2. 2
Total length of DBO drain is 4.89 kilometers
Key
DBO drain network
Critical zones
Temp 82°C
Depth 4 feet
Temp 80°C
Depth 5 feet
Temp 70°C
Depth 4 feet
Temp 67°C
Depth 3 feet
Standard depth of drain is 2.5 feet except at the highlighted points
Total length of critical zones is 1 kilometers
Critical zone:
Where depth is 3 feet or more
3. 3
Issueathand
• Exposure of risk of accident due to open drains
Existingcontrol
• Manned check post for ensuring the structural integrity of DBO bridge