Catering Information Sheet No 10HSE information sheet
Ventilation in catering kitchens
Introduction
This information sheet was produced by the Hospitality
and Catering Industry Liaison Forum, which has
members from trade and professional associations,
unions and enforcement authorities. Members’
associations are free to reproduce and distribute this
guidance to catering establishments. The guidance is
issued by the Health and Safety Executive.
The guidance is aimed at employers in the catering and
hospitality industry and gives guidance on ventilation
requirements for kitchens. It will help employers assess
whether existing ventilation is adequate. It will also
be useful for planning the ventilation specification for
new or refurbished kitchens. The guidance advises on
management, as well as design and performance issues.
While much of the information concerns gas appliances,
those with solid fuel appliances, such as charcoal
ovens and grills, will also find it useful. Owners of such
equipment should be aware that because charcoal
ovens cannot be switched off, adequate ventilation is
necessary, even when the oven is covered and cooling
down overnight. This will prevent a build-up of carbon
monoxide that could affect neighbouring properties.
What the law says
The Workplace (Health, Safety and Welfare)
Regulations 1992
These Regulations require that employers provide
effective and suitable ventilation in every enclosed
workplace. This includes kitchens, which need
ventilation to create a safe and comfortable working
environment. Catering and cooking can produce
significant amounts of fumes and vapours, as well as
large amounts of heat. Mechanical extraction, via a
canopy hood installed over the cooking appliances,
can remove these fumes and vapour and discharge
them to a safe location.
Gas Safety (Installation and Use)
Regulations 1998
These Regulations impose additional requirements
and apply to gas appliances found in most catering
premises. Some gas appliances will be a type (known
as type B) that require a flue to comply with the
Regulations. Where extraction serves that purpose,
it is considered a flue and requires an appropriate
interlocking system connecting the airflow to the gas
supply.
Gas safety in catering is the subject of Catering
Information Sheet 23. However, in considering
general ventilation requirements for kitchens it is
important to consider the impact of such ventilation
on gas appliances covered by these regulations. It
is particularly important to ensure there is adequate
make-up air for gas-fired appliances, the lack of
which can lead to incomplete combustion and an
accumulation of combustion products, such as
carbon monoxide.
Work on gas appliances should be carried out by a
Gas Safe engineer.
You can find further details in Safety in the installation
and use of gas systems and appliances. Gas Safety
(Installation and Use) Regulations 1998. Approved
Code of Practice and guidance.
The Health and Safety at Work etc Act 1974
The Act places duties on anyone in control of
premises who makes them available as a place of
work for others to take reasonable measures to
ensure, so far as is reasonably practicable, that the
premises, plant and equipment are safe and without
risks to health.
2 of 4 pages
Health and Safety
Executive
Effective kitchen ventilation systems
The objectives of an effective kitchen ventilation
system are to:
remove cooking fumes at source, ie at the appliance;■■
remove excess hot air and bring in cool, clean■■
air, so the working environment is comfortable.
Inadequate ventilation can cause stress,
contributing to unsafe systems of work and high
staff turnover;
make sure that the air movement in the kitchen■■
does not cause discomfort, eg from strong
draughts;
provide enough air for complete combustion at■■
fired appliances, and prevent the risk of carbon
monoxide accumulating;
be easy to clean, avoiding build-up of fat residues■■
and blocked air inlets, which lead to loss of
efficiency and increased risk of fire;
be quiet and vibration free.■■
The ventilation system design needs to take
account of the:
cooking load;■■
amount of cooking equipment used;■■
layout and shape of the kitchen;■■
number of staff;■■
need for easy cleaning and maintenance.■■
The following guidance outlines effective design
features. Assess existing and planned systems to
make sure they meet these ventilation objectives.
Canopies
Design
The canopy hood needs to be designed and operated
to ensure effective removal of cooking fumes. It needs
to be a suitable size and have enough extraction to
minimise fume spillage into the kitchen. There should be
a canopy hood for every appliance and other sources
generating fumes and heat. The canopy hood should
be as close as possible to the source, taking into
account the work requirements.
The airflow into the canopy should be uniform and
constant, and meet the appropriate design flow for the
appliances and room ventilation rate. Canopies and
ductwork need to be constructed from non-combustible
material and made so they discourage accumulations
of dirt or grease, and condensation. There should be
suitable access to the ductwork, to allow regular cleaning
to prevent accumulation of fat etc. Grease filters need to
be readily removable for cleaning/replacement.
Performance
The extraction rate is best calculated from the
information supplied with the appliances. It should also
take account of air change rates required for kitchens.
Where canopies are not used, eg where extraction is
through ventilated ceilings, consult a competent heating
and ventilation engineer to calculate the appropriate
ventilation rates.
The design should avoid draughts where the kitchen is
subdivided (eg wash-ups, vegetable preparations).
Maintenance
Mechanical ventilation systems should be maintained
in efficient working order in accordance with the
manufacturer’s/installer’s instructions.
Replacement air
The ventilation system design should take into account
the need to replace extracted air. Mechanical and/or
natural means can provide make-up air, but it should
be fresh and unadulterated from the outside.
In smaller kitchens, there may be sufficient
replacement air drawn in naturally via ventilation grilles
in walls, doors or windows.
Where air is drawn in naturally, some means of control
over pest entry is usually needed. A fine mesh grille
will restrict the ventilation, and a larger grille area
can compensate. However, for larger installations, a
mechanical system using a fan and filter is more suitable.
The ‘clean air’ should not be taken from ‘dirty’ areas,
eg waste storage, smoking areas etc. The make-up air
should not impair the performance of flues serving gas
appliances.
Cooling air
Balancing incoming cool air and extracted hot air
effectively should help prevent the kitchen becoming
too hot. For mechanical make-up air systems, direct
