SlideShare a Scribd company logo
1 of 5
The CIPS Supply Management
Awards 2012
ENGINEERING MATERIAL
RATIONALISATION
THE CIPS SUPPLY MANAGEMENT AWARDS
ENGINEERING MATERIAL RATIONALISATION
CATEGORY – CROSS FUNCTIONAL TEAM
PROJECT TITLE – Engineering Materials Rationalisation (MRO)
ORGANISATION – Jaguar Land Rover
Challenges Faced
When Jaguar Land Rover (JLR) separated from Ford it was left with four manufacturing sites,each with its own engineering
material stores (MRO). These were run independently with no shared visibilityof stock, part number structure,facilities for
stock sharing,or defined processes for managing the stores,for example, anyone on the manufacturing floor could raise a
new part number.The implications ofthese ways of working were:
 MRO stock availabilityat each site was <50%, yet while one site was out of stock on a particular item,another site
was overstocked
 JLR had 23 part numbers for AA batteries and more than 300 different types of hammers. There were a total of
88,000 MRO part numbers,with £40million ofstock for an annual spend of£12m,against a supplier base of73.For
comparison,the total number ofparts used to make all JLR models was less than 50,000.
 The shiftof responsibilityfor these sites from Ford to JLR increased the administration workload,requiring JLR to
increase the team from 2 to 9 people with no extra funding.
 Significant‘urgent’ spend on ProcurementCard which was uncontrolled and unleveraged.
Aims & Objectives
A cross functional team was formed and a Project Charter drafted, with the following aims:
1) Reduce inventory by 20%
2) Reduce the number ofparts by 20%
3) Reduce the purchase price of MRO materials by5%
4) Implementstock classification and appropriate stock policies
5) Reduce ProcurementCard spend on MRO Parts
Planning and Execution
From the offset it was clear that the projectwould only succeed if Planning,Manufacturing and Purchasing worked closely
together. There were some significantorganisational difficulties thatrequired addressing organisationally,in order for the
projectto be successful. The first step was to engage the three Senior Directors responsible for these areas,and briefthem
on the challenge and the objectives and secure their sponsorship.A full project plan was then developed and used to track
progress.
 Thousands ofhourly& staff users of the service across all sites,resulting in a high business impactacross a
diverse range of customers.
 Functionallythe procurement,stores management& machine spares elements ofthe existing service sat
across differentdepartments/owners.
 If successful trade-offs between cost,service & space would be required. Such trade-offs would require
understanding & involvementof senior JLR members.
The organisation solution for the projectwas a key reason thatthe procurementlead for the projectwas able to able to work
successfullyto conclusion. The first part of this was to splitactivity across 3 work streams,where each work stream had a
functional owner with mutual dependencies upon other functions to deliver the content of the work stream. (Please see
Appendix)
THE CIPS SUPPLY MANAGEMENT AWARDS
ENGINEERING MATERIAL RATIONALISATION
Key steps included:-
Benchmarking –The team visited a number of similar companies and quicklyrealised thatour key internal processes
needed to be cleaned up as a priority. An interesting finding from our benchmarking was thata high percentage ofthe
benchmarked companies had outsourced their stores and mosthad achieved significantgains.Unfortunatelya few had
outsourced without firstcompleting their internal clean-up and the outcomes were notpositive. Our team took this on board
as a key learning.
 MRO Part Clean Up & CommodityRationalisation
 MRO Single Provider
 MRO Spares rationalisation.
Stock Analysis – This painstaking task required detailed analysis ofall 88,000 parts including stock levels,cost,and stock
availability at each site. Each part was classified with regards to its criticality and availability. The strategy for each part was
based on this classification. The second partof the stock analysis was to clean the parts database,with the aim of reducing
the number ofparts in stock. Initial internal efforts enabled the number ofparts to be reduced to 65,000; however the team
felt there was further opportunity We worked with suppliers and achieved a dramatic reduction to 8,000 parts numbers in
total, a reduction in excess of 90%.
Prepare for Tender – The cleaned up stock profile was divided into 23 bundles ofitems and each was separatelytendered
to the external market. Given that JLR’s volumes were significantlylower than those of the combined Ford Motor Company;
our best hope was to maintain current pricing.
However, through the tender process we reduced
prices by 10% and delivered £1m of annualised
savings. The number of suppliers was reduced or
changed from 73 to 36; a best in class approach
based on our benchmarking.
Define Stock Share Mechanisms – Our aim
was to implement a process where stock held in one store was available to all sites.To achieve this we needed a common
part number coding.We brought together the MRO managers and agreed new partnumbers for the 65,000 part numbers we
had after the initial stock clean up. The next stage was to make the stock visible across all the stores.The only way to
achieve this was to investin a new IT system.A decision on this was delayed until later in the project.
Introduce Governance and Control Gatekeepers – The continued success ofthe projectwas dependenton strong
governance to control the creation of new part numbers and to ensure communication between the sites. The JLR MRO
managers were given the final decision on all new submitted parts for the stores to ensure tight control was maintained
throughoutthe projectand beyond. There is now a weekly Gatekeeper Meeting where Manufacturing, Stores and
Procurement mustagree the purchase ofany new MRO parts.
Material Advantages – This projectdid not start as an outsourcing plan,butit was clear from our benchmarking thatthis
