SlideShare a Scribd company logo
1 of 31
WHAT IS QUALITY RISK MANGEMENT
Quality - Fulfillment of requirements
Risk– Probability of failure to fulfill the requirements and its severity
Management- Systematic process to review and manage the risk to quality
QRM PROCESS - ICH Q9
QRM PROCESS - ICH Q9
Risk identification is a systematic use of information to identify potential failure.
Risk analysis is the estimation of the risk associated with the identified potential failure.
Risk evaluation compares the identified and analyzed risk against given risk criteria
QRM PROCESS - ICH Q9
Risk reduction
Actions to mitigate the severity & probability of potential failure and/or to improve
detectability of failures.
Risk acceptance
Acceptance of residual risks
QRM PROCESS - ICH Q9
Risk Communication
Sharing of information about risk and risk management between the decision makers
and others.
The output/result of the quality risk management process should be appropriately
communicated and documented.
QRM PROCESS - ICH Q9
Risk Review
Sharing of information about risk and risk management between the decision makers
and others.
The frequency of any review should be based upon the level of risk. Risk review might
include reconsideration of risk acceptance decisions
RISK ASSESSMENT METHODS
FAILURE MODE EFFECTIVE ANALYSIS
(FMEA)
To identify potential failures before they occur and eliminate / minimize risk of failure
FAILURE MODE EFFECTIVE ANALYSIS (FMEA)
Every thing that can fail, will fail – Murphy's Law
The main reason behind FMEA
It will usually fails at worst possible moment
FMEA identifies ‘can fail’ situations and eliminate or minimize from ‘will fail’ situation
FAILURE MODE EFFECTIVE ANALYSIS (FMEA)
Review past Analyze present Control future
For frequency of occurrences For detection levels by reducing its impact
What will FMEA do
1 2 3
Probability Detectability Severity
IS CALLED RISK PRIORITY NUMBER (RPN)
RISK PRIORITY NMBER = (PXSXD)
• The likelihood that failure will
occur
Probability
(P)
• The potential effect of failure
Severity
(S)
• Likelihood that failure will be
detected immediately after
occurrence
Detectability
(D)
RPN is
to Prioritize actions
on Identified risks
FAILURE MODE EFFECTIVE ANALYSIS (FMEA)
Likelihood / Probability (P)
Severity (S)
Detectability (D)
RPN = P X S X D
To reduce RPN to acceptance level
RPN = P X S X D
FMEA APPROACH
Item or
Function
Potential
failure
mode
Potential
causes of
failure
Probability Potential
effect of
failure
Severity Current
Controls
Detectability RPN
Recommended
actions
Probability Severity Detectability RPN With in
acceptance
(Yes / No)
FMEA APPROACH
Item or
Functio
n
Potential
failure
mode
Potential
causes of
failure
Probability Potential
effect of
failure
Severity Current
Controls
Detectability RPN Recommended
actions
Probability Severity Detectability RPN With in
acceptance
(Yes / No)
ITEM /
FUNCTION
• Identifies individual function of the process.
• Top down approach Bottom Up approach
Up to what extent?, the extent it takes
FMEA APPROACH
Item or
Functio
n
Potential
failure
mode
Potential
causes of
failure
Probability Potential
effect of
failure
Severity Current
Controls
Detectability RPN Recommended
actions
Probability Severity Detectability RPN With in
acceptance
(Yes / No)
Potential
failures
• Identify the potential failure modes on each step or function
i.e To identify something that can fail.
• There can be several failures for single function – List all
Function
Potential Failure 1
?
Potential Failure 2
?
Potential Failure 3
?
FMEA APPROACH
Item or
Functio
n
Potential
failure
mode
Potential
causes of
failure
Probability Potential
effect of
failure
Severity Current
Controls
Detectability RPN Recommended
actions
Probability Severity Detectability RPN With in
acceptance
(Yes / No)
Potential
causes of
failures
• Identify the cause of each potential failure modes
i.e To identify something that can fail.
• There can be several causes for a single failure – List all
Function
Potential Failure 1 Cause ?
Potential Failure 2 Cause ?
Potential Failure 3 Cause ?
FMEA APPROACH
Item or
Functio
n
Potential
failure
mode
Potential
causes of
failure
Probability Potential
effect of
failure
Severity Current
Controls
Detectability RPN Recommended
actions
Probability Severity Detectability RPN With in
acceptance
(Yes / No)
Probability
Probability is the likelihood that failure will occur
Gather all related data
Review the old failures and their frequency
Come to a judgment on probability (or) likely hood
Potential Probability Rank
Certain 4
High degree 3
Occasionally 2
Unlikely 1
FMEA APPROACH
Item or
Functio
n
Potential
failure
mode
Potential
causes of
failure
Probability Potential
effect of
failure
Severity Current
Controls
Detectability RPN Recommended
actions
Probability Severity Detectability RPN With in
acceptance
(Yes / No)
Probability
It is very good if we have quantified data as follows
Potential Probability Rank
Certain 4
High degree 3
Occasionally 2
Unlikely 1
Unlikely – 1failure in 1000 cases
Occasionally – 5 failures out of 1000 cases
High Degree – 20 failures out of 1000
cases
Certain - 100 failures out of 1000
cases
A
S
A
N
E
X
A
M
P
L
E
D
E
F
I
N
E
Y
O
U
R
L
I
M
I
T
S
FMEA APPROACH
Item or
Functio
n
Potential
failure
mode
Potential
causes of
failure
Probability Potential
effect of
failure
Severity Current
Controls
Detectability RPN Recommended
actions
Probability Severity Detectability RPN With in
acceptance
(Yes / No)
Potential
effects of
failures
Identify what happens if this failure occurs.
There can be several effects – List them all
Activity – Working at height ,
Potential Failure – Fall down
Potential Impacts – Death of personnel
Injury of personnel
Death or Injury of personnel under him
Malfunction equipment under Him
Malfunction of PPE wear by personnel
FMEA APPROACH
Item or
Functio
n
Potential
failure
mode
Potential
causes of
failure
Probability Potential
effect of
failure
Severity Current
Controls
Detectability RPN Recommended
actions
Probability Severity Detectability RPN With in
acceptance
(Yes / No)
Severity
Severity is the rating of potential effect of failure
RANK
Potential Consequences
Patient /
Customer
Compliance Business
15
Death Import Alert 100% business
