Towards a Better Project
Management @ STIB-MIVB
November 2013
Corporate PMO - Stefano Vicenzi
« If you want to travel fast, walk alone;
If you want to travel far, walk together »
African saying
Structure of Presentation
 Where are we coming from ?
 October 2013 situation
 Work in progress …
 Perspectives
Where is the STIB coming from ? : A weak
Project Management (Source: ComEx Pres. – Oct. 2010)
Project Methodology
• No internal visibility on Projects (Scope, Planning, …)
• Lack of Project Management competencies
 Technical experts are promoted as « chef de projet »
• No unified Methodology in PM
• No Structured approach in Project Organisation nor in
Project Governance;
Project Costs
• Total cost of a Project is unknown (FTE - CapEx - OpEx)
• Poor effeciency in Resources allocation i.e. Project VS
Operations
Project Planning
• Delays in Project deliveries
• Operational Urgencies in conflicts with Projects
Management
• Lack of priority between Projects
Gestion de Projets
1
2
3
4
5
Q. 8
Q. 9
Q. 10
Q. 11
Q. 12Q. 13
Q. 14
Q. 15
Q. 16
Average answ ers
Enquiry on STIB maturity (source : P3M3) performed between March and May 2011
Level 1 (centre of the ‘radar’)
identifies Organisations :
• without Projects Management
structure,
• without Methodology,
• with poor or without resource (FTE
or €) control,
• without Risk Management,
• without ROI evaluation.
Le niveau 5 (border of the ‘radar’)
identifies Mature Organisations in
terms of Project/Program
Management Gestion de Projets
Jan 2011: launch of LIGHT Project
Increase Maturity in Project Management
Change Plan 2011 - 2013 :
Value
Creation
Program
Management
Processes
Enablers
Organization
Change
Management
Organize and supervise transformation program
to implement a PMO Organisation
Measure and report business impact based on KPI which reflect success of
the implementation of the PMO
Develop “To Be” processes. Align existing processes
Tools which support PMO processes (Templates, IT tools, reporting)
Roles and responsibilities linked to PMO;
Populating new organization
Facilitate the change in the organization, the processes and the people
(communication, leadership alignment, training, culture)
LIGHT Project : Achievements and Perspectives
Change Plan 2010
Mid
Term Livrables 2012
PMO Organisation PMO Corporate (Tour de contôle)
PMO Départementaux
Processes Project Life Cycle (processus)
Project Charter (documentation)
Governance Project / Program Board: Sponsor & mbrs
Project Leads (PM, BO, PA)
Project Reporting Project Status Report (Statut des Projets)
Monthly ExCom Flash (Reporting)
Portfolio Management Project / Program Dashboard
Reporting (Fin.) Lien OI / Projet (Cash Out),
Business Case
Priorisation Prioritié Business, Famille Stratégique
Project Team Capacity
Management
Capacity planning
Time Registration
Flying Doctors -
P3M3 Maturity Assessment will be the indicator of the successful Light Project
implementation. New evaluation planned end of 2013
Q3
2013 Developpement axes 2014-2017
Enrichment of the existing Light Methodology
(focus on the operationality)
Follow-up and deployment of coaching
Fine-tuning of current tools (alerts, workflow, …)
Reinforcement within the STIB Org.
Fine-tuning of Governance
Focus sur le Data Quality
Deployment of a tool to perform Project
Financials follow-up
Industrialisation of the prioritisation process