was a further cost-reducing option ifmanaged correctly.Once our internal procedures were in place we were in a position to
be able to confidently compare quotes from the external marketand a decision was taken to place the services with an
external provider. Included in the requirements was the IT system which would allow cross site visibilityto satisfyour
immediate needs,as well as to be compatible with the upcoming JLR global SAP implementation.
Innovation and Creativity
The key to initiating this projectwas upside down Procurement,in other words looking atProcurement priorities in a different
way. Traditionallyprocurementdid notactively manage MRO as it was a (relatively) small spend,however,MRO stores did
have a big impacton service levels into the site and a disproportionallynegative impacton the perception of Procurement
within JLR. When someone can go and buy a hammer cheaper from B&Qthan within JLR stores,it’s Procurement’s name
that is tarnished!
Classification Policy
Non critical spares Minimal Centralised stock holding
Consumable Centralised stock holding
Critical specific spares Hold on each site
Industry standard
spares
Nil stock holding
THE CIPS SUPPLY MANAGEMENT AWARDS
ENGINEERING MATERIAL RATIONALISATION
The projectchallenged the corporate culture as it engaged three members ofthe Executive
ManagementTeam and conveyed the message thatthis was an importantand supported
project. This project provides a great example of how Procurementcan extend its reach and
provide benefits beyond cost. In many cases the MRO stores are the only contact staff has
with Procurement, and the new process means theyno longer feel the need to store stock
in their bottom desk drawers!
Best Practice
The key elementofthis process was thatwe carried out the nitty gritty work to ensure we
understood the situation before we considered outsourcing the services. This level of
granularityis not common in today’s business world butwas absolutelycrucial to the
successes achieved as itprovided us with a clear insight into the MRO operation and the
needs ofthe business. Through our benchmarking process we gained fantastic awareness
of how other companies had approached their MRO spend.It was clear that good work had
been done in this area,but generallythrough top down approaches. We found it was this
approach which had led to projects notdelivering the expected outcomes and itwas
importantthat we first carried out the groundwork first.
Organisational Benefits Achieved
The projectover delivered on all of its key targets.The operating costs were reduced by
£1m,the costof parts purchased came down by£1.7m and stock holding was reduced by
more than 75%. This at a time when, production has doubled. The neteffect of these
financial reductions is a decrease in the costof production of £34 per vehicle. (Please see
table and Appendix).
The savings have not
just been financial.
The number of parts
was reduced by more
than 90%,significantly
simplifying stock
holding and picking
complexity. On time
delivery has increased
from 67% to 96% and purchase of MRO parts via Procurement Card has been eliminated,
reducing the annual P Card expenditure by £5m and increasing the visibility of purchases.
Our decision to outsource to an external provider will ensure a number of additional benefits
as well as reducing the costs ofrunningthe service. We have alreadymoved one ofthe stores
off site, which has provided more space for manufacturing plant expansion. We are looking
to move all of the Midlands based stores to a single location, reducing costs further and
simplifying the process.Finally,our outsourcer alreadyhad an IT tool developed to facilitate
stock visibility and ordering, which eliminated the need for us to develop or buy our own
system.
In Summary
Jaguar Land Rover has been a UK manufacturing success storyover the lastfew years,
and projects such as these,with an attention to detail and a passion for improvement,are
what has made the difference.This project has truly met our Corporate Objective:
‘TO BE AGILE AND COST EFFECTIVE’
Summary of Benefits
Part numbers down from 88,000 to 8,000 (target 55,000)
Unit prices down by 10% or £1.2m pa ( target £600k)
Further price reductions of £515k
Service running cost savings £1m (target 400K)
Stock Holding down from £40m to £8.9m
On time delivery up from 67% to 96%
‘Thisprojecthas brought
JLR intothe 21st century
…………….. the feedback
fromour usersis that
storesservice have
improveddramatically”
Darren Kendal,MRO
Stores Manager
"There were many
obstaclestoovercome
alongthe way and itwas
onlybystrong team
work, and sheer
determinationthatthe
teamwere successful in
deliveringandexceeding
the original objectives
witha significant
businessbenefit.”
David Dyke, Director,
Global Material Planning
& Logistics
"The projectdeservesto
be recognisedforits
innovative andmulti-
disciplinary approach,
withgreatteamworkat
itscore, leadingonto
very tangible benefitsfor
the company."
Paul Cope,Board
Director of
Manufacturing
THE CIPS SUPPLY MANAGEMENT AWARDS
ENGINEERING MATERIAL RATIONALISATION
APPENDIX
Total Saving Achieved related to vehicle production:
Savings Area
Cost
impact
(£000's)
Unit Price Savings 1,200
Further Unit Price Savings 515
Reduction in Stock Holding Costs
(@9% pa) 2,799
Service Running Costs 1,000
Pcard Fee 100
Avoidance of Staff Recruitment 210
Total 5,824
Number of vehicles 170,000
Cost impact per vehicle £34
Project Team Work Stream:
Engineering Materials Rationalisation (MRO)
Board Review I. Harnett P. Cope
Quarterly Purchasing Director Manufacturing Director
Level 1
Work stream 1 Work stream 2 Work stream 3
MRO Part & Commodity MRO Single Provider MRO Spares
Work stream
DirectorOwners B. Davy D. Dyke P. Peterson
Monthly Purchasing Director Logistics Director Adv Manufacturing Director
Level 2
Work stream
Leaders& Teams R. Vaughan R. Osborne C. Holman
Weekly Procurement Manager Logistics Manager AME Manager
Level 3
Cross-functional team Cross-functional team Cross-functional team