the cooler air towards hot work positions. Otherwise,
consider air conditioning or fixed fans that do not
affect the efficiency of fume extraction.
Local freestanding fans may cause air currents or
turbulence, affecting the efficiency of fume extraction.
They are not normally an effective way to provide make-
up air. They may also introduce other hazards, such as
tripping and electric shock hazards from the trailing cable.
3 of 4 pages
Health and Safety
Executive
Discharge
High-level discharge of extracted air is often needed to
prevent nuisance to neighbouring properties. Avoid rain
caps and other devices that impede upward vertical
velocity. Never use devices that direct the discharge
downward as they encourage down draught and
re-entry of fumes into the building. Fume discharge
should also be away from wet cooling towers.
New ventilation systems
The caterer
The caterer will need to provide detailed information
for the competent advisor, designer and installer,
including the following information:
maximum demands likely to be placed on the■■
ventilation (eg to cope with peaks of activity);
amount and type of kitchen equipment;■■
the menu;■■
number of meals; and■■
number of staff.■■
Advisors, suppliers and installers should be
competent and have knowledge of industry practice
and relevant health and safety guidance and
legislation.
The caterer should consult with the safety or
employee representatives in good time about any
significant changes.
The caterer should keep records of design
criteria, commissioning performance, maintenance
requirements, and of tests and inspections. These
enable maintenance, modification, and testing against
the original specification.
The building owner or manager
The owner or manager of the building may provide
facilities such as equipment and ventilation. In these
cases, they should follow the advice here. Providing
adequate ventilation will require the owner to obtain
information on probable kitchen usage from the caterer.
The designer/design team
The ‘design team’ means the various interested parties
(owner, caterer, designer, supplier and installer). They
need to discuss their respective information needs and
what information each should supply.
The ventilation design engineer will need to take into
account:
The presence of gas appliances subject to the■■
Gas Safety (Installation and Use) Regulations
1998. In particular, the requirement for an
adequate supply of air for combustion and flueing
arrangements.
kitchen usage information from the caterer;■■
equipment information from the caterer or■■
supplier, eg cleaning requirements, the amount
of air required for complete combustion, and the
performance of the existing installation;
the requirements or specifications for the air■■
cleaning system, eg for grease removal at the
canopy and also before final discharge outside;
the limitations of the building, eg the available■■
room may influence the sites and routes for air
inlets or discharges;
food hygiene requirements, eg identify a suitable■■
source for clean make-up air; prevent pest entry;
avoid grease accumulation and ensure easy
cleaning of the system;
heat control.■■
Assess the need for interlocking the ventilation power
supply to the gas supply and take appropriate action.
This decision should be based on a competent
persons’ assessment of the risks associated with the
use of the gas appliance.
Further guidance for designers is available from
industry produced technical guidance, for example
guidance from The Chartered Institution of Building
Services Engineers (CIBSE) and The Heating and
Ventilation Contractors’ Association (HVCA) (see
‘Further information’).
The equipment installer
The equipment should be installed by a competent
person. The equipment installer needs to know the
design performance and capacity of the ventilation
system, so they can ensure adequate ventilation.
For existing installations where data is absent or
unavailable, the installer should recommission the
system of extraction and make-up air, and produce a
report detailing its performance. A competent heating
and ventilation specialist can provide this information.
Gas-fired appliances should be installed by a Gas
Safe engineer.
4 of 4 pages
Health and Safety
Executive
Published by the Health and Safety Executive 				 CAIS10(rev2)			 07/12
Before installing a gas-fired appliance, the gas installer
needs to know the specific air inlet requirements.
Manufacturers of new catering appliances have to
provide this under the Gas Appliances Directive. The
gas installer can then check that these requirements
are met by the ventilation system provided, taking into
account other existing appliances.
Information on the ventilation requirements of the
existing appliances could be obtained from the
caterer’s records or from the manufacturers.
Further information
Gas safety in catering and hospitality Catering
Information Sheet CAIS23(rev1) HSE Books 2007
www.hse.gov.uk/pubns/cais23.pdf
Health and safety made simple: The basics for your
business www.hse.gov.uk/simple-health-safety/index.htm
Safety in the installation and use of gas systems
and appliances. Gas Safety (Installation and Use)
Regulations 1998. Approved Code of Practice and
guidance L56 (Third edition) HSE Books 2011
ISBN 978 0 7176 6419 1
www.hse.gov.uk/pubns/books/l56.htm
HSE catering and hospitality web pages:
www.hse.gov.uk/catering/index.htm
For more information about health and safety, or to report
inconsistencies or inaccuracies in this guidance, visit
www.hse.gov.uk/. You can view HSE guidance online
and order priced publications from the website. HSE
priced publications are also available from bookshops.
BS 6173: 2009 Specification for installation of gas
fired catering appliances for use in all types of catering
establishments British Standards Institution 2009.
British Standards can be obtained in PDF or hard copy
formats from BSI: http://shop.bsigroup.com or by
contacting BSI Customer Services for hard copies only
Tel: 020 8996 9001 email: cservices@bsigroup.com
Specification for kitchen ventilation systems DW172
Building and Engineering Services Association.
Available from B&ES Publications, Old Mansion House,
Eamont Bridge, Penrith CA10 2BX Tel: 01768 860405
e-mail: b-espublications@welplan.co.uk
The Chartered Institution of Building Services
Engineers (CIBSE) is the professional body for building
services engineers and provides its members and
the public with information and education services,
222 Balham High Road, London, SW12 9BS
Tel: 020 8675 5211 www.cibse.org.
This document contains notes on good practice
which are not compulsory but which you may
find helpful in considering what you need to do.
This document is available at www.hse.gov.uk/pubns/
cais10.htm.
© Crown copyright If you wish to reuse this
information visit www.hse.gov.uk/copyright.htm for
details. First published 07/12.

