SlideShare a Scribd company logo
1 of 5
Rajiv Misra XLRI
Time: 15 minutes
Name:
The 2H Project: sHape and Hoover Dam
Debriefing Questions (put yourviews and then answer the same questions in yourgroup)
1.0 What were the similarities between the project you participated in and the Hoover Dam project?
Adequate resource & manpower planning, project scheduling, execution & monitoring were done
at different stages of project. Prototyping, rescheduling, replanning was involved in both the
project at every milestone setpoint.
2.0 What are the Things that went right and Things that went wrong in the project?
Things that went Right Things that went wrong
Shapes Shapes
Resource planning was adequate (scissors,
Ruler & paper) Time was not managed properly.
Adequate cost was allocated. Milestone was not defined.
Hoover Hoover
Proper Site visit was done with scheduling of Employees health factor & basic necessity were
Activities. challenged for the project
External barrier like rock, water was given
due consideration.
3.0 What do you think would be the main role of the Project Managerbased on yourexperience in
performing and watching these projects?
-A Project manager role starts from successfulinitiation of project planning, prototyping,
executing, monitoring, controlling, scheduling,setting target & achieving them. He should also
replan & reschedule the project accordingly.
4.0 Why was the quality of the drawing on the shape not ‘so good’?
-The drawing part was mentioned at the end of the contract clause, although after knowing that we
should have replanned and scheduled it accordingly, but we failed. No time and importance was
given to the drawing part as to whether it should be done before or after the finished prototype as
for the feasibility.
5.0 What do you think would be the common processes/activities in all projects ?
-1. Project planning
-2. Prototyping
-3. Prioritizing
-4. Execution
-5. Scheduling
-6. Setting milestone
-7. Risk assessment
-8. Commissioning and closure of project
6.0 What would be your reaction the statement ‘ A successfulproject manager in IT can be successful
in a Road project i.e. a successfulproject manager anywhere can be successfulanywhere’
-The above statement totally justifies project manager from any background.
The main duty of the project manager is to utilize his resources at different stage of project i.e
planning, prototyping,execution, and commissioning and to find the critical in those phases and
monitor these phases and schedule and replan them accordingly.
1.0 a) Stakeholder Analysis for Hoover Dam
SL Name of
Stakeholder
Likely Concerns
(What would make them say the project was a success)
1. Government Timely & effectiveness of project
2. Top Management Doing the project as per set goals
3. Project Team Doing project effectively, timely & as per demand.
4. Contractor Making the most out of the investment.
5. Supplier Fulfilling the requirement sufficiently & effectively.
6. Customer Getting the benefits from the project effectively.
1.0 b) Plot some of the Stakeholders on the Power Interest
Matrix
Keep Satisfied Key Player
Minimal Effort Keep Informed
HIGH
LOW
LOW HIGH
Government
Local authority
Project Top Management
Project Team Members
Contractors
Sub-contractors
Labor
End User
Customer
Suppliers
P
O
W
E
R
INTEREST
2.0 Identify some Risk Events
Id Risk Event Impact on
Project
(Identification
of
consequences)
Trigger Prevention
Plan
Contingency
Plan
1 Natural Calamities Project delay &
capital loss
Prioritizing
different
stages of
execution
2 Union Strikes Project delay &
exceeding in
budget
Poor HR
manage
ment
Following &
setting HR
Policies
3.0 Plot the risks on PROBABILTY IMPACT MATRIX
HIGH
LOW
LOW HIGH
Govt policies Natural Calamity
End User Supplier
I
M
P
A
C
T
PROBABILTY

More Related Content

What's hot

Case Study: Cisco Acquisition
Case Study: Cisco AcquisitionCase Study: Cisco Acquisition
Case Study: Cisco AcquisitionDjadja Sardjana
 
Performance management at vitality health enterprise inc
Performance management at vitality health enterprise incPerformance management at vitality health enterprise inc
Performance management at vitality health enterprise incDS Adi Pratomo
 