Loss
10
Permanent
Injury
Warning Letters 50% business Loss
5
Hospital stay
with full
recovery
Audit
Observations
25% business Loss
1
No health No impact No impact
List out potential impacts of failures w.r.t
Patient safety
GMP Compliance
Business loss
And judge the severity of the impact.
FMEA APPROACH
Item or
Functio
n
Potential
failure
mode
Potential
causes of
failure
Probability Potential
effect of
failure
Severity Current
Controls
Detectability RPN Recommended
actions
Probability Severity Detectability RPN With in
acceptance
(Yes / No)
Current
Controls
Identify current controls that are in place
Design controls
Process controls
Personnel controls
Detection controls
FMEA APPROACH
Item or
Functio
n
Potential
failure
mode
Potential
causes of
failure
Probability Potential
effect of
failure
Severity Current
Controls
Detectability RPN Recommended
actions
Probability Severity Detectability RPN With in
acceptance
(Yes / No)
Detectability
Likelihood that failure will be detected immediately after occurrence
Likelihood of detection Rank
Not detectable 4
Detectable between 1% - 50% time 3
Detectable between 50% - 99% time 2
Detectable more than 99% time 1
FMEA APPROACH
Item or
Functio
n
Potential
failure
mode
Potential
causes of
failure
Probability Potential
effect of
failure
Severity Current
Controls
Detectability RPN Recommended
actions
Probability Severity Detectability RPN With in
acceptance
(Yes / No)
RPN
RPN is Risk Priority Number = SEVERITY X DETECTABILITY X PROBABILITY
RPN is to categories risk and overall priority.
Severity
Rank
Detection
Rank
Probability
Rank
15 4 4
10 3 3
5 2 2
1 1 1
Zone RPN Score Action
High (Red) Above 60
High Risk. Action needed
Immediately.
Medium
(Yellow)
31 to 60
Low Risk. Some action
needed
Low (Green) Less than 30
Risk Acceptable. No action
needed
FMEA APPROACH
Recommended actions Probability Severity Detectability RPN With in
acceptance
(Yes / No)
Based on your RPN score,
Propose some actions to reduce the risk score.
After completion of actions
Redefine Risk score of Severity , detectability & Probability
and take actions accordingly
Identify
potential
failures & its
impact
Risk Rating
P X S X D
Risk
Reduction
Risk
Acceptance
Risk Rating
P X S X D
Priorities
Actions based
on RPN
FMEA PROCESS – CASE STUDY FOR UNDERSTANDING
REQUIREMENT: All staff should reach to office by 8.00 am in the morning.
Bus
Driver
Employees
Start point
End point
Route
No.of stops
Employee
reach office on
time.
Identify the potential
failures
Map the process
HOW TO DO PROCESS MAPPING
Vehicle driver pick up employee daily in the morning from each stop and reach office at 8.00 a.m.
daily
General shift vehicle driver collects vehicle key from security person and ensures petrol in the
vehicle and pick up employs daily in the morning from each stop and reach office at 8.00 a.m. daily
General shift vehicle driver collects vehicle key from security person and ensures petrol in the
vehicle and moves towards jebel ali road and pick up employees daily in the morning from each stop
of discovery garden & garden and reach office at 8.00 a.m. daily
Is above comes under process mapping
Map the process
General shift security person will report office at 6.00 am and keep all vehicle keys with him.
Every day morning at 6.50 am vehicle driver comes to security and collect vehicle key and ensure enough
petrol in the in the vehicle.
Driver starts from office at 7.00 to pick up employees and security records the time.
Vehicle moves through jebel ali road to IBN metro road and on to discovery garden of first pickup point.
Where there are 5 signal crossings and two school that can create delays due to traffic.
Vehicle starts picking up employees stop by stop and move towards DPS school road and to LF office.
Where there are one signal crossing and one school that can create delays due to traffic.
After picking up all employee vehicle moves on to jebel ali road and crosses JAFJA security check and reach
office at 8.00 a.m
1
2
3
4
5
6
Up to what extent?, the extent it takes
T
O
P
D
O
W
N
B
O
T
T
O
M
U
P
HOW TO DO PROCESS MAPPING
Map the process & Brainstorm on potential failures
IDENTIFICATION OF POTENTIAL FAILURES
Up to what extent?, the extent it takes
Process step Potential failure
General shift security person will report office at
6.00 am and keep all vehicle keys with him.
General shift security person not reported at office?
Reported but keys not available him.
Every day morning at 6.50 am vehicle driver comes
to security and collect vehicle key and ensure
enough petrol in the in the vehicle.
Driver not came? Or Driver came late?
Drive came on time but petrol not enough in the
vehicle?
Driver starts from office at 7.00 to pick up
employees and security records the time
Driver not started on time due to vehicle problem
Vehicle moves through jebel ali road to IBN metro
road and on to discovery garden of first pickup
point. Where there are 5 signal crossings and two
school that can create delays due to traffic.
Driver don’t know the root.
Traffic at signal crossings or at school area?
Vehicle met accident
Vehicle starts picking up employees stop by stop
and move towards DPS school road and to LF
office. Where there are one signal crossing and one
school that can create delays due to traffic.
Employee not available at stop.
Delayed due to employee called and told to wait
Traffic delays.
Map the process & Brainstorm on potential failures
IDENTIFICATION OF POTENTIAL FAILURES
Potential failure Controls & Actions
General shift security person not reported at
office?
Reported but keys not available him.
Measure current controls
Plan controls if require
Driver not came? Or Driver came late?
Drive came on time but petrol not enough in
the vehicle?
Measure current controls
Plan controls if require
Driver not started on time due to vehicle
problem
Measure current controls
Plan controls if require
Driver don’t know the root.
Traffic at signal crossings or at school area?
Vehicle met accident
Measure current controls
Plan controls if require
Employee not available at stop.
Delayed due to employee called and told to
wait
Traffic delays.
Measure current controls
Plan controls if require
KIRANREDDY MUNNANGI
www.analyticalstudents.blogspot.in

