SlideShare a Scribd company logo
1 of 9
Download to read offline
Technical Specification
METAL WORK, GATES AND WELDING
1. Gates and Gate Hardware
1.1 Design, Drawing and Data
No drawings other than those included in the Bidding Documents shall be provided by
the Employer. The Drawings provided show general details only. The Contractor shall therefore
prepare the necessary detailed Design Drawings and data required for the fabrication and
installation of the gates and other metal-works. Steel gates shall be designed/fabricated by a firm
which has reasonable past experience. If the Contractor lacks sufficient experience in fabricating
gates, a specialist firm shall be engaged.
Any fabrication or procurement, prior to approval of the design, drawings and the relevant
data, shall be at the Contractor’s own risk. The Employer’s Representative has the right to order
the Contractor to make any change in the design, drawings and data so as to make the gates and
metal-works conform to the requirement of the under mentioned specifications without additional
cost to the Employer. However, approval from the Employer’s Representative on the Contractor’s
design, drawings and data shall not relieve the Contractor of any part of the Contractor’s
responsibility.
Before proceeding with fabrication or procurement of gates and metal-works, the
Contractor shall submit two (2) sets of the drawings and data showing specification of materials,
assembly, lift capacity and detailed dimensions for approval for Employer’s Representative.
The costs of preparing the design, drawings and data, and submitting such things to the
Employer’s Representative shall be included in the unit rates in the Bill of Quantities for
furnishing and installing the gates and other metal-works.
1.2 Design to Suit Climate
The water control equipment to be supplied, shall be designed with due regard to the climatic
conditions prevailing in the Project area, particular care being taken to accommodate expansion
and contraction due to temperature changes. Water control equipment shall be suitable for
operating in ambient air temperatures from 5° C to 45° C but parts exposed to the sun may reach
higher temperatures.
1.3 Materials, Stresses and Workmanship
The water control equipment shall be designed and constructed in accordance with the
requirements of BS 153 except where inconsistent with the terms of the Specifications. The
deflection of gates shall be restricted to 1/600 of their clear span.
1.4 Minimum Thickness
An allowance of 2 mm shall be added to the thickness of gate skin plates over and above
the calculated thickness required to meet the design stresses, but in no case shall the actual skin
plate thickness be less than 8 mm, unless otherwise shown on the Drawings.
Unless otherwise shown on the Drawings, plates (other than skin plates) rolled steel angles
and tee sections used in the construction of gates shall have a minimum thickness of 10 mm and
the webs of rolled steel beams and channel sections shall have a minimum thickness of 10 mm.
Unless otherwise shown on the Drawings, metal-works which will be permanently or semi-
permanently submerged, such as that used for embedded guides, frames, etc., shall have a
minimum thickness of 10 mm, with the exception of rolled steel beam and channel sections which
shall have a minimum thickness of 7.5 mm.
1.5 Gate Design
Each gate shall be designed to withstand and operate against the seating head of water
specified on the relevant Drawings with no water downstream and of being raised clear of the
orifice soffit.
Each gate shall consist of framing incorporating guide grooves, sealing faces and a spindle guide
bracket supporting members specified on the Drawings, movable gate leaf with sealing faces and
operating gear.
1.6 Framing and Gear Supporting Members
The gate framing shall consist of steel guide grooves fabricated from a standard MS
sections with sill, lintel and spindle guide bracket supporting members, where specified on the
Drawing, and shall all be connected to the grooves by bolts at their ends.
Gear supporting members shall be angle sections or other suitable sections connected to
the grooves by bolts at their ends.
The groove members shall extend upwards to support and guide the gate throughout its
travel and shall be arranged for bolting on to the concrete headwall, or casting into gate slots, as
shown on the Drawings.
The framing shall be fitted with machined non-ferrous or stainless steel faces upon which
the gate shall slide and seal. Arrangements shall be incorporated to permit the framing to be
accurately aligned and levelled and finally held in position before being grouted to the concrete
headwall, or gate slot filled with concrete.
The gear supporting members shall be designed to resist the loads resulting from operating
the gate.
1.7 Gate
The gate shall consist of a steel skin plate supported by horizontal stiffening members
connected to vertical side guiding and stiffening members contained within the grooves.
Arrangements shall be provided for attaching the gate to the operating spindle by a non-ferrous
hinge pin.
Slide Gates - The gate shall be fitted with machined non-ferrous sliding faces and approved
rubber seals, as detailed on the Drawings, to achieve an effective watertight seal.
Roller Gates -The gate shall have cast iron self-lubricating rollers with ARMCO
“Lubrite”, or similar, bushings.
1.8 Operating Gear
The operating gear shall consist of a hand operated self-sustaining gear capable of
operating the gate against the maximum water loading conditions specified, and capable of
positively holding the gate in any position when the hand wheel or crank handle is released. The
operating gear shall be capable of being operated by one man.
The gear units shall consist of a bronze operating nut engaging with a mild steel operating
screw attached to the gate. The lifting mechanisms shall be either Armco type HB 18 to 24 Armco
type for gates requiring only a single lifting mechanism or Armco type CPE 2 or 4 for gates
requiring tandem lifting mechanisms with one stem left threaded and one right threaded. Other
proprietary lifting mechanisms of equivalent specification to the Armco units can be supplied with
the prior approval of the Employer’s Representative.
All gear sprockets and pinions shall be machine cut with ratio and strength adequate to
withstand operating loads.
1.9 Bolted Joints
The Contractor shall supply all the necessary bolts, nuts, washers etc, for fixing the
