1. HOW TO MANAGE EARTH WORK ACTIVITIES WITH TILOS
(MASS HAULAGE & BRUDNER DIAGRAM)
Tekin Guvercin
Civil Engineer
2.
3. 81
Who is
FND is an exclusive
solution providers of
international project
management systems
Essential Business Commination
- Founded in 2009 in Poland
- 57 Partners worldwide
- 2000+ Customers
- Customers in 84 countries
- Deliver Support 7*24h*365d
- 9 Language Speaking Company
- Very strong AEC Background
- Very Strong Partner Network
10. Repetition of each activity along the length of the project
The goal is to have exact quantities and optimize the productivity rates
Minimizing the total time of crews and avoid clashes
Reducing project duration
Reducing overall cost
Linear Projects Characteristics
Have an axis (ROW) along which the work is performed
11. Linear Planning usage at any project stage
Predesign Planning Procurement Execution Claims
Feasibilty Studies
Overall Plan
Production plan
Special studies
Contractor & Sub-Contractor & Supplier
Owner / Engineering companies
Offer Preparation
Tender
12.
13. C1 C2
F1
C3
RC1
F2 F3
Start Location
“0 m”
Start Date “
10th of
March”
End Location
“500 m”
Finish Date “ 25th of March”
d=15days
C1 C2 C3
F1
C4
C4
F2
F3
RC1
RC2
RC2