More Related Content

What's hot

STERILE PROCESS OF VALIDATION
STERILE PROCESS OF VALIDATIONSTERILE PROCESS OF VALIDATION
STERILE PROCESS OF VALIDATIONSagar Savale
 
Quality Risk Managemment ICH Q9
Quality Risk Managemment ICH Q9Quality Risk Managemment ICH Q9
Quality Risk Managemment ICH Q9Kiransingh0610
 
Air circulation maintenance industry for sterile and non sterile area
Air circulation maintenance  industry for sterile and non sterile areaAir circulation maintenance  industry for sterile and non sterile area
Air circulation maintenance industry for sterile and non sterile areaGNIPST
 
Nonsterile Manufacturing process Technology
Nonsterile Manufacturing process TechnologyNonsterile Manufacturing process Technology
Nonsterile Manufacturing process TechnologyDnyaneshwarKhodse
 
PROBLEMS ENCOUNTERED COATING TECHNOLOGY
PROBLEMS ENCOUNTERED COATING TECHNOLOGYPROBLEMS ENCOUNTERED COATING TECHNOLOGY
PROBLEMS ENCOUNTERED COATING TECHNOLOGYPRATIKKUMARMORE
 
Quality control of packaging Material and filling Equipment
Quality control of packaging Material and filling EquipmentQuality control of packaging Material and filling Equipment
Quality control of packaging Material and filling EquipmentShankar Maind Patil
 
ICH Guideline Q9 - Quality Risk Management
ICH Guideline Q9 - Quality Risk ManagementICH Guideline Q9 - Quality Risk Management
ICH Guideline Q9 - Quality Risk Managementmuna_ali
 
Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...Malla Reddy College of Pharmacy
 
Vendor Audit
Vendor Audit Vendor Audit
Vendor Audit PRAVADA
 
Sterile area
Sterile areaSterile area
Sterile areavijjya22
 
Pat process analytical technique
Pat  process analytical techniquePat  process analytical technique
Pat process analytical techniqueSalmanLatif14
 
Design of aseptic area plant layout
Design of aseptic area plant layoutDesign of aseptic area plant layout
Design of aseptic area plant layoutArchana Chavhan
 
Contamination Control in Cleanrooms_Dr.A. Amsavel
Contamination Control in Cleanrooms_Dr.A. AmsavelContamination Control in Cleanrooms_Dr.A. Amsavel
Contamination Control in Cleanrooms_Dr.A. AmsavelDr. Amsavel A
 
Process analytical technology
Process analytical technologyProcess analytical technology
Process analytical technologyanjalibharat19
 

What's hot (20)

STERILE PROCESS OF VALIDATION
STERILE PROCESS OF VALIDATIONSTERILE PROCESS OF VALIDATION
STERILE PROCESS OF VALIDATION
 
Quality Risk Managemment ICH Q9
Quality Risk Managemment ICH Q9Quality Risk Managemment ICH Q9
Quality Risk Managemment ICH Q9
 
Air circulation maintenance industry for sterile and non sterile area
Air circulation maintenance  industry for sterile and non sterile areaAir circulation maintenance  industry for sterile and non sterile area
Air circulation maintenance industry for sterile and non sterile area
 
Air based hazards
Air based hazardsAir based hazards
Air based hazards
 
Nonsterile Manufacturing process Technology
Nonsterile Manufacturing process TechnologyNonsterile Manufacturing process Technology
Nonsterile Manufacturing process Technology
 
PROBLEMS ENCOUNTERED COATING TECHNOLOGY
PROBLEMS ENCOUNTERED COATING TECHNOLOGYPROBLEMS ENCOUNTERED COATING TECHNOLOGY
PROBLEMS ENCOUNTERED COATING TECHNOLOGY
 
Quality control of packaging Material and filling Equipment
Quality control of packaging Material and filling EquipmentQuality control of packaging Material and filling Equipment
Quality control of packaging Material and filling Equipment
 
ICH Guideline Q9 - Quality Risk Management
ICH Guideline Q9 - Quality Risk ManagementICH Guideline Q9 - Quality Risk Management
ICH Guideline Q9 - Quality Risk Management
 
Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...
 
Vendor Audit
Vendor Audit Vendor Audit
Vendor Audit
 
Pilot plant design
Pilot plant designPilot plant design
Pilot plant design
 
Cross contamination
Cross contaminationCross contamination
Cross contamination
 
Asepting procesing
Asepting procesingAsepting procesing
Asepting procesing
 
Sterile area
Sterile areaSterile area
Sterile area
 
Pat process analytical technique
Pat  process analytical techniquePat  process analytical technique
Pat process analytical technique
 
Clean room standards
Clean room standardsClean room standards
Clean room standards
 
Design of aseptic area plant layout
Design of aseptic area plant layoutDesign of aseptic area plant layout
Design of aseptic area plant layout
 
Contamination Control in Cleanrooms_Dr.A. Amsavel
Contamination Control in Cleanrooms_Dr.A. AmsavelContamination Control in Cleanrooms_Dr.A. Amsavel
Contamination Control in Cleanrooms_Dr.A. Amsavel
 
Process analytical technology
Process analytical technologyProcess analytical technology
Process analytical technology
 
Q7 good-manufacturing-practice-guidance-for-active-pharmaceutical-ingredients...
Q7 good-manufacturing-practice-guidance-for-active-pharmaceutical-ingredients...Q7 good-manufacturing-practice-guidance-for-active-pharmaceutical-ingredients...
Q7 good-manufacturing-practice-guidance-for-active-pharmaceutical-ingredients...
 