metalwork, together with a suitable number of spare bolts, nuts and washers. Bolted joints subject
to vibration shall be securely locked.
All bolt holes shall be drilled and the outside edges slightly countersunk.
Friction grip bolts, nuts and washers shall comply with BS 4604, Part 1. They shall be used
on all bolted joints which are liable to vibrate and elsewhere to the approval of the Employer’s
Representative.
Gears shall be enclosed with casings to avoid dust and rain.
To prevent unauthorised use, operating gear shall be provided with appropriate locking
devices.
The lift housing or hand wheel shall be provided with a cast-in direction arrow and the
word “OPEN” to indicate the direction of operation, to open gates.
1.10 Field Connections
Field connections shall, whenever possible, be bolted connections. Welded field
connections will be permitted where it is considered by the Employer’s Representative
impractical to form bolted connections, in which case the weld preparation shall be carried out in
the manufacturer’s works before despatch and the prepared surfaces shall be fully protected for
transport to, and storage on, the Site. The Contractor shall supply the electrodes for completing
the connections on site.
Connections to be welded at Site shall be made by the Contractor’s welders using their own
welding plant.
Lift mechanisms shall be provided with a cast iron stop nut to allow adjustable end-stop
travel.
1.11 Standardization and Maintenance
Wherever possible, corresponding parts shall be finished with sufficient accuracy to ensure
that they are interchangeable, and where required by the Employer’s Representative
interchangeability shall be proved by actually changing the various parts.
The design shall be such that all parts of the installations are accessible for inspection and
maintenance and for use where continuity of operation is a first consideration. Drainage holes shall
be provided in members, which are likely to collect or retain water.
1.12 Advance Delivery of Anchor Members, etc.
Anchor members, seating plates etc. for building into primary concrete work to facilitate
alignment and fixing of embedded parts shall be supplied by the Contractor and delivered in
advance of the remainder of the parts, in accordance with a programme arranged by the Contractor
and agreed by the Employer’s Representative to fit the overall construction programme.
1.13 Preparation and Storage of Bolts
Before they are despatched to the Site, the Contractor shall protect all bolts (other than
rag-bolts, Lewis bolts and galvanised bolts) by heating them and dipping them while hot into
boiled linseed oil, or shall provide such other protection as may be approved by the Employer’s
Representative. The Contractor shall pack the bolts carefully so that the threads do not become
damaged or dirty during delivery, storage and transport to Site.
5.1.14 Packing and Marking
The Contractor shall pack, mark, and as necessary protect, all parts for delivery, unloading,
storage and subsequent transport to Site in accordance with the relevant section of BS 1133.
Attention shall be given to the protection of parts which are liable to deterioration in the
climatic condition prevailing in the Project Area, and the form of packaging shall be such that no
damage to the equipment shall result from normal handling or prolonged storage in the open.
Small parts shall be boxed and suitably marked on the outside. Larger parts shall be
protected as necessary and shall be suitably marked and listed.
Lists of contents of crates, boxes and bunches shall be supplied and shall be handed over
to the Employer’s Representative on delivery of each consignment.
Attention shall be given to the method of marking sub-assemblies and other components
to assist in identifying them at Site. The method of marking employed shall enable any particular
component or sub-assembly to be easily identified from the Contractor’s Drawings and also from
the shipping specification.
Where practicable, components for each individual site shall be packed separately so that
all items required for each site may be easily separated and transported to individual sites.
1.15 Erection at Place of Manufacture
Each gate and operating gear shall be fully assembled at the place of manufacture for
inspection by the Employer’s Representative and, if considered necessary, testing before despatch.
The Contractor shall arrange for the manufacturer to give the Employer’s Representative, in
writing, a minimum of fourteen (14) days’ notice prior to the date when the assemblies will be
ready for inspection. No parts shall be despatched from the manufacturer’s works until they have
been marked to ensure correct re-assembly at Site.
1.16 Inspection at Place of Manufacture
Inspection of materials, workmanship, manufacture of the gates, and the trial assembly of
components at the place of manufacture, in accordance with the preceding Sub-Clause of these
Specifications, shall be carried out by the Employer’s Representative at his discretion and shall
include the following:
a. Checks on steel and other materials used to ensure compliance with accepted standards.
Manufacturer's chemical analysis sheets and report sheets showing results of tests on
any physical properties, which may be called for.
b. Dimensional checks to ensure conformity with approved Drawings.
c. Weld inspection and testing where required.
d. Inspection of cleaning and painting of steelwork.
e. Witnessing erection and testing at the manufacturer’s works.
f. Inspection of method of packing components for despatch.
1.17 Erection of Metalwork
The erection of the metalwork at the Site shall comply with BS 449, Part 5 and be in
accordance with the recommendations of BS 5531. When lifting and fitting metalwork into
position care shall be taken that the parts thereof are not strained, twisted, bent or damaged in any
way whatsoever. Should any parts be strained, twisted, bent or damaged they shall be rectified in
such manner as the Employer’s Representative may approve. Any parts that are, in the opinion of
the Supervisor, too badly damaged for rectification in the manner aforesaid shall be replaced by
new material. All rectification and/or replacement shall be carried out at the Contractor’s own cost.
The stacking of metalwork, or the individual parts thereof, that are stored in positions as
may, in the opinion of the Employer’s Representative, cause damage to any of the members or
parts thereof or to any portion of the Works, shall not be permitted.
