SlideShare a Scribd company logo
1 of 5
Download to read offline
File IN 070
Team member(s) :
Francois Descous
Craig Roberston
Maxime Panafieu
Tony Simmonds
MLC Project Team
Context – What was the problem to be solved?
MLC tower: height 220 m, 68 floors, octagonal shape, variable cross
section.
Work conditions: 4 locations with two platforms one above the other.
Rain, Wind and storm.
Environment: building remains operational, including retail and food
court. At the corner of two main streets of Sydney.
Freyssinet designed and supplied 4 Non Standard mast climber
platforms: 40m long x C shaped
Challenge: a NEW SET UP must be achieved at each movement.
During a platform relocation between levels, a tape measure fell from
Level 32 and landed approximately 1m from a pedestrian. Nobody was
injured but it has been an important reality check for us and the client.
2
Solution chosen
3
Objectives:
ü  Remove hazards
ü  Increase redundancy
ü  Simplify platform setup
ü  Improve working procedure
ü  Restore client confidence
Solution chosen
1. Remove hazard
Reduce gaps => Platform clearance reduced to 30mm instead of 70mm
Remove small items installation=> No more screws or items which cannot be lanyarded
Mast encapsulation & deck extension
2. Simplify the setup
More standardized modules => simplify platform decking and platform ends
3. Increase redundancy
Install net / catching system prior to any installation from deck level
Lanyarded tools to be dedicated to high risk work
Increase the level of supervision while performing high risk work
4. Improve working procedure
Reduce the quantity of exposed works => Isolate and identify high risk area…
Dedicated tools and crew to perform those works => Red zone tool box, dedicated crew…
Documents updated => Procedure, training, competency assessment…
4
Results obtained and wider adoption of the innovation
Major improvement : 25 000h used for modifications
Safety:
Ø  No more spillage / waterproofing massively improved,
Ø  Workers reduce exposure to a free edge,
Ø  No loose item, no small items,
Ø  Catching system under the entire platform,
⇒ Risk of falling object close to nil.
Productivity:
ü  Standardizing and improving the platform is good for guys moral and productivity,
ü  No more spotter required for spillage => 19 600h saved on project duration
ü  Platform setup is faster than before => 11 760h saved on project duration
Client confidence:
ü  Trust and confidence with Freyssinet
ü  The client is impressed by the outstanding job done, ‘’ you’re going above and beyond industry standards.’’
ü  We renegotiated the contract, extending the duration and increasing the contract sum: from 55 to 110Million AUD
Wider adoption:
ü  This project is a benchmark for the company – safety wise – and the clients safety manager is using our project as an example for
their own future projects
5

More Related Content

Similar to INTERNATIONALE_070

Industrial Trainig report fdocxhshjjdlvgeiheqkddwy
Industrial Trainig report fdocxhshjjdlvgeiheqkddwyIndustrial Trainig report fdocxhshjjdlvgeiheqkddwy
Industrial Trainig report fdocxhshjjdlvgeiheqkddwy
ssuserc4e7cc1
 
Intelligent engineering to maximize productivity and reduce maintenance
Intelligent engineering to maximize productivity and reduce maintenanceIntelligent engineering to maximize productivity and reduce maintenance
Intelligent engineering to maximize productivity and reduce maintenance
X-tec Ag
 
Intelligent engineering to maximize productivity and reduce maintenance
Intelligent engineering to maximize productivity and reduce maintenanceIntelligent engineering to maximize productivity and reduce maintenance
Intelligent engineering to maximize productivity and reduce maintenance
X-tec Ag
 
Evan Gritman Lewis
Evan Gritman LewisEvan Gritman Lewis
Evan Gritman Lewis
Evan Lewis
 
"Passivhaus Training & Courses, how to expand our understanding" - Steve Char...
"Passivhaus Training & Courses, how to expand our understanding" - Steve Char..."Passivhaus Training & Courses, how to expand our understanding" - Steve Char...
"Passivhaus Training & Courses, how to expand our understanding" - Steve Char...
Sustainable Business Partnership
 
Proconsultores Telecommunication Presentation
Proconsultores Telecommunication PresentationProconsultores Telecommunication Presentation
Proconsultores Telecommunication Presentation
Joaquim Almeida
 
Company Presentation 2015
Company Presentation 2015Company Presentation 2015
Company Presentation 2015
Mach Cao Xuan
 

Similar to INTERNATIONALE_070 (20)

Industrial Trainig report fdocxhshjjdlvgeiheqkddwy
Industrial Trainig report fdocxhshjjdlvgeiheqkddwyIndustrial Trainig report fdocxhshjjdlvgeiheqkddwy
Industrial Trainig report fdocxhshjjdlvgeiheqkddwy
 
Introduction to djuvik
Introduction to djuvikIntroduction to djuvik
Introduction to djuvik
 
Intelligent engineering to maximize productivity and reduce maintenance
Intelligent engineering to maximize productivity and reduce maintenanceIntelligent engineering to maximize productivity and reduce maintenance
Intelligent engineering to maximize productivity and reduce maintenance
 
productivity improvement using work studt tools.pptx
productivity improvement using work studt tools.pptxproductivity improvement using work studt tools.pptx
productivity improvement using work studt tools.pptx
 