Similar to Quality Risk Management - FMEA

Similar to Quality Risk Management - FMEA (20)

Failure mode and effect analysis
Failure mode and effect analysisFailure mode and effect analysis
Failure mode and effect analysis
 
FMEA
FMEAFMEA
FMEA
 
FMEA Analysis Cycle
FMEA Analysis CycleFMEA Analysis Cycle
FMEA Analysis Cycle
 
Fmea v1
Fmea v1Fmea v1
Fmea v1
 
11. faliure mode & effect analysis
11. faliure mode & effect analysis11. faliure mode & effect analysis
11. faliure mode & effect analysis
 
FMEA - Failure mode and effects analysis
FMEA - Failure mode and effects analysisFMEA - Failure mode and effects analysis
FMEA - Failure mode and effects analysis
 
Presentation on QRM
Presentation on QRMPresentation on QRM
Presentation on QRM
 
PFMEA-Training.pptx
PFMEA-Training.pptxPFMEA-Training.pptx
PFMEA-Training.pptx
 
FMEA.pptx
FMEA.pptxFMEA.pptx
FMEA.pptx
 
Manper07 fmea
Manper07 fmeaManper07 fmea
Manper07 fmea
 
Process fmea breakfast
Process fmea  breakfastProcess fmea  breakfast
Process fmea breakfast
 
FMICA ppt
FMICA pptFMICA ppt
FMICA ppt
 
FMEA.pptx
FMEA.pptxFMEA.pptx
FMEA.pptx
 
Quality risk management
Quality risk managementQuality risk management
Quality risk management
 
Mootaz+el halawany+view+to+risk+management
Mootaz+el halawany+view+to+risk+managementMootaz+el halawany+view+to+risk+management
Mootaz+el halawany+view+to+risk+management
 
Failure Mode and Effects Analysis WithAdrian™ FMEA 2013 Adrian Beale
Failure Mode and Effects Analysis WithAdrian™ FMEA 2013 Adrian BealeFailure Mode and Effects Analysis WithAdrian™ FMEA 2013 Adrian Beale
Failure Mode and Effects Analysis WithAdrian™ FMEA 2013 Adrian Beale
 
FMEA.ppt
FMEA.pptFMEA.ppt
FMEA.ppt
 
FAILURE MODE EFFECTS ANALYSIS vs FAULT TREE ANALYSIS
FAILURE MODE EFFECTS ANALYSIS vs FAULT TREE ANALYSISFAILURE MODE EFFECTS ANALYSIS vs FAULT TREE ANALYSIS
FAILURE MODE EFFECTS ANALYSIS vs FAULT TREE ANALYSIS
 
Fmea Final
Fmea FinalFmea Final
Fmea Final
 
Design fmea
Design fmeaDesign fmea
Design fmea
 

More from kiranreddy munnangi

More from kiranreddy munnangi (6)

Good Documentation Practices
Good Documentation PracticesGood Documentation Practices
Good Documentation Practices
 
Corrective & Preventive Action
Corrective & Preventive ActionCorrective & Preventive Action
Corrective & Preventive Action
 
Lessons from geese
Lessons from geeseLessons from geese
Lessons from geese
 
Chromatographic Column chemistry
Chromatographic Column chemistryChromatographic Column chemistry
Chromatographic Column chemistry
 
Chromarogaphy system suitability ppt
Chromarogaphy system suitability pptChromarogaphy system suitability ppt
Chromarogaphy system suitability ppt
 
Stability Study
Stability StudyStability Study
Stability Study
 

Recently uploaded

Call Girls ITPL Just Call 7001305949 Top Class Call Girl Service Available
Call Girls ITPL Just Call 7001305949 Top Class Call Girl Service AvailableCall Girls ITPL Just Call 7001305949 Top Class Call Girl Service Available
Call Girls ITPL Just Call 7001305949 Top Class Call Girl Service Availablenarwatsonia7
 
Call Girls Jayanagar Just Call 7001305949 Top Class Call Girl Service Available
Call Girls Jayanagar Just Call 7001305949 Top Class Call Girl Service AvailableCall Girls Jayanagar Just Call 7001305949 Top Class Call Girl Service Available
Call Girls Jayanagar Just Call 7001305949 Top Class Call Girl Service Availablenarwatsonia7
 
Call Girl Service Bidadi - For 7001305949 Cheap & Best with original Photos
Call Girl Service Bidadi - For 7001305949 Cheap & Best with original PhotosCall Girl Service Bidadi - For 7001305949 Cheap & Best with original Photos
Call Girl Service Bidadi - For 7001305949 Cheap & Best with original Photosnarwatsonia7
 
Call Girls Hosur Just Call 7001305949 Top Class Call Girl Service Available
Call Girls Hosur Just Call 7001305949 Top Class Call Girl Service AvailableCall Girls Hosur Just Call 7001305949 Top Class Call Girl Service Available
Call Girls Hosur Just Call 7001305949 Top Class Call Girl Service Availablenarwatsonia7
 
Call Girls Jp Nagar Just Call 7001305949 Top Class Call Girl Service Available
Call Girls Jp Nagar Just Call 7001305949 Top Class Call Girl Service AvailableCall Girls Jp Nagar Just Call 7001305949 Top Class Call Girl Service Available
Call Girls Jp Nagar Just Call 7001305949 Top Class Call Girl Service Availablenarwatsonia7
 