Proper and suitable slings, blocks, tackles, shear legs, derricks, cranes and other types of
lifting appliances and equipment shall be provided, whenever needed for the erection of the
metalwork. Every care and precaution shall be taken to ensure the safety of all persons engaged
in such work and to prevent damage to any metalwork in the process of being erected or already
erected or to any part of the Works from the results of any mishap, failure, breakdown or other
accident to any of the aforesaid lifting appliances and equipment. The lifting of metalwork in
bundles or in such quantities or in any manner which, in the opinion of the Supervisor, is liable
to cause damage or strain or is in any way considered to be insecure or unsafe shall not be
permitted.
The use of high strength friction grip bolts and nuts in the erection of metalwork shall be
generally in accordance with the provisions of BS 4604: Part 1, except that the method of
tightening load indicating bolts or bolts incorporating load indicators shall be in conformity with
the manufacturer’s instructions.
1.18 Testing after Erection
After erection, the Contractor shall check that the gates and gate hardware are complete
and in working order, and satisfactorily fulfils the purpose for which it is intended.
The Contractor shall test all gates to the satisfaction of the Employer’s Representative.
Each gate shall be made to move through a full cycle of operation using the equipment specified
for the purpose, unless otherwise instructed, and each gate when closed shall affect a watertight
seal to the approval of the Employer’s Representative.
1.19. Painting of Gates
1.19.1 Supply of Paint and Painting at Site
The Contractor shall prepare the surfaces and apply the finishing coats of paints during
erection at Site.
The Contractor shall supply and deliver to the Site a sufficient quantity of priming paint to
make good any damage during delivery, handling and erection. The Contractor shall also supply
and deliver to the Site sufficient paint for two finishing. The supply and delivery of the paint shall
be in accordance with programmes which the Contractor shall have previously agreed with the
Employer’s Representative and having proper regard to the shelf life of the paints, and all to the
approval of the Employer’s Representative.
The paint shall be delivered in the paint manufacturer’s drums with seals unbroken. Each
drum shall be clearly and indelibly marked with a description of its contents, its date of
manufacture, and the date before which it should be used. Each drum shall have a different serial
number. The Contractor shall keep a record of the delivery dates of each drum and its use-by date.
Copies of the records should be available if requested by the Employer’s Representative or the
Contracting Authority.
1.19.2 Paint
Unless otherwise specified all coating and painting of metalwork shall be executed in
accordance with the principles and practices recommended by BS 5493. Testing of paints shall
be in accordance with BS 3900.
Linseed oil for coating steel pins, bolts, nuts, etc. shall be boiled oil as specified in BS 257.
Black paint, tar based, shall comply with BS 1070, Type A.
Lead-based priming paint shall comply with BS 2523, Type B. Zinc-rich paint shall
comply with BS 4652.
Aluminium paint for use on metalwork shall conform to the following requirements:
- The pigment shall consist entirely of leafing aluminium powder and shall be Type 1 as
specified in BS 388.
- The proportion of pigment to medium shall not be less than 20% by weight.
- The medium for priming paint shall be either a mixture of quick-drying phenolic resin or
tungoil and linseed oil, or alkyd resins.
The medium for finishing paint shall be acrylic resin.
The following schedule sets out the components of the schemes for protection of the water
control part:
Surface preparations: Blast cleaning as specified
Priming Paint
Underwater parts: 2 coats of zinc epoxy paint. Total dry film thickness 50 microns.
Above water parts: 2 coats of zinc phosphate priming paint to suit the finishing paint.
Total dry film thickness 70 microns.
Finishing Paint
Underwater parts: 2 coats of coal tar/epoxy. Total dry film thickness 250 microns.
Above water parts: 1 undercoat and 1 finishing coat of high build M10 chlorinated rubber
paint in silver grey. Total dry film thickness 200 microns.
All the paints shall be obtained from the same manufacturer and shall be compatible with
the other paints in the same protective scheme. They shall be suitable for the climatic conditions
in the Contracting Authority’s country. The manufacturer and the formulation of the paints shall
be subject to the approval of the Supervisor. The Contractor shall supply to the Employer’s
Representative samples of the paints at least thirty days before their being used on the Works.
The primer used beneath the coal tar/epoxy paint shall be specially formulated for the
purpose.
In selecting or formulating the zinc rich priming paint, the Contractor shall give due regard
to the period of storage and to the requirement that it shall give protection outdoors for periods of
possibly up to six (6) months.
The coal tar/epoxy paint shall be such that the coating will not run or craze when exposed
to direct sunlight on the Site for prolonged periods after immersion in water.
1.19.3 Painting during Erection
During the erection of the gates, the Contractor shall observe the following with regard to
painting:
ď‚· Contact surfaces that will be completely sealed in welded construction shall not be
painted.
ď‚· Surfaces which will be in continuous contact with concrete after completion of erection
shall not be painted.
ď‚· Contact surfaces of sub-assemblies and other members which are put together at Site, and
which will be in permanent contact with each other or concealed after erection shall each
be cleaned and painted with one coat priming paint before assembly and then assembled
while the paint is still wet.
1.19.4 Measurement and Payment of Gates
Measurement for payment shall be made in the unit rate as indicated in Bill of Quantities.
The rate that the Contractor quotes will incorporate the cost of guide frame, hoisting mechanism,
installation, painting, and all other accessories. The unit rate shall cover the cost of preparing the
design data, cost of all materials, fabrication, manufacturing, painting, loading and unloading
labour, furnishing and installing the slide gate including frame, hoist, operation handwheel and
all other accessories, cost of operation test.