Follow-up and deployment of Project n°142
Livrables Q3 2013
Project Typology on going (based on
Prince2) & M_o_R launched in TE Projects
Pilots on PIVO, MCH, … Projects
Financial elements in Project Dashboard
Finalised Organisation
Board & Project Teams Members of Top-
ExCom (TE) Projects identified and agreed
95% of Top-ExCom Projects with a Project
Status Report (PSR)
Integration within CG and PE Processes
Project n°142 launched and on-going
Roll-out link ‘OI ‘(SAP internal orders) /
PMO Projects
Q4
LIGHT Project @ STIB-MIVB: Lessons Learned
What Most
People Think
What we have
Learned
LIGHT Project : PMO Organisation
Nov. 2013 Corporate PMO : B. R.
R. K.
Stefano Vicenzi
 PMO Départementaux :
o SM & N S. L.
o Finance & Services Z. H.
o Human Resources L. Z.
o Operations D. D. (Business Development Dir.)
 BUM M. T.
 BUT V. L.
 BUB C. V., G. D.
 Field Support J.-L. V.
o Transport System D. V. (Business Development Dir.)
 IS-IT S. D.
 IS-Infotech O. V.
 Infrastructure Q. M.
LIGHT Project : First Methodological model
adopted (Project Life-Cycle - WF ) (1/3)
New Project Life Cycle Typologies integrating local
needs i.e. :
 IT : Scrum, Agile, RAAD, …
 HR : Reorganisation Projects, …
 Infra : Studies and Pre-Studies, …
 Transversal Domains : Process Studies,
Re-engineering, ‘Plans Directeurs’, …
 …
Processes : 2013 - 2017 Perspectives (2/3)(3/3)
LIGHT Project : Project Governance (1/2)
Final Authority on Projects
Accoutable of the Project
Collective Decisions about
Manage the Project
Responsible to Define
the Project (‘What’ & ‘How’)
Project Deliverers (int./ext.)
Support the Project Management at
each stage of a Projects
ExCom
LIGHT Project : Program Governance (2/2)
CMMI Project Management Maturity Model used to measure our performance
ExCom
A Program has the same
characteristics as a Project; except
that Program is divided into more
managed elements.
These elements must be organised
and managed in a coordinated way
in order to achieve defined
objectives & consolidated
advantages .
LIGHT Project : Project Reporting (1/2)
CMMI Project Management Maturity Model used to measure our performance
3 levels of Project Reporting
Project Status Report
Project
Dashboard
Reporting
Top-ExCom Project Portfolio
# of RED indicators per family (Scope, Budget, …) in Project Status
Report (PSR) (Trend on last 12 monthis)
Today’s reporting : Situation … (2/2)
LIGHT Project : Portfolio Management (1/2)
CMMI Project Management Maturity Model used to measure our performance
(2/2)
Project Fin. Reporting - Current situation (1/2)
CMMI Project Management Maturity Model used to measure our performance
Current Reporting based on the association of ‘PMO Project nr’
(from the Project Dashboard) & ‘Internal Ordres’ (SAP-OI)
Objectives : a Project Portfolio Reporting …
Project Financial Reporting - Needs (2/2)
Size related to the Project Budget (Business Case)
Underspent
On budget
Overspent
No info
No infoTo plan LateEarly
1
3
2
4
Respect of
Timing
Respect of
Budget
5
6
… to do so, a new Project was launched in Q3-13
(Sponsor : Corporate PMO - Supplier : Fin Services)
May 2012
Inventory and creation of the STIB Initiatives Portfolio (including Programs, Projects,
corrective & evolutive maintenance, …).
• Projects with Priority # 1 confirmed by the ExCom (e.g. PULSAR,
MoBIB²…)
• Projects to Prioritise