Call Girl Lucknow Mallika 7001305949 Independent Escort Service Lucknow
Call Girl Lucknow Mallika 7001305949 Independent Escort Service LucknowCall Girl Lucknow Mallika 7001305949 Independent Escort Service Lucknow
Call Girl Lucknow Mallika 7001305949 Independent Escort Service Lucknownarwatsonia7
 
Call Girls Service Nandiambakkam | 7001305949 At Low Cost Cash Payment Booking
Call Girls Service Nandiambakkam | 7001305949 At Low Cost Cash Payment BookingCall Girls Service Nandiambakkam | 7001305949 At Low Cost Cash Payment Booking
Call Girls Service Nandiambakkam | 7001305949 At Low Cost Cash Payment BookingNehru place Escorts
 
VIP Call Girls Pune Vrinda 9907093804 Short 1500 Night 6000 Best call girls S...
VIP Call Girls Pune Vrinda 9907093804 Short 1500 Night 6000 Best call girls S...VIP Call Girls Pune Vrinda 9907093804 Short 1500 Night 6000 Best call girls S...
VIP Call Girls Pune Vrinda 9907093804 Short 1500 Night 6000 Best call girls S...Miss joya
 
Artifacts in Nuclear Medicine with Identifying and resolving artifacts.
Artifacts in Nuclear Medicine with Identifying and resolving artifacts.Artifacts in Nuclear Medicine with Identifying and resolving artifacts.
Artifacts in Nuclear Medicine with Identifying and resolving artifacts.MiadAlsulami
 
Bangalore Call Girls Marathahalli 📞 9907093804 High Profile Service 100% Safe
Bangalore Call Girls Marathahalli 📞 9907093804 High Profile Service 100% SafeBangalore Call Girls Marathahalli 📞 9907093804 High Profile Service 100% Safe
Bangalore Call Girls Marathahalli 📞 9907093804 High Profile Service 100% Safenarwatsonia7
 
Call Girl Surat Madhuri 7001305949 Independent Escort Service Surat
Call Girl Surat Madhuri 7001305949 Independent Escort Service SuratCall Girl Surat Madhuri 7001305949 Independent Escort Service Surat
Call Girl Surat Madhuri 7001305949 Independent Escort Service Suratnarwatsonia7
 
Call Girls Electronic City Just Call 7001305949 Top Class Call Girl Service A...
Call Girls Electronic City Just Call 7001305949 Top Class Call Girl Service A...Call Girls Electronic City Just Call 7001305949 Top Class Call Girl Service A...
Call Girls Electronic City Just Call 7001305949 Top Class Call Girl Service A...narwatsonia7
 
Call Girls Service in Bommanahalli - 7001305949 with real photos and phone nu...
Call Girls Service in Bommanahalli - 7001305949 with real photos and phone nu...Call Girls Service in Bommanahalli - 7001305949 with real photos and phone nu...
Call Girls Service in Bommanahalli - 7001305949 with real photos and phone nu...narwatsonia7
 
Book Call Girls in Kasavanahalli - 7001305949 with real photos and phone numbers
Book Call Girls in Kasavanahalli - 7001305949 with real photos and phone numbersBook Call Girls in Kasavanahalli - 7001305949 with real photos and phone numbers
Book Call Girls in Kasavanahalli - 7001305949 with real photos and phone numbersnarwatsonia7
 
Call Girls Budhwar Peth 7001305949 All Area Service COD available Any Time
Call Girls Budhwar Peth 7001305949 All Area Service COD available Any TimeCall Girls Budhwar Peth 7001305949 All Area Service COD available Any Time
Call Girls Budhwar Peth 7001305949 All Area Service COD available Any Timevijaych2041
 
Aspirin presentation slides by Dr. Rewas Ali
Aspirin presentation slides by Dr. Rewas AliAspirin presentation slides by Dr. Rewas Ali
Aspirin presentation slides by Dr. Rewas AliRewAs ALI
 
Call Girls Service In Shyam Nagar Whatsapp 8445551418 Independent Escort Service
Call Girls Service In Shyam Nagar Whatsapp 8445551418 Independent Escort ServiceCall Girls Service In Shyam Nagar Whatsapp 8445551418 Independent Escort Service
Call Girls Service In Shyam Nagar Whatsapp 8445551418 Independent Escort Serviceparulsinha
 
Russian Call Girls Chickpet - 7001305949 Booking and charges genuine rate for...
Russian Call Girls Chickpet - 7001305949 Booking and charges genuine rate for...Russian Call Girls Chickpet - 7001305949 Booking and charges genuine rate for...
Russian Call Girls Chickpet - 7001305949 Booking and charges genuine rate for...narwatsonia7
 
Call Girls Whitefield Just Call 7001305949 Top Class Call Girl Service Available
Call Girls Whitefield Just Call 7001305949 Top Class Call Girl Service AvailableCall Girls Whitefield Just Call 7001305949 Top Class Call Girl Service Available
Call Girls Whitefield Just Call 7001305949 Top Class Call Girl Service Availablenarwatsonia7
 

Recently uploaded (20)

Call Girls ITPL Just Call 7001305949 Top Class Call Girl Service Available
Call Girls ITPL Just Call 7001305949 Top Class Call Girl Service AvailableCall Girls ITPL Just Call 7001305949 Top Class Call Girl Service Available
Call Girls ITPL Just Call 7001305949 Top Class Call Girl Service Available
 
Call Girls Jayanagar Just Call 7001305949 Top Class Call Girl Service Available
Call Girls Jayanagar Just Call 7001305949 Top Class Call Girl Service AvailableCall Girls Jayanagar Just Call 7001305949 Top Class Call Girl Service Available
Call Girls Jayanagar Just Call 7001305949 Top Class Call Girl Service Available
 