More Related Content

What's hot

HVAC Atlanta Checklist
HVAC Atlanta ChecklistHVAC Atlanta Checklist
HVAC Atlanta ChecklistDan Jape
 
The Money-Saving Survival Guide: AC, Heating, and Air Quality
The Money-Saving Survival Guide: AC, Heating, and Air QualityThe Money-Saving Survival Guide: AC, Heating, and Air Quality
The Money-Saving Survival Guide: AC, Heating, and Air QualityJohnMooreSvcs
 
Control system for HVAC
Control system for HVACControl system for HVAC
Control system for HVACfarooq husain
 
Energy Saving Report-NEI Jaipur
Energy Saving Report-NEI JaipurEnergy Saving Report-NEI Jaipur
Energy Saving Report-NEI JaipurChiraag Naithani
 
Air circulation maintenance industry for sterile and non sterile area
Air circulation maintenance  industry for sterile and non sterile areaAir circulation maintenance  industry for sterile and non sterile area
Air circulation maintenance industry for sterile and non sterile areaGNIPST
 
Residential hvac system
Residential hvac systemResidential hvac system
Residential hvac systemJoy Clark
 
Alternate ventilation in hospitals
Alternate ventilation in hospitalsAlternate ventilation in hospitals
Alternate ventilation in hospitalsajayhvaidya
 