• Departemental Projects (managed locally)  Details
The 74 STIB Project Managers were coached and challenged by Corporate PMO &
Roland Berger in order to create Project Charters & Business Cases.  Details
Based on the STIB Business Model, definition of 3 Strategical Families:
 Efficiency Net Present Value (NPV)
 Mobility Impact on # of Travels (voyages)
 Customer Satisfaction Impact on Satisfaction
& Safety
31
43
306
Prioritisation - First Steps (1/3)
Source : ExCom Presentation - 8 October 2012
Outcomes :
A Improvement of Efficiency B Improvement of Mobility C
Improvement of Safety
and Quality of Services
MOBIB² 2015 Q2
MOBIB² (Short term evolution) 2014 Q4
Sésame 2015 Q4
MCH - Infrastructure 2017 Q1
Optimalisation du portefeuille d’achat 2012 Q4
Flow 2013 Q2
Automatisation planchette des agents 2013 Q2
Koyakimi (production kilométrique) 2014 Q4
COLIBRI Matériel Roulant 2013 Q4
COLIBRI (GMAO) 2014 Q4
CoVo (Comptage Voyageur) 2014 Q1
Automatisation attribution des congés 2013 Q1
TEMPORIS 2013 Q4
BI Transport 2013 Q4
Pré étude OCC Intégré 2013 Q2
Re-engineering INFRA 2013 Q1
PULSAR 2019 Q4
AMSTER (Sureté du trafic en réseau) 2014 Q2
Métro Nord - CBTC 2022
Construction & Accès - Dépôt Marconi 2016 Q4
Achat BUS Diesel 2014 Q1
OBC (On Board Conputer) 2014 Q1
Achat BUS Gaz 2016 Q1
Véhicules de service Rail / Route 2014 Q1
Phoenix (Nouveau SAE) 2013 Q1
SYREM (Phase 2) 2013 Q2
NESTOR (Nouveaux Mini BUS) 2014 Q2
Extension - TRAM Gare Centrale 2016 Q4
Extension - TRAM Woluwe Roodebeek 2016 Q4
Extension - TRAM L9 Simonis Jette 2018 Q4
ALTERNO (Gestion des incidents) 2013 Q4
Système de gestion SAFETY 2016 Q4
Business Continuity Mangement 2014 Q4
Enterprise Risk Management 2016 Q4
SPIDER 2014 Q3
PIVO (information voyageur) 2014 Q4
CBS (communication boarded systems) 2014 Q2
Re-engineering Sûreté & Contrôle 2013 Q4
Adaptations infrastructures TRAM 2024
Gestion des correspondances 2013 Q4
Interfaces Infrastructure de TP et Voirie 2014 Q4
Prioritisation - Outcomes (2/3)
Source : ExCom Presentation - 8 October 2012
Today: Portfolio Management (3/3)
Integration of the Portfolio Management Process (Project Portfolio
creation & Budgetary exercise) within the ‘Plan d’Entreprise’ Process
including the ‘Annuals’ et ‘Multi-Annuals’ Depts Plans
Contrat de
Gestion
Plan
d’Entreprise
Plans
Pluriannuels Plans
Annuels
Budgets
Annuels
Exercice de
Priorisation
Portfolio Management
Project Charters & Business Cases
 Business Cases using the Net Present Value (NPV) as
Financial evaluation criteria
(taking into account Prince2 Principles & Theme)
 Impact on Quality of Services measured via the
‘baromètre de la Satisfaction Client’
 33 types of critical technical competencies were
identified and tracked in Business Cases
Project Charters (mix of PID & PDD) ensure a
standardised documentation ensuring information on :
 Context and Objectives
 Scope and Perimeter (in & out)
 Impact and dependencies
 Risk inventory (1st iteration)
 Planning (1st iteration)
 Organisation
Projects Portfolio Stages
31
43
Gestion de la Capacité
des ETP ‘Projet’
Today: ‘Flying Doctors’ Activity
CMMI Project Management Maturity Model used to measure our performance
Based on 2013 Pilots (MCH, PIVO, ‘Achat Bus’, …), implementation of a Coaching
function triggered by Business Requests or by malfunctioning Projects.
Today’s log :

