SlideShare a Scribd company logo
1 of 59
PROJECT MANAGEMENT
TIME MANAGEMENT TECHNIQUES
Presented by:
Piyush Agarwal
2015MB22
Completing a project on time and within budget is not an
easy task. The project scheduling phase plays a central role
in predicting both the time and cost aspects of a project.
More precisely, it determines a timetable in order to be
able to predict the expected time and cost of each
individual activity.
ABSTRACT
Introduction
• What is the expected project finish date?
• How can precedence relations between activities be
modeled in a network?
• What are the expected activity start and finish times?
• What is the effect of variability in activity time
estimates on the project duration?
Project Definition Phase
• In the definition phase of a project’s life cycle, the organization defines the
project objectives, the project specifications and requirements and the
organization of the entire project. In doing so, the organization decides on how
it is going to achieve all project objectives.
• The Work Breakdown Structure (WBS) is a fundamental concept of the
denition phase that, along with the Organizational Breakdown Structure (OBS),
identies the set of activities needed to achieve the project goal as well as the
responsibilities of the project team for the various subparts of the project.
• This information needs to be transformed into a network diagram that identifies
a list of project activities and the technological links with the other activities.
This project network is an easy and accessible tool for the critical path
calculations to determine the earliest and latest activity start times of the
scheduling phase.
WBS and OBS
• The preparation of a Work Breakdown Structure (WBS) is an important step in
managing and mastering the inherent complexity of the project. It involves the
decomposition of major project deliverables into smaller, more manageable
components until the deliverables are defined in sufficient detail to support
development of project activities (PMBOK 2004).
• The WBS is a tool that defines the project and groups the project’s discrete
work elements to help organize and define the total work scope of the project.
It provides the necessary framework for detailed cost estimation and control
along with providing guidance for schedule development and control. Each
descending level of the WBS represents an increased level of detailed definition
of the project work.
Network Analysis
• To construct a complete and detailed WBS, the work packages of a WBS need to be
further subdivided into activities.
• It might improve the level of detail and accuracy of cost, duration and resource
estimates which serve as inputs for the construction of a project network and
scheduling phase.
• The definition phase, which determines the list of activities, the precedence relations,
possible resource requirements and the major milestones of the project, is different
from the scheduling phase in the level of detail and the timing of project activities.
• The scheduling phase aims at the determination of start and finish times of each activity
of the project, and consequently, determines the milestones in detail. This can only be
done after the construction of the network in the definition phase.
• Incorporating these technological links between any pair of activities is a first step in the
construction of the project network. A network consists of nodes and arcs and
incorporates all the activities and their technological precedence relations. A network
can be seen as a graph G(N, A) where the set N is used to denote the set of nodes and A
to denote the set of arcs. The network has a single start node and a single end node and
is used as an input for the scheduling phase
9
Project Network
• Network analysis is the general name given to certain specific
techniques which can be used for the planning, management and
control of projects
■ Use of nodes and arrows
Arrows  An arrow leads from tail to head directionally
– Indicate ACTIVITY, a time consuming effort that is required to
perform a part of the work.
Nodes  A node is represented by a circle
- Indicate EVENT, a point in time where one or more activities start
and/or finish.
• Activity