HVAC SYSTEM IN PHARMACEUTICAL INDUSTRY
HVAC SYSTEM IN PHARMACEUTICAL INDUSTRYHVAC SYSTEM IN PHARMACEUTICAL INDUSTRY
HVAC SYSTEM IN PHARMACEUTICAL INDUSTRYNamdeo Shinde
 
Indoor and outdoor air quality in hospital environment
Indoor and outdoor air quality in hospital environmentIndoor and outdoor air quality in hospital environment
Indoor and outdoor air quality in hospital environmentAlexander Decker
 
ProService indoor air quality for Hospitals & Healthcare
ProService indoor air quality for Hospitals & HealthcareProService indoor air quality for Hospitals & Healthcare
ProService indoor air quality for Hospitals & HealthcareMohamed Ramadan
 
Important of clean room and hvac system
Important of clean room and  hvac systemImportant of clean room and  hvac system
Important of clean room and hvac systemRonak654321
 

What's hot (18)

Egonomics_and_work_place_engineering
Egonomics_and_work_place_engineeringEgonomics_and_work_place_engineering
Egonomics_and_work_place_engineering
 
HVAC Atlanta Checklist
HVAC Atlanta ChecklistHVAC Atlanta Checklist
HVAC Atlanta Checklist
 
Pharmaceutical hvac system by adnan et.al
Pharmaceutical hvac system by adnan et.alPharmaceutical hvac system by adnan et.al
Pharmaceutical hvac system by adnan et.al
 
The Money-Saving Survival Guide: AC, Heating, and Air Quality
The Money-Saving Survival Guide: AC, Heating, and Air QualityThe Money-Saving Survival Guide: AC, Heating, and Air Quality
The Money-Saving Survival Guide: AC, Heating, and Air Quality
 
Control system for HVAC
Control system for HVACControl system for HVAC
Control system for HVAC
 
Presentation on HVAC
Presentation on HVAC Presentation on HVAC
Presentation on HVAC
 
Energy Saving Report-NEI Jaipur
Energy Saving Report-NEI JaipurEnergy Saving Report-NEI Jaipur
Energy Saving Report-NEI Jaipur
 
Air circulation maintenance industry for sterile and non sterile area
Air circulation maintenance  industry for sterile and non sterile areaAir circulation maintenance  industry for sterile and non sterile area
Air circulation maintenance industry for sterile and non sterile area
 
HVAC SYSTEM by Pratik
HVAC SYSTEM by PratikHVAC SYSTEM by Pratik
HVAC SYSTEM by Pratik
 
Residential hvac system
Residential hvac systemResidential hvac system
Residential hvac system
 
Alternate ventilation in hospitals
Alternate ventilation in hospitalsAlternate ventilation in hospitals
Alternate ventilation in hospitals
 
HVAC SYSTEM IN PHARMACEUTICAL INDUSTRY
HVAC SYSTEM IN PHARMACEUTICAL INDUSTRYHVAC SYSTEM IN PHARMACEUTICAL INDUSTRY
HVAC SYSTEM IN PHARMACEUTICAL INDUSTRY
 
Importance of HVAC System
Importance of HVAC SystemImportance of HVAC System
Importance of HVAC System
 
Clearafin ppt copy
Clearafin ppt copyClearafin ppt copy
Clearafin ppt copy
 
Inex innovation
Inex innovationInex innovation
Inex innovation
 
Indoor and outdoor air quality in hospital environment
Indoor and outdoor air quality in hospital environmentIndoor and outdoor air quality in hospital environment
Indoor and outdoor air quality in hospital environment
 
ProService indoor air quality for Hospitals & Healthcare
ProService indoor air quality for Hospitals & HealthcareProService indoor air quality for Hospitals & Healthcare
ProService indoor air quality for Hospitals & Healthcare
 
Important of clean room and hvac system
Important of clean room and  hvac systemImportant of clean room and  hvac system
Important of clean room and hvac system
 

Similar to DW172

Pathway Cleaning - TR19 regulations - Ductwork Clean - Extraction Clean
Pathway Cleaning - TR19 regulations - Ductwork Clean - Extraction Clean Pathway Cleaning - TR19 regulations - Ductwork Clean - Extraction Clean
Pathway Cleaning - TR19 regulations - Ductwork Clean - Extraction Clean The Pathway Group
 
