SlideShare a Scribd company logo
1 of 28
Download to read offline
MP14 Barge Salvage Survey
                         Tuesday, March 31, 2009
  Location: 30 01 03.47N 089 54 21.67W, Acergy (Michound Slip) N.O.
   Description of Casualty: Sunken, Total immersion, Damaged
 Concrete barge 90’ x 60’ x 12’ main-deck displacement hull with eight two-
                90’ 60’ 12’ main-                                       two-
    column concrete bents supporting an upper concrete deck stringer.
                                                               stringer.
           New Construction weight: nominally 1105 short tons
     Last known dead-weight (taken from 9.5 draft): 1616 short tons
                 dead-
Orientation of casualty:
• Reference marks are located at each corner of the main deck with
    mud-line elevations at corners of barge. Elevation of the water
    surface at time of survey was +1.25’. Beginning at the South-East
    corner of the casualty
•   (DC-1) elevation was -9.75’ (water depth 11’) mud-line depth was -
    22.25’ (water depth 23.5’) moving clock-wise to South-West Corner
•   (DC-2) elevation was -27.75’ (water depth 29’), mud-line elevation
    was -33.75’ (water depth 35’), moving clock-wise to North-West
    corner
•   (DC-3) elevation was -37.75’ (water depth 39’) and mud-line
    elevation was -36.75’ (water depth 38’). Moving clock-wise to North-
    East corner
•   (DC-4) elevation was -19.75’ (water depth 21’) and mud-line
    elevation was -28.25 (water depth 29.5’).
Side-Scan Sonar Images
DC-2

       DC-1
DC-3
Note open
hatch at DC-3
and excavated
bottom profile
DC-2

       DC-1
Three dimensional drawing shows present mud-line
                        Details thre dimensional re
                      in relationship to casualty interior




Presents 3-dimensional relationship of mud-line to casualty
Obstruction Beneath Casualty
• The barges was then referenced in fifteen feet increments beginning at DC-1 to DC-4
    (the shore-ward 90’ side) and began jetting 70’ long sections of 2” diameter conduit
    beneath the barge to determine if jetting lifting bands beneath the casualty would be
    a viable option. From corner DC1 (South to North):
•   0+15’: Encountered solid obstruction at 37’ penetration. Divers attempted to adjust
    angle slightly Southward and encountered solid obstruction at 40’ penetration. A third
    conduit was attempted at a greater angle and conduit deflected off solid and exited
    the front of casualty 15’ from corner rather than exiting the opposing side of the
    casualty.
•   0+30: Divers inserted conduit and encountered solid obstruction at 32’ penetration. A
    second attempt was made with similar results.
•   0+45’ (center-line): Divers encountered solid obstruction at 26’ penetration.
•   0+60’: divers encountered solid obstruction at 20’ penetration.
•   0+75’: divers encountered solid obstruction at 12’ penetration.
•   After a consultation with Wayne Fillingame (Acergy), it was noted that a previous
    tenant had disposed of two concrete bridge deck sections in the vicinity of the
    casualty and that the casualty is resting atop of one or both of them, there-by
    precluding the use of lifting bands beneath the casualty by conventional means.
Internal Inspection
• Divers entered the casualty at an open access point located in the North-
    West quadrant (DC-3, lowest elevation) and determined a depth of
    siltation average of 6.75’ inside that quadrant. Since the majority of the
    main-deck is beneath the natural mud-line, this was not unexpected
    information. Divers deployed an air-lift to remove mud from inside this
    quadrant to survey potential damage to the side-walls and deck, Four
    primary areas of damage were noted, including:
•   North Side wall hole nominally 12” x undetermined length
•   West Side wall and deck has apparent collision damage that is detailed in
    attached sketch, measuring:
     –   Deck has hole extending seven feet inboard by fourteen feet long
     –   Side-wall has hole and fractured area six feet by fourteen feet
         Side-
• Near centerline west hatch (sealed by salvage patch) has deck
    surrounding it heavily fractured and holed by apparent compressed air
•   North-west deck shows heavy spall and fractured concrete with exposed
    rebars at juncture to side-wall and indications of deck separation.
•   All mud removed from inside this quadrant by air-lifting was replenished
    through deck and side-wall damage in under 12 hours.
Areas of deck
separation noted
DC-3   DC-4