Tank Inspection by Consultec
Tank Inspection by ConsultecTank Inspection by Consultec
Tank Inspection by Consultec
 
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian Showcase
 
Intelligent engineering to maximize productivity and reduce maintenance
Intelligent engineering to maximize productivity and reduce maintenanceIntelligent engineering to maximize productivity and reduce maintenance
Intelligent engineering to maximize productivity and reduce maintenance
 
Block-transformer house
Block-transformer houseBlock-transformer house
Block-transformer house
 
Evan Gritman Lewis
Evan Gritman LewisEvan Gritman Lewis
Evan Gritman Lewis
 
"Passivhaus Training & Courses, how to expand our understanding" - Steve Char...
"Passivhaus Training & Courses, how to expand our understanding" - Steve Char..."Passivhaus Training & Courses, how to expand our understanding" - Steve Char...
"Passivhaus Training & Courses, how to expand our understanding" - Steve Char...
 
Process selection & facility layout.pptx
Process selection & facility layout.pptxProcess selection & facility layout.pptx
Process selection & facility layout.pptx
 
Design and Development of Dynamo Testing Machine
Design and Development of Dynamo Testing MachineDesign and Development of Dynamo Testing Machine
Design and Development of Dynamo Testing Machine
 
Passivhaus: What is it, and what has it got to do with me?
Passivhaus: What is it, and what has it got to do with me?Passivhaus: What is it, and what has it got to do with me?
Passivhaus: What is it, and what has it got to do with me?
 
Global Trends in Delivery Projects
Global Trends in Delivery ProjectsGlobal Trends in Delivery Projects
Global Trends in Delivery Projects
 
TeamCapabilitiesBro
TeamCapabilitiesBroTeamCapabilitiesBro
TeamCapabilitiesBro
 
GTM Blow Off Cabinets Best Practice
GTM Blow Off Cabinets Best PracticeGTM Blow Off Cabinets Best Practice
GTM Blow Off Cabinets Best Practice
 
Proconsultores Telecommunication Presentation
Proconsultores Telecommunication PresentationProconsultores Telecommunication Presentation
Proconsultores Telecommunication Presentation
 
Proconsultores Telecommunication Presentation
Proconsultores Telecommunication PresentationProconsultores Telecommunication Presentation
Proconsultores Telecommunication Presentation
 
Company Presentation 2015
Company Presentation 2015Company Presentation 2015
Company Presentation 2015
 
Case Studies Ii
Case Studies IiCase Studies Ii
Case Studies Ii
 

INTERNATIONALE_070

  • 1. File IN 070 Team member(s) : Francois Descous Craig Roberston Maxime Panafieu Tony Simmonds MLC Project Team
  • 2. Context – What was the problem to be solved? MLC tower: height 220 m, 68 floors, octagonal shape, variable cross section. Work conditions: 4 locations with two platforms one above the other. Rain, Wind and storm. Environment: building remains operational, including retail and food court. At the corner of two main streets of Sydney. Freyssinet designed and supplied 4 Non Standard mast climber platforms: 40m long x C shaped Challenge: a NEW SET UP must be achieved at each movement. During a platform relocation between levels, a tape measure fell from Level 32 and landed approximately 1m from a pedestrian. Nobody was injured but it has been an important reality check for us and the client. 2
  • 3. Solution chosen 3 Objectives: ü  Remove hazards ü  Increase redundancy ü  Simplify platform setup ü  Improve working procedure ü  Restore client confidence
  • 4. Solution chosen 1. Remove hazard Reduce gaps => Platform clearance reduced to 30mm instead of 70mm Remove small items installation=> No more screws or items which cannot be lanyarded Mast encapsulation & deck extension 2. Simplify the setup More standardized modules => simplify platform decking and platform ends 3. Increase redundancy Install net / catching system prior to any installation from deck level Lanyarded tools to be dedicated to high risk work Increase the level of supervision while performing high risk work 4. Improve working procedure Reduce the quantity of exposed works => Isolate and identify high risk area… Dedicated tools and crew to perform those works => Red zone tool box, dedicated crew… Documents updated => Procedure, training, competency assessment… 4
  • 5. Results obtained and wider adoption of the innovation Major improvement : 25 000h used for modifications Safety: Ø  No more spillage / waterproofing massively improved, Ø  Workers reduce exposure to a free edge, Ø  No loose item, no small items, Ø  Catching system under the entire platform, ⇒ Risk of falling object close to nil. Productivity: ü  Standardizing and improving the platform is good for guys moral and productivity, ü  No more spotter required for spillage => 19 600h saved on project duration ü  Platform setup is faster than before => 11 760h saved on project duration Client confidence: ü  Trust and confidence with Freyssinet ü  The client is impressed by the outstanding job done, ‘’ you’re going above and beyond industry standards.’’ ü  We renegotiated the contract, extending the duration and increasing the contract sum: from 55 to 110Million AUD Wider adoption: ü  This project is a benchmark for the company – safety wise – and the clients safety manager is using our project as an example for their own future projects 5