MECHANICAL VENTILATION commercial kitchen.pptx
MECHANICAL VENTILATION commercial kitchen.pptxMECHANICAL VENTILATION commercial kitchen.pptx
MECHANICAL VENTILATION commercial kitchen.pptxFizaNaaz8
 
Natural ventilation, Artificial ventilation, Air conditioning
Natural ventilation, Artificial ventilation, Air conditioningNatural ventilation, Artificial ventilation, Air conditioning
Natural ventilation, Artificial ventilation, Air conditioningSusmitaMulayPatil
 
kitchen.services-The Only HVAC Tune-Up Checklist You Need.pdf
kitchen.services-The Only HVAC Tune-Up Checklist You Need.pdfkitchen.services-The Only HVAC Tune-Up Checklist You Need.pdf
kitchen.services-The Only HVAC Tune-Up Checklist You Need.pdfAhmad Affan
 
TR19 Regulations - B&ES Guide to Good Practice - London & Midland Cleaning C...
TR19 Regulations - B&ES Guide to Good Practice -  London & Midland Cleaning C...TR19 Regulations - B&ES Guide to Good Practice -  London & Midland Cleaning C...
TR19 Regulations - B&ES Guide to Good Practice - London & Midland Cleaning C...The Pathway Group
 
alturascontractors.com-Ways to Extend the Life of an HVAC System.pdf
alturascontractors.com-Ways to Extend the Life of an HVAC System.pdfalturascontractors.com-Ways to Extend the Life of an HVAC System.pdf
alturascontractors.com-Ways to Extend the Life of an HVAC System.pdfAhmad Affan
 
Building services.pptx
Building services.pptxBuilding services.pptx
Building services.pptxpriyanka415514
 
HVAC presentation for masters in architecture
HVAC presentation for masters in architectureHVAC presentation for masters in architecture
HVAC presentation for masters in architecturegamertagore1999
 
What is done during hvac maintenance
What is done during hvac maintenanceWhat is done during hvac maintenance
What is done during hvac maintenanceangelinarobert1
 
VENTILATION.pdf
VENTILATION.pdfVENTILATION.pdf
VENTILATION.pdfKishAgrwa1
 
Laboratory design, safety and management
Laboratory design, safety and managementLaboratory design, safety and management
Laboratory design, safety and managementponnala saikumar
 
Mechanical systems of building (1)
Mechanical systems of building (1)Mechanical systems of building (1)
Mechanical systems of building (1)Muhammad Muhyuddin
 
Commercial HVAC System Maintenance Tips.pdf
Commercial HVAC System Maintenance Tips.pdfCommercial HVAC System Maintenance Tips.pdf
Commercial HVAC System Maintenance Tips.pdfAhmad Affan
 

Similar to DW172 (20)

Chap 43
Chap 43Chap 43
Chap 43
 
Pathway Cleaning - TR19 regulations - Ductwork Clean - Extraction Clean
Pathway Cleaning - TR19 regulations - Ductwork Clean - Extraction Clean Pathway Cleaning - TR19 regulations - Ductwork Clean - Extraction Clean
Pathway Cleaning - TR19 regulations - Ductwork Clean - Extraction Clean
 
MECHANICAL VENTILATION commercial kitchen.pptx
MECHANICAL VENTILATION commercial kitchen.pptxMECHANICAL VENTILATION commercial kitchen.pptx
MECHANICAL VENTILATION commercial kitchen.pptx
 
Natural ventilation, Artificial ventilation, Air conditioning
Natural ventilation, Artificial ventilation, Air conditioningNatural ventilation, Artificial ventilation, Air conditioning
Natural ventilation, Artificial ventilation, Air conditioning
 
kitchen.services-The Only HVAC Tune-Up Checklist You Need.pdf
kitchen.services-The Only HVAC Tune-Up Checklist You Need.pdfkitchen.services-The Only HVAC Tune-Up Checklist You Need.pdf
kitchen.services-The Only HVAC Tune-Up Checklist You Need.pdf
 
TR19 Regulations - B&ES Guide to Good Practice - London & Midland Cleaning C...
TR19 Regulations - B&ES Guide to Good Practice -  London & Midland Cleaning C...TR19 Regulations - B&ES Guide to Good Practice -  London & Midland Cleaning C...
TR19 Regulations - B&ES Guide to Good Practice - London & Midland Cleaning C...
 