Case study of webvan - The extravagant rise and fall of Webvan
Case study of webvan - The extravagant rise and fall of WebvanCase study of webvan - The extravagant rise and fall of Webvan
Case study of webvan - The extravagant rise and fall of WebvanRutvik Bapat
 
Alphabet Eyes New Frontiers
Alphabet Eyes New FrontiersAlphabet Eyes New Frontiers
Alphabet Eyes New FrontiersRadha Gupta
 
Managing a global team: Sun Microsystems business case
Managing a global team: Sun Microsystems business caseManaging a global team: Sun Microsystems business case
Managing a global team: Sun Microsystems business caseEmanuele Garzelli
 
Newells strategic management case study
Newells strategic management case studyNewells strategic management case study
Newells strategic management case studyMeghnaJaiswal5
 
Global supply chain case study team8_submit v2
Global supply chain case study team8_submit v2Global supply chain case study team8_submit v2
Global supply chain case study team8_submit v2Meghan Histand
 
100 quotes on Talent Management
100 quotes on Talent Management100 quotes on Talent Management
100 quotes on Talent ManagementVijay Bankar
 
Henry tam at mgi team
Henry tam at mgi teamHenry tam at mgi team
Henry tam at mgi teamDhiraj Meher
 
Mindtree: A community of communities
Mindtree: A community of communitiesMindtree: A community of communities
Mindtree: A community of communitiesRiya Aseef
 
Akshay Patra Foundation
Akshay Patra FoundationAkshay Patra Foundation
Akshay Patra FoundationISHITA BHAYANI
 
Donner case study om
Donner case study   omDonner case study   om
Donner case study omPratik Patel
 
Thomas Green Case Study Presentation.
Thomas Green Case Study Presentation.Thomas Green Case Study Presentation.
Thomas Green Case Study Presentation.Mimansha Bahadur
 
Morgan Stanely Case Study
Morgan Stanely Case StudyMorgan Stanely Case Study
Morgan Stanely Case Studynitishagupta
 

What's hot (20)

Case Study: Cisco Acquisition
Case Study: Cisco AcquisitionCase Study: Cisco Acquisition
Case Study: Cisco Acquisition
 
Performance management at vitality health enterprise inc
Performance management at vitality health enterprise incPerformance management at vitality health enterprise inc
Performance management at vitality health enterprise inc
 
Case study of webvan - The extravagant rise and fall of Webvan
Case study of webvan - The extravagant rise and fall of WebvanCase study of webvan - The extravagant rise and fall of Webvan
Case study of webvan - The extravagant rise and fall of Webvan
 
Alphabet Eyes New Frontiers
Alphabet Eyes New FrontiersAlphabet Eyes New Frontiers
Alphabet Eyes New Frontiers
 
MediSys Corp- Case Study
MediSys Corp- Case Study MediSys Corp- Case Study
MediSys Corp- Case Study
 
Managing a global team: Sun Microsystems business case
Managing a global team: Sun Microsystems business caseManaging a global team: Sun Microsystems business case
Managing a global team: Sun Microsystems business case
 
Newells strategic management case study
Newells strategic management case studyNewells strategic management case study
Newells strategic management case study
 
Global supply chain case study team8_submit v2
Global supply chain case study team8_submit v2Global supply chain case study team8_submit v2
Global supply chain case study team8_submit v2
 
Queueing theory
Queueing theoryQueueing theory
Queueing theory
 
Dakota product
Dakota productDakota product
Dakota product
 
100 quotes on Talent Management
100 quotes on Talent Management100 quotes on Talent Management
100 quotes on Talent Management
 
Henry tam at mgi team
Henry tam at mgi teamHenry tam at mgi team
Henry tam at mgi team
 
Mindtree: A community of communities
Mindtree: A community of communitiesMindtree: A community of communities
Mindtree: A community of communities
 
Akshay Patra Foundation
Akshay Patra FoundationAkshay Patra Foundation
Akshay Patra Foundation
 
SEMCO
SEMCOSEMCO
SEMCO
 
Donner case study om
Donner case study   omDonner case study   om
Donner case study om
 
Thomas Green Case Study Presentation.
Thomas Green Case Study Presentation.Thomas Green Case Study Presentation.
Thomas Green Case Study Presentation.
 