More Related Content

What's hot

Ch 3 process strategies
Ch 3  process strategiesCh 3  process strategies
Ch 3 process strategiesShadina Shah
 
324335997 131-mcqs
324335997 131-mcqs324335997 131-mcqs
324335997 131-mcqsRakeshNimhan
 
Procurement cost reduction for auto electrical player
Procurement cost reduction for auto electrical playerProcurement cost reduction for auto electrical player
Procurement cost reduction for auto electrical playerAnirban Mazumdar
 
IRJET- Application of Quality Function Deployment (QFD) in Aluminium Pot Manu...
IRJET- Application of Quality Function Deployment (QFD) in Aluminium Pot Manu...IRJET- Application of Quality Function Deployment (QFD) in Aluminium Pot Manu...
IRJET- Application of Quality Function Deployment (QFD) in Aluminium Pot Manu...IRJET Journal
 
Global Supply Chain Management
Global Supply Chain ManagementGlobal Supply Chain Management
Global Supply Chain ManagementHammaduddin
 
Unit 5 strategic issues in logistics lscm (32 pages)logistics management
Unit 5 strategic issues in logistics   lscm (32 pages)logistics management Unit 5 strategic issues in logistics   lscm (32 pages)logistics management
Unit 5 strategic issues in logistics lscm (32 pages)logistics management Suzana Vaidya
 
World class manufacturing.PPT
World class manufacturing.PPTWorld class manufacturing.PPT
World class manufacturing.PPTConrad Sebego
 

What's hot (10)

Prashanth naik cv
Prashanth naik  cvPrashanth naik  cv
Prashanth naik cv
 
Ch 3 process strategies
Ch 3  process strategiesCh 3  process strategies
Ch 3 process strategies
 
TPG CV_update 04042016
TPG CV_update 04042016TPG CV_update 04042016
TPG CV_update 04042016
 