alturascontractors.com-Ways to Extend the Life of an HVAC System.pdf
alturascontractors.com-Ways to Extend the Life of an HVAC System.pdfalturascontractors.com-Ways to Extend the Life of an HVAC System.pdf
alturascontractors.com-Ways to Extend the Life of an HVAC System.pdf
 
Building services.pptx
Building services.pptxBuilding services.pptx
Building services.pptx
 
Point 2.pptx
Point 2.pptxPoint 2.pptx
Point 2.pptx
 
HVAC presentation for masters in architecture
HVAC presentation for masters in architectureHVAC presentation for masters in architecture
HVAC presentation for masters in architecture
 
What is done during hvac maintenance
What is done during hvac maintenanceWhat is done during hvac maintenance
What is done during hvac maintenance
 
VENTILATION.pdf
VENTILATION.pdfVENTILATION.pdf
VENTILATION.pdf
 
Air washer
Air washerAir washer
Air washer
 
EnviroGroupBrochure
EnviroGroupBrochureEnviroGroupBrochure
EnviroGroupBrochure
 
Laboratory design, safety and management
Laboratory design, safety and managementLaboratory design, safety and management
Laboratory design, safety and management
 
Mechanical systems of building (1)
Mechanical systems of building (1)Mechanical systems of building (1)
Mechanical systems of building (1)
 
25985 (1).pdf
25985 (1).pdf25985 (1).pdf
25985 (1).pdf
 
Techfest
TechfestTechfest
Techfest
 
Forced Draft Ventilation
Forced Draft VentilationForced Draft Ventilation
Forced Draft Ventilation
 
Commercial HVAC System Maintenance Tips.pdf
Commercial HVAC System Maintenance Tips.pdfCommercial HVAC System Maintenance Tips.pdf
Commercial HVAC System Maintenance Tips.pdf
 