              Note depth of casualty
              below existing bottom
              contour at corner DC-3
Ground Reaction Forces
• The DC-3 quadrant is resting in a depression created by dredging during
    the previous salvage attempt with the natural mud-line elevation sloped
    from -27’ to the reference point DC-3 elevation of -37.75. This is a critical
    component because, without this dredged depression, most of the barge
    would be completely below the mud-line with the deepest point being 10’
    below the mud-line at DC-3. The initial dredging depression created a mud-
    line elevation lower than the deck surface of the barge but has
    subsequently slumped material back into the depression to an elevation
    slightly covering the DC-3 quadrant and consistently replacing any
    sediments removed from inside the casualty by ingress through large
    damage openings in the North-west side-wall, North-West Deck, West
    center-line deck opening, and the North Side-wall (all beneath the existing
    mud-line except the center-line access).
•   Actual ground reaction is extrapolated at 88 pounds per square ft. across
    the bottom of the casualty based on laboratory results of samples taken
    from each of the four corners. Overcoming the reaction (soil suction) for
    initial movement will require an additional force of 237.6 Tons above total
    dead-weight. This reaction component will go away once initial movement
    is achieved.
DC-3
       Note open hatches in deck
       and sediment above deck
       at North-west corner


            DC-4
Summary
• This casualty is immersed on a descending mud bank near parallel to the
    shore-line with a 14º Port to starboard list and a 16º diagonal (port bow to
    starboard stern) trim. Average depth of mud surrounding the casualty is
    5.5’ with corner DC-1 being 12.5’ above the mud-line and corner DC-3
    being 1’ below the mud-line. Most of the DC-3 quadrant (the only quadrant
    penetrated during the inspection) is filled with sediment to an
    approximate level surface, estimated at minimally1200 cubic yards, if
    consistent through-out the plane of the entire barge interior (we would
    assume this to be so).
•   Quadrant DC-3 is heavily damaged on both side-walls and deck and is not
    capable of supporting the forces anticipated to gain buoyancy and will
    have to be carefully planned by weight and dimension, to maintain
    structural integrity necessary to lift.
•   Solid obstruction beneath the barge is probably a remnant bridge deck
    section (per Wayne Fillingame, Acergy). This obstruction eliminates the
    possibility of jetting lifting bands beneath the casualty by conventional
    methods. There remains an option of directional boring beneath the
    casualty to insert rigging but this method is both costly and inefficient and
    severely limits load distribution of the rigging slings by size.
Salvage/Removal Options




            350 Ton Chain Pullers
Wreck in Place
• Due to the amount of structural steel (rebars) in
  the casualty and the depth and consistency of
  the sediments surrounding the casualty,
  demolition by breaking would be virtually
  impossible to guarantee substantial removal
  without permitting for bucket dredging. Previous
  removal attempts by Pearl River Navigation of a
  similar concrete barge near this location were
  eventually abandoned after removing an
  estimated 30-40% of the casualty.
Refloat
•   A previous salvage attempt of this casualty conducted by Offshore Marine
                                                                Offshore
    Contractors, utilizing pump capacity in excess of 15,000 gpm (per Steve Pemberton,
    owner of Fast-flow Pumps Inc.) combined with compressed air injection rather than
              Fast-                                                                    than
    ambient air intake, resulted in a partial refloat of one end of the casualty before air
    pressure fractured numerous areas of deck surface and separated portions of the
    deck from the side-walls. This is in evidence by heavy spall and exposed rebars at the
                    side-
    juncture of the deck to the side-walls through-out the casualty and by a severely
                                side-       through-
    damaged area of the deck surrounding the Southern end of the centerline deck
                                                                       centerline
    access 3’ x 5’ that had been sealed by a salvage patch.
           3’ 5’

•   While it may be possible to patch this casualty to a point where a refloat could be
    achieved, several factors need to be accounted:

•   Substantial ground reaction from the present attitude (beneath the existing mud-
                                                                     the         mud-
    line) will require a considerable amount of dredging around the casualty and some
    means of slowing re-ingress for the duration of the salvage operations.
                        re-
•   Near complete removal of all sediment inside the casualty will be required to reduce
                                                                    be
    both the static and dynamic loads prior to refloat.
•   There is heavy potential of severe damage as yet unidentified which may include the
                                                                   which
    bottom of the casualty that would eliminate the possibility of refloat.
                                                                   refloat.
•   With these factors in mind, I would estimate less than a 30% probability of
                                                                   probability
    successful salvage by conventional refloat.
Intact Lift
•   Lifting the casualty intact is a viable option with a moderate to high probability of
                                                                   to
    success but would entail several factors:
•   Since the casualty is resting upon some type of solid structure, the possibility of
    lifting from beneath the barge with metal straps is not a viable or cost effective
    option.
•   While the static load, as constructed, should be only around 700-800 tons (while
                                                                   700-
    immersed), The dynamic load would include the displaced weight of nominally 1200
                                                                         of
    cubic yards of sediment inside the barge (648 tons displaced weight), and a ground
                                                                    weight),
    reaction force of nominally 237.6 tons.
      – Sediments inside the barge can be removed by divers and most of the points of
          ingress arrested but will require substantial time and costs for penetration diving
          operations.
      – Ground reaction forces can be greatly reduced by dredging but may require
                                                                           may
          permitting and other environmental costs and time-lines.
                                                          time-
•   Lifting points on the casualty will have to be distributed along the side-walls
                                                                          side-
    equilaterally to allow for a maximum tension force of 200 tons per leg and would
                                                                      per
    require a minimum of ten chain-pullers to guarantee a high probability of success
                                chain-
    (see Lifting-pin diagram).
           Lifting-
      – Would require four barges to distribute the loads safely
      – Equilateral distribution of the load may be affected by concrete damage as yet
          undiscovered on the casualty
•   Final disposition of the casualty would be limited to reefing or releasing the load to
    another location until patches could be installed in damaged areas and lifting point
                                                                   areas
    access holes to allow the barge to be refloated.
Dragging to Shore
• Dragging the casualty to shore utilizing chain-pullers, either intact or in sections, is
    also a viable option with the following considerations:
•   Shore soil compaction factored to determine the number of Manta-anchors necessary
    to dead-man the pullers
•   Installation of slide-beams beneath the leading edge of the casualty to insure a lesser
    degree of friction as well as to preclude the possibility of the casualty “bull-dozing”
    into the strata while being pulled
•   It may be possible to “Choke” the ends of the casualty with heavy chain by dredging
    but will need to be reinforced to prevent the chains from breaking into the concrete.
•   Ground reaction forces still have to be taken into account when estimating the
    number of pullers needed to drag the load to shore. Should this factor be in excess of
    the holding force of the manta-anchors, sectioning of the casualty would be required
    to reduce the weight of the load.
•   The casualty will be heavily damaged, probably beyond recovery, by this method and
    would require complete demolition and removal by truck or barge.
•   While this method is a viable option with a very high probability of success, the time-
    line is not predictable enough to allow as an option other than under a “Time and
    Materials” agreement.
Sectional Removal
•   This method of removal has the highest probability of success of all the options considered with the
    additional advantage of moderately predictable costs and time-lines. The casualty would be cross-
                                                                   time-                             cross-
    sectioned into five roughly proportional sized sections (60’ x 18’) utilizing a “top-down” diamond wire
                                                              (60’ 18’                top- down”
    saw (see attached sketch ).
•   An air-lift would be deployed by crane to excavate access at each point to be sectioned to allow the
         air-
    diver to attach each turning sheave to the side-wall of the casualty with the sheave extending below the
                                                 side-
    bottom edge of the casualty. The sheave plates are attached utilizing four (4) 3/8” grade eight stud
                                                                      utilizing        3/8”
    bolts driven into the side-wall with an underwater powder-actuated fastener tool. The diamond wire is
                           side-                          powder-
    then threaded from the work platform barge through the outside of one sheave, over the top of the
                                                                            of
    casualty and down to the second sheave and back to the saw unit located on the work platform barge.
•   Each end (side-wall) of a section will require two 6.25” diameter core-borings to act as a receiver for the
               (side-                                    6.25”             core-
    lifting pins (see attached lifting pin drawing). Core drill is hydraulically operated and requires a single
                                                                   hydraulically
    5/8” x 6” Red-head to attach to the side-wall. Three inch chain will be shackled to each lifting pin and
    5/8” 6” Red-                           side-
    passed to a 250 ton hydraulic chain puller, mounted on a barge. Each piece will then be lifted between
    the two staging barges and towed to a pre-determined place for disposal. There are several advantages
                                              pre-
    to this method of removal:
•   Requires only two inland work barges (one with small crane) to assist with operations.
                                                                          assist
•   Requires minimal shore staging of operations
•   Requires minimal dredging or permits
•   Requires only four (4) chain-pullers, lifting pins, and chain shots
                             chain-
•   Greatly reduced ground reaction forces
      – Reduced surface area
      – Renders interior sediments a means of egress
•   Offers increased disposal options
•   Engineering data supports load bearing design of lifting pins and attachments.
                                                                      and
Appendices

