2. OUTLINE
Systems of a drilling rig
Broad classification of drilling rigs
• Parts/ Features
• Specificity
• Capacity ranges
• Pros and Cons
• Evolution : 1st to Current Generation
Types of drilling rigs (6 offshore rigs)
3. Systems of a drilling rig
Hoisting system
Rotating system
Circulating system
Well control system
Power system
Well monitoring system
Mooring system (offshore)
4. Broad classification of drilling Rigs
Classification
of drilling
rigs
By Power used: Mechanical, Electric,
Hydraulic, Pneumatic and Steam
By location, Pipe used (cable,
conventional and coiled tubing
By Height: Single, double
and triple
By method of Rotation: non-rotation, rotary
table, top drive, sonic, hammer.
5. Types of Drilling Rigs
Drilling
Rigs
Land
Rigs
Conventional
Mobile
Offshore
Rigs
Floating
Semi-submersible
Drill Ship
Bottom
Supported
Platform
Barge
Jack-up etc.
6. Semi-submersible
Parts / Features
• Subsea wellhead
• Submerged pontoon keeps it afloat
• Bottled or column stabilized
• Connected to deck by columns
• Moonpool below the derrick
• Less cross-sectional area in the water line
• High degree of stability
• Dynamic positioning / anchor mooring
Source: Offshore drilling volume 1
7. Semi-submersible specificity
Transportation: Towed / self propelled
Spudding the Rig: Temporary and permanent guide base adopted
Stability: Tolerates harsh conditions as a result of space between the columns.
compensate vertical motion using telescopic joint; tensioner system ; Wave
motion compensator system
Anchoring: use of conventional mooring / dynamic positioning with thrusters
{short baseline system (4 hydrophones and at least one transponder) or Long
baseline system (4 transducers and 4 transponders)}
Functionality: Utilized in drilling exploratory and development wells.
8. Semi-submersible
Capacity Ranges Specification Range
Size (ft.) L*W*H 246 *230* 90 to 390* 260* 150
Water Depth (ft.) up to 12,000
Drilling depth (ft.) 25,000 to 40,000
Variable deck load (LT) 1,700 to 10,000 LT
Hook load (ST) 200 t0 1500
Displacement 15,000 to 60,000 LT
BOP rating psi 10,000 to 15,000
Derrick load 1,000,000 to > 2,000,000 lbs
Mud pumps 2 to 6 pumps
Quarters capacity 68 to 180 persons
9. Semi-submersible
Pros
• Mobile with high transit speed (~10
kts)
• Highly stable with minimal response to
wave action
• Large deck area
Pros and Cons
Cons
• High initial and operating costs
• Limited deck load (due to buoyancy)
• Structural fatigue
• Expensive to move over large distances
• Limited dry-docking facilities available
• Difficulty in handling mooring systems
and landing BOP stack in rough seas
10. Semi-submersible
• Constructed 1961 - 1972
• Max depth - 1,500 ft.
• Max variable deck load –
2k tons
• BOP stack – 10,000 psi
rating
• Conventional mooring
• No top drive
1st Gen
• Constructed 1973 -
1979
• Max water depth –
2,000 ft.
• Conventional mooring
• No top drive
2nd Gen • Constructed 1980 - 1985
• Avg. WD – 2,500 ft. Max
– 4000 ft.
• Conventional and DP
• No top drive
• Built for harsh
environments e.g. North
Sea
3rd Gen
• Constructed 1986 -1997
• Water depth- 2,500 to
6,500 ft.
• DP and conventional
• Top drive available
• e.g. Oceanics Smith 3
4th Gen
Evolution (First Semi-submersible: Shell’s Blue Water 1- 1962)
11. Semi-submersible
• Constructed 1998 - 2004
• Water depth – 7,000 to
10,000 ft.
• Most are DP (Dynamically
positioned)
• e.g. Sedco Forex Express
2000 5th Gen
• Constructed 2009 onwards
• Max water depth – 10,000 ft.
• Dual derrick
• Drilling depth > 30,000 ft
• e.g. Ensco 8500s
6th Gen • 2015 onwards
• Max water depth – 12,000 ft.
• Dual derrick
• Larger Variable deck load >
10,000 T
• Drilling depth up to 40,000 ft.
• Can accommodate dual BOPs
7th Gen
Evolution
12. Drill Ship
Parts / Features
• Subsea wellhead
• Self propelled
• High storage capacity
• Capacity for dual derrick
• Dynamic positioning / anchor mooring
Source: Offshore drilling volume 1
13. Drill Ship specificity
Transportation: Self propelled
Spudding the Rig: Temporary and permanent guide base adopted
Stability: compensate vertical motion using telescopic joint; tensioner system ;
Wave motion compensator system
Anchoring: use of conventional mooring / dynamic positioning with thrusters
{short baseline system (4 hydrophones and at least one transponder) or Long
baseline system (4 transducers and 4 transponders)}
Functionality: Utilized in drilling exploratory and development wells.
