1. Transmission Annual Planning Report 2014 Forum
2014 NSW Transmission Annual Planning
Report Forum
Asset renewal
Garrie Chubb
Manager Asset Performance
5 August 2014
2. 5 August 2014 Transmission Annual Planning Report 2014 Forum
Forum summary
•
•
•
•
•
•
•
•
•
The 2014 NSW Transmission Annual Planning Report Forum was held on
5 August in Sydney.
This is an annual event that TransGrid holds to provide further detail on the
Transmission Annual Planning Report published at the end of June every
year.
More than 100 stakeholders gathered to hear speakers from TransGrid
and AEMO to discuss TransGrid’s future plans.
Representatives were from consumer advocacy groups, academics,
government, regulators, large energy users, infrastructure organisations
and energy providers.
3. 5 August 2014
Asset Management System
Asset Management
Full lifecycle from Conception through to Renewal/Dispose
Transformation to ISO55001 is almost complete
Pre-certification complete
Certification November 2014
Balance between Cost – Risk – Service
Trade-offs must be made
May not be confined just to TransGrid
Transmission Annual Planning Report 2014 Forum
4. 5 August 2014
Condition based replacement
TransGrid replaces assets based on condition
Each project has a detailed business case
Condition assessment
Condition-based risk quantification
Option identification
Option scoping
Economic evaluation to select the most efficient feasible option
Low-cost alternatives to replacement
Changes to network configuration
De-rating of equipment
Transmission Annual Planning Report 2014 Forum
5. 5 August 2014
Transmission lines
Corrosion of steel towers in coastal areas
Structure life extension
Renewal of high value structures to defer
replacement
Monitor lower value structures in preparation
for future replacement
Wood pole replacements in inland areas
Loss of strength due to age
Termite infestations
Two wood pole structure with single pole
structure
Transmission Annual Planning Report 2014 Forum
6. 5 August 2014
A range of indicators are used to rank sites
Each site is individually assessed
Primary plant
Civil works and structures
Secondary systems
Options developed
Address each specific need
Existing and future requirements
Technology path for secondary systems
Majority of renewals are targeted solutions
Substations
Transmission Annual Planning Report 2014 Forum
7. 5 August 2014
Secondary systems
Multiple technologies
Analogue (click clack), electronic, microprocessor
Loss of product support
Transition to next generation
IEC61850
Move from copper/specialist technician to fibre/IT focus
Targeted renewals
Solutions based on site need
Optimise the full utility of modern Intelligent Electronic Devices
Transmission Annual Planning Report 2014 Forum
8. 5 August 2014
Further Information
Extensive documentation set
Asset Management System
Asset Lifecycle
Specific projects in the TAPR
All available on transgrid.com.au
Transmission Annual Planning Report 2014 Forum
9. 5 August 2014 Transmission Annual Planning Report 2014 Forum
Questions