More Related Content

What's hot

Sandwich panels
Sandwich panelsSandwich panels
Sandwich panelsEusebio Apaza
 
Fire Proofing works
Fire Proofing works Fire Proofing works
Fire Proofing works Babu Arumugam
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentationsomitra bhardwaj
 
Planta de calzaduras e 01
Planta de calzaduras e 01Planta de calzaduras e 01
Planta de calzaduras e 01junior alvarado
 
Chapter 8 floorings
Chapter 8 flooringsChapter 8 floorings
Chapter 8 flooringsKHUSHBU SHAH
 
Especificaciones tecnicas piso en ladrillo pdf
Especificaciones tecnicas piso en ladrillo pdfEspecificaciones tecnicas piso en ladrillo pdf
Especificaciones tecnicas piso en ladrillo pdfalexitacorrea
 
MDF, Medium Density Fiberboard (Interior-use Engineered Wood Panel Product, M...
MDF, Medium Density Fiberboard (Interior-use Engineered Wood Panel Product, M...MDF, Medium Density Fiberboard (Interior-use Engineered Wood Panel Product, M...
MDF, Medium Density Fiberboard (Interior-use Engineered Wood Panel Product, M...Ajjay Kumar Gupta
 
Scrap handling systems
Scrap handling systemsScrap handling systems
Scrap handling systemsmetudgn
 
Prefrabricated - puf panel
Prefrabricated - puf panelPrefrabricated - puf panel
Prefrabricated - puf panelBimenpreet Kaur
 
Prefabricated components
Prefabricated componentsPrefabricated components
Prefabricated componentsSofia Rajesh
 
Artificial Construction Materials- A beginners presentation
Artificial Construction Materials- A beginners presentationArtificial Construction Materials- A beginners presentation
Artificial Construction Materials- A beginners presentationPrashant P
 
Floors by chakamba john
Floors  by chakamba johnFloors  by chakamba john
Floors by chakamba johnJohn Chakamba
 
Artificial construction materials.pptxpsg
Artificial construction materials.pptxpsgArtificial construction materials.pptxpsg
Artificial construction materials.pptxpsgPallavi Gonjari
 
prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated StructuresBoopathi Raja
 
Piles, Piers and Caissons
Piles, Piers and CaissonsPiles, Piers and Caissons
Piles, Piers and CaissonsKalokwera Samuel
 
Plaques de sol fermacell - Des solutions, systèmes pour tous les types de sol
Plaques de sol fermacell - Des solutions, systèmes pour tous les types de solPlaques de sol fermacell - Des solutions, systèmes pour tous les types de sol
Plaques de sol fermacell - Des solutions, systèmes pour tous les types de solFermacell BV
 
National Building Code : Building Services
National Building Code : Building ServicesNational Building Code : Building Services
National Building Code : Building ServicesSunayana Miglani
 

What's hot (20)

Cubiertas
CubiertasCubiertas
Cubiertas
 
Sandwich panels
Sandwich panelsSandwich panels
Sandwich panels
 
Fire Proofing works
Fire Proofing works Fire Proofing works
Fire Proofing works
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentation
 
Planta de calzaduras e 01
Planta de calzaduras e 01Planta de calzaduras e 01
Planta de calzaduras e 01
 
Chapter 8 floorings
Chapter 8 flooringsChapter 8 floorings
Chapter 8 floorings
 
Heat & sound insulation
Heat & sound insulationHeat & sound insulation
Heat & sound insulation
 
Especificaciones tecnicas piso en ladrillo pdf
Especificaciones tecnicas piso en ladrillo pdfEspecificaciones tecnicas piso en ladrillo pdf
Especificaciones tecnicas piso en ladrillo pdf
 
MDF, Medium Density Fiberboard (Interior-use Engineered Wood Panel Product, M...
MDF, Medium Density Fiberboard (Interior-use Engineered Wood Panel Product, M...MDF, Medium Density Fiberboard (Interior-use Engineered Wood Panel Product, M...
MDF, Medium Density Fiberboard (Interior-use Engineered Wood Panel Product, M...
 
Scrap handling systems
Scrap handling systemsScrap handling systems
Scrap handling systems
 
Prefrabricated - puf panel
Prefrabricated - puf panelPrefrabricated - puf panel
Prefrabricated - puf panel
 
Prefabricated components
Prefabricated componentsPrefabricated components
Prefabricated components
 
Artificial Construction Materials- A beginners presentation
Artificial Construction Materials- A beginners presentationArtificial Construction Materials- A beginners presentation
Artificial Construction Materials- A beginners presentation
 
Floors by chakamba john
Floors  by chakamba johnFloors  by chakamba john
Floors by chakamba john
 
Artificial construction materials.pptxpsg
Artificial construction materials.pptxpsgArtificial construction materials.pptxpsg
Artificial construction materials.pptxpsg
 
prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated Structures
 
Piles, Piers and Caissons
Piles, Piers and CaissonsPiles, Piers and Caissons
Piles, Piers and Caissons
 
Plaques de sol fermacell - Des solutions, systèmes pour tous les types de sol
Plaques de sol fermacell - Des solutions, systèmes pour tous les types de solPlaques de sol fermacell - Des solutions, systèmes pour tous les types de sol
Plaques de sol fermacell - Des solutions, systèmes pour tous les types de sol
 
Light Gauge Steel
Light Gauge SteelLight Gauge Steel
Light Gauge Steel
 
National Building Code : Building Services
National Building Code : Building ServicesNational Building Code : Building Services
National Building Code : Building Services
 