– A task or a certain amount of work required in the project
– Requires time to complete
– Represented by an arrow
• Dummy Activity
– Indicates only precedence relationships
– Does not require any time of effort
10
■ Event
– Signals the beginning or ending of an activity
– Designates a point in time
– Represented by a circle (node)
■ Network
– Shows the sequential relationships among activities
using nodes and arrows
Activity-on-node (AON)
nodes represent activities, and arrows show precedence
relationships
Activity-on-arrow (AOA)
arrows represent activities and nodes are events for points in
time
Project Network
• One type is the activity-on-arc (AOA) project network, where each activity is represented by an arc. A
node is used to separate an activity (an outgoing arc) from each of its immediate predecessors (an
incoming arc). The sequencing of the arcs thereby shows the precedence relationships between the
activities.
• The second type is the activity-on-node (AON) project network, where each activity is represented by
a node. The arcs then are used just to show the precedence relationships between the activities. In
particular, the node for each activity with immediate predecessors has an arc coming in from each of
these predecessors.
darla/smbs/vit 12
AOA Project Network for House
3
2 0
1
3
1 1
1
1 2 4 6 7
3
5
Lay
foundation
Design house
and obtain
financing
Order and
receive
materials
Dummy
Finish
work
Select
carpet
Select
paint
Build
house
AON Project Network for House
1
3
2
2
4
3
3
1 5
1
6
1
7
1
Start
Design house and
obtain financing
Order and receive
materials
Select paint
Select carpet
Lay foundations Build house
Finish work
13
Situations in network diagram
A
B
C
A must finish before either B or C can start
A
B
C both A and B must finish before C can start
D
C
B
A
both A and C must finish before either of B
or D can start
A
C
B
D
Dummy
A must finish before B can start
both A and C must finish before D can start
My word.....
My purpose here is to give a few ideas about PERT , CPM
& other project management tools for entrepreneurs .
These are introductory ideas. Be an Entrepreneur, change
the society, change the world. Go with positive spirit.
Please pass this presentation to all those who might need
it. Let us spread knowledge as widely as possible. I
welcome your suggestions. I also request you to help me
in spreading social entrepreneurship across the globe –
for which I need support of you people – not of any VIP.
With your help, I can spread the ideas – for which we
stand....
15
History of CPM/PERT
■ Critical Path Method (CPM)
– E I Du Pont de Nemours & Co. (1957) for construction
of new chemical plant and maintenance shut-down
– Deterministic task times
– Activity-on-node network construction
– Repetitive nature of jobs
■ Project Evaluation and Review Technique (PERT)
– U S Navy (1958) for the POLARIS missile program
– Multiple task time estimates (probabilistic nature)
– Activity-on-arrow network construction
– Non-repetitive jobs (R & D work)
What is CPM ?
■ Critical Path Method = here we try to identify the
critical path for completion of a project. Cricial = very
important
■ When we are implementing a project, we are doing
a series of activities, which are called project. There
are many ways to do a project. In CPM, we try to pick
up the path which consists of all the activities which
cannot be delayed. This path requires greater
attention.
Why is CPM more important ?
■ If an activity is on CPM, it cannot be delayed. Other
activities can be delayed, but the activities on CPM
cannot be delayed. Delay of one day will delay the
project.
What is SLACK?
■You can delay other activities (other than Critical Path activities ).
–Thus there is slack (means you can delay some activities ).
■ Slack denotes flexibility / freedom / ease on the part of those
implementing the project
What is PERT ?
■ PERT = project evaluation and review technique
■ Here we try to look at each activity and try to find
out expected time to complete the project.
What is the difference between
PERT & CPM?
■ PERT gives us the best possible estimate of doing
the project ( in time).
■ CPM tells us about activities which are critical
(delay in these activities will delay the project
Network example