More Related Content

Similar to STIB Corporate PMO - QRP presentation - 2013 11 28

Cv bi short_gillet_guillaume_virtuoz_it_072015
Cv bi short_gillet_guillaume_virtuoz_it_072015Cv bi short_gillet_guillaume_virtuoz_it_072015
Cv bi short_gillet_guillaume_virtuoz_it_072015Guillaume Gillet
 
SharjeelAnjum_CV @pakistangroup.pdf
SharjeelAnjum_CV @pakistangroup.pdfSharjeelAnjum_CV @pakistangroup.pdf
SharjeelAnjum_CV @pakistangroup.pdfWaqasAhmad560436
 
Sid Tripathi PMOCv
Sid Tripathi PMOCvSid Tripathi PMOCv
Sid Tripathi PMOCvsidlko
 
Sahar Kamal's CV _2016
Sahar Kamal's CV _2016Sahar Kamal's CV _2016
Sahar Kamal's CV _2016Sahar Kamal
 
Ayman Mohamed Alyan - Resume
Ayman Mohamed Alyan - ResumeAyman Mohamed Alyan - Resume
Ayman Mohamed Alyan - ResumeAyman Alyan
 
Ayman Mohamed Alyan - Resume
Ayman Mohamed Alyan - ResumeAyman Mohamed Alyan - Resume
Ayman Mohamed Alyan - ResumeAyman Alyan
 
EAC MBA Project Management - Railway GDS Distribution - Westbahn
EAC MBA Project Management - Railway GDS Distribution - WestbahnEAC MBA Project Management - Railway GDS Distribution - Westbahn
EAC MBA Project Management - Railway GDS Distribution - WestbahnSimon Riha, MSc, MBA
 
OLATOMI_OGUNJOBI_PM_CV_ 2016
OLATOMI_OGUNJOBI_PM_CV_ 2016OLATOMI_OGUNJOBI_PM_CV_ 2016
OLATOMI_OGUNJOBI_PM_CV_ 2016Tomi Ogunjobi
 
Motorola Advaced Project Portfolio Management
Motorola Advaced Project Portfolio ManagementMotorola Advaced Project Portfolio Management
Motorola Advaced Project Portfolio ManagementAras
 
Professional-Rahmat Hashim-2016
Professional-Rahmat Hashim-2016Professional-Rahmat Hashim-2016
Professional-Rahmat Hashim-2016Rahmat Hashim, PMP
 
Lecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdfLecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdfTanzeelShahid5
 
projectmanagement-141108102434-conversion-gate01-converted.pptx
projectmanagement-141108102434-conversion-gate01-converted.pptxprojectmanagement-141108102434-conversion-gate01-converted.pptx
projectmanagement-141108102434-conversion-gate01-converted.pptxChandrasen Sharma
 
EU Horizon2020 proposal development by Anastasia Walter
EU Horizon2020 proposal development by Anastasia Walter EU Horizon2020 proposal development by Anastasia Walter
EU Horizon2020 proposal development by Anastasia Walter Anastasia Walter
 

Similar to STIB Corporate PMO - QRP presentation - 2013 11 28 (20)

Cv bi short_gillet_guillaume_virtuoz_it_072015
Cv bi short_gillet_guillaume_virtuoz_it_072015Cv bi short_gillet_guillaume_virtuoz_it_072015
Cv bi short_gillet_guillaume_virtuoz_it_072015
 
SharjeelAnjum_CV @pakistangroup.pdf
SharjeelAnjum_CV @pakistangroup.pdfSharjeelAnjum_CV @pakistangroup.pdf
SharjeelAnjum_CV @pakistangroup.pdf
 
Agile pgm
Agile pgmAgile pgm
Agile pgm
 
Sid Tripathi PMOCv
Sid Tripathi PMOCvSid Tripathi PMOCv
Sid Tripathi PMOCv
 
Sahar Kamal's CV _2016
Sahar Kamal's CV _2016Sahar Kamal's CV _2016
Sahar Kamal's CV _2016
 
Ayman Mohamed Alyan - Resume
Ayman Mohamed Alyan - ResumeAyman Mohamed Alyan - Resume
Ayman Mohamed Alyan - Resume
 
Ayman Mohamed Alyan - Resume
Ayman Mohamed Alyan - ResumeAyman Mohamed Alyan - Resume
Ayman Mohamed Alyan - Resume
 
EAC MBA Project Management - Railway GDS Distribution - Westbahn
EAC MBA Project Management - Railway GDS Distribution - WestbahnEAC MBA Project Management - Railway GDS Distribution - Westbahn
EAC MBA Project Management - Railway GDS Distribution - Westbahn
 
RESUME-lyf-20161129
RESUME-lyf-20161129RESUME-lyf-20161129
RESUME-lyf-20161129
 
OLATOMI_OGUNJOBI_PM_CV_ 2016
OLATOMI_OGUNJOBI_PM_CV_ 2016OLATOMI_OGUNJOBI_PM_CV_ 2016
OLATOMI_OGUNJOBI_PM_CV_ 2016
 
Motorola Advaced Project Portfolio Management
Motorola Advaced Project Portfolio ManagementMotorola Advaced Project Portfolio Management
Motorola Advaced Project Portfolio Management
 