Similar to Annex 1 technical specification-gates

Section 4 tower-volume-ii_6
Section 4 tower-volume-ii_6Section 4 tower-volume-ii_6
Section 4 tower-volume-ii_6BUDDHADEV KORA
 
Acsr moose conductor
Acsr moose conductorAcsr moose conductor
Acsr moose conductorDineshsenthil
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02Minh Bui Si
 
0400 Series - Safetydfsdfsdf Fencing & Parapets.doc
0400 Series - Safetydfsdfsdf Fencing & Parapets.doc0400 Series - Safetydfsdfsdf Fencing & Parapets.doc
0400 Series - Safetydfsdfsdf Fencing & Parapets.docmatrixpmp2
 
Aluminum work
Aluminum workAluminum work
Aluminum workRajiva Gupta
 
Sample Wall Shop Drawings
Sample Wall Shop DrawingsSample Wall Shop Drawings
Sample Wall Shop DrawingsGeoffrey Jennings
 
Yee s2&s2
Yee s2&s2Yee s2&s2
Yee s2&s2Jennifer Yee
 
Escalator replacement specifications rev 2 consolidated comments
Escalator replacement specifications   rev 2 consolidated commentsEscalator replacement specifications   rev 2 consolidated comments
Escalator replacement specifications rev 2 consolidated commentsgulilero
 
Methodology Of Fabrication_R4_19.08.16.pptx
Methodology Of Fabrication_R4_19.08.16.pptxMethodology Of Fabrication_R4_19.08.16.pptx
Methodology Of Fabrication_R4_19.08.16.pptxharmanpnrgroup
 
2014-05-12 255 138th Street NYCTA Structural Drawings
2014-05-12 255 138th Street NYCTA Structural Drawings2014-05-12 255 138th Street NYCTA Structural Drawings
2014-05-12 255 138th Street NYCTA Structural DrawingsTodd Mordoh
 
GADFORROB.pdf
GADFORROB.pdfGADFORROB.pdf
GADFORROB.pdfssuserbde39d
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilatorMinh Bui Si
 
Precast Concrete Specifications.doc
Precast Concrete Specifications.docPrecast Concrete Specifications.doc
Precast Concrete Specifications.docAbdallah437436
 
10 pile foundation_specification
10 pile foundation_specification10 pile foundation_specification
10 pile foundation_specificationAtul Duggal
 
NB1C ANCHOR FLANGE
NB1C ANCHOR FLANGE NB1C ANCHOR FLANGE
NB1C ANCHOR FLANGE SEO Consultant
 
SAR_SEPTEMBER_2014_LCP
SAR_SEPTEMBER_2014_LCPSAR_SEPTEMBER_2014_LCP
SAR_SEPTEMBER_2014_LCPLyndsay Cotton
 
Submarine Pipeline Ball Valves
Submarine Pipeline Ball ValvesSubmarine Pipeline Ball Valves
Submarine Pipeline Ball ValvesVinod Daftari
 

Similar to Annex 1 technical specification-gates (20)

Section 4 tower-volume-ii_6
Section 4 tower-volume-ii_6Section 4 tower-volume-ii_6
Section 4 tower-volume-ii_6
 
Acsr moose conductor
Acsr moose conductorAcsr moose conductor
Acsr moose conductor
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
 
0400 Series - Safetydfsdfsdf Fencing & Parapets.doc
0400 Series - Safetydfsdfsdf Fencing & Parapets.doc0400 Series - Safetydfsdfsdf Fencing & Parapets.doc
0400 Series - Safetydfsdfsdf Fencing & Parapets.doc
 
Aluminum work
Aluminum workAluminum work
Aluminum work
 
Sample Wall Shop Drawings
Sample Wall Shop DrawingsSample Wall Shop Drawings
Sample Wall Shop Drawings
 
Schedule 9
Schedule 9Schedule 9
Schedule 9
 
Yee s2&s2
Yee s2&s2Yee s2&s2
Yee s2&s2
 
Spec u kon fsi 2021
Spec u kon fsi 2021Spec u kon fsi 2021
Spec u kon fsi 2021
 
Escalator replacement specifications rev 2 consolidated comments
Escalator replacement specifications   rev 2 consolidated commentsEscalator replacement specifications   rev 2 consolidated comments
Escalator replacement specifications rev 2 consolidated comments
 
Methodology Of Fabrication_R4_19.08.16.pptx
Methodology Of Fabrication_R4_19.08.16.pptxMethodology Of Fabrication_R4_19.08.16.pptx
Methodology Of Fabrication_R4_19.08.16.pptx
 
2014-05-12 255 138th Street NYCTA Structural Drawings
2014-05-12 255 138th Street NYCTA Structural Drawings2014-05-12 255 138th Street NYCTA Structural Drawings
2014-05-12 255 138th Street NYCTA Structural Drawings
 
GADFORROB.pdf
GADFORROB.pdfGADFORROB.pdf
GADFORROB.pdf
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilator
 
Precast Concrete Specifications.doc
Precast Concrete Specifications.docPrecast Concrete Specifications.doc
Precast Concrete Specifications.doc
 
10 pile foundation_specification
10 pile foundation_specification10 pile foundation_specification
10 pile foundation_specification
 
NB1C ANCHOR FLANGE
NB1C ANCHOR FLANGE NB1C ANCHOR FLANGE
NB1C ANCHOR FLANGE
 
Presentation on Pot Bearings
Presentation on Pot BearingsPresentation on Pot Bearings
Presentation on Pot Bearings
 
