SlideShare a Scribd company logo
1 of 27
Koyesha Hydroelectric Power
Project
GIBE-OMO Cascade hydro Plant & project location
BACKGROUND
Project Name Koysha Hydroelectric Project.
Employer Ethiopian Electric Power (EEP).
Contractor Webuild (former Salini Impregilo SPA.)
Contract type
EPC (Engineering, Procurement and
Construction).
Contract Signing Date 28th March, 2016.
Installed Capacity 1,800 MW
Total Project Cost 2.5 Billion Euro.
Main features
 Roller compacted concrete dam (RCC
Dam).
 Independent an overflow gated spillway.
 Two diversion box culvert.
 Upstream and downstream cofferdam.
 2 waterways comprising intakes,
penstocks and manifolds.
 Powerhouse.
 Switchyard.
 400kv transmission line from gibe iii.
 Two middle level outlets (MLO).
RESERVOIR
 Maximum operating
level- el.680m a.s.l.
 Minimum operating
level- el.660m a.s.l.
 Surface area at
maximum operating
level 100km2
.
 Total storage 6.5Bm3
.
 Dead storage 483Mm3
Reservoir
Omo River flow
Legend
Existing Road
New Road
alignment
LAYOUT OF KEY STRUCTURES
CIVIL WORKS
Diversion Culvert &Cofferdams
 Excavation quantity 2.6 Mm3,
 Two Diversion Box Culverts 9m x
11.5m and 284 long,
 Concrete quantity 119,000m3.
 38m high U/S Cofferdam &14m high
D/S Cofferdam
Status:-operational since July 20, 2018.
RCC Dam
 The Dam Crest level is -
el.688.5m a.s.l.
 The Crest length is 1,012 m.
 The max. height above
foundation 201.5m.
 RCC volume 7.4Mm3.
Status:
Excavation works
 Substantially completed.
 Dam foundation treatment on
progress.
 RCC placement on progress( to
date 299,218m³ RCC placed)
Major advantage of RCC
 Rapid construction (It have fast construction time)
 Economically
 It use minimum cement
RCC Dam Cont ….
Activities during RCC Placement
The dam construction is done by repeating the process by considering if there is contraction
joint, and Waterstop on the construction drawing.
1. RCC cleaning
2. Spread Bedding
3. RCC damping
4. RCC Spreading
5. RCC compaction
6. GERCC activities
7. RCC Curing
RCC Dam Cont ….
RCC Dam Cont ….
Spread Bedding
 Is located on the left side of
the river.
 Dimensions (l x w x h)
211m x 51.5m x 44.3m.
 The erection bay floor is
located - el. 541m a.s.l.
 The turbines axis is at el.
518m a.s.l.
Power house
Power House Cont.…
Status:
Excavation works
 Foreseen quantity 2.0Mm3,
99% is completed.
 Rebar fixing & Concrete
casting on progress.
 To date 38,999 m³ concrete
casted.
Parts of Power House
Power House is composed of the following structural elements, which are separated
by contraction & expansion joints:
1. Intake
2. Penstock
3. Manifold
4. Erection bays and control building
5. Power house Units
Power House Cont…
Power House Cont…
Construction Process of PH
1. Survey Setting‐Out
2. Foundation Preparation
3. Rebar Preparation And Placing
4. Formwork Application
5. Concreting
Power House Cont.…
Geology
In this section the contact or consolidation grouting will be performed in the dam
foundation. The purpose is to consolidate the rock below the dam and to fill the void (if
any) between leveling concrete (RCC) and the rock itself.
The contact/consolidation grouting activities will be carried out during the RCC
dam construction period. The works will be performed when the RCC surface is available
(when the compaction is done). The minimum cover criteria for RCC thickness is above
3m for starting the drilling and grouting activities.
• Contact/consolidation grouting: purpose of consolidating the rock below the dam and
filling the void between leveling concrete and the rock.
• Curtain grouting: Purpose of curtain grouting is to prevent risk of erosion of foundation
material sand control permeability by establishing an effective seepage barrier along the
dam upstream face in order to limit seepage discharge under and around the dam.
• Bulb grouting: completed the curtain grouting increasing the effectiveness of the screen
near the dam upstream toe. Executed from the galleries inside the dam body, one in every
40 m of height and extended inside both right and left abutment of the dam to control the
seepage of front water from the reservoir and the rock of the abutment.
Consolidation grouting is a treatment for the rock and RCC itself. There are different