14. Drill Ship
Capacity Ranges Specification Range
Size (ft.) L*W 500 *120 to 800* 180
Water Depth (ft.) up to 14,000
Drilling depth (ft.) 20,000 to 45,000
Variable deck load (T) 3,000 to 30,000 T
Hook load (ST) 200 to 1500
Power (kw) up to 100,000
BOP rating psi 10,000 to 20,000
Mud pumps 2 to 6 pumps
Quarters capacity 68 to 250 persons
15. Drill Ship
Pros
• Mobile with high transit speed up to 16
kts
• Greater deck and total load capacity
than semi-submersible and jack-ups
• Low mobilization costs
• Low initial and operating costs
• Superior sea worthiness and survival
capability
Pros and Cons
Cons
• Poor stability in rough sea areas
• Minimum deck area
• Difficulty in handling mooring systems
and landing BOP stack in rough seas
16. Drill Ship
• Constructed 1961 –
1970
• Drilling depth – 20,000
ft.
• Max water depth – 1,000
ft.
• Conventional mooring1st Gen
• Constructed 1971 –
1979
• Max water depth – 1,500
ft.
• Max drilling depth –
20,000 ft.
• Conventional mooring
2nd Gen
• Constructed 1980 – 1985
• Max water depth – 3,000
ft.
• Max drilling depth -
~20,000 ft.
• Conventional mooring
3rd Gen
• Constructed 1986 -1997
• Max water depth – 7,000
ft.
• Max drilling depth –
25,000 ft.
• Dynamic positioning
• VDL up to 8,000 T
4th Gen
Evolution (Global Marine Drilling Company commissioned the first drill
ship, CUSS I in 1956)
17. Drill Ship
• Constructed 1998 – 2005
• Max water depth – 10,000 ft.
• Dynamic Positioning
• Drilling depth up to 30,000 ft.
• Dual derrick
• e.g. Saipem 10000
5th Gen
• Constructed 2006 onwards
• Max water depth – 10,000 ft.
• Dynamic positioning
• Dual activity
• e.g. Ocean Rig Olympia
6th Gen
• Constructed 2010 onwards
• Max water depth – 12,000 ft.
• Dynamic positioning
• Dual activity rig
• e.g. Ocean rig Athena
7th Gen
Evolution
18. Jack-up Rig
Parts / Features
• Self Elevating
• Surface wellhead
• Movable legs
• Derrick package as cantilever/ non
cantilever
• Jack-up legs: columnar or truss type
• Hull (for ballasting and de-ballasting)
Truss type Jack-up rig
Source: Offshore drilling volume 1
Columnar Jack-up rig
Source: Petrowiki.org
19. Jack-up Rigs specificity
Jack-up Rigs
Legs
Columnar type
Open Truss type
Stabilization
Mat supported
Spud can
Elevating devices
Hydraulics
Rack and pinion gears
20. Jack-up Rigs specificity
Transportation: Self propelled / Towed
Spudding the Rig: adequate soil testing; preloading (ballasting) the hull
Stability: 3 legs are common, Truss legs aid stability. Air gap requirement.
Anchoring: through the Legs of the jack-up; secondary anchors may be
deployed
Functionality: Utilized in drilling exploratory and also development wells
(cantilever).
21. Jack-up Rig
Capacity Ranges Specification Range
Size (ft.) L*W*H 157* 132* 18 to 291* 336*39
Water Depth (ft.) Up to 625
Drilling depth (ft.) Up to 25,000
Cantilever load (lbm) 1m to 3mlb.
Cantilever length (ft.) 25 to 90
Hook load capacity (kips) 1,400 to 2000
BOP rating psi 10,000 to 15,000
Variable Deck load (T) 1500 to 10,000
Mud pumps pressure (psi) Up to 7,500
Quarters capacity 50 to 120 persons
22. Jack-up Rig
Pros
• Mobility
• Stable when elevated
• Low cost (construction and
maintenance)
• Efficient
Pros and Cons
Cons
• Dependent on weather windows for
placement
• Restricted to shallow areas
• Sea flour erosion
• Possible collapse as a result of soil
fluidization from blowouts.
23. Jack-up Rig
• Max depth - 300 ft.
• Drilling variable deck load –
2k tons
• Leg length – 300 to 400 ft.
• No Cantilever
1970-1988
• Max water depth – 250 ft.
• Drilling VDL – 1,900 tons
• Leg length – 162 to 336 ft.
• Cantilever load rating – 1m lbs.
1978 - 1982
• Max water depth – 300 ft.
• Drilling VDL – 2,200 tons
• Leg length – 251 to 417 ft.
• Cantilever load rating – 1m
lbs.
1981 - 1983
Evolution (Colonel Leon B Delong: first jack-up drilling rig, 1954 (Delong Corporation))
24. Jack-up Rig
• Max water depth – 400 ft.
• Drilling VDL – 4000 tons
• Leg length – 496 to 540 ft.
• Cantilever load rating – 1m to
2.5m lbs
1986 - date
• Max water depth – 625 ft.
• Drilling VDL – 10,000 tons
• Leg length – up to 673 ft.
• Cantilever load rating – 3m lbs.