SAR_SEPTEMBER_2014_LCP
SAR_SEPTEMBER_2014_LCPSAR_SEPTEMBER_2014_LCP
SAR_SEPTEMBER_2014_LCP
 
Submarine Pipeline Ball Valves
Submarine Pipeline Ball ValvesSubmarine Pipeline Ball Valves
Submarine Pipeline Ball Valves
 

Recently uploaded

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 

Recently uploaded (20)

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 

Annex 1 technical specification-gates

  • 1. Technical Specification METAL WORK, GATES AND WELDING 1. Gates and Gate Hardware 1.1 Design, Drawing and Data No drawings other than those included in the Bidding Documents shall be provided by the Employer. The Drawings provided show general details only. The Contractor shall therefore prepare the necessary detailed Design Drawings and data required for the fabrication and installation of the gates and other metal-works. Steel gates shall be designed/fabricated by a firm which has reasonable past experience. If the Contractor lacks sufficient experience in fabricating gates, a specialist firm shall be engaged. Any fabrication or procurement, prior to approval of the design, drawings and the relevant data, shall be at the Contractor’s own risk. The Employer’s Representative has the right to order the Contractor to make any change in the design, drawings and data so as to make the gates and metal-works conform to the requirement of the under mentioned specifications without additional cost to the Employer. However, approval from the Employer’s Representative on the Contractor’s design, drawings and data shall not relieve the Contractor of any part of the Contractor’s responsibility. Before proceeding with fabrication or procurement of gates and metal-works, the Contractor shall submit two (2) sets of the drawings and data showing specification of materials, assembly, lift capacity and detailed dimensions for approval for Employer’s Representative. The costs of preparing the design, drawings and data, and submitting such things to the Employer’s Representative shall be included in the unit rates in the Bill of Quantities for furnishing and installing the gates and other metal-works. 1.2 Design to Suit Climate The water control equipment to be supplied, shall be designed with due regard to the climatic conditions prevailing in the Project area, particular care being taken to accommodate expansion and contraction due to temperature changes. Water control equipment shall be suitable for operating in ambient air temperatures from 5° C to 45° C but parts exposed to the sun may reach higher temperatures.
  • 2. 1.3 Materials, Stresses and Workmanship The water control equipment shall be designed and constructed in accordance with the requirements of BS 153 except where inconsistent with the terms of the Specifications. The deflection of gates shall be restricted to 1/600 of their clear span. 1.4 Minimum Thickness An allowance of 2 mm shall be added to the thickness of gate skin plates over and above the calculated thickness required to meet the design stresses, but in no case shall the actual skin plate thickness be less than 8 mm, unless otherwise shown on the Drawings. Unless otherwise shown on the Drawings, plates (other than skin plates) rolled steel angles and tee sections used in the construction of gates shall have a minimum thickness of 10 mm and the webs of rolled steel beams and channel sections shall have a minimum thickness of 10 mm. Unless otherwise shown on the Drawings, metal-works which will be permanently or semi- permanently submerged, such as that used for embedded guides, frames, etc., shall have a minimum thickness of 10 mm, with the exception of rolled steel beam and channel sections which shall have a minimum thickness of 7.5 mm. 1.5 Gate Design Each gate shall be designed to withstand and operate against the seating head of water specified on the relevant Drawings with no water downstream and of being raised clear of the orifice soffit. Each gate shall consist of framing incorporating guide grooves, sealing faces and a spindle guide bracket supporting members specified on the Drawings, movable gate leaf with sealing faces and operating gear. 1.6 Framing and Gear Supporting Members The gate framing shall consist of steel guide grooves fabricated from a standard MS sections with sill, lintel and spindle guide bracket supporting members, where specified on the Drawing, and shall all be connected to the grooves by bolts at their ends. Gear supporting members shall be angle sections or other suitable sections connected to the grooves by bolts at their ends. The groove members shall extend upwards to support and guide the gate throughout its travel and shall be arranged for bolting on to the concrete headwall, or casting into gate slots, as shown on the Drawings.
  • 3. The framing shall be fitted with machined non-ferrous or stainless steel faces upon which the gate shall slide and seal. Arrangements shall be incorporated to permit the framing to be accurately aligned and levelled and finally held in position before being grouted to the concrete headwall, or gate slot filled with concrete. The gear supporting members shall be designed to resist the loads resulting from operating the gate. 1.7 Gate The gate shall consist of a steel skin plate supported by horizontal stiffening members connected to vertical side guiding and stiffening members contained within the grooves. Arrangements shall be provided for attaching the gate to the operating spindle by a non-ferrous hinge pin. Slide Gates - The gate shall be fitted with machined non-ferrous sliding faces and approved rubber seals, as detailed on the Drawings, to achieve an effective watertight seal. Roller Gates -The gate shall have cast iron self-lubricating rollers with ARMCO “Lubrite”, or similar, bushings. 1.8 Operating Gear The operating gear shall consist of a hand operated self-sustaining gear capable of operating the gate against the maximum water loading conditions specified, and capable of positively holding the gate in any position when the hand wheel or crank handle is released. The operating gear shall be capable of being operated by one man. The gear units shall consist of a bronze operating nut engaging with a mild steel operating screw attached to the gate. The lifting mechanisms shall be either Armco type HB 18 to 24 Armco type for gates requiring only a single lifting mechanism or Armco type CPE 2 or 4 for gates requiring tandem lifting mechanisms with one stem left threaded and one right threaded. Other proprietary lifting mechanisms of equivalent specification to the Armco units can be supplied with the prior approval of the Employer’s Representative. All gear sprockets and pinions shall be machine cut with ratio and strength adequate to withstand operating loads. 1.9 Bolted Joints The Contractor shall supply all the necessary bolts, nuts, washers etc, for fixing the metalwork, together with a suitable number of spare bolts, nuts and washers. Bolted joints subject to vibration shall be securely locked.