types of treatment:-
Geology Cont…..
Laboratory
Laboratory tests are done to check the workability of the raw and processed construction
materials before they deliver it to the construction site. Laboratory tests are carried out daily,
which gave me an opportunity to observe tests like-
1. VeBe Test (vibrating table)
2. Compressive Strength Tests
3. Materials Finer Than
4. Density Test for Cement
VeBe Test (vibrating table)
Laboratory Cont …..
Objective: to know the workability of concrete and slump value
Procedure:
• Fresh RCC mix is placed into slump cone, inside the cylinder
• Clean plastic disk then placed on the top of the concrete and the vibrating table is
turned on and simultaneously starts the stopwatch.
• Immediately when the conical shape of the concrete disappears and takes a cylindrical
shape, which is observable through the glass disk, switch off the stopwatch.
• The time taken measured for the concrete cone to shorten and change from the conical
to a cylindrical shape, until the transparent disk to be completely covered concrete, is
measured in seconds and is reported as the number of VeBe seconds.
Laboratory Cont …..
Procedure of VeBe Test
Compressive Strength Tests
Laboratory Cont …..
Objective: to check the cylindrical compressive strength of hardened concrete.
Procedure:
1. Place the fresh prepared concrete mix (CVC or RCC) in to cylindrical plastic mold
with three layers & compact each layers for 12 sec.
2. Dates chosen between 7, 28, 90 and 365 days, weather they attain the required
strength or not within the specified days before applying for structures.
3. Leave the sample for 4hrs in air & soak in water for the dedicated dates for
each sample.
4. Take the sample from soaking room & make the sample saturated surface dry.
5. Place the sample in to compressive strength machine and apply the load
progressively until the spacemen collapse and read the displacement for each
applied load per second.
Materials Finer Than
Laboratory Cont …..
Objective: determination of the amount of material finer than a 75-μm (No. 200)
sieve in aggregate by Washing. The procedure is using only water for the
washing operation.
Procedure of Materials Finer Than
• Dry the test sample in the oven to constant mass at a temperature of 110 °C.
• Determine the mass of the test sample.
• Place the test sample in the container and add sufficient water to cover it.
• Agitate the sample with sufficient vigor to result in complete separation of all particles
finer than the 75-μm (No. 200) sieve from the coarser particles, and to bring the fine
material into suspension.
• Immediately pour the wash water containing the suspended and dissolved solids over
the nested sieves, arranged with the coarser sieve on top. Take care to avoid, as much as
feasible, the decantation of coarser particles of the sample. Add a second charge of
water to the sample in the container, agitate, and decant as before. Repeat this operation
until the wash water is clear.
• Return all material retained on the nested sieves by flushing to the washed sample. Dry
the washed aggregate in the oven to constant mass at a temperature of 110 °C and
determine the mass to the nearest 0.1 % of the original mass of the sample.
Laboratory Cont …..
Density Test for Cement
Laboratory Cont …..
Objective determination of the density of hydraulic cement. Its particular usefulness is
in connection with the design and control of concrete mixtures.
Procedure:-
• Fill the flask with kerosene to a mark on the stem between the 0 and the 1 cm mark.
• Place the flask in a constant temperature bath and record the initial height of
the kerosene in the flask.
• Carefully introduce about 64 grams of cement, weighed to the nearest 0.1 grams.
• Remove the flask from the bath and place it on the rubber mat. Take off the
lead weight and manipulate the flask on the mat so as to remove all air bubbles from
the flask.
• Return the flask to the bath and check the temperature within the flask. If it is within
0.2°C of the original temperature inside the flask, take the final reading.
Laboratory Cont …..
Procedure of Density Test for Cement
Thank you!!!