Illustration of network analysis of a minor redesign of a product and
its associated packaging.
The key question is: How long will it take to complete this project ?
For clarity, this list is kept to a minimum by specifying only
immediate relationships, that is relationships involving activities
that "occur near to each other in time".
darla/smbs/vit
Questions to prepare activity network
■ Is this a Start Activity?
■ Is this a Finish Activity?
■ What Activity Precedes this?
■ What Activity Follows this?
■ What Activity is Concurrent with this?
CPM calculation
■ Path
– A connected sequence of activities leading from the starting
event to the ending event
■ Critical Path
– The longest path (time); determines the project duration
■ Critical Activities
– All of the activities that make up the critical path
Forward Pass
■ Earliest Start Time (ES)
– earliest time an activity can start
– ES = maximum EF of immediate predecessors
■ Earliest finish time (EF)
– earliest time an activity can finish
– earliest start time plus activity time
EF= ES + t
Latest Start Time (LS)
Latest time an activity can start without delaying critical path
time
LS= LF - t
Latest finish time (LF)
latest time an activity can be completed without delaying
critical path time
LS = minimum LS of immediate predecessors
Backward Pass
CPM analysis
■ Draw the CPM network
■ Analyze the paths through the network
■ Determine the float for each activity
– Compute the activity’s float
float = LS - ES = LF - EF
– Float is the maximum amount of time that this
activity can be delay in its completion before it
becomes a critical activity, i.e., delays completion of
the project
■ Find the critical path is that the sequence of activities
and events where there is no “slack” i.e.. Zero slack
– Longest path through a network
■ Find the project duration is minimum project completion
time
CPM Example:
■ CPM Network
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17 h, 9
i, 6
j, 12
CPM Example
■ ES and EF Times
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17 h, 9
i, 6
j, 12
0 6
0 8
0 5
CPM Example
■ ES and EF Times
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17 h, 9
i, 6
j, 12
0 6
0 8
0 5
5 14
8 21
6 23
6 21
CPM Example
■ ES and EF Times
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17 h, 9
i, 6
j, 12
0 6
0 8
0 5
5 14
8 21 21 33
6 23
21 30
23 29
6 21
Project’s EF = 33
CPM Example
■ LS and LF Times
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17
h, 9
i, 6
j, 12
0 6
0 8
0 5
5 14
8 21
21 33
6 23
21 30
23 29
6 21
21 33
27 33
24 33
CPM Example
■ LS and LF Times
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17
h, 9
i, 6
j, 12
0 6
0 8
0 5
5 14
8 21
21 33
6 23
21 30
23 29
6 21
4 10
0 8
7 12
12 21
21 33
27 33
8 21
10 27
24 33
18 24
CPM Example
■ Float
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17
h, 9
i, 6
j, 12
0 6
0 8
0 5
5 14
8 21 21 33
6 23
21 30
23 29
6 21
3 9
0 8
7 12
12 21
21 33
27 33
8 21
10 27
24 33
9 24
3 4
3
3
4
0
0
7
7
0
CPM Example
■ Critical Path
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17 h, 9
i, 6
j, 12
darla/smbs/vit
PERT
■ PERT is based on the assumption that an activity’s
duration follows a probability distribution instead of
being a single value
■ Three time estimates are required to compute the
parameters of an activity’s duration distribution:
– pessimistic time (tp ) - the time the activity would
take if things did not go well
– most likely time (tm ) - the consensus best estimate
of the activity’s duration
– optimistic time (to ) - the time the activity would
take if things did go well
Mean (expected time): te =
tp + 4 tm + to
6
Variance: Vt = 2 =
tp - to
6
2
PERT analysis
■ Draw the network.
■ Analyze the paths through the network and find the
critical path.
■ The length of the critical path is the mean of the project
duration probability distribution which is assumed to be
normal
■ The standard deviation of the project duration probability
distribution is computed by adding the variances of the
critical activities (all of the activities that make up the
critical path) and taking the square root of that sum
■ Probability computations can now be made using the
normal distribution table.
Probability computation
Determine probability that project is completed within specified time
Z =
x - 