  • 4. All bolt holes shall be drilled and the outside edges slightly countersunk. Friction grip bolts, nuts and washers shall comply with BS 4604, Part 1. They shall be used on all bolted joints which are liable to vibrate and elsewhere to the approval of the Employer’s Representative. Gears shall be enclosed with casings to avoid dust and rain. To prevent unauthorised use, operating gear shall be provided with appropriate locking devices. The lift housing or hand wheel shall be provided with a cast-in direction arrow and the word “OPEN” to indicate the direction of operation, to open gates. 1.10 Field Connections Field connections shall, whenever possible, be bolted connections. Welded field connections will be permitted where it is considered by the Employer’s Representative impractical to form bolted connections, in which case the weld preparation shall be carried out in the manufacturer’s works before despatch and the prepared surfaces shall be fully protected for transport to, and storage on, the Site. The Contractor shall supply the electrodes for completing the connections on site. Connections to be welded at Site shall be made by the Contractor’s welders using their own welding plant. Lift mechanisms shall be provided with a cast iron stop nut to allow adjustable end-stop travel. 1.11 Standardization and Maintenance Wherever possible, corresponding parts shall be finished with sufficient accuracy to ensure that they are interchangeable, and where required by the Employer’s Representative interchangeability shall be proved by actually changing the various parts. The design shall be such that all parts of the installations are accessible for inspection and maintenance and for use where continuity of operation is a first consideration. Drainage holes shall be provided in members, which are likely to collect or retain water. 1.12 Advance Delivery of Anchor Members, etc. Anchor members, seating plates etc. for building into primary concrete work to facilitate alignment and fixing of embedded parts shall be supplied by the Contractor and delivered in advance of the remainder of the parts, in accordance with a programme arranged by the Contractor and agreed by the Employer’s Representative to fit the overall construction programme.
  • 5. 1.13 Preparation and Storage of Bolts Before they are despatched to the Site, the Contractor shall protect all bolts (other than rag-bolts, Lewis bolts and galvanised bolts) by heating them and dipping them while hot into boiled linseed oil, or shall provide such other protection as may be approved by the Employer’s Representative. The Contractor shall pack the bolts carefully so that the threads do not become damaged or dirty during delivery, storage and transport to Site. 5.1.14 Packing and Marking The Contractor shall pack, mark, and as necessary protect, all parts for delivery, unloading, storage and subsequent transport to Site in accordance with the relevant section of BS 1133. Attention shall be given to the protection of parts which are liable to deterioration in the climatic condition prevailing in the Project Area, and the form of packaging shall be such that no damage to the equipment shall result from normal handling or prolonged storage in the open. Small parts shall be boxed and suitably marked on the outside. Larger parts shall be protected as necessary and shall be suitably marked and listed. Lists of contents of crates, boxes and bunches shall be supplied and shall be handed over to the Employer’s Representative on delivery of each consignment. Attention shall be given to the method of marking sub-assemblies and other components to assist in identifying them at Site. The method of marking employed shall enable any particular component or sub-assembly to be easily identified from the Contractor’s Drawings and also from the shipping specification. Where practicable, components for each individual site shall be packed separately so that all items required for each site may be easily separated and transported to individual sites. 1.15 Erection at Place of Manufacture Each gate and operating gear shall be fully assembled at the place of manufacture for inspection by the Employer’s Representative and, if considered necessary, testing before despatch. The Contractor shall arrange for the manufacturer to give the Employer’s Representative, in writing, a minimum of fourteen (14) days’ notice prior to the date when the assemblies will be ready for inspection. No parts shall be despatched from the manufacturer’s works until they have been marked to ensure correct re-assembly at Site.
  • 6. 1.16 Inspection at Place of Manufacture Inspection of materials, workmanship, manufacture of the gates, and the trial assembly of components at the place of manufacture, in accordance with the preceding Sub-Clause of these Specifications, shall be carried out by the Employer’s Representative at his discretion and shall include the following: a. Checks on steel and other materials used to ensure compliance with accepted standards. Manufacturer's chemical analysis sheets and report sheets showing results of tests on any physical properties, which may be called for. b. Dimensional checks to ensure conformity with approved Drawings. c. Weld inspection and testing where required. d. Inspection of cleaning and painting of steelwork. e. Witnessing erection and testing at the manufacturer’s works. f. Inspection of method of packing components for despatch. 1.17 Erection of Metalwork The erection of the metalwork at the Site shall comply with BS 449, Part 5 and be in accordance with the recommendations of BS 5531. When lifting and fitting metalwork into position care shall be taken that the parts thereof are not strained, twisted, bent or damaged in any way whatsoever. Should any parts be strained, twisted, bent or damaged they shall be rectified in such manner as the Employer’s Representative may approve. Any parts that are, in the opinion of the Supervisor, too badly damaged for rectification in the manner aforesaid shall be replaced by new material. All rectification and/or replacement shall be carried out at the Contractor’s own cost. The stacking of metalwork, or the individual parts thereof, that are stored in positions as may, in the opinion of the Employer’s Representative, cause damage to any of the members or parts thereof or to any portion of the Works, shall not be permitted. Proper and suitable slings, blocks, tackles, shear legs, derricks, cranes and other types of lifting appliances and equipment shall be provided, whenever needed for the erection of the metalwork. Every care and precaution shall be taken to ensure the safety of all persons engaged in such work and to prevent damage to any metalwork in the process of being erected or already erected or to any part of the Works from the results of any mishap, failure, breakdown or other accident to any of the aforesaid lifting appliances and equipment. The lifting of metalwork in bundles or in such quantities or in any manner which, in the opinion of the Supervisor, is liable to cause damage or strain or is in any way considered to be insecure or unsafe shall not be permitted.