More Related Content

Similar to koyesha hydropower.pptx

SEMI DESTRUCTIVE Test On Concrete _by Imran B K
SEMI DESTRUCTIVE  Test On Concrete _by Imran B KSEMI DESTRUCTIVE  Test On Concrete _by Imran B K
SEMI DESTRUCTIVE Test On Concrete _by Imran B KBk Imran
 
Final Presentation
Final PresentationFinal Presentation
Final PresentationMonique F M
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil EngineersSHAZEBALIKHAN1
 
Thirsty Concrete application in Road pavement
Thirsty Concrete application in Road pavementThirsty Concrete application in Road pavement
Thirsty Concrete application in Road pavementSachinPawarUCOE
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)y Sahaja
 
Fresh Concrete - Presentation.pptx
Fresh Concrete - Presentation.pptxFresh Concrete - Presentation.pptx
Fresh Concrete - Presentation.pptxBhanumathiBadana
 
New microsoft power point presentation
New microsoft power point presentationNew microsoft power point presentation
New microsoft power point presentationmuradalif
 
BEHAVIOUR OF REINFORCED CONCRETE BEAMS WITH COCONUT SHELL AS COARSE AGGREGATES
 BEHAVIOUR OF REINFORCED CONCRETE BEAMS WITH COCONUT SHELL AS COARSE AGGREGATES  BEHAVIOUR OF REINFORCED CONCRETE BEAMS WITH COCONUT SHELL AS COARSE AGGREGATES
BEHAVIOUR OF REINFORCED CONCRETE BEAMS WITH COCONUT SHELL AS COARSE AGGREGATES Eswari Kasil
 
Fluids & cementing 2022-2023 (1) (1).pdf
Fluids & cementing 2022-2023 (1) (1).pdfFluids & cementing 2022-2023 (1) (1).pdf
Fluids & cementing 2022-2023 (1) (1).pdfLokmanDridah
 
Compacting Factor Test
Compacting Factor TestCompacting Factor Test
Compacting Factor TestXinYee Khoo
 
IRJET- Roughness Coefficient of Alkali Activated Mineral based Concrete C...
IRJET-  	  Roughness Coefficient of Alkali Activated Mineral based Concrete C...IRJET-  	  Roughness Coefficient of Alkali Activated Mineral based Concrete C...
IRJET- Roughness Coefficient of Alkali Activated Mineral based Concrete C...IRJET Journal
 
Laboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil EngineersLaboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil EngineersPhurba Tamang
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017ktx500
 
Quality control lab
Quality control labQuality control lab
Quality control labRaja Katoch
 
Buildingmaterialslabmanuallab01 161125043012
Buildingmaterialslabmanuallab01 161125043012Buildingmaterialslabmanuallab01 161125043012
Buildingmaterialslabmanuallab01 161125043012Vijay Patidar
 
Buildingmaterialslabmanuallab01 161125043012 (1)
Buildingmaterialslabmanuallab01 161125043012 (1)Buildingmaterialslabmanuallab01 161125043012 (1)
Buildingmaterialslabmanuallab01 161125043012 (1)Vijay Patidar
 
Building materials lab_manual lab 01
Building materials lab_manual  lab 01Building materials lab_manual  lab 01
Building materials lab_manual lab 01Engr. Umair Razzaq
 

Similar to koyesha hydropower.pptx (20)

SEMI DESTRUCTIVE Test On Concrete _by Imran B K
SEMI DESTRUCTIVE  Test On Concrete _by Imran B KSEMI DESTRUCTIVE  Test On Concrete _by Imran B K
SEMI DESTRUCTIVE Test On Concrete _by Imran B K
 
Final Presentation
Final PresentationFinal Presentation
Final Presentation
 
Oedometer test
Oedometer testOedometer test
Oedometer test
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers
 
Properties of concrete
Properties of concrete Properties of concrete
Properties of concrete
 
Thirsty Concrete application in Road pavement
Thirsty Concrete application in Road pavementThirsty Concrete application in Road pavement
Thirsty Concrete application in Road pavement
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)
 
Fresh Concrete - Presentation.pptx
Fresh Concrete - Presentation.pptxFresh Concrete - Presentation.pptx
Fresh Concrete - Presentation.pptx
 
New microsoft power point presentation
New microsoft power point presentationNew microsoft power point presentation
New microsoft power point presentation
 
BEHAVIOUR OF REINFORCED CONCRETE BEAMS WITH COCONUT SHELL AS COARSE AGGREGATES
 BEHAVIOUR OF REINFORCED CONCRETE BEAMS WITH COCONUT SHELL AS COARSE AGGREGATES  BEHAVIOUR OF REINFORCED CONCRETE BEAMS WITH COCONUT SHELL AS COARSE AGGREGATES
BEHAVIOUR OF REINFORCED CONCRETE BEAMS WITH COCONUT SHELL AS COARSE AGGREGATES
 
Fluids & cementing 2022-2023 (1) (1).pdf
Fluids & cementing 2022-2023 (1) (1).pdfFluids & cementing 2022-2023 (1) (1).pdf
Fluids & cementing 2022-2023 (1) (1).pdf
 
Compacting Factor Test
Compacting Factor TestCompacting Factor Test
Compacting Factor Test
 
IRJET- Roughness Coefficient of Alkali Activated Mineral based Concrete C...
IRJET-  	  Roughness Coefficient of Alkali Activated Mineral based Concrete C...IRJET-  	  Roughness Coefficient of Alkali Activated Mineral based Concrete C...
IRJET- Roughness Coefficient of Alkali Activated Mineral based Concrete C...
 
Laboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil EngineersLaboratory Instruction Manual for Civil Engineers
Laboratory Instruction Manual for Civil Engineers
 
Mahi ppt suez (2)
Mahi ppt suez (2)Mahi ppt suez (2)
Mahi ppt suez (2)
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017
 
Quality control lab
Quality control labQuality control lab
Quality control lab
 
Buildingmaterialslabmanuallab01 161125043012
Buildingmaterialslabmanuallab01 161125043012Buildingmaterialslabmanuallab01 161125043012
Buildingmaterialslabmanuallab01 161125043012
 
Buildingmaterialslabmanuallab01 161125043012 (1)
Buildingmaterialslabmanuallab01 161125043012 (1)Buildingmaterialslabmanuallab01 161125043012 (1)
Buildingmaterialslabmanuallab01 161125043012 (1)
 
Building materials lab_manual lab 01
Building materials lab_manual  lab 01Building materials lab_manual  lab 01
Building materials lab_manual lab 01
 

Recently uploaded

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 

Recently uploaded (20)

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 

koyesha hydropower.pptx

  • 2. GIBE-OMO Cascade hydro Plant & project location
  • 3. BACKGROUND Project Name Koysha Hydroelectric Project. Employer Ethiopian Electric Power (EEP). Contractor Webuild (former Salini Impregilo SPA.) Contract type EPC (Engineering, Procurement and Construction). Contract Signing Date 28th March, 2016. Installed Capacity 1,800 MW Total Project Cost 2.5 Billion Euro.
  • 4. Main features  Roller compacted concrete dam (RCC Dam).  Independent an overflow gated spillway.  Two diversion box culvert.  Upstream and downstream cofferdam.  2 waterways comprising intakes, penstocks and manifolds.  Powerhouse.  Switchyard.  400kv transmission line from gibe iii.  Two middle level outlets (MLO).
  • 5. RESERVOIR  Maximum operating level- el.680m a.s.l.  Minimum operating level- el.660m a.s.l.  Surface area at maximum operating level 100km2 .  Total storage 6.5Bm3 .  Dead storage 483Mm3 Reservoir Omo River flow Legend Existing Road New Road alignment
  • 6. LAYOUT OF KEY STRUCTURES
  • 7. CIVIL WORKS Diversion Culvert &Cofferdams  Excavation quantity 2.6 Mm3,  Two Diversion Box Culverts 9m x 11.5m and 284 long,  Concrete quantity 119,000m3.  38m high U/S Cofferdam &14m high D/S Cofferdam Status:-operational since July 20, 2018.
  • 8. RCC Dam  The Dam Crest level is - el.688.5m a.s.l.  The Crest length is 1,012 m.  The max. height above foundation 201.5m.  RCC volume 7.4Mm3. Status: Excavation works  Substantially completed.  Dam foundation treatment on progress.  RCC placement on progress( to date 299,218m³ RCC placed)
  • 9. Major advantage of RCC  Rapid construction (It have fast construction time)  Economically  It use minimum cement RCC Dam Cont ….
  • 10. Activities during RCC Placement The dam construction is done by repeating the process by considering if there is contraction joint, and Waterstop on the construction drawing. 1. RCC cleaning 2. Spread Bedding 3. RCC damping 4. RCC Spreading 5. RCC compaction 6. GERCC activities 7. RCC Curing RCC Dam Cont ….
  • 11. RCC Dam Cont …. Spread Bedding
  • 12.  Is located on the left side of the river.  Dimensions (l x w x h) 211m x 51.5m x 44.3m.  The erection bay floor is located - el. 541m a.s.l.  The turbines axis is at el. 518m a.s.l. Power house
  • 13. Power House Cont.… Status: Excavation works  Foreseen quantity 2.0Mm3, 99% is completed.  Rebar fixing & Concrete casting on progress.  To date 38,999 m³ concrete casted.
  • 14. Parts of Power House Power House is composed of the following structural elements, which are separated by contraction & expansion joints: 1. Intake 2. Penstock 3. Manifold 4. Erection bays and control building 5. Power house Units Power House Cont…
  • 16. Construction Process of PH 1. Survey Setting‐Out 2. Foundation Preparation 3. Rebar Preparation And Placing 4. Formwork Application 5. Concreting Power House Cont.…
  • 17. Geology In this section the contact or consolidation grouting will be performed in the dam foundation. The purpose is to consolidate the rock below the dam and to fill the void (if any) between leveling concrete (RCC) and the rock itself. The contact/consolidation grouting activities will be carried out during the RCC dam construction period. The works will be performed when the RCC surface is available (when the compaction is done). The minimum cover criteria for RCC thickness is above 3m for starting the drilling and grouting activities.