where  = tp = project mean time
 = project standard mean time
x = (proposed ) specified time
Normal Distribution of Project Time
 = tp Time
x
Z
Probability
PERT Example
Immed. Optimistic Most Likely Pessimistic
Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.)
A -- 4 6 8
B -- 1 4.5 5
C A 3 3 3
D A 4 5 6
E A 0.5 1 1.5
F B,C 3 4 5
G B,C 1 1.5 5
H E,F 5 6 7
I E,F 2 5 8
J D,H 2.5 2.75 4.5
K G,I 3 5 7
PERT Example
A
D
C
B
F
E
G
I
H
K
J
PERT Network
PERT Example
Activity Expected Time Variance
A 6 4/9
B 4 4/9
C 3 0
D 5 1/9
E 1 1/36
F 4 1/9
G 2 4/9
H 6 1/9
I 5 1
J 3 1/9
K 5 4/9
PERT Example
Activity ES EF LS LF Slack
A 0 6 0 6 0
*critical
B 0 4 5 9
5
C 6 9 6 9 0 *
D 6 11 15 20 9
E 6 7 12 13 6
F 9 13 9 13
0 *
G 9 11 16 18 7
H 13 19 14 20
1
PERT Example
Vpath = VA + VC + VF + VI + VK
= 4/9 + 0 + 1/9 + 1 + 4/9
= 2
path = 1.414
z = (24 - 23)/(24-23)/1.414 = .71
From the Standard Normal Distribution table:
P(z < .71) = .5 + .2612 = .7612
Project Crashing
■ Crashing
– reducing project time by expending additional
resources
■ Crash time
– an amount of time an activity is reduced
■ Crash cost
– cost of reducing activity time
■ Goal
– reduce project duration at minimum cost
Activity crashing
Activity time
Crashing activity
Crash
time
Crash
cost
Normal Activity
Normal
time
Normal
cost
Slope = crash cost per unit time
Time-Cost Relationship
 Crashing costs increase as project duration decreases
 Indirect costs increase as project duration increases
 Reduce project length as long as crashing costs are less than
indirect costs
Time-Cost Tradeoff
time
Direct cost
Indirect
cost
Total project cost
Min total cost =
optimal project
time
Project Crashing example
1
12
2
8
4
12
3
4 5
4
6
4
7
4
Time Cost data
Activity Normal
time
Normal
cost Rs
Crash
time
Crash
cost Rs
Allowable
crash time
slope
1
2
3
4
5
6
7
12
8
4
12
4
4
4
3000
2000
4000
50000
500
500
1500
7
5
3
9
1
1
3
5000
3500
7000
71000
1100
1100
22000
5
3
1
3
3
3
1
400
500
3000
7000
200
200
7000
75000 110700
1
12
2
8
3
4 5
4
6
4
7
4
R400
R500
R3000
R7000
R200
R200
R700
12
4
Project duration = 36
From…..
To…..
1
7
2
8
3
4 5
4
6
4
7
4
R400
R500
R3000
R7000
R200
R200
R700
12
4
Project
duration = 31
Additional cost
= R2000
Benefits of CPM/PERT
■ Useful at many stages of project management
■ Mathematically simple
■ Give critical path and slack time
■ Provide project documentation
■ Useful in monitoring costs
•How long will the entire project take to be completed? What are the
risks involved?
•Which are the critical activities or tasks in the project which could
delay the entire project if they were not completed on time?
•Is the project on schedule, behind schedule or ahead of schedule?
•If the project has to be finished earlier than planned, what is the best
way to do this at the least cost?
CPM/PERT can answer the following important
questions:
Limitations to CPM/PERT
■ Clearly defined, independent and stable activities
■ Specified precedence relationships
■ Over emphasis on critical paths
■ Deterministic CPM model
■ Activity time estimates are subjective and depend on
judgment
■ PERT assumes a beta distribution for these time estimates,
but the actual distribution may be different
■ PERT consistently underestimates the expected project
completion time due to alternate paths becoming critical
To overcome the limitation, Monte Carlo simulations can be
performed on the network to eliminate the optimistic bias
Computer Software
for Project Management
■ Microsoft Project (Microsoft Corp.)
■ MacProject (Claris Corp.)
■ PowerProject (ASTA Development Inc.)
■ Primavera Project Planner (Primavera)
■ Project Scheduler (Scitor Corp.)
■ Project Workbench (ABT Corp.)
Gantt Charts
• The Gantt chart is named after its originator Henry Gantt and displays a
timetable for each activity of the project. Each activity is shown as a
block or bar and drawn to scale in time. The timescale is usually drawn
horizontally while the different activities are displayed on the vertical
axis.
• This chart is used for scheduling and is often used in conjunction with
the project network to show the technological dependencies between
activities.
• The bars represent the earliest start and finish times of each activity of
the example project. The gray lines following the activity bars represent
the activity slack, and hence, shifting activities towards the end of these
gray bars results in the corresponding LSS. Activities without slack (i.e.
activities 1, 3, 5, 10, 12, 13 and 14) belong to the critical path and need
the attention of the project manager.
All The best