  • 7. The use of high strength friction grip bolts and nuts in the erection of metalwork shall be generally in accordance with the provisions of BS 4604: Part 1, except that the method of tightening load indicating bolts or bolts incorporating load indicators shall be in conformity with the manufacturer’s instructions. 1.18 Testing after Erection After erection, the Contractor shall check that the gates and gate hardware are complete and in working order, and satisfactorily fulfils the purpose for which it is intended. The Contractor shall test all gates to the satisfaction of the Employer’s Representative. Each gate shall be made to move through a full cycle of operation using the equipment specified for the purpose, unless otherwise instructed, and each gate when closed shall affect a watertight seal to the approval of the Employer’s Representative. 1.19. Painting of Gates 1.19.1 Supply of Paint and Painting at Site The Contractor shall prepare the surfaces and apply the finishing coats of paints during erection at Site. The Contractor shall supply and deliver to the Site a sufficient quantity of priming paint to make good any damage during delivery, handling and erection. The Contractor shall also supply and deliver to the Site sufficient paint for two finishing. The supply and delivery of the paint shall be in accordance with programmes which the Contractor shall have previously agreed with the Employer’s Representative and having proper regard to the shelf life of the paints, and all to the approval of the Employer’s Representative. The paint shall be delivered in the paint manufacturer’s drums with seals unbroken. Each drum shall be clearly and indelibly marked with a description of its contents, its date of manufacture, and the date before which it should be used. Each drum shall have a different serial number. The Contractor shall keep a record of the delivery dates of each drum and its use-by date. Copies of the records should be available if requested by the Employer’s Representative or the Contracting Authority. 1.19.2 Paint Unless otherwise specified all coating and painting of metalwork shall be executed in accordance with the principles and practices recommended by BS 5493. Testing of paints shall be in accordance with BS 3900. Linseed oil for coating steel pins, bolts, nuts, etc. shall be boiled oil as specified in BS 257.
  • 8. Black paint, tar based, shall comply with BS 1070, Type A. Lead-based priming paint shall comply with BS 2523, Type B. Zinc-rich paint shall comply with BS 4652. Aluminium paint for use on metalwork shall conform to the following requirements: - The pigment shall consist entirely of leafing aluminium powder and shall be Type 1 as specified in BS 388. - The proportion of pigment to medium shall not be less than 20% by weight. - The medium for priming paint shall be either a mixture of quick-drying phenolic resin or tungoil and linseed oil, or alkyd resins. The medium for finishing paint shall be acrylic resin. The following schedule sets out the components of the schemes for protection of the water control part: Surface preparations: Blast cleaning as specified Priming Paint Underwater parts: 2 coats of zinc epoxy paint. Total dry film thickness 50 microns. Above water parts: 2 coats of zinc phosphate priming paint to suit the finishing paint. Total dry film thickness 70 microns. Finishing Paint Underwater parts: 2 coats of coal tar/epoxy. Total dry film thickness 250 microns. Above water parts: 1 undercoat and 1 finishing coat of high build M10 chlorinated rubber paint in silver grey. Total dry film thickness 200 microns. All the paints shall be obtained from the same manufacturer and shall be compatible with the other paints in the same protective scheme. They shall be suitable for the climatic conditions in the Contracting Authority’s country. The manufacturer and the formulation of the paints shall be subject to the approval of the Supervisor. The Contractor shall supply to the Employer’s Representative samples of the paints at least thirty days before their being used on the Works. The primer used beneath the coal tar/epoxy paint shall be specially formulated for the purpose. In selecting or formulating the zinc rich priming paint, the Contractor shall give due regard to the period of storage and to the requirement that it shall give protection outdoors for periods of possibly up to six (6) months. The coal tar/epoxy paint shall be such that the coating will not run or craze when exposed to direct sunlight on the Site for prolonged periods after immersion in water.
  • 9. 1.19.3 Painting during Erection During the erection of the gates, the Contractor shall observe the following with regard to painting: ď‚· Contact surfaces that will be completely sealed in welded construction shall not be painted. ď‚· Surfaces which will be in continuous contact with concrete after completion of erection shall not be painted. ď‚· Contact surfaces of sub-assemblies and other members which are put together at Site, and which will be in permanent contact with each other or concealed after erection shall each be cleaned and painted with one coat priming paint before assembly and then assembled while the paint is still wet. 1.19.4 Measurement and Payment of Gates Measurement for payment shall be made in the unit rate as indicated in Bill of Quantities. The rate that the Contractor quotes will incorporate the cost of guide frame, hoisting mechanism, installation, painting, and all other accessories. The unit rate shall cover the cost of preparing the design data, cost of all materials, fabrication, manufacturing, painting, loading and unloading labour, furnishing and installing the slide gate including frame, hoist, operation handwheel and all other accessories, cost of operation test.