Professional-Rahmat Hashim-2016
Professional-Rahmat Hashim-2016Professional-Rahmat Hashim-2016
Professional-Rahmat Hashim-2016
 
Lecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdfLecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdf
 
LOAY FARAHAT PMP
LOAY FARAHAT PMPLOAY FARAHAT PMP
LOAY FARAHAT PMP
 
Project planning logic, how to optimise your schedule
Project planning logic, how to optimise your scheduleProject planning logic, how to optimise your schedule
Project planning logic, how to optimise your schedule
 
projectmanagement-141108102434-conversion-gate01-converted.pptx
projectmanagement-141108102434-conversion-gate01-converted.pptxprojectmanagement-141108102434-conversion-gate01-converted.pptx
projectmanagement-141108102434-conversion-gate01-converted.pptx
 
P30 information management system webinar
P30 information management system webinarP30 information management system webinar
P30 information management system webinar
 
EU Horizon2020 proposal development by Anastasia Walter
EU Horizon2020 proposal development by Anastasia Walter EU Horizon2020 proposal development by Anastasia Walter
EU Horizon2020 proposal development by Anastasia Walter
 
Project Management
Project ManagementProject Management
Project Management
 
AJ Best PM ENG
AJ Best PM ENGAJ Best PM ENG
AJ Best PM ENG
 

STIB Corporate PMO - QRP presentation - 2013 11 28

  • 1. Towards a Better Project Management @ STIB-MIVB November 2013 Corporate PMO - Stefano Vicenzi « If you want to travel fast, walk alone; If you want to travel far, walk together » African saying
  • 2. Structure of Presentation  Where are we coming from ?  October 2013 situation  Work in progress …  Perspectives
  • 3. Where is the STIB coming from ? : A weak Project Management (Source: ComEx Pres. – Oct. 2010) Project Methodology • No internal visibility on Projects (Scope, Planning, …) • Lack of Project Management competencies  Technical experts are promoted as « chef de projet » • No unified Methodology in PM • No Structured approach in Project Organisation nor in Project Governance; Project Costs • Total cost of a Project is unknown (FTE - CapEx - OpEx) • Poor effeciency in Resources allocation i.e. Project VS Operations Project Planning • Delays in Project deliveries • Operational Urgencies in conflicts with Projects Management • Lack of priority between Projects Gestion de Projets 1 2 3 4 5 Q. 8 Q. 9 Q. 10 Q. 11 Q. 12Q. 13 Q. 14 Q. 15 Q. 16 Average answ ers Enquiry on STIB maturity (source : P3M3) performed between March and May 2011 Level 1 (centre of the ‘radar’) identifies Organisations : • without Projects Management structure, • without Methodology, • with poor or without resource (FTE or €) control, • without Risk Management, • without ROI evaluation. Le niveau 5 (border of the ‘radar’) identifies Mature Organisations in terms of Project/Program Management Gestion de Projets
  • 4. Jan 2011: launch of LIGHT Project Increase Maturity in Project Management Change Plan 2011 - 2013 : Value Creation Program Management Processes Enablers Organization Change Management Organize and supervise transformation program to implement a PMO Organisation Measure and report business impact based on KPI which reflect success of the implementation of the PMO Develop “To Be” processes. Align existing processes Tools which support PMO processes (Templates, IT tools, reporting) Roles and responsibilities linked to PMO; Populating new organization Facilitate the change in the organization, the processes and the people (communication, leadership alignment, training, culture)