Call Girl Service Bidadi - For 7001305949 Cheap & Best with original Photos
Call Girl Service Bidadi - For 7001305949 Cheap & Best with original PhotosCall Girl Service Bidadi - For 7001305949 Cheap & Best with original Photos
Call Girl Service Bidadi - For 7001305949 Cheap & Best with original Photos
 
sauth delhi call girls in Bhajanpura 🔝 9953056974 🔝 escort Service
sauth delhi call girls in Bhajanpura 🔝 9953056974 🔝 escort Servicesauth delhi call girls in Bhajanpura 🔝 9953056974 🔝 escort Service
sauth delhi call girls in Bhajanpura 🔝 9953056974 🔝 escort Service
 
Call Girls Hosur Just Call 7001305949 Top Class Call Girl Service Available
Call Girls Hosur Just Call 7001305949 Top Class Call Girl Service AvailableCall Girls Hosur Just Call 7001305949 Top Class Call Girl Service Available
Call Girls Hosur Just Call 7001305949 Top Class Call Girl Service Available
 
Call Girls Jp Nagar Just Call 7001305949 Top Class Call Girl Service Available
Call Girls Jp Nagar Just Call 7001305949 Top Class Call Girl Service AvailableCall Girls Jp Nagar Just Call 7001305949 Top Class Call Girl Service Available
Call Girls Jp Nagar Just Call 7001305949 Top Class Call Girl Service Available
 
Call Girl Lucknow Mallika 7001305949 Independent Escort Service Lucknow
Call Girl Lucknow Mallika 7001305949 Independent Escort Service LucknowCall Girl Lucknow Mallika 7001305949 Independent Escort Service Lucknow
Call Girl Lucknow Mallika 7001305949 Independent Escort Service Lucknow
 
Call Girls Service Nandiambakkam | 7001305949 At Low Cost Cash Payment Booking
Call Girls Service Nandiambakkam | 7001305949 At Low Cost Cash Payment BookingCall Girls Service Nandiambakkam | 7001305949 At Low Cost Cash Payment Booking
Call Girls Service Nandiambakkam | 7001305949 At Low Cost Cash Payment Booking
 
VIP Call Girls Pune Vrinda 9907093804 Short 1500 Night 6000 Best call girls S...
VIP Call Girls Pune Vrinda 9907093804 Short 1500 Night 6000 Best call girls S...VIP Call Girls Pune Vrinda 9907093804 Short 1500 Night 6000 Best call girls S...
VIP Call Girls Pune Vrinda 9907093804 Short 1500 Night 6000 Best call girls S...
 
Artifacts in Nuclear Medicine with Identifying and resolving artifacts.
Artifacts in Nuclear Medicine with Identifying and resolving artifacts.Artifacts in Nuclear Medicine with Identifying and resolving artifacts.
Artifacts in Nuclear Medicine with Identifying and resolving artifacts.
 
Bangalore Call Girls Marathahalli 📞 9907093804 High Profile Service 100% Safe
Bangalore Call Girls Marathahalli 📞 9907093804 High Profile Service 100% SafeBangalore Call Girls Marathahalli 📞 9907093804 High Profile Service 100% Safe
Bangalore Call Girls Marathahalli 📞 9907093804 High Profile Service 100% Safe
 
Call Girl Surat Madhuri 7001305949 Independent Escort Service Surat
Call Girl Surat Madhuri 7001305949 Independent Escort Service SuratCall Girl Surat Madhuri 7001305949 Independent Escort Service Surat
Call Girl Surat Madhuri 7001305949 Independent Escort Service Surat
 
Call Girls Electronic City Just Call 7001305949 Top Class Call Girl Service A...
Call Girls Electronic City Just Call 7001305949 Top Class Call Girl Service A...Call Girls Electronic City Just Call 7001305949 Top Class Call Girl Service A...
Call Girls Electronic City Just Call 7001305949 Top Class Call Girl Service A...
 
Call Girls Service in Bommanahalli - 7001305949 with real photos and phone nu...
Call Girls Service in Bommanahalli - 7001305949 with real photos and phone nu...Call Girls Service in Bommanahalli - 7001305949 with real photos and phone nu...
Call Girls Service in Bommanahalli - 7001305949 with real photos and phone nu...
 
Book Call Girls in Kasavanahalli - 7001305949 with real photos and phone numbers
Book Call Girls in Kasavanahalli - 7001305949 with real photos and phone numbersBook Call Girls in Kasavanahalli - 7001305949 with real photos and phone numbers
Book Call Girls in Kasavanahalli - 7001305949 with real photos and phone numbers
 
Call Girls Budhwar Peth 7001305949 All Area Service COD available Any Time
Call Girls Budhwar Peth 7001305949 All Area Service COD available Any TimeCall Girls Budhwar Peth 7001305949 All Area Service COD available Any Time
Call Girls Budhwar Peth 7001305949 All Area Service COD available Any Time
 
Aspirin presentation slides by Dr. Rewas Ali
Aspirin presentation slides by Dr. Rewas AliAspirin presentation slides by Dr. Rewas Ali
Aspirin presentation slides by Dr. Rewas Ali
 
Call Girls Service In Shyam Nagar Whatsapp 8445551418 Independent Escort Service
Call Girls Service In Shyam Nagar Whatsapp 8445551418 Independent Escort ServiceCall Girls Service In Shyam Nagar Whatsapp 8445551418 Independent Escort Service
Call Girls Service In Shyam Nagar Whatsapp 8445551418 Independent Escort Service
 
Russian Call Girls Chickpet - 7001305949 Booking and charges genuine rate for...
Russian Call Girls Chickpet - 7001305949 Booking and charges genuine rate for...Russian Call Girls Chickpet - 7001305949 Booking and charges genuine rate for...
Russian Call Girls Chickpet - 7001305949 Booking and charges genuine rate for...
 
