Section 7: Project Scheduling PERT/ CPM (2)
1. By:
Zakaria Elsayed Hasaneen
Teaching Assistant at Faculty of Commerce
Accounting Department (English Section)
Kafrelsheikh University
OR
Section (7)
Project Scheduling: PERT/CPM
With Uncertain ActivityTime
Grade 4 –Term 2
Zakaria Hasaneen
Zakaria Hasaneen
Zakaria Hasaneen
2. Required
• Calculate expected times
• Calculate variances
• Calculate probability of completion of project at specified time
• Calculate the project completion time given probability
3.
4.
5.
6.
7.
8.
9.
10.
11. 3-Determine the probability that project will
be completed
A- in less than 35 weeks
B- in more than 31 weeks
C- between 31 and 35 weeks
D-in less than 31 or more than 35
12. A- in less than 35 weeks
Determine the probability that project will be completed