  • 5. LIGHT Project : Achievements and Perspectives Change Plan 2010 Mid Term Livrables 2012 PMO Organisation PMO Corporate (Tour de contôle) PMO Départementaux Processes Project Life Cycle (processus) Project Charter (documentation) Governance Project / Program Board: Sponsor & mbrs Project Leads (PM, BO, PA) Project Reporting Project Status Report (Statut des Projets) Monthly ExCom Flash (Reporting) Portfolio Management Project / Program Dashboard Reporting (Fin.) Lien OI / Projet (Cash Out), Business Case Priorisation Prioritié Business, Famille Stratégique Project Team Capacity Management Capacity planning Time Registration Flying Doctors - P3M3 Maturity Assessment will be the indicator of the successful Light Project implementation. New evaluation planned end of 2013 Q3 2013 Developpement axes 2014-2017 Enrichment of the existing Light Methodology (focus on the operationality) Follow-up and deployment of coaching Fine-tuning of current tools (alerts, workflow, …) Reinforcement within the STIB Org. Fine-tuning of Governance Focus sur le Data Quality Deployment of a tool to perform Project Financials follow-up Industrialisation of the prioritisation process Follow-up and deployment of Project n°142 Livrables Q3 2013 Project Typology on going (based on Prince2) & M_o_R launched in TE Projects Pilots on PIVO, MCH, … Projects Financial elements in Project Dashboard Finalised Organisation Board & Project Teams Members of Top- ExCom (TE) Projects identified and agreed 95% of Top-ExCom Projects with a Project Status Report (PSR) Integration within CG and PE Processes Project n°142 launched and on-going Roll-out link ‘OI ‘(SAP internal orders) / PMO Projects Q4
  • 6. LIGHT Project @ STIB-MIVB: Lessons Learned What Most People Think What we have Learned
  • 7. LIGHT Project : PMO Organisation Nov. 2013 Corporate PMO : B. R. R. K. Stefano Vicenzi  PMO Départementaux : o SM & N S. L. o Finance & Services Z. H. o Human Resources L. Z. o Operations D. D. (Business Development Dir.)  BUM M. T.  BUT V. L.  BUB C. V., G. D.  Field Support J.-L. V. o Transport System D. V. (Business Development Dir.)  IS-IT S. D.  IS-Infotech O. V.  Infrastructure Q. M.
  • 8. LIGHT Project : First Methodological model adopted (Project Life-Cycle - WF ) (1/3) New Project Life Cycle Typologies integrating local needs i.e. :  IT : Scrum, Agile, RAAD, …  HR : Reorganisation Projects, …  Infra : Studies and Pre-Studies, …  Transversal Domains : Process Studies, Re-engineering, ‘Plans Directeurs’, …  … Processes : 2013 - 2017 Perspectives (2/3)(3/3)
  • 9. LIGHT Project : Project Governance (1/2) Final Authority on Projects Accoutable of the Project Collective Decisions about Manage the Project Responsible to Define the Project (‘What’ & ‘How’) Project Deliverers (int./ext.) Support the Project Management at each stage of a Projects ExCom
  • 10. LIGHT Project : Program Governance (2/2) CMMI Project Management Maturity Model used to measure our performance ExCom A Program has the same characteristics as a Project; except that Program is divided into more managed elements. These elements must be organised and managed in a coordinated way in order to achieve defined objectives & consolidated advantages .
  • 11. LIGHT Project : Project Reporting (1/2) CMMI Project Management Maturity Model used to measure our performance 3 levels of Project Reporting Project Status Report Project Dashboard Reporting
  • 12. Top-ExCom Project Portfolio # of RED indicators per family (Scope, Budget, …) in Project Status Report (PSR) (Trend on last 12 monthis) Today’s reporting : Situation … (2/2)
  • 13. LIGHT Project : Portfolio Management (1/2) CMMI Project Management Maturity Model used to measure our performance (2/2)
  • 14. Project Fin. Reporting - Current situation (1/2) CMMI Project Management Maturity Model used to measure our performance Current Reporting based on the association of ‘PMO Project nr’ (from the Project Dashboard) & ‘Internal Ordres’ (SAP-OI)