DW172

  • 1. 1 of 4 pages Health and Safety Executive Health and Safety Executive Catering Information Sheet No 10HSE information sheet Ventilation in catering kitchens Introduction This information sheet was produced by the Hospitality and Catering Industry Liaison Forum, which has members from trade and professional associations, unions and enforcement authorities. Members’ associations are free to reproduce and distribute this guidance to catering establishments. The guidance is issued by the Health and Safety Executive. The guidance is aimed at employers in the catering and hospitality industry and gives guidance on ventilation requirements for kitchens. It will help employers assess whether existing ventilation is adequate. It will also be useful for planning the ventilation specification for new or refurbished kitchens. The guidance advises on management, as well as design and performance issues. While much of the information concerns gas appliances, those with solid fuel appliances, such as charcoal ovens and grills, will also find it useful. Owners of such equipment should be aware that because charcoal ovens cannot be switched off, adequate ventilation is necessary, even when the oven is covered and cooling down overnight. This will prevent a build-up of carbon monoxide that could affect neighbouring properties. What the law says The Workplace (Health, Safety and Welfare) Regulations 1992 These Regulations require that employers provide effective and suitable ventilation in every enclosed workplace. This includes kitchens, which need ventilation to create a safe and comfortable working environment. Catering and cooking can produce significant amounts of fumes and vapours, as well as large amounts of heat. Mechanical extraction, via a canopy hood installed over the cooking appliances, can remove these fumes and vapour and discharge them to a safe location. Gas Safety (Installation and Use) Regulations 1998 These Regulations impose additional requirements and apply to gas appliances found in most catering premises. Some gas appliances will be a type (known as type B) that require a flue to comply with the Regulations. Where extraction serves that purpose, it is considered a flue and requires an appropriate interlocking system connecting the airflow to the gas supply. Gas safety in catering is the subject of Catering Information Sheet 23. However, in considering general ventilation requirements for kitchens it is important to consider the impact of such ventilation on gas appliances covered by these regulations. It is particularly important to ensure there is adequate make-up air for gas-fired appliances, the lack of which can lead to incomplete combustion and an accumulation of combustion products, such as carbon monoxide. Work on gas appliances should be carried out by a Gas Safe engineer. You can find further details in Safety in the installation and use of gas systems and appliances. Gas Safety (Installation and Use) Regulations 1998. Approved Code of Practice and guidance. The Health and Safety at Work etc Act 1974 The Act places duties on anyone in control of premises who makes them available as a place of work for others to take reasonable measures to ensure, so far as is reasonably practicable, that the premises, plant and equipment are safe and without risks to health.
  • 2. 2 of 4 pages Health and Safety Executive Effective kitchen ventilation systems The objectives of an effective kitchen ventilation system are to: remove cooking fumes at source, ie at the appliance;■■ remove excess hot air and bring in cool, clean■■ air, so the working environment is comfortable. Inadequate ventilation can cause stress, contributing to unsafe systems of work and high staff turnover; make sure that the air movement in the kitchen■■ does not cause discomfort, eg from strong draughts; provide enough air for complete combustion at■■ fired appliances, and prevent the risk of carbon monoxide accumulating; be easy to clean, avoiding build-up of fat residues■■ and blocked air inlets, which lead to loss of efficiency and increased risk of fire; be quiet and vibration free.■■ The ventilation system design needs to take account of the: cooking load;■■ amount of cooking equipment used;■■ layout and shape of the kitchen;■■ number of staff;■■ need for easy cleaning and maintenance.■■ The following guidance outlines effective design features. Assess existing and planned systems to make sure they meet these ventilation objectives. Canopies Design The canopy hood needs to be designed and operated to ensure effective removal of cooking fumes. It needs to be a suitable size and have enough extraction to minimise fume spillage into the kitchen. There should be a canopy hood for every appliance and other sources generating fumes and heat. The canopy hood should be as close as possible to the source, taking into account the work requirements. The airflow into the canopy should be uniform and constant, and meet the appropriate design flow for the appliances and room ventilation rate. Canopies and ductwork need to be constructed from non-combustible material and made so they discourage accumulations of dirt or grease, and condensation. There should be suitable access to the ductwork, to allow regular cleaning to prevent accumulation of fat etc. Grease filters need to be readily removable for cleaning/replacement. Performance The extraction rate is best calculated from the information supplied with the appliances. It should also take account of air change rates required for kitchens. Where canopies are not used, eg where extraction is through ventilated ceilings, consult a competent heating and ventilation engineer to calculate the appropriate ventilation rates. The design should avoid draughts where the kitchen is subdivided (eg wash-ups, vegetable preparations). Maintenance Mechanical ventilation systems should be maintained in efficient working order in accordance with the manufacturer’s/installer’s instructions. Replacement air The ventilation system design should take into account the need to replace extracted air. Mechanical and/or natural means can provide make-up air, but it should be fresh and unadulterated from the outside. In smaller kitchens, there may be sufficient replacement air drawn in naturally via ventilation grilles in walls, doors or windows. Where air is drawn in naturally, some means of control over pest entry is usually needed. A fine mesh grille will restrict the ventilation, and a larger grille area can compensate. However, for larger installations, a mechanical system using a fan and filter is more suitable. The ‘clean air’ should not be taken from ‘dirty’ areas, eg waste storage, smoking areas etc. The make-up air should not impair the performance of flues serving gas appliances. Cooling air Balancing incoming cool air and extracted hot air effectively should help prevent the kitchen becoming too hot. For mechanical make-up air systems, direct the cooler air towards hot work positions. Otherwise, consider air conditioning or fixed fans that do not affect the efficiency of fume extraction. Local freestanding fans may cause air currents or turbulence, affecting the efficiency of fume extraction. They are not normally an effective way to provide make- up air. They may also introduce other hazards, such as tripping and electric shock hazards from the trailing cable.