• Diagram of Lifting Pin
• 200 Ton Chain Puller
• 350 Ton Chain-puller
• Diamond Wire-saw
• Hydraulic Pile Cutter
• Diamond Wire Routing Diagram
250 Ton Chain-Puller
Diamond Wire-saw

More Related Content

What's hot

Control Of SEEPAGE THROUGH EMBANKMENTS
Control Of SEEPAGE THROUGH EMBANKMENTSControl Of SEEPAGE THROUGH EMBANKMENTS
Control Of SEEPAGE THROUGH EMBANKMENTScomsats
 
4.4 cyclone shelter design
4.4 cyclone shelter design4.4 cyclone shelter design
4.4 cyclone shelter designctlachu
 
Shallow and deep excavation & dewatering
Shallow and deep excavation & dewateringShallow and deep excavation & dewatering
Shallow and deep excavation & dewateringAdil Vahora
 
Failure of weir and barrage
Failure of weir and barrageFailure of weir and barrage
Failure of weir and barrageDivya Vishnoi
 
Soil arching in granular soil
Soil arching in granular soilSoil arching in granular soil
Soil arching in granular soilJithu G Francis
 
Prediction of Surface Subsidence and Its Monitoring
Prediction of Surface Subsidence and Its MonitoringPrediction of Surface Subsidence and Its Monitoring
Prediction of Surface Subsidence and Its MonitoringVR M
 
Modes of failure earth dams
Modes of failure   earth damsModes of failure   earth dams
Modes of failure earth damssaibabu48
 
Bearing Capacity of Shallow Foundation.
Bearing Capacity of Shallow Foundation.Bearing Capacity of Shallow Foundation.
Bearing Capacity of Shallow Foundation.faizanNoor8
 
IMPACT OF SUBSIDENCE
IMPACT OF SUBSIDENCEIMPACT OF SUBSIDENCE
IMPACT OF SUBSIDENCEKapil Beniwal
 
Diversion head works ajitha miss
Diversion head works ajitha missDiversion head works ajitha miss
Diversion head works ajitha missSHAMJITH KM
 
Diversionheadworks
DiversionheadworksDiversionheadworks
Diversionheadworkssaibabu48
 

What's hot (20)

Control Of SEEPAGE THROUGH EMBANKMENTS
Control Of SEEPAGE THROUGH EMBANKMENTSControl Of SEEPAGE THROUGH EMBANKMENTS
Control Of SEEPAGE THROUGH EMBANKMENTS
 
Weirs on Permeable Foundations
Weirs on Permeable FoundationsWeirs on Permeable Foundations
Weirs on Permeable Foundations
 
Geotechnical Aspects
Geotechnical AspectsGeotechnical Aspects
Geotechnical Aspects
 
Subsidence in coal mines
Subsidence in coal minesSubsidence in coal mines
Subsidence in coal mines
 
4.4 cyclone shelter design
4.4 cyclone shelter design4.4 cyclone shelter design
4.4 cyclone shelter design
 
Retaining walls
Retaining wallsRetaining walls
Retaining walls
 
Shallow and deep excavation & dewatering
Shallow and deep excavation & dewateringShallow and deep excavation & dewatering
Shallow and deep excavation & dewatering
 
design of weirs
design of weirsdesign of weirs
design of weirs
 
Failure of weir and barrage
Failure of weir and barrageFailure of weir and barrage
Failure of weir and barrage
 
Soil arching in granular soil
Soil arching in granular soilSoil arching in granular soil
Soil arching in granular soil
 
Prediction of Surface Subsidence and Its Monitoring
Prediction of Surface Subsidence and Its MonitoringPrediction of Surface Subsidence and Its Monitoring
Prediction of Surface Subsidence and Its Monitoring
 
Retaining wall
 Retaining wall  Retaining wall
Retaining wall
 
Modes of failure earth dams
Modes of failure   earth damsModes of failure   earth dams
Modes of failure earth dams
 
Bearing Capacity of Shallow Foundation.
Bearing Capacity of Shallow Foundation.Bearing Capacity of Shallow Foundation.
Bearing Capacity of Shallow Foundation.
 
