have a design and construction of a construction work to be executed by the same construction entrepreneur.  The public entity shall start the work under this contract only after causing the design of construction work to be examined and approved by a technician or a team of technicians.  The technician or team of technicians who so examines the design shall examine and approve such design, drawing and cost estimate by following the procedure set forth in this Regulation for examination and approval.
  • 31. Management contract:  May be used in Project where there are Diverse Activities.  Contractor takes the Legal and Contractual Responsibility about Quality and Timely Completion.  Payment for the work under this contract shall be made only to the construction entrepreneur who has concluded the procurement contract with the public entity.
  • 32. Performance-based maintenance or management contract:  The performance-based maintenance or management contract may be concluded to execute a construction work without mentioning the equipment required to maintain and manage the construction work and item wise work and by mentioning only the final performance.  Used in Repair and Maintenance Projects.  Payment based on Performance rather than Item-wise quantity.  Penalty Provision if Performance Indicators not met.
  • 33. Piecework Contract  Used for small Repair and Maintenance works  On As and When required basis.  Contract Period generally not to be more than 1 year
  • 34. Build and maintenance contract:  The build and maintenance contract may be concluded to build a big fast track, power plant with a big reservoir or pumping station or turbine, ropeway, railway cable car or similar other physical structure with sophisticated or complex technology, conduct testing, give training, as required, to the employees of the concerned public entity for operating such structure and also to repair and maintain such structure.
  • 35. Turnkey contract:  The turnkey contract may be concluded to build a big fast track, power plant with a big reservoir or pumping station or turbine, ropeway, railway cable car, bridge or road with sophisticate technology or similar other physical structure with sophisticated or complex technology, conduct testing, complete operation of such structure and hand it over to the public entity.
  • 36. Preparation of Bid Documents  Bidding Documents should be prepared on the basis of Standard Bidding Documents (SBDs) of PPMO, WB and ADB, etc. as the case may be. The following step wise points to be followed to prepare Bid documents: • Decide the SBD to be used; • Finalize Cost Estimate; • Collect the Scope of specialized works like pavement, Concrete, bridge etc; • Finalize BoQ • Discuss with authority on qualification criteria including financial capacity and technical capacity to be applied; • Prepare Qualification criteria in separate Excel sheet (for easy reference);
  • 37. Preparation of Bid Documents • Decide on whether to go for E-bidding or not; • Prepare IFB providing all required information; • Prepare Bidding Data Sheet as per project requirement and complexity; • Prepare qualification requirements as per project requirement and complexity, referring qualification criteria excel sheet prepared earlier; • Prepare Contract Data/PCC as per project requirement and complexity; • Take care of Price adjustment factor (whether for construction material only or standard practice); • Prepare Preamble for BoQ; • Provide supplementary information, if any. • Get NOL or approval of Bid document, as the case may be.
  • 38. Outline of Bidding Documents Invitation for Bids Part I: Bidding Procedures Section - I Instructions to Bidders Section - II Bid Data Sheet Section - III Evaluation and Qualification Criteria Section – IV Bidding Forms Part - II Requirements Section - V Works Requirements Section - VI Bill of Quantities Part - III Conditions of Contract and Contract Forms Section - VII General Conditions of Contract Section - VIII Special Conditions of Contract Section - IX Contract Forms
  • 39. Thank you for your kind attention Your queries please !