2003 - date
Evolution
25. Tension Leg Platform
Parts / Features
Source: www.phb/wordpress.com/2009/TLP
• Drilling / Production
• Vertical anchoring by tendons to piled seafloor
templates
• Tendons maintained in tension by buoyancy
• Drilling through a drilling template
• Hull: combination of Pontoons and columns
• Use of pontoons in maintaining stability
• Drilled with subsea wellhead. Tie-back to surface
tree for production.
26. Tension Leg Platform specificity
Transportation: Topsides lift / modular installed (foundation is built onshore
and towed to site)
Spudding the Rig: Foundation set using concrete piles (hammered), structure
follows
Stability: Provided by the tendons in tension. Ballasting to control tension. Use
of hydraulic tensioners.
Anchoring: Anchored using the tendons.
Functionality: Utilized mainly for development wells
27. Tension Leg Platform
Capacity Ranges Specification Range
Height (ft.) 100 to 180
Water Depth (ft.) up to 5,000
Drilling depth (ft.) 20,000 to 25,000
Concrete piles (ft.) L*W Up to 500*100
Displacement (T) 10,000 to 100,000
Number of columns 1 to 4
BOP rating psi 10,000 to 15,000
Design Conventional / extended TLP
Quarters capacity 68 to 150+ persons
28. Tension Leg Platform
Pros
• Mobile and reusable
• Good stability with minimal vertical
motion
• Low incremental cost with increasing
depth
• Low maintenance cost
• Possible in deep water
Pros and Cons
Cons
• Initial cost is high
• High subsea cost
• Tension leg fatigue with time
• Difficulty in maintaining subsea systems
• Little storage capacity
29. Tension Leg Platform
Evolution (First TLP built for Conoco Phillips’s Hutton Field 1984)
1984 (482 ft.) 2006 (5,000 ft.)
30. Spar Platform
Parts / Features
Spar platform. Source: www.worldoceanreview.com
• SPAR: Single Point Anchor Reservoir
• Drilling / Production
• Catenary or taut mooring system
• 3 designs available: Classic, truss and cell spar
• Drilling through the center of the cylinder.
• Drilled with subsea/surface wellhead.
• Buoyancy cans adopted for stability
31. Spar specificity
Transportation: Towed; Topside installed on site
Spudding the Rig: Rig is towed to location and ballasted upright.
Stability: Deep draft hull(90% submerged)/ buoyancy cans. Use of spiral fins /
truss frame reduced vortex induced vibrations (VIV).
Anchoring: Anchored using catenary or taut mooring system.
Functionality: Utilized mainly for development wells
32. Spar
Capacity Ranges Specification Range
Height* width (ft.) 300 * 75 to 750 * 150
Water Depth (ft.) up to 8,000
Drilling depth (ft.) 20,000 to 30,000
Topside (T) Up to 4000
Draft (ft.) Up to 90% of height
Number of well slots 15 to 30
BOP rating psi 10,000 to 15,000
Design 3 variations
Quarters capacity 70 to 150+ persons
33. Spar
Pros
• Good degree of stability
• Use of surface wellhead possible with
reduced heave.
• Lower costs with truss spar
• Mobile
Pros and Cons
Cons
• Susceptible vortex induced vibration.
(classic spar)
• Cost intensive with increasing water
depth
• Requires large facilities for
manufacturing
34. Spar Platform
Evolution (Genesis Spar 1998: First Spar with drilling facilities)
• Classic Spar
• Max water depth - 3,000 ft.
• length – 700 to 750 ft.
• Diameter – 70 to 120 ft.
• e.g. Genesis Spar
1st Gen
• Truss Spar
• Max water depth – 6,000 ft.
• Length – 500 to 650 ft.
• Diameter – 90 to 110 ft.
• e.g. Holstein Spar
2nd Gen
• Cell Spar
• Max water depth – 6,000 ft.
• Length – up to 600 ft.
• Diameter up to 100 ft.
• e.g. Red Hawk Spar
3rd Gen
36. Concrete Platform
Parts / Features
Concrete platform. Source: www.bolohair.uk
• Gravity based, seat on seabed
• Drilling / Production
• No mooring required
• Drilling through the center of the structure.
• High storage capacity.
• Variation: monopod and multi-pod.
37. Concrete Platform specificity
Transportation: bottom section constructed in dry dock; towed to site and
lowered to seabed; Topside installed on site.
Spudding the Rig: Platform is towed to location and ballasted to seabed.
Stability: stabilized by the weight of the structure (up to 850,000 T) resting on
seabed.
Anchoring: No anchoring system required.
Functionality: Utilized for development wells (drilling and production).
38. Concrete Platform
Capacity Ranges Specification Range
Water Depth (ft.) up to 1200
Drilling depth (ft.) 20,000 to 30,000
Topside weight (T) 10,000 to 50,000
Substructure weight (T) 100,000 to 850,000
Number of well slots 30 to 50
Storage capacity mbbl 1m to 2m
Design 2 variations
Quarters capacity 100 to 180+ persons
39. Concrete Platform
Pros
• Cheap and easy installation
• Low maintenance required
• High storage capacity
• Can withstand severe
• No reduction in load carrying capacity
with time.
Pros and Cons
Cons
• Expensive capital cost
• Challenges with decommissioning