1. J. Wold, project manager of Print Software, Inc., wants you to prepare a project network; compute the early, late, and slack activity times; determine the planned project duration; and identify the critical path. His assistant has collected the following information for the Color Printer Drivers Software Project: 1. J. Wold, project manager of Print Software, Inc., wants you to prepare a project network; compute the early, late, and slack activity times; determine the planned project duration; and identify the critical path. His assistant has collected the following information for the Color Printer Drivers Software Project: Solution Path – 1 ) A-B-E-H-J-K-L = 115 days = Critical Path 2 ) A-C-F-H-J-K-L = 45 days 3 ) A-D-G-I-J-K-L = 105 DAYS Project Duration 115 DaysIDearliest start schedulelatest start scheduleslack activity timesA000B880C86557D81810E10100F116857G687810H70700I708010J90900K1001000L11 21120.