Dam engineering i 5
Dam engineering i 5Dam engineering i 5
Dam engineering i 5
 
SHALLOW FOUNDATION
SHALLOW FOUNDATIONSHALLOW FOUNDATION
SHALLOW FOUNDATION
 
IMPACT OF SUBSIDENCE
IMPACT OF SUBSIDENCEIMPACT OF SUBSIDENCE
IMPACT OF SUBSIDENCE
 
Diversion head works ajitha miss
Diversion head works ajitha missDiversion head works ajitha miss
Diversion head works ajitha miss
 
Dam engineering i 4
Dam engineering i 4Dam engineering i 4
Dam engineering i 4
 
Diversionheadworks
DiversionheadworksDiversionheadworks
Diversionheadworks
 

Similar to Mp14 Barge Salvage Survey Final

UNIT-V Slope Stability - Land Slides.ppt
UNIT-V Slope Stability - Land Slides.pptUNIT-V Slope Stability - Land Slides.ppt
UNIT-V Slope Stability - Land Slides.pptmythili spd
 
presentation-of-cofferdam-design.pptx
presentation-of-cofferdam-design.pptxpresentation-of-cofferdam-design.pptx
presentation-of-cofferdam-design.pptxglencristianrivera
 
Circular and Toppling failure 1.pdf
Circular and Toppling failure 1.pdfCircular and Toppling failure 1.pdf
Circular and Toppling failure 1.pdfKuEsyra
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundationsDar Hilal
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdfRijuDasgupta
 
Suction caissons and response to long term lateral cyclic loading
Suction caissons and response to long term lateral cyclic loadingSuction caissons and response to long term lateral cyclic loading
Suction caissons and response to long term lateral cyclic loadingMichael dessalegn
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalIEI GSC
 
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptx
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptxdamandtypesofdamwithsiteselection-170403160723 (1) (1).pptx
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptxabhijitsaha99
 
Chapter 4.2 coffer dam, well foundation-final1
Chapter 4.2   coffer dam, well foundation-final1Chapter 4.2   coffer dam, well foundation-final1
Chapter 4.2 coffer dam, well foundation-final1DYPCET
 
Bombardem breakwaters
Bombardem breakwatersBombardem breakwaters
Bombardem breakwatersAjit Kumar
 
Oguk fpso network side shell repairs on-station.
Oguk fpso network   side shell repairs on-station.Oguk fpso network   side shell repairs on-station.
Oguk fpso network side shell repairs on-station.Danny O'Connor
 
2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTUVATSAL PATEL
 

Similar to Mp14 Barge Salvage Survey Final (20)

OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements
 
UNIT-V Slope Stability - Land Slides.ppt
UNIT-V Slope Stability - Land Slides.pptUNIT-V Slope Stability - Land Slides.ppt
UNIT-V Slope Stability - Land Slides.ppt
 
presentation-of-cofferdam-design.pptx
presentation-of-cofferdam-design.pptxpresentation-of-cofferdam-design.pptx
presentation-of-cofferdam-design.pptx
 
Earthen dam
Earthen damEarthen dam
Earthen dam
 
Circular and Toppling failure 1.pdf
Circular and Toppling failure 1.pdfCircular and Toppling failure 1.pdf
Circular and Toppling failure 1.pdf
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf
 
Suction caissons and response to long term lateral cyclic loading
Suction caissons and response to long term lateral cyclic loadingSuction caissons and response to long term lateral cyclic loading
Suction caissons and response to long term lateral cyclic loading
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canal
 
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptx
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptxdamandtypesofdamwithsiteselection-170403160723 (1) (1).pptx