More Related Content

Similar to pert-cpm.pptx

Chapter 4.pptx
Chapter 4.pptxChapter 4.pptx
Chapter 4.pptxssuser8cd298
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pertSheetu Goel
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTsalsa moyara
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management UploadBhuWan Khadka
 
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptxSession 9 - Project scheduling-PERT-CPM-Network diagram.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptxAlRashedinKawser2
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxMdSabujHossen2
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxMdSabujHossen2
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysisHarinadh Karimikonda
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesSAJID ALI RUK
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering EconomicsDeepak Paithankar
 
Pert
PertPert
Pertcorvinno
 
3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdf3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdfPabitraMitra3
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 

Similar to pert-cpm.pptx (20)

Chapter 4.pptx
Chapter 4.pptxChapter 4.pptx
Chapter 4.pptx
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management Upload
 
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptxSession 9 - Project scheduling-PERT-CPM-Network diagram.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
 
PERT CPM Intro
PERT CPM IntroPERT CPM Intro
PERT CPM Intro
 
Pert 182
Pert 182Pert 182
Pert 182
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
Pert
PertPert
Pert
 
3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdf3210cpmslideshare-1610302073773770419.pdf
3210cpmslideshare-1610302073773770419.pdf
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 

More from Sougata Das

JGP PROFILE civil engineering deptartment
JGP PROFILE civil engineering deptartmentJGP PROFILE civil engineering deptartment
JGP PROFILE civil engineering deptartmentSougata Das
 
76107373-Waste-Water-Treatment-Process.ppt
76107373-Waste-Water-Treatment-Process.ppt76107373-Waste-Water-Treatment-Process.ppt
76107373-Waste-Water-Treatment-Process.pptSougata Das
 
Direct-Bendng-Stress-pptx IMP.pptx
Direct-Bendng-Stress-pptx IMP.pptxDirect-Bendng-Stress-pptx IMP.pptx
Direct-Bendng-Stress-pptx IMP.pptxSougata Das
 
Wind-Analysis-Building Sdas.ppt
Wind-Analysis-Building Sdas.pptWind-Analysis-Building Sdas.ppt
Wind-Analysis-Building Sdas.pptSougata Das
 
CENTROID & MI.pptx
CENTROID & MI.pptxCENTROID & MI.pptx
CENTROID & MI.pptxSougata Das
 

More from Sougata Das (6)

JGP PROFILE civil engineering deptartment
JGP PROFILE civil engineering deptartmentJGP PROFILE civil engineering deptartment
JGP PROFILE civil engineering deptartment
 
76107373-Waste-Water-Treatment-Process.ppt
76107373-Waste-Water-Treatment-Process.ppt76107373-Waste-Water-Treatment-Process.ppt
76107373-Waste-Water-Treatment-Process.ppt
 
Direct-Bendng-Stress-pptx IMP.pptx
Direct-Bendng-Stress-pptx IMP.pptxDirect-Bendng-Stress-pptx IMP.pptx
Direct-Bendng-Stress-pptx IMP.pptx
 
Wind-Analysis-Building Sdas.ppt
Wind-Analysis-Building Sdas.pptWind-Analysis-Building Sdas.ppt
Wind-Analysis-Building Sdas.ppt
 
CENTROID & MI.pptx
CENTROID & MI.pptxCENTROID & MI.pptx
CENTROID & MI.pptx
 
tall.pptx
tall.pptxtall.pptx
tall.pptx
 

Recently uploaded

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 

Recently uploaded (20)