  • 15. Objectives : a Project Portfolio Reporting … Project Financial Reporting - Needs (2/2) Size related to the Project Budget (Business Case) Underspent On budget Overspent No info No infoTo plan LateEarly 1 3 2 4 Respect of Timing Respect of Budget 5 6 … to do so, a new Project was launched in Q3-13 (Sponsor : Corporate PMO - Supplier : Fin Services)
  • 16. May 2012 Inventory and creation of the STIB Initiatives Portfolio (including Programs, Projects, corrective & evolutive maintenance, …). • Projects with Priority # 1 confirmed by the ExCom (e.g. PULSAR, MoBIB²…) • Projects to Prioritise • Departemental Projects (managed locally)  Details The 74 STIB Project Managers were coached and challenged by Corporate PMO & Roland Berger in order to create Project Charters & Business Cases.  Details Based on the STIB Business Model, definition of 3 Strategical Families:  Efficiency Net Present Value (NPV)  Mobility Impact on # of Travels (voyages)  Customer Satisfaction Impact on Satisfaction & Safety 31 43 306 Prioritisation - First Steps (1/3) Source : ExCom Presentation - 8 October 2012 Outcomes :
  • 17. A Improvement of Efficiency B Improvement of Mobility C Improvement of Safety and Quality of Services MOBIB² 2015 Q2 MOBIB² (Short term evolution) 2014 Q4 Sésame 2015 Q4 MCH - Infrastructure 2017 Q1 Optimalisation du portefeuille d’achat 2012 Q4 Flow 2013 Q2 Automatisation planchette des agents 2013 Q2 Koyakimi (production kilométrique) 2014 Q4 COLIBRI Matériel Roulant 2013 Q4 COLIBRI (GMAO) 2014 Q4 CoVo (Comptage Voyageur) 2014 Q1 Automatisation attribution des congés 2013 Q1 TEMPORIS 2013 Q4 BI Transport 2013 Q4 Pré étude OCC Intégré 2013 Q2 Re-engineering INFRA 2013 Q1 PULSAR 2019 Q4 AMSTER (Sureté du trafic en réseau) 2014 Q2 Métro Nord - CBTC 2022 Construction & Accès - Dépôt Marconi 2016 Q4 Achat BUS Diesel 2014 Q1 OBC (On Board Conputer) 2014 Q1 Achat BUS Gaz 2016 Q1 Véhicules de service Rail / Route 2014 Q1 Phoenix (Nouveau SAE) 2013 Q1 SYREM (Phase 2) 2013 Q2 NESTOR (Nouveaux Mini BUS) 2014 Q2 Extension - TRAM Gare Centrale 2016 Q4 Extension - TRAM Woluwe Roodebeek 2016 Q4 Extension - TRAM L9 Simonis Jette 2018 Q4 ALTERNO (Gestion des incidents) 2013 Q4 Système de gestion SAFETY 2016 Q4 Business Continuity Mangement 2014 Q4 Enterprise Risk Management 2016 Q4 SPIDER 2014 Q3 PIVO (information voyageur) 2014 Q4 CBS (communication boarded systems) 2014 Q2 Re-engineering Sûreté & Contrôle 2013 Q4 Adaptations infrastructures TRAM 2024 Gestion des correspondances 2013 Q4 Interfaces Infrastructure de TP et Voirie 2014 Q4 Prioritisation - Outcomes (2/3) Source : ExCom Presentation - 8 October 2012
  • 18. Today: Portfolio Management (3/3) Integration of the Portfolio Management Process (Project Portfolio creation & Budgetary exercise) within the ‘Plan d’Entreprise’ Process including the ‘Annuals’ et ‘Multi-Annuals’ Depts Plans Contrat de Gestion Plan d’Entreprise Plans Pluriannuels Plans Annuels Budgets Annuels Exercice de Priorisation Portfolio Management
  • 19. Project Charters & Business Cases  Business Cases using the Net Present Value (NPV) as Financial evaluation criteria (taking into account Prince2 Principles & Theme)  Impact on Quality of Services measured via the ‘baromètre de la Satisfaction Client’  33 types of critical technical competencies were identified and tracked in Business Cases Project Charters (mix of PID & PDD) ensure a standardised documentation ensuring information on :  Context and Objectives  Scope and Perimeter (in & out)  Impact and dependencies  Risk inventory (1st iteration)  Planning (1st iteration)  Organisation
  • 20. Projects Portfolio Stages 31 43 Gestion de la Capacité des ETP ‘Projet’
  • 21. Today: ‘Flying Doctors’ Activity CMMI Project Management Maturity Model used to measure our performance Based on 2013 Pilots (MCH, PIVO, ‘Achat Bus’, …), implementation of a Coaching function triggered by Business Requests or by malfunctioning Projects. Today’s log :