- 1. Week
beginning Task
3-‐Oct-‐14 Group
meeting
and
delegation
10-‐Oct-‐14 Finalise
planning
17-‐Oct-‐14 Update
Blog
HALF
TERM Practice
filming
27-‐Oct-‐14 Planning
and
Research
3-‐Nov-‐14 Planning
and
Research
10-‐Nov-‐14 Planning
and
Research
17-‐Nov-‐14 Research-‐Exemplary
short
films
24-‐Nov-‐14 Planning-‐Brainstorming
(1
hr)
15-‐Dec-‐14 Research-‐Short
films
analysis
x
2
(2
hrs)
22-‐Dec-‐14
Research-‐Short
films
analysis-‐
radio
podcast
x2
(1
hr),
Generic
Codes
and
Conventions
(2
hrs)
Planning-‐Film
title
ideas,
narrative
(1hr)
Update
Blog:
1
hr
29-‐Dec-‐14
Planning-‐Potential
plotlines
(30
mins),
initial
location
recce
(1
hr),
moodboard
(30
mins),
synopsis
(1-‐2hrs)
Update
Blog:
1
hr
Planning-‐Shotlist
(2
hrs),
Characters
(1
hr),
costumes
(1
hr),
props
(1
hr).
Research-‐Audience
research
survey
(1hr)
Research-‐Genre
technical
codes
(1
hr)
Update
project
plan
and
blog
(1
hr)
5-‐Jan-‐15
Planning-‐
Recce
and
secure
locations
(2-‐3
hrs),
Storyboard
(3
hrs),
animatic
(1hr)
Research-‐Genre
Technical
Codes
(2
hrs)
Presentation
and
edit
(2-‐3
hrs
hrs)
12-‐Jan-‐15
Risk
assessment
(1
hr)
Film
(2-‐3
hrs)
Update
blog:
Behind
the
scenes
(1
hr)
19-‐Jan-‐15
Edit
(2
hrs)
Risk
assessment
(45
mins)
Film
(2-‐3
hrs)
Update
blog:
Director's
progress
log
(1
hr)
26-‐Jan-‐15
Edit
(4
hrs)
Research:
Posters
x
2
(3
hrs)
Planning:
Poster
mockup
(2
hrs)
Photoshoot
plan
(2
hrs)
Update
blog:
Director's
VLOG
(2
hrs)
2-‐Feb-‐15
Film/Edit
(2
hrs)
Poster
photoshoot
(1
hr)
Poster
first
draft
construction
(3
hrs)
Update
blog:
Director's
progress
log
(1
hr)
9-‐Feb-‐15
Edit
(2
hrs)
Research:
Soundtracks
(2hrs)
Edit
Soundtrack
(2
hrs)
Titles
and
credits(2
hrs)
First
Cut
Due/Audience
Feedback
on
First
Cut
Update
blog:
Director's
progress
log
(1
hr)
Media
Studies
Project
Plan
- 2. 16-‐Feb-‐15
Poster
Final
Draft
(3
hrs)
Filming/Editing
(4
hrs)
Edit
Colour
and
grading
(6
hrs)
Research:
Film
Reviews
x2
(4
hrs)
23-‐Feb-‐15
Planning:
Film
Review
photoshoot
plan
(1
hr)
Planning:
Film
Review
mockup
(1hr)
Film
review
layout
first
draft
(3hrs)
Film
review
article
(2hrs)
Film
review
audience
feedback
2-‐Mar-‐15
Film
review
re-‐draft
(2
hrs)
Edit
(6
hrs)
Final
Drafts
(All)
FINAL
CUT
9-‐Mar-‐15 Evaluation
Q's
(4
hrs)
16-‐Mar-‐15 Evaluation
Q's
(4
hrs)
23-‐Mar-‐15
Evaluation
Presentation
editing
(4
hrs)
4pm
Fri
25th
March-‐DEADLINE
30-‐Mar-‐15 Finalise
Blog
and
hand
in