  • 3. 3 of 4 pages Health and Safety Executive Discharge High-level discharge of extracted air is often needed to prevent nuisance to neighbouring properties. Avoid rain caps and other devices that impede upward vertical velocity. Never use devices that direct the discharge downward as they encourage down draught and re-entry of fumes into the building. Fume discharge should also be away from wet cooling towers. New ventilation systems The caterer The caterer will need to provide detailed information for the competent advisor, designer and installer, including the following information: maximum demands likely to be placed on the■■ ventilation (eg to cope with peaks of activity); amount and type of kitchen equipment;■■ the menu;■■ number of meals; and■■ number of staff.■■ Advisors, suppliers and installers should be competent and have knowledge of industry practice and relevant health and safety guidance and legislation. The caterer should consult with the safety or employee representatives in good time about any significant changes. The caterer should keep records of design criteria, commissioning performance, maintenance requirements, and of tests and inspections. These enable maintenance, modification, and testing against the original specification. The building owner or manager The owner or manager of the building may provide facilities such as equipment and ventilation. In these cases, they should follow the advice here. Providing adequate ventilation will require the owner to obtain information on probable kitchen usage from the caterer. The designer/design team The ‘design team’ means the various interested parties (owner, caterer, designer, supplier and installer). They need to discuss their respective information needs and what information each should supply. The ventilation design engineer will need to take into account: The presence of gas appliances subject to the■■ Gas Safety (Installation and Use) Regulations 1998. In particular, the requirement for an adequate supply of air for combustion and flueing arrangements. kitchen usage information from the caterer;■■ equipment information from the caterer or■■ supplier, eg cleaning requirements, the amount of air required for complete combustion, and the performance of the existing installation; the requirements or specifications for the air■■ cleaning system, eg for grease removal at the canopy and also before final discharge outside; the limitations of the building, eg the available■■ room may influence the sites and routes for air inlets or discharges; food hygiene requirements, eg identify a suitable■■ source for clean make-up air; prevent pest entry; avoid grease accumulation and ensure easy cleaning of the system; heat control.■■ Assess the need for interlocking the ventilation power supply to the gas supply and take appropriate action. This decision should be based on a competent persons’ assessment of the risks associated with the use of the gas appliance. Further guidance for designers is available from industry produced technical guidance, for example guidance from The Chartered Institution of Building Services Engineers (CIBSE) and The Heating and Ventilation Contractors’ Association (HVCA) (see ‘Further information’). The equipment installer The equipment should be installed by a competent person. The equipment installer needs to know the design performance and capacity of the ventilation system, so they can ensure adequate ventilation. For existing installations where data is absent or unavailable, the installer should recommission the system of extraction and make-up air, and produce a report detailing its performance. A competent heating and ventilation specialist can provide this information. Gas-fired appliances should be installed by a Gas Safe engineer.
  • 4. 4 of 4 pages Health and Safety Executive Published by the Health and Safety Executive CAIS10(rev2) 07/12 Before installing a gas-fired appliance, the gas installer needs to know the specific air inlet requirements. Manufacturers of new catering appliances have to provide this under the Gas Appliances Directive. The gas installer can then check that these requirements are met by the ventilation system provided, taking into account other existing appliances. Information on the ventilation requirements of the existing appliances could be obtained from the caterer’s records or from the manufacturers. Further information Gas safety in catering and hospitality Catering Information Sheet CAIS23(rev1) HSE Books 2007 www.hse.gov.uk/pubns/cais23.pdf Health and safety made simple: The basics for your business www.hse.gov.uk/simple-health-safety/index.htm Safety in the installation and use of gas systems and appliances. Gas Safety (Installation and Use) Regulations 1998. Approved Code of Practice and guidance L56 (Third edition) HSE Books 2011 ISBN 978 0 7176 6419 1 www.hse.gov.uk/pubns/books/l56.htm HSE catering and hospitality web pages: www.hse.gov.uk/catering/index.htm For more information about health and safety, or to report inconsistencies or inaccuracies in this guidance, visit www.hse.gov.uk/. You can view HSE guidance online and order priced publications from the website. HSE priced publications are also available from bookshops. BS 6173: 2009 Specification for installation of gas fired catering appliances for use in all types of catering establishments British Standards Institution 2009. British Standards can be obtained in PDF or hard copy formats from BSI: http://shop.bsigroup.com or by contacting BSI Customer Services for hard copies only Tel: 020 8996 9001 email: cservices@bsigroup.com Specification for kitchen ventilation systems DW172 Building and Engineering Services Association. Available from B&ES Publications, Old Mansion House, Eamont Bridge, Penrith CA10 2BX Tel: 01768 860405 e-mail: b-espublications@welplan.co.uk The Chartered Institution of Building Services Engineers (CIBSE) is the professional body for building services engineers and provides its members and the public with information and education services, 222 Balham High Road, London, SW12 9BS Tel: 020 8675 5211 www.cibse.org. This document contains notes on good practice which are not compulsory but which you may find helpful in considering what you need to do. This document is available at www.hse.gov.uk/pubns/ cais10.htm. © Crown copyright If you wish to reuse this information visit www.hse.gov.uk/copyright.htm for details. First published 07/12.