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 

pert-cpm.pptx

  • 1. PROJECT MANAGEMENT TIME MANAGEMENT TECHNIQUES Presented by: Piyush Agarwal 2015MB22
  • 2. Completing a project on time and within budget is not an easy task. The project scheduling phase plays a central role in predicting both the time and cost aspects of a project. More precisely, it determines a timetable in order to be able to predict the expected time and cost of each individual activity. ABSTRACT
  • 3. Introduction • What is the expected project finish date? • How can precedence relations between activities be modeled in a network? • What are the expected activity start and finish times? • What is the effect of variability in activity time estimates on the project duration?
  • 4. Project Definition Phase • In the definition phase of a project’s life cycle, the organization defines the project objectives, the project specifications and requirements and the organization of the entire project. In doing so, the organization decides on how it is going to achieve all project objectives. • The Work Breakdown Structure (WBS) is a fundamental concept of the denition phase that, along with the Organizational Breakdown Structure (OBS), identies the set of activities needed to achieve the project goal as well as the responsibilities of the project team for the various subparts of the project. • This information needs to be transformed into a network diagram that identies a list of project activities and the technological links with the other activities. This project network is an easy and accessible tool for the critical path calculations to determine the earliest and latest activity start times of the scheduling phase.
  • 5. WBS and OBS • The preparation of a Work Breakdown Structure (WBS) is an important step in managing and mastering the inherent complexity of the project. It involves the decomposition of major project deliverables into smaller, more manageable components until the deliverables are defined in sufficient detail to support development of project activities (PMBOK 2004). • The WBS is a tool that defines the project and groups the project’s discrete work elements to help organize and define the total work scope of the project. It provides the necessary framework for detailed cost estimation and control along with providing guidance for schedule development and control. Each descending level of the WBS represents an increased level of detailed definition of the project work.
  • 6.
  • 7.
  • 8. Network Analysis • To construct a complete and detailed WBS, the work packages of a WBS need to be further subdivided into activities. • It might improve the level of detail and accuracy of cost, duration and resource estimates which serve as inputs for the construction of a project network and scheduling phase. • The definition phase, which determines the list of activities, the precedence relations, possible resource requirements and the major milestones of the project, is different from the scheduling phase in the level of detail and the timing of project activities. • The scheduling phase aims at the determination of start and finish times of each activity of the project, and consequently, determines the milestones in detail. This can only be done after the construction of the network in the definition phase. • Incorporating these technological links between any pair of activities is a first step in the construction of the project network. A network consists of nodes and arcs and incorporates all the activities and their technological precedence relations. A network can be seen as a graph G(N, A) where the set N is used to denote the set of nodes and A to denote the set of arcs. The network has a single start node and a single end node and is used as an input for the scheduling phase
  • 9. 9 Project Network • Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects ■ Use of nodes and arrows Arrows  An arrow leads from tail to head directionally – Indicate ACTIVITY, a time consuming effort that is required to perform a part of the work. Nodes  A node is represented by a circle - Indicate EVENT, a point in time where one or more activities start and/or finish. • Activity – A task or a certain amount of work required in the project – Requires time to complete – Represented by an arrow • Dummy Activity – Indicates only precedence relationships – Does not require any time of effort
  • 10. 10 ■ Event – Signals the beginning or ending of an activity – Designates a point in time – Represented by a circle (node) ■ Network – Shows the sequential relationships among activities using nodes and arrows Activity-on-node (AON) nodes represent activities, and arrows show precedence relationships Activity-on-arrow (AOA) arrows represent activities and nodes are events for points in time Project Network
  • 11. • One type is the activity-on-arc (AOA) project network, where each activity is represented by an arc. A node is used to separate an activity (an outgoing arc) from each of its immediate predecessors (an incoming arc). The sequencing of the arcs thereby shows the precedence relationships between the activities. • The second type is the activity-on-node (AON) project network, where each activity is represented by a node. The arcs then are used just to show the precedence relationships between the activities. In particular, the node for each activity with immediate predecessors has an arc coming in from each of these predecessors.
  • 12. darla/smbs/vit 12 AOA Project Network for House 3 2 0 1 3 1 1 1 1 2 4 6 7 3 5 Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house AON Project Network for House 1 3 2 2 4 3 3 1 5 1 6 1 7 1 Start Design house and obtain financing Order and receive materials Select paint Select carpet Lay foundations Build house Finish work