  • 18. • Contact/consolidation grouting: purpose of consolidating the rock below the dam and filling the void between leveling concrete and the rock. • Curtain grouting: Purpose of curtain grouting is to prevent risk of erosion of foundation material sand control permeability by establishing an effective seepage barrier along the dam upstream face in order to limit seepage discharge under and around the dam. • Bulb grouting: completed the curtain grouting increasing the effectiveness of the screen near the dam upstream toe. Executed from the galleries inside the dam body, one in every 40 m of height and extended inside both right and left abutment of the dam to control the seepage of front water from the reservoir and the rock of the abutment. Consolidation grouting is a treatment for the rock and RCC itself. There are different types of treatment:- Geology Cont…..
  • 19. Laboratory Laboratory tests are done to check the workability of the raw and processed construction materials before they deliver it to the construction site. Laboratory tests are carried out daily, which gave me an opportunity to observe tests like- 1. VeBe Test (vibrating table) 2. Compressive Strength Tests 3. Materials Finer Than 4. Density Test for Cement
  • 20. VeBe Test (vibrating table) Laboratory Cont ….. Objective: to know the workability of concrete and slump value
  • 21. Procedure: • Fresh RCC mix is placed into slump cone, inside the cylinder • Clean plastic disk then placed on the top of the concrete and the vibrating table is turned on and simultaneously starts the stopwatch. • Immediately when the conical shape of the concrete disappears and takes a cylindrical shape, which is observable through the glass disk, switch off the stopwatch. • The time taken measured for the concrete cone to shorten and change from the conical to a cylindrical shape, until the transparent disk to be completely covered concrete, is measured in seconds and is reported as the number of VeBe seconds. Laboratory Cont ….. Procedure of VeBe Test
  • 22. Compressive Strength Tests Laboratory Cont ….. Objective: to check the cylindrical compressive strength of hardened concrete. Procedure: 1. Place the fresh prepared concrete mix (CVC or RCC) in to cylindrical plastic mold with three layers & compact each layers for 12 sec. 2. Dates chosen between 7, 28, 90 and 365 days, weather they attain the required strength or not within the specified days before applying for structures. 3. Leave the sample for 4hrs in air & soak in water for the dedicated dates for each sample. 4. Take the sample from soaking room & make the sample saturated surface dry. 5. Place the sample in to compressive strength machine and apply the load progressively until the spacemen collapse and read the displacement for each applied load per second.
  • 23. Materials Finer Than Laboratory Cont ….. Objective: determination of the amount of material finer than a 75-μm (No. 200) sieve in aggregate by Washing. The procedure is using only water for the washing operation.
  • 24. Procedure of Materials Finer Than • Dry the test sample in the oven to constant mass at a temperature of 110 °C. • Determine the mass of the test sample. • Place the test sample in the container and add sufficient water to cover it. • Agitate the sample with sufficient vigor to result in complete separation of all particles finer than the 75-μm (No. 200) sieve from the coarser particles, and to bring the fine material into suspension. • Immediately pour the wash water containing the suspended and dissolved solids over the nested sieves, arranged with the coarser sieve on top. Take care to avoid, as much as feasible, the decantation of coarser particles of the sample. Add a second charge of water to the sample in the container, agitate, and decant as before. Repeat this operation until the wash water is clear. • Return all material retained on the nested sieves by flushing to the washed sample. Dry the washed aggregate in the oven to constant mass at a temperature of 110 °C and determine the mass to the nearest 0.1 % of the original mass of the sample. Laboratory Cont …..
  • 25. Density Test for Cement Laboratory Cont ….. Objective determination of the density of hydraulic cement. Its particular usefulness is in connection with the design and control of concrete mixtures.
  • 26. Procedure:- • Fill the flask with kerosene to a mark on the stem between the 0 and the 1 cm mark. • Place the flask in a constant temperature bath and record the initial height of the kerosene in the flask. • Carefully introduce about 64 grams of cement, weighed to the nearest 0.1 grams. • Remove the flask from the bath and place it on the rubber mat. Take off the lead weight and manipulate the flask on the mat so as to remove all air bubbles from the flask. • Return the flask to the bath and check the temperature within the flask. If it is within 0.2°C of the original temperature inside the flask, take the final reading. Laboratory Cont ….. Procedure of Density Test for Cement