E-HRM and HRIS
E-HRM and HRISE-HRM and HRIS
E-HRM and HRIS
 
Morgan Stanely Case Study
Morgan Stanely Case StudyMorgan Stanely Case Study
Morgan Stanely Case Study
 
Peak Stealing Technologies
Peak Stealing TechnologiesPeak Stealing Technologies
Peak Stealing Technologies
 

Similar to Comparing projects hoover and shape cutting (1)

MANAGEMENT in construction planning and management
MANAGEMENT in construction planning and managementMANAGEMENT in construction planning and management
MANAGEMENT in construction planning and managementMuhammadIrfan561681
 
Drs 255 project management skills
Drs 255 project management skillsDrs 255 project management skills
Drs 255 project management skillspaulyeboah
 
Engineering Project Management
Engineering Project Management Engineering Project Management
Engineering Project Management Nzar Braim
 
Project management : Pert and Cpm
Project management : Pert and CpmProject management : Pert and Cpm
Project management : Pert and CpmShashank Kapoor
 
Sydney Opera House
Sydney Opera HouseSydney Opera House
Sydney Opera HouseMelvin Lim
 
Project management for technologies MGT410
Project management for technologies   MGT410Project management for technologies   MGT410
Project management for technologies MGT410Saqib Imran
 
Software Project Management | An Overview of the Software Project Management
Software Project Management | An Overview of the Software Project ManagementSoftware Project Management | An Overview of the Software Project Management
Software Project Management | An Overview of the Software Project ManagementAhsan Rahim
 
Project management 02112009
Project management 02112009Project management 02112009
Project management 02112009Manish Chaurasia
 
Project Management Diploma
Project Management DiplomaProject Management Diploma
Project Management DiplomaTheunis Venter
 
A presentation on Agile Methodology for Project Managers
A presentation on Agile Methodology for Project ManagersA presentation on Agile Methodology for Project Managers
A presentation on Agile Methodology for Project ManagersAdeolu Adeleye
 
Fundamentals of project management july 7, 2012 revised
Fundamentals of project management july 7, 2012 revisedFundamentals of project management july 7, 2012 revised
Fundamentals of project management july 7, 2012 revisedgorby626
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project ManagementMostafa Ewees
 
Project management course 2020
Project management course 2020Project management course 2020
Project management course 2020Wajdi Ben Rejeb
 
Project management
Project managementProject management
Project managementArnab Ghosh
 
Project scheduling
Project schedulingProject scheduling
Project schedulingJaafer Saeed
 

Similar to Comparing projects hoover and shape cutting (1) (20)

MANAGEMENT in construction planning and management
MANAGEMENT in construction planning and managementMANAGEMENT in construction planning and management
MANAGEMENT in construction planning and management
 
lecture 8 (1).ppt
lecture 8 (1).pptlecture 8 (1).ppt
lecture 8 (1).ppt
 
Drs 255 project management skills
Drs 255 project management skillsDrs 255 project management skills
Drs 255 project management skills
 
Engineering Project Management
Engineering Project Management Engineering Project Management
Engineering Project Management
 
Project management : Pert and Cpm
Project management : Pert and CpmProject management : Pert and Cpm
Project management : Pert and Cpm
 
Project management
Project managementProject management
Project management
 
Project Management
Project ManagementProject Management
Project Management
 
Sydney Opera House
Sydney Opera HouseSydney Opera House
Sydney Opera House
 
Project management for technologies MGT410
Project management for technologies   MGT410Project management for technologies   MGT410
Project management for technologies MGT410
 
Software Project Management | An Overview of the Software Project Management
Software Project Management | An Overview of the Software Project ManagementSoftware Project Management | An Overview of the Software Project Management
Software Project Management | An Overview of the Software Project Management
 
Project management 02112009
Project management 02112009Project management 02112009
Project management 02112009
 
Managing IT Projects
Managing IT ProjectsManaging IT Projects
Managing IT Projects
 
Project
ProjectProject
Project
 
Project Management Diploma
Project Management DiplomaProject Management Diploma
Project Management Diploma
 