Call Girls Whitefield Just Call 7001305949 Top Class Call Girl Service Available
Call Girls Whitefield Just Call 7001305949 Top Class Call Girl Service AvailableCall Girls Whitefield Just Call 7001305949 Top Class Call Girl Service Available
Call Girls Whitefield Just Call 7001305949 Top Class Call Girl Service Available
 

Quality Risk Management - FMEA

  • 1.
  • 2. WHAT IS QUALITY RISK MANGEMENT Quality - Fulfillment of requirements Risk– Probability of failure to fulfill the requirements and its severity Management- Systematic process to review and manage the risk to quality
  • 3. QRM PROCESS - ICH Q9
  • 4. QRM PROCESS - ICH Q9 Risk identification is a systematic use of information to identify potential failure. Risk analysis is the estimation of the risk associated with the identified potential failure. Risk evaluation compares the identified and analyzed risk against given risk criteria
  • 5. QRM PROCESS - ICH Q9 Risk reduction Actions to mitigate the severity & probability of potential failure and/or to improve detectability of failures. Risk acceptance Acceptance of residual risks
  • 6. QRM PROCESS - ICH Q9 Risk Communication Sharing of information about risk and risk management between the decision makers and others. The output/result of the quality risk management process should be appropriately communicated and documented.
  • 7. QRM PROCESS - ICH Q9 Risk Review Sharing of information about risk and risk management between the decision makers and others. The frequency of any review should be based upon the level of risk. Risk review might include reconsideration of risk acceptance decisions
  • 9. FAILURE MODE EFFECTIVE ANALYSIS (FMEA) To identify potential failures before they occur and eliminate / minimize risk of failure
  • 10. FAILURE MODE EFFECTIVE ANALYSIS (FMEA) Every thing that can fail, will fail – Murphy's Law The main reason behind FMEA It will usually fails at worst possible moment FMEA identifies ‘can fail’ situations and eliminate or minimize from ‘will fail’ situation
  • 11. FAILURE MODE EFFECTIVE ANALYSIS (FMEA) Review past Analyze present Control future For frequency of occurrences For detection levels by reducing its impact What will FMEA do 1 2 3 Probability Detectability Severity IS CALLED RISK PRIORITY NUMBER (RPN)
  • 12. RISK PRIORITY NMBER = (PXSXD) • The likelihood that failure will occur Probability (P) • The potential effect of failure Severity (S) • Likelihood that failure will be detected immediately after occurrence Detectability (D) RPN is to Prioritize actions on Identified risks
  • 13. FAILURE MODE EFFECTIVE ANALYSIS (FMEA) Likelihood / Probability (P) Severity (S) Detectability (D) RPN = P X S X D To reduce RPN to acceptance level RPN = P X S X D
  • 14. FMEA APPROACH Item or Function Potential failure mode Potential causes of failure Probability Potential effect of failure Severity Current Controls Detectability RPN Recommended actions Probability Severity Detectability RPN With in acceptance (Yes / No)
  • 15. FMEA APPROACH Item or Functio n Potential failure mode Potential causes of failure Probability Potential effect of failure Severity Current Controls Detectability RPN Recommended actions Probability Severity Detectability RPN With in acceptance (Yes / No) ITEM / FUNCTION • Identifies individual function of the process. • Top down approach Bottom Up approach Up to what extent?, the extent it takes
  • 16. FMEA APPROACH Item or Functio n Potential failure mode Potential causes of failure Probability Potential effect of failure Severity Current Controls Detectability RPN Recommended actions Probability Severity Detectability RPN With in acceptance (Yes / No) Potential failures • Identify the potential failure modes on each step or function i.e To identify something that can fail. • There can be several failures for single function – List all Function Potential Failure 1 ? Potential Failure 2 ? Potential Failure 3 ?
  • 17. FMEA APPROACH Item or Functio n Potential failure mode Potential causes of failure Probability Potential effect of failure Severity Current Controls Detectability RPN Recommended actions Probability Severity Detectability RPN With in acceptance (Yes / No) Potential causes of failures • Identify the cause of each potential failure modes i.e To identify something that can fail. • There can be several causes for a single failure – List all Function Potential Failure 1 Cause ? Potential Failure 2 Cause ? Potential Failure 3 Cause ?
  • 18. FMEA APPROACH Item or Functio n Potential failure mode Potential causes of failure Probability Potential effect of failure Severity Current Controls Detectability RPN Recommended actions Probability Severity Detectability RPN With in acceptance (Yes / No) Probability Probability is the likelihood that failure will occur Gather all related data Review the old failures and their frequency Come to a judgment on probability (or) likely hood Potential Probability Rank Certain 4 High degree 3 Occasionally 2 Unlikely 1
  • 19. FMEA APPROACH Item or Functio n Potential failure mode Potential causes of failure Probability Potential effect of failure Severity Current Controls Detectability RPN Recommended actions Probability Severity Detectability RPN With in acceptance (Yes / No) Probability It is very good if we have quantified data as follows Potential Probability Rank Certain 4 High degree 3 Occasionally 2 Unlikely 1 Unlikely – 1failure in 1000 cases Occasionally – 5 failures out of 1000 cases High Degree – 20 failures out of 1000 cases Certain - 100 failures out of 1000 cases A S A N E X A M P L E D E F I N E Y O U R L I M I T S
  • 20. FMEA APPROACH Item or Functio n Potential failure mode Potential causes of failure Probability Potential effect of failure Severity Current Controls Detectability RPN Recommended actions Probability Severity Detectability RPN With in acceptance (Yes / No) Potential effects of failures Identify what happens if this failure occurs. There can be several effects – List them all Activity – Working at height , Potential Failure – Fall down Potential Impacts – Death of personnel Injury of personnel Death or Injury of personnel under him Malfunction equipment under Him Malfunction of PPE wear by personnel