324335997 131-mcqs
324335997 131-mcqs324335997 131-mcqs
324335997 131-mcqs
 
Wcm
WcmWcm
Wcm
 
Procurement cost reduction for auto electrical player
Procurement cost reduction for auto electrical playerProcurement cost reduction for auto electrical player
Procurement cost reduction for auto electrical player
 
IRJET- Application of Quality Function Deployment (QFD) in Aluminium Pot Manu...
IRJET- Application of Quality Function Deployment (QFD) in Aluminium Pot Manu...IRJET- Application of Quality Function Deployment (QFD) in Aluminium Pot Manu...
IRJET- Application of Quality Function Deployment (QFD) in Aluminium Pot Manu...
 
Global Supply Chain Management
Global Supply Chain ManagementGlobal Supply Chain Management
Global Supply Chain Management
 
Unit 5 strategic issues in logistics lscm (32 pages)logistics management
Unit 5 strategic issues in logistics   lscm (32 pages)logistics management Unit 5 strategic issues in logistics   lscm (32 pages)logistics management
Unit 5 strategic issues in logistics lscm (32 pages)logistics management
 
World class manufacturing.PPT
World class manufacturing.PPTWorld class manufacturing.PPT
World class manufacturing.PPT
 

Viewers also liked (7)

ENCUESTA CONSUMO ARTES
ENCUESTA CONSUMO ARTESENCUESTA CONSUMO ARTES
ENCUESTA CONSUMO ARTES
 
Loc
LocLoc
Loc
 
Loc
LocLoc
Loc
 
Loc
LocLoc
Loc
 
Lidji Design Office Highlights
Lidji Design Office HighlightsLidji Design Office Highlights
Lidji Design Office Highlights
 
Qué cantan los niños de hoy
Qué cantan los niños de hoy Qué cantan los niños de hoy
Qué cantan los niños de hoy
 
Pacasmayo
PacasmayoPacasmayo
Pacasmayo
 

Similar to CIPS award Submission 2012 (Finalist) Version 1

Tightening The Chain – Supply Chain Cost Cutting Strategies
Tightening The Chain – Supply Chain Cost Cutting StrategiesTightening The Chain – Supply Chain Cost Cutting Strategies
Tightening The Chain – Supply Chain Cost Cutting StrategiesZubin Poonawalla
 
Smu mba om- solved assignments spring -2016
Smu mba  om- solved assignments spring -2016Smu mba  om- solved assignments spring -2016
Smu mba om- solved assignments spring -2016smumbahelp
 
What is MRO Integrated Supply_0915
What is MRO Integrated Supply_0915What is MRO Integrated Supply_0915
What is MRO Integrated Supply_0915missydecker
 
Procurement Processes in Automotive Manufacturing
Procurement Processes in Automotive ManufacturingProcurement Processes in Automotive Manufacturing
Procurement Processes in Automotive ManufacturingKevin Harmon-Smith
 
White Paper - Distribution Network Optimization
White Paper - Distribution Network OptimizationWhite Paper - Distribution Network Optimization
White Paper - Distribution Network OptimizationLen Pannett
 
Increase production through improved spare parts availability
Increase production through improved spare parts availabilityIncrease production through improved spare parts availability
Increase production through improved spare parts availabilityIMAFS
 
Bba501 & production and operations management
Bba501 & production and operations managementBba501 & production and operations management
Bba501 & production and operations managementsmumbahelp
 
Design of a generic value chain
Design of a generic value chainDesign of a generic value chain
Design of a generic value chainsijo23
 
Om0013 advanced production and operations management
Om0013   advanced production and operations managementOm0013   advanced production and operations management
Om0013 advanced production and operations managementsmumbahelp
 
Largest Electricity provider in the US- Case Study
Largest Electricity provider in the US- Case StudyLargest Electricity provider in the US- Case Study
Largest Electricity provider in the US- Case StudyHappiest Minds Technologies
 
Executive policy report
Executive policy report Executive policy report
Executive policy report NILAMH
 
Revolutionizing_the_downstream_supply_chain
Revolutionizing_the_downstream_supply_chainRevolutionizing_the_downstream_supply_chain
Revolutionizing_the_downstream_supply_chainDavid Evans
 