A presentation on Agile Methodology for Project Managers
A presentation on Agile Methodology for Project ManagersA presentation on Agile Methodology for Project Managers
A presentation on Agile Methodology for Project Managers
 
Fundamentals of project management july 7, 2012 revised
Fundamentals of project management july 7, 2012 revisedFundamentals of project management july 7, 2012 revised
Fundamentals of project management july 7, 2012 revised
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project Management
 
Project management course 2020
Project management course 2020Project management course 2020
Project management course 2020
 
Project management
Project managementProject management
Project management
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 

Recently uploaded

VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...AgileNetwork
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 

Recently uploaded (17)

VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 

Comparing projects hoover and shape cutting (1)

  • 1. Rajiv Misra XLRI Time: 15 minutes Name: The 2H Project: sHape and Hoover Dam Debriefing Questions (put yourviews and then answer the same questions in yourgroup) 1.0 What were the similarities between the project you participated in and the Hoover Dam project? Adequate resource & manpower planning, project scheduling, execution & monitoring were done at different stages of project. Prototyping, rescheduling, replanning was involved in both the project at every milestone setpoint. 2.0 What are the Things that went right and Things that went wrong in the project? Things that went Right Things that went wrong Shapes Shapes Resource planning was adequate (scissors, Ruler & paper) Time was not managed properly. Adequate cost was allocated. Milestone was not defined. Hoover Hoover Proper Site visit was done with scheduling of Employees health factor & basic necessity were Activities. challenged for the project External barrier like rock, water was given due consideration. 3.0 What do you think would be the main role of the Project Managerbased on yourexperience in performing and watching these projects? -A Project manager role starts from successfulinitiation of project planning, prototyping, executing, monitoring, controlling, scheduling,setting target & achieving them. He should also replan & reschedule the project accordingly. 4.0 Why was the quality of the drawing on the shape not ‘so good’? -The drawing part was mentioned at the end of the contract clause, although after knowing that we should have replanned and scheduled it accordingly, but we failed. No time and importance was given to the drawing part as to whether it should be done before or after the finished prototype as for the feasibility.
  • 2. 5.0 What do you think would be the common processes/activities in all projects ? -1. Project planning -2. Prototyping -3. Prioritizing -4. Execution -5. Scheduling -6. Setting milestone -7. Risk assessment -8. Commissioning and closure of project 6.0 What would be your reaction the statement ‘ A successfulproject manager in IT can be successful in a Road project i.e. a successfulproject manager anywhere can be successfulanywhere’ -The above statement totally justifies project manager from any background. The main duty of the project manager is to utilize his resources at different stage of project i.e planning, prototyping,execution, and commissioning and to find the critical in those phases and monitor these phases and schedule and replan them accordingly. 1.0 a) Stakeholder Analysis for Hoover Dam SL Name of Stakeholder Likely Concerns (What would make them say the project was a success) 1. Government Timely & effectiveness of project 2. Top Management Doing the project as per set goals 3. Project Team Doing project effectively, timely & as per demand. 4. Contractor Making the most out of the investment. 5. Supplier Fulfilling the requirement sufficiently & effectively. 6. Customer Getting the benefits from the project effectively.
  • 3. 1.0 b) Plot some of the Stakeholders on the Power Interest Matrix Keep Satisfied Key Player Minimal Effort Keep Informed HIGH LOW LOW HIGH Government Local authority Project Top Management Project Team Members Contractors Sub-contractors Labor End User Customer Suppliers P O W E R INTEREST
  • 4. 2.0 Identify some Risk Events Id Risk Event Impact on Project (Identification of consequences) Trigger Prevention Plan Contingency Plan 1 Natural Calamities Project delay & capital loss Prioritizing different stages of execution 2 Union Strikes Project delay & exceeding in budget Poor HR manage ment Following & setting HR Policies
  • 5. 3.0 Plot the risks on PROBABILTY IMPACT MATRIX HIGH LOW LOW HIGH Govt policies Natural Calamity End User Supplier I M P A C T PROBABILTY