  • 21. FMEA APPROACH Item or Functio n Potential failure mode Potential causes of failure Probability Potential effect of failure Severity Current Controls Detectability RPN Recommended actions Probability Severity Detectability RPN With in acceptance (Yes / No) Severity Severity is the rating of potential effect of failure RANK Potential Consequences Patient / Customer Compliance Business 15 Death Import Alert 100% business Loss 10 Permanent Injury Warning Letters 50% business Loss 5 Hospital stay with full recovery Audit Observations 25% business Loss 1 No health No impact No impact List out potential impacts of failures w.r.t Patient safety GMP Compliance Business loss And judge the severity of the impact.
  • 22. FMEA APPROACH Item or Functio n Potential failure mode Potential causes of failure Probability Potential effect of failure Severity Current Controls Detectability RPN Recommended actions Probability Severity Detectability RPN With in acceptance (Yes / No) Current Controls Identify current controls that are in place Design controls Process controls Personnel controls Detection controls
  • 23. FMEA APPROACH Item or Functio n Potential failure mode Potential causes of failure Probability Potential effect of failure Severity Current Controls Detectability RPN Recommended actions Probability Severity Detectability RPN With in acceptance (Yes / No) Detectability Likelihood that failure will be detected immediately after occurrence Likelihood of detection Rank Not detectable 4 Detectable between 1% - 50% time 3 Detectable between 50% - 99% time 2 Detectable more than 99% time 1
  • 24. FMEA APPROACH Item or Functio n Potential failure mode Potential causes of failure Probability Potential effect of failure Severity Current Controls Detectability RPN Recommended actions Probability Severity Detectability RPN With in acceptance (Yes / No) RPN RPN is Risk Priority Number = SEVERITY X DETECTABILITY X PROBABILITY RPN is to categories risk and overall priority. Severity Rank Detection Rank Probability Rank 15 4 4 10 3 3 5 2 2 1 1 1 Zone RPN Score Action High (Red) Above 60 High Risk. Action needed Immediately. Medium (Yellow) 31 to 60 Low Risk. Some action needed Low (Green) Less than 30 Risk Acceptable. No action needed
  • 25. FMEA APPROACH Recommended actions Probability Severity Detectability RPN With in acceptance (Yes / No) Based on your RPN score, Propose some actions to reduce the risk score. After completion of actions Redefine Risk score of Severity , detectability & Probability and take actions accordingly Identify potential failures & its impact Risk Rating P X S X D Risk Reduction Risk Acceptance Risk Rating P X S X D Priorities Actions based on RPN
  • 26. FMEA PROCESS – CASE STUDY FOR UNDERSTANDING REQUIREMENT: All staff should reach to office by 8.00 am in the morning. Bus Driver Employees Start point End point Route No.of stops Employee reach office on time. Identify the potential failures
  • 27. Map the process HOW TO DO PROCESS MAPPING Vehicle driver pick up employee daily in the morning from each stop and reach office at 8.00 a.m. daily General shift vehicle driver collects vehicle key from security person and ensures petrol in the vehicle and pick up employs daily in the morning from each stop and reach office at 8.00 a.m. daily General shift vehicle driver collects vehicle key from security person and ensures petrol in the vehicle and moves towards jebel ali road and pick up employees daily in the morning from each stop of discovery garden & garden and reach office at 8.00 a.m. daily Is above comes under process mapping
  • 28. Map the process General shift security person will report office at 6.00 am and keep all vehicle keys with him. Every day morning at 6.50 am vehicle driver comes to security and collect vehicle key and ensure enough petrol in the in the vehicle. Driver starts from office at 7.00 to pick up employees and security records the time. Vehicle moves through jebel ali road to IBN metro road and on to discovery garden of first pickup point. Where there are 5 signal crossings and two school that can create delays due to traffic. Vehicle starts picking up employees stop by stop and move towards DPS school road and to LF office. Where there are one signal crossing and one school that can create delays due to traffic. After picking up all employee vehicle moves on to jebel ali road and crosses JAFJA security check and reach office at 8.00 a.m 1 2 3 4 5 6 Up to what extent?, the extent it takes T O P D O W N B O T T O M U P HOW TO DO PROCESS MAPPING
  • 29. Map the process & Brainstorm on potential failures IDENTIFICATION OF POTENTIAL FAILURES Up to what extent?, the extent it takes Process step Potential failure General shift security person will report office at 6.00 am and keep all vehicle keys with him. General shift security person not reported at office? Reported but keys not available him. Every day morning at 6.50 am vehicle driver comes to security and collect vehicle key and ensure enough petrol in the in the vehicle. Driver not came? Or Driver came late? Drive came on time but petrol not enough in the vehicle? Driver starts from office at 7.00 to pick up employees and security records the time Driver not started on time due to vehicle problem Vehicle moves through jebel ali road to IBN metro road and on to discovery garden of first pickup point. Where there are 5 signal crossings and two school that can create delays due to traffic. Driver don’t know the root. Traffic at signal crossings or at school area? Vehicle met accident Vehicle starts picking up employees stop by stop and move towards DPS school road and to LF office. Where there are one signal crossing and one school that can create delays due to traffic. Employee not available at stop. Delayed due to employee called and told to wait Traffic delays.
  • 30. Map the process & Brainstorm on potential failures IDENTIFICATION OF POTENTIAL FAILURES Potential failure Controls & Actions General shift security person not reported at office? Reported but keys not available him. Measure current controls Plan controls if require Driver not came? Or Driver came late? Drive came on time but petrol not enough in the vehicle? Measure current controls Plan controls if require Driver not started on time due to vehicle problem Measure current controls Plan controls if require Driver don’t know the root. Traffic at signal crossings or at school area? Vehicle met accident Measure current controls Plan controls if require Employee not available at stop. Delayed due to employee called and told to wait Traffic delays. Measure current controls Plan controls if require