EX8-2 (Static) Bjorn and Thor are plumbers... Bjorn and Thor are plumbers who have been scheduled to work on the construction of a new school building. Just before the start of the project, Bjorn broke his arm and cannot work on the project. Now Thor has to handle his own activities as well as Bjorn's. Level the project Gantt chart so that Thor is responsible for activities 3,4,6, and 7 . How will the project completion date be affected?The figure to the right shows an economy's long- run aggregate supply (LAS) curve. Suppose this economy experiences a depletion of natural resources. Use the Line Drawing Tool to draw and label a new LAS curve that illustrates the effect of this event. The shift in the LAS curve indicates that the economy's potential output has.