  • 13. 13 Situations in network diagram A B C A must finish before either B or C can start A B C both A and B must finish before C can start D C B A both A and C must finish before either of B or D can start A C B D Dummy A must finish before B can start both A and C must finish before D can start
  • 14. My word..... My purpose here is to give a few ideas about PERT , CPM & other project management tools for entrepreneurs . These are introductory ideas. Be an Entrepreneur, change the society, change the world. Go with positive spirit. Please pass this presentation to all those who might need it. Let us spread knowledge as widely as possible. I welcome your suggestions. I also request you to help me in spreading social entrepreneurship across the globe – for which I need support of you people – not of any VIP. With your help, I can spread the ideas – for which we stand....
  • 15. 15 History of CPM/PERT ■ Critical Path Method (CPM) – E I Du Pont de Nemours & Co. (1957) for construction of new chemical plant and maintenance shut-down – Deterministic task times – Activity-on-node network construction – Repetitive nature of jobs ■ Project Evaluation and Review Technique (PERT) – U S Navy (1958) for the POLARIS missile program – Multiple task time estimates (probabilistic nature) – Activity-on-arrow network construction – Non-repetitive jobs (R & D work)
  • 16. What is CPM ? ■ Critical Path Method = here we try to identify the critical path for completion of a project. Cricial = very important ■ When we are implementing a project, we are doing a series of activities, which are called project. There are many ways to do a project. In CPM, we try to pick up the path which consists of all the activities which cannot be delayed. This path requires greater attention.
  • 17. Why is CPM more important ? ■ If an activity is on CPM, it cannot be delayed. Other activities can be delayed, but the activities on CPM cannot be delayed. Delay of one day will delay the project.
  • 18. What is SLACK? ■You can delay other activities (other than Critical Path activities ). –Thus there is slack (means you can delay some activities ). ■ Slack denotes flexibility / freedom / ease on the part of those implementing the project
  • 19. What is PERT ? ■ PERT = project evaluation and review technique ■ Here we try to look at each activity and try to find out expected time to complete the project.
  • 20. What is the difference between PERT & CPM? ■ PERT gives us the best possible estimate of doing the project ( in time). ■ CPM tells us about activities which are critical (delay in these activities will delay the project
  • 21. Network example Illustration of network analysis of a minor redesign of a product and its associated packaging. The key question is: How long will it take to complete this project ?
  • 22. For clarity, this list is kept to a minimum by specifying only immediate relationships, that is relationships involving activities that "occur near to each other in time".
  • 23. darla/smbs/vit Questions to prepare activity network ■ Is this a Start Activity? ■ Is this a Finish Activity? ■ What Activity Precedes this? ■ What Activity Follows this? ■ What Activity is Concurrent with this?
  • 24. CPM calculation ■ Path – A connected sequence of activities leading from the starting event to the ending event ■ Critical Path – The longest path (time); determines the project duration ■ Critical Activities – All of the activities that make up the critical path
  • 25. Forward Pass ■ Earliest Start Time (ES) – earliest time an activity can start – ES = maximum EF of immediate predecessors ■ Earliest finish time (EF) – earliest time an activity can finish – earliest start time plus activity time EF= ES + t Latest Start Time (LS) Latest time an activity can start without delaying critical path time LS= LF - t Latest finish time (LF) latest time an activity can be completed without delaying critical path time LS = minimum LS of immediate predecessors Backward Pass
  • 26. CPM analysis ■ Draw the CPM network ■ Analyze the paths through the network ■ Determine the float for each activity – Compute the activity’s float float = LS - ES = LF - EF – Float is the maximum amount of time that this activity can be delay in its completion before it becomes a critical activity, i.e., delays completion of the project ■ Find the critical path is that the sequence of activities and events where there is no “slack” i.e.. Zero slack – Longest path through a network ■ Find the project duration is minimum project completion time
  • 27. CPM Example: ■ CPM Network a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12
  • 28. CPM Example ■ ES and EF Times a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5
  • 29. CPM Example ■ ES and EF Times a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 6 23 6 21
  • 30. CPM Example ■ ES and EF Times a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 21 33 6 23 21 30 23 29 6 21 Project’s EF = 33
  • 31. CPM Example ■ LS and LF Times a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 21 33 6 23 21 30 23 29 6 21 21 33 27 33 24 33
  • 32. CPM Example ■ LS and LF Times a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 21 33 6 23 21 30 23 29 6 21 4 10 0 8 7 12 12 21 21 33 27 33 8 21 10 27 24 33 18 24
  • 33. CPM Example ■ Float a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 21 33 6 23 21 30 23 29 6 21 3 9 0 8 7 12 12 21 21 33 27 33 8 21 10 27 24 33 9 24 3 4 3 3 4 0 0 7 7 0
  • 34. CPM Example ■ Critical Path a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12