Revolutionizing_the_downstream_supply_chain
Revolutionizing_the_downstream_supply_chainRevolutionizing_the_downstream_supply_chain
Revolutionizing_the_downstream_supply_chainDavid Evans
 
Is your mro spare parts reduction program compliant with iso55000 rev 3
Is your mro spare parts reduction program compliant with iso55000 rev 3Is your mro spare parts reduction program compliant with iso55000 rev 3
Is your mro spare parts reduction program compliant with iso55000 rev 3David Thompson
 
MRO Spare Parts Improvement Programme Conforms to ISO55000
MRO Spare Parts Improvement Programme Conforms to ISO55000MRO Spare Parts Improvement Programme Conforms to ISO55000
MRO Spare Parts Improvement Programme Conforms to ISO55000David Thompson
 
RFP1. Project Initiation Phase The purpose of the RFP document.docx
RFP1. Project Initiation Phase The purpose of the RFP document.docxRFP1. Project Initiation Phase The purpose of the RFP document.docx
RFP1. Project Initiation Phase The purpose of the RFP document.docxhealdkathaleen
 
Horizon 2013 Driving Global Adoption to Procurement Technology - A Cargill Ap...
Horizon 2013 Driving Global Adoption to Procurement Technology - A Cargill Ap...Horizon 2013 Driving Global Adoption to Procurement Technology - A Cargill Ap...
Horizon 2013 Driving Global Adoption to Procurement Technology - A Cargill Ap...Zycus
 
ARC Forum Highlights RPM as an Enabler to Optimized Business Performance
ARC Forum Highlights RPM as an Enabler to Optimized Business PerformanceARC Forum Highlights RPM as an Enabler to Optimized Business Performance
ARC Forum Highlights RPM as an Enabler to Optimized Business PerformanceARC Advisory Group
 
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - National Finalists
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - National FinalistsLarsen & Toubro - Outthink 2017 (Strategy Case Competition) - National Finalists
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - National FinalistsAnupreet Choudhary
 
Giacomo Squintani, PTC presenation at Spare Parts 2013
Giacomo Squintani, PTC presenation at Spare Parts 2013Giacomo Squintani, PTC presenation at Spare Parts 2013
Giacomo Squintani, PTC presenation at Spare Parts 2013Copperberg
 

Similar to CIPS award Submission 2012 (Finalist) Version 1 (20)

Tightening The Chain – Supply Chain Cost Cutting Strategies
Tightening The Chain – Supply Chain Cost Cutting StrategiesTightening The Chain – Supply Chain Cost Cutting Strategies
Tightening The Chain – Supply Chain Cost Cutting Strategies
 
Smu mba om- solved assignments spring -2016
Smu mba  om- solved assignments spring -2016Smu mba  om- solved assignments spring -2016
Smu mba om- solved assignments spring -2016
 
What is MRO Integrated Supply_0915
What is MRO Integrated Supply_0915What is MRO Integrated Supply_0915
What is MRO Integrated Supply_0915
 
Procurement Processes in Automotive Manufacturing
Procurement Processes in Automotive ManufacturingProcurement Processes in Automotive Manufacturing
Procurement Processes in Automotive Manufacturing
 
White Paper - Distribution Network Optimization
White Paper - Distribution Network OptimizationWhite Paper - Distribution Network Optimization
White Paper - Distribution Network Optimization
 
Increase production through improved spare parts availability
Increase production through improved spare parts availabilityIncrease production through improved spare parts availability
Increase production through improved spare parts availability
 
Bba501 & production and operations management
Bba501 & production and operations managementBba501 & production and operations management
Bba501 & production and operations management
 
Design of a generic value chain
Design of a generic value chainDesign of a generic value chain
Design of a generic value chain
 
Om0013 advanced production and operations management
Om0013   advanced production and operations managementOm0013   advanced production and operations management
Om0013 advanced production and operations management
 
Largest Electricity provider in the US- Case Study
Largest Electricity provider in the US- Case StudyLargest Electricity provider in the US- Case Study
Largest Electricity provider in the US- Case Study
 
Executive policy report
Executive policy report Executive policy report
Executive policy report
 
Revolutionizing_the_downstream_supply_chain
Revolutionizing_the_downstream_supply_chainRevolutionizing_the_downstream_supply_chain
Revolutionizing_the_downstream_supply_chain
 
