3. SDH
• TOTAL AREA 350
SQ. YARDS
• TOTAL COVERED
AREA 3000 SFT.
• RATE PER SDH
Rs.12,20,000.00
4. IH
• TOTAL AREA 500
SQ. YARDS
• TOTAL COVERED
AREA 4000 SFT.
• RATE PER I H
Rs.15,50,000.00/=
5. COST CURTAILMENT
RCC PIPE
• 01 X RCC PIPE LINE OF 6” DIAMETER
MAY BE DELETED
• TOTAL PIPE IN USE
32 METER
• RATE
Rs.130.00 PER METER
• TOTAL COST
Rs.4,160.00
• TOTAL SAVING
Rs.2,080.00
6. MAIN HOLES / C.I. COVER
• IF WE DELETE ONE RCC PIPELINE,
05 X MAIN HOLES AND 05 X
C.I.COVER WOULD ALSO BE
DELETED.
• COST OF 01XMAIN HOLE Rs.1500.00
• COST OF 01XC.I.COVER Rs.500.00
• TOTAL SAVING
Rs.10,000.00
8. STEEL RAILING
•
•
•
•
•
•
•
STEEL RAILING OF BACK SIDE
TERRACE MAY BE DELETED
WALL OF 3’-6’’ MAY BE RAISED
INSTEAD
TOTAL RAILING IN USE
25 RFT
RATE
Rs 400/= RFT
TOTAL COST
Rs 10,000/=
BLOCK MASONARY Rs.2000/=C.M
TOTAL COST(1.5
CUM) RS.3000/=
DIFFERENCE OF COST RS.7000/=
9. PIPE RAILING
•
•
BACK SIDE WALL OF FRONT
TERRACE HAS A PIPE RAILING
MAY BE REPLACED WITH
BLOCK MASONARY
RATE OF RAILING RS.500/- RFT
•
COST ( 5 RFT)
•
•
BLOCK MASONARY Rs.670/COST SAVING
RS.1830/-
•
RS.2500/-
10. CLAD STONE
•
•
CLAD STONE MAY BE REPLACED
WITH GRAFFIATTO
RATE OF CLAD STONE RS.30/-SFT
•
•
•
RATE OF GRAFFIATTO RS.12/- SFT
TOTAL AREA
500 SFT
COST OF CLAD STONE RS.15000/-
•
COST OF GRAFFIATTO
RS.6000/-
•
COST SAVING
RS.9000/=
11. M.S. SHEET / G.I.
• M S SHEET/ G I OF 16 GAUGE MAY BE
REPLACED WITH 18 GAUGE DOOR
FRAMES
• RATE OF 16 GAUGE
Rs.75/=RFT
• RATE OF 18 GAUGE
Rs.65/=RFT
• TOTAL USAGE
300 RFT
• COST OF 16 GAUGE
Rs. 22500/=
• COST OF 18 GAUGE
Rs 19500/=
• COST SAVING
Rs 3000/=
12. WOODEN BIDDING
•
•
DEODAR WOOD IS USED FOR
BIDDING/GOLAS
MAY BE REPLACED WITH
PERTAL/GOLDEN TEAK
RATE OF DEODAR WOOD RS.2500/- CFT
•
RATE OF PERTAL
•
TOTAL REQUIREMENT
•
COST OF DEODAR
RS.42000/-
•
COST OF PERTAL
RS.12000/-
•
COST SAVING
RS.30,000/-
•
RS.700/- CFT
17 CFT
13. STAIR RAILING
.
•
WOODEN STAIR RAILING MAY BE
REPLACED WITH ALLUMINIUM
RAILING
RATE OF WOOD
RS.45O/-RFT
•
RATE OF ALLUMINIUM
RS.250/-RFT
•
TOTAL REQUIREMENT
30 RFT
•
COST OF WOOD
•
COST OF ALLUMINIUM RS.7500/-
•
COST SAVING
RS.13500/-
RS.6000/-
14. UPVC PIPE
•
•
4’’ DIA UPVC PIPES MAY BE
REPLACED WITH 3’’
RATE OF 4’’ DIA PIPE RS.145/-R.M.
•
RATE OF 3’’ DIA PIPE RS.100/-R.M.
•
TOTAL CONSUMPTION
•
COST OF 4’’ DIA PIPE
RS.5220/-
•
COST OF 3’’ DIA PIPE
RS.3600/-
•
COST SAVING
RS.1620/-
36 R.M.
15. UPVC PIPE(RAIN WATER)
• TOTAL OF 06xUPVC PIPES
ARE LAID FROM THE ROOF
MAY BE DELETED
• 3’’ DIA UPVC PIPES OF THE
TWO BATH ROOMS ON THE
FIRST FLOOR MAY BE
EXTENDED UPTO ROOF AND
AN ELBOW MAY BE FIXED
FOR THE RAIN WATER
• COST SAVING
RS.4400/-
16. RECOMMENDATIONS FOR IMPROVEMENT
• CAR PORCH ROOF OF SDH MAY BE INCREASED IN
HEIGHT UPTO DRAWING ROOM SLAB
• WOODEN STAIR RAILING MAY BE REPLACED WITH
ALLUMINIUM
• GRAFFIATTO OF DIFFERENT SHADES MAY BE
USED FOR FRONT ELEVATION IN CASE STONE
CLADDING IS DELETED
• SEPTIC TANK IN SDH MAY BE SHIFTED OUT SIDE
THE BOUNDARY WALL (IF IT IS NOT DELETED)