Given the table below, assuming that there are only 9 resources available at any time: Activity Duration Dependency Resources Start 0 0 A 12 start 4 B 15 start 3 C 11 start 2 D 3 A 6 E 1 C 6 F 7 B 3 G 5 D,E 4 H 2 D,E 5 I 4 E,F 4 J 10 H,I 6 K 8 G,J 3 Provide the network diagram Provide the steps and process to update the schedule based on resource availability Provide the final Gantt chart. What is the final project duration? Activity Duration Dependency Resources Start 0 0 A 12 start 4 B 15 start 3 C 11 start 2 D 3 A 6 E 1 C 6 F 7 B 3 G 5 D,E 4 H 2 D,E 5 I 4 E,F 4 J 10 H,I 6 K 8 G,J 3.