  • 35. darla/smbs/vit PERT ■ PERT is based on the assumption that an activity’s duration follows a probability distribution instead of being a single value ■ Three time estimates are required to compute the parameters of an activity’s duration distribution: – pessimistic time (tp ) - the time the activity would take if things did not go well – most likely time (tm ) - the consensus best estimate of the activity’s duration – optimistic time (to ) - the time the activity would take if things did go well Mean (expected time): te = tp + 4 tm + to 6 Variance: Vt = 2 = tp - to 6 2
  • 36. PERT analysis ■ Draw the network. ■ Analyze the paths through the network and find the critical path. ■ The length of the critical path is the mean of the project duration probability distribution which is assumed to be normal ■ The standard deviation of the project duration probability distribution is computed by adding the variances of the critical activities (all of the activities that make up the critical path) and taking the square root of that sum ■ Probability computations can now be made using the normal distribution table.
  • 37. Probability computation Determine probability that project is completed within specified time Z = x -   where  = tp = project mean time  = project standard mean time x = (proposed ) specified time
  • 38. Normal Distribution of Project Time  = tp Time x Z Probability
  • 39. PERT Example Immed. Optimistic Most Likely Pessimistic Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.) A -- 4 6 8 B -- 1 4.5 5 C A 3 3 3 D A 4 5 6 E A 0.5 1 1.5 F B,C 3 4 5 G B,C 1 1.5 5 H E,F 5 6 7 I E,F 2 5 8 J D,H 2.5 2.75 4.5 K G,I 3 5 7
  • 41. PERT Example Activity Expected Time Variance A 6 4/9 B 4 4/9 C 3 0 D 5 1/9 E 1 1/36 F 4 1/9 G 2 4/9 H 6 1/9 I 5 1 J 3 1/9 K 5 4/9
  • 42. PERT Example Activity ES EF LS LF Slack A 0 6 0 6 0 *critical B 0 4 5 9 5 C 6 9 6 9 0 * D 6 11 15 20 9 E 6 7 12 13 6 F 9 13 9 13 0 * G 9 11 16 18 7 H 13 19 14 20 1
  • 43. PERT Example Vpath = VA + VC + VF + VI + VK = 4/9 + 0 + 1/9 + 1 + 4/9 = 2 path = 1.414 z = (24 - 23)/(24-23)/1.414 = .71 From the Standard Normal Distribution table: P(z < .71) = .5 + .2612 = .7612
  • 44. Project Crashing ■ Crashing – reducing project time by expending additional resources ■ Crash time – an amount of time an activity is reduced ■ Crash cost – cost of reducing activity time ■ Goal – reduce project duration at minimum cost
  • 45. Activity crashing Activity time Crashing activity Crash time Crash cost Normal Activity Normal time Normal cost Slope = crash cost per unit time
  • 46. Time-Cost Relationship  Crashing costs increase as project duration decreases  Indirect costs increase as project duration increases  Reduce project length as long as crashing costs are less than indirect costs Time-Cost Tradeoff time Direct cost Indirect cost Total project cost Min total cost = optimal project time
  • 48. Time Cost data Activity Normal time Normal cost Rs Crash time Crash cost Rs Allowable crash time slope 1 2 3 4 5 6 7 12 8 4 12 4 4 4 3000 2000 4000 50000 500 500 1500 7 5 3 9 1 1 3 5000 3500 7000 71000 1100 1100 22000 5 3 1 3 3 3 1 400 500 3000 7000 200 200 7000 75000 110700
  • 49. 1 12 2 8 3 4 5 4 6 4 7 4 R400 R500 R3000 R7000 R200 R200 R700 12 4 Project duration = 36 From….. To….. 1 7 2 8 3 4 5 4 6 4 7 4 R400 R500 R3000 R7000 R200 R200 R700 12 4 Project duration = 31 Additional cost = R2000
  • 50. Benefits of CPM/PERT ■ Useful at many stages of project management ■ Mathematically simple ■ Give critical path and slack time ■ Provide project documentation ■ Useful in monitoring costs •How long will the entire project take to be completed? What are the risks involved? •Which are the critical activities or tasks in the project which could delay the entire project if they were not completed on time? •Is the project on schedule, behind schedule or ahead of schedule? •If the project has to be finished earlier than planned, what is the best way to do this at the least cost? CPM/PERT can answer the following important questions:
  • 51. Limitations to CPM/PERT ■ Clearly defined, independent and stable activities ■ Specified precedence relationships ■ Over emphasis on critical paths ■ Deterministic CPM model ■ Activity time estimates are subjective and depend on judgment ■ PERT assumes a beta distribution for these time estimates, but the actual distribution may be different ■ PERT consistently underestimates the expected project completion time due to alternate paths becoming critical To overcome the limitation, Monte Carlo simulations can be performed on the network to eliminate the optimistic bias
  • 52. Computer Software for Project Management ■ Microsoft Project (Microsoft Corp.) ■ MacProject (Claris Corp.) ■ PowerProject (ASTA Development Inc.) ■ Primavera Project Planner (Primavera) ■ Project Scheduler (Scitor Corp.) ■ Project Workbench (ABT Corp.)
  • 53. Gantt Charts • The Gantt chart is named after its originator Henry Gantt and displays a timetable for each activity of the project. Each activity is shown as a block or bar and drawn to scale in time. The timescale is usually drawn horizontally while the different activities are displayed on the vertical axis. • This chart is used for scheduling and is often used in conjunction with the project network to show the technological dependencies between activities. • The bars represent the earliest start and finish times of each activity of the example project. The gray lines following the activity bars represent the activity slack, and hence, shifting activities towards the end of these gray bars results in the corresponding LSS. Activities without slack (i.e. activities 1, 3, 5, 10, 12, 13 and 14) belong to the critical path and need the attention of the project manager.
  • 54.
  • 55.
  • 56.
  • 57.
  • 58.