Revolutionizing_the_downstream_supply_chain
Revolutionizing_the_downstream_supply_chainRevolutionizing_the_downstream_supply_chain
Revolutionizing_the_downstream_supply_chain
 
Is your mro spare parts reduction program compliant with iso55000 rev 3
Is your mro spare parts reduction program compliant with iso55000 rev 3Is your mro spare parts reduction program compliant with iso55000 rev 3
Is your mro spare parts reduction program compliant with iso55000 rev 3
 
MRO Spare Parts Improvement Programme Conforms to ISO55000
MRO Spare Parts Improvement Programme Conforms to ISO55000MRO Spare Parts Improvement Programme Conforms to ISO55000
MRO Spare Parts Improvement Programme Conforms to ISO55000
 
RFP1. Project Initiation Phase The purpose of the RFP document.docx
RFP1. Project Initiation Phase The purpose of the RFP document.docxRFP1. Project Initiation Phase The purpose of the RFP document.docx
RFP1. Project Initiation Phase The purpose of the RFP document.docx
 
Horizon 2013 Driving Global Adoption to Procurement Technology - A Cargill Ap...
Horizon 2013 Driving Global Adoption to Procurement Technology - A Cargill Ap...Horizon 2013 Driving Global Adoption to Procurement Technology - A Cargill Ap...
Horizon 2013 Driving Global Adoption to Procurement Technology - A Cargill Ap...
 
ARC Forum Highlights RPM as an Enabler to Optimized Business Performance
ARC Forum Highlights RPM as an Enabler to Optimized Business PerformanceARC Forum Highlights RPM as an Enabler to Optimized Business Performance
ARC Forum Highlights RPM as an Enabler to Optimized Business Performance
 
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - National Finalists
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - National FinalistsLarsen & Toubro - Outthink 2017 (Strategy Case Competition) - National Finalists
Larsen & Toubro - Outthink 2017 (Strategy Case Competition) - National Finalists
 
Giacomo Squintani, PTC presenation at Spare Parts 2013
Giacomo Squintani, PTC presenation at Spare Parts 2013Giacomo Squintani, PTC presenation at Spare Parts 2013
Giacomo Squintani, PTC presenation at Spare Parts 2013
 

CIPS award Submission 2012 (Finalist) Version 1

  • 1. The CIPS Supply Management Awards 2012 ENGINEERING MATERIAL RATIONALISATION THE CIPS SUPPLY MANAGEMENT AWARDS ENGINEERING MATERIAL RATIONALISATION
  • 2. CATEGORY – CROSS FUNCTIONAL TEAM PROJECT TITLE – Engineering Materials Rationalisation (MRO) ORGANISATION – Jaguar Land Rover Challenges Faced When Jaguar Land Rover (JLR) separated from Ford it was left with four manufacturing sites,each with its own engineering material stores (MRO). These were run independently with no shared visibilityof stock, part number structure,facilities for stock sharing,or defined processes for managing the stores,for example, anyone on the manufacturing floor could raise a new part number.The implications ofthese ways of working were:  MRO stock availabilityat each site was <50%, yet while one site was out of stock on a particular item,another site was overstocked  JLR had 23 part numbers for AA batteries and more than 300 different types of hammers. There were a total of 88,000 MRO part numbers,with £40million ofstock for an annual spend of£12m,against a supplier base of73.For comparison,the total number ofparts used to make all JLR models was less than 50,000.  The shiftof responsibilityfor these sites from Ford to JLR increased the administration workload,requiring JLR to increase the team from 2 to 9 people with no extra funding.  Significant‘urgent’ spend on ProcurementCard which was uncontrolled and unleveraged. Aims & Objectives A cross functional team was formed and a Project Charter drafted, with the following aims: 1) Reduce inventory by 20% 2) Reduce the number ofparts by 20% 3) Reduce the purchase price of MRO materials by5% 4) Implementstock classification and appropriate stock policies 5) Reduce ProcurementCard spend on MRO Parts Planning and Execution From the offset it was clear that the projectwould only succeed if Planning,Manufacturing and Purchasing worked closely together. There were some significantorganisational difficulties thatrequired addressing organisationally,in order for the projectto be successful. The first step was to engage the three Senior Directors responsible for these areas,and briefthem on the challenge and the objectives and secure their sponsorship.A full project plan was then developed and used to track progress.  Thousands ofhourly& staff users of the service across all sites,resulting in a high business impactacross a diverse range of customers.  Functionallythe procurement,stores management& machine spares elements ofthe existing service sat across differentdepartments/owners.  If successful trade-offs between cost,service & space would be required. Such trade-offs would require understanding & involvementof senior JLR members. The organisation solution for the projectwas a key reason thatthe procurementlead for the projectwas able to able to work successfullyto conclusion. The first part of this was to splitactivity across 3 work streams,where each work stream had a functional owner with mutual dependencies upon other functions to deliver the content of the work stream. (Please see Appendix) THE CIPS SUPPLY MANAGEMENT AWARDS ENGINEERING MATERIAL RATIONALISATION
  • 3. Key steps included:- Benchmarking –The team visited a number of similar companies and quicklyrealised thatour key internal processes needed to be cleaned up as a priority. An interesting finding from our benchmarking was thata high percentage ofthe benchmarked companies had outsourced their stores and mosthad achieved significantgains.Unfortunatelya few had outsourced without firstcompleting their internal clean-up and the outcomes were notpositive. Our team took this on board as a key learning.  MRO Part Clean Up & CommodityRationalisation  MRO Single Provider  MRO Spares rationalisation. Stock Analysis – This painstaking task required detailed analysis ofall 88,000 parts including stock levels,cost,and stock availability at each site. Each part was classified with regards to its criticality and availability. The strategy for each part was based on this classification. The second partof the stock analysis was to clean the parts database,with the aim of reducing the number ofparts in stock. Initial internal efforts enabled the number ofparts to be reduced to 65,000; however the team felt there was further opportunity We worked with suppliers and achieved a dramatic reduction to 8,000 parts numbers in total, a reduction in excess of 90%. Prepare for Tender – The cleaned up stock profile was divided into 23 bundles ofitems and each was separatelytendered to the external market. Given that JLR’s volumes were significantlylower than those of the combined Ford Motor Company; our best hope was to maintain current pricing. However, through the tender process we reduced prices by 10% and delivered £1m of annualised savings. The number of suppliers was reduced or changed from 73 to 36; a best in class approach based on our benchmarking. Define Stock Share Mechanisms – Our aim was to implement a process where stock held in one store was available to all sites.To achieve this we needed a common part number coding.We brought together the MRO managers and agreed new partnumbers for the 65,000 part numbers we had after the initial stock clean up. The next stage was to make the stock visible across all the stores.The only way to achieve this was to investin a new IT system.A decision on this was delayed until later in the project. Introduce Governance and Control Gatekeepers – The continued success ofthe projectwas dependenton strong governance to control the creation of new part numbers and to ensure communication between the sites. The JLR MRO managers were given the final decision on all new submitted parts for the stores to ensure tight control was maintained throughoutthe projectand beyond. There is now a weekly Gatekeeper Meeting where Manufacturing, Stores and Procurement mustagree the purchase ofany new MRO parts. Material Advantages – This projectdid not start as an outsourcing plan,butit was clear from our benchmarking thatthis was a further cost-reducing option ifmanaged correctly.Once our internal procedures were in place we were in a position to be able to confidently compare quotes from the external marketand a decision was taken to place the services with an external provider. Included in the requirements was the IT system which would allow cross site visibilityto satisfyour immediate needs,as well as to be compatible with the upcoming JLR global SAP implementation. Innovation and Creativity The key to initiating this projectwas upside down Procurement,in other words looking atProcurement priorities in a different way. Traditionallyprocurementdid notactively manage MRO as it was a (relatively) small spend,however,MRO stores did have a big impacton service levels into the site and a disproportionallynegative impacton the perception of Procurement within JLR. When someone can go and buy a hammer cheaper from B&Qthan within JLR stores,it’s Procurement’s name that is tarnished! Classification Policy Non critical spares Minimal Centralised stock holding Consumable Centralised stock holding Critical specific spares Hold on each site Industry standard spares Nil stock holding THE CIPS SUPPLY MANAGEMENT AWARDS ENGINEERING MATERIAL RATIONALISATION
  • 4. The projectchallenged the corporate culture as it engaged three members ofthe Executive ManagementTeam and conveyed the message thatthis was an importantand supported project. This project provides a great example of how Procurementcan extend its reach and provide benefits beyond cost. In many cases the MRO stores are the only contact staff has with Procurement, and the new process means theyno longer feel the need to store stock in their bottom desk drawers! Best Practice The key elementofthis process was thatwe carried out the nitty gritty work to ensure we understood the situation before we considered outsourcing the services. This level of granularityis not common in today’s business world butwas absolutelycrucial to the successes achieved as itprovided us with a clear insight into the MRO operation and the needs ofthe business. Through our benchmarking process we gained fantastic awareness of how other companies had approached their MRO spend.It was clear that good work had been done in this area,but generallythrough top down approaches. We found it was this approach which had led to projects notdelivering the expected outcomes and itwas importantthat we first carried out the groundwork first. Organisational Benefits Achieved The projectover delivered on all of its key targets.The operating costs were reduced by £1m,the costof parts purchased came down by£1.7m and stock holding was reduced by more than 75%. This at a time when, production has doubled. The neteffect of these financial reductions is a decrease in the costof production of £34 per vehicle. (Please see table and Appendix). The savings have not just been financial. The number of parts was reduced by more than 90%,significantly simplifying stock holding and picking complexity. On time delivery has increased from 67% to 96% and purchase of MRO parts via Procurement Card has been eliminated, reducing the annual P Card expenditure by £5m and increasing the visibility of purchases. Our decision to outsource to an external provider will ensure a number of additional benefits as well as reducing the costs ofrunningthe service. We have alreadymoved one ofthe stores off site, which has provided more space for manufacturing plant expansion. We are looking to move all of the Midlands based stores to a single location, reducing costs further and simplifying the process.Finally,our outsourcer alreadyhad an IT tool developed to facilitate stock visibility and ordering, which eliminated the need for us to develop or buy our own system. In Summary Jaguar Land Rover has been a UK manufacturing success storyover the lastfew years, and projects such as these,with an attention to detail and a passion for improvement,are what has made the difference.This project has truly met our Corporate Objective: ‘TO BE AGILE AND COST EFFECTIVE’ Summary of Benefits Part numbers down from 88,000 to 8,000 (target 55,000) Unit prices down by 10% or £1.2m pa ( target £600k) Further price reductions of £515k Service running cost savings £1m (target 400K) Stock Holding down from £40m to £8.9m On time delivery up from 67% to 96% ‘Thisprojecthas brought JLR intothe 21st century …………….. the feedback fromour usersis that storesservice have improveddramatically” Darren Kendal,MRO Stores Manager "There were many obstaclestoovercome alongthe way and itwas onlybystrong team work, and sheer determinationthatthe teamwere successful in deliveringandexceeding the original objectives witha significant businessbenefit.” David Dyke, Director, Global Material Planning & Logistics "The projectdeservesto be recognisedforits innovative andmulti- disciplinary approach, withgreatteamworkat itscore, leadingonto very tangible benefitsfor the company." Paul Cope,Board Director of Manufacturing THE CIPS SUPPLY MANAGEMENT AWARDS ENGINEERING MATERIAL RATIONALISATION
  • 5. APPENDIX Total Saving Achieved related to vehicle production: Savings Area Cost impact (£000's) Unit Price Savings 1,200 Further Unit Price Savings 515 Reduction in Stock Holding Costs (@9% pa) 2,799 Service Running Costs 1,000 Pcard Fee 100 Avoidance of Staff Recruitment 210 Total 5,824 Number of vehicles 170,000 Cost impact per vehicle £34 Project Team Work Stream: Engineering Materials Rationalisation (MRO) Board Review I. Harnett P. Cope Quarterly Purchasing Director Manufacturing Director Level 1 Work stream 1 Work stream 2 Work stream 3 MRO Part & Commodity MRO Single Provider MRO Spares Work stream DirectorOwners B. Davy D. Dyke P. Peterson Monthly Purchasing Director Logistics Director Adv Manufacturing Director Level 2 Work stream Leaders& Teams R. Vaughan R. Osborne C. Holman Weekly Procurement Manager Logistics Manager AME Manager Level 3 Cross-functional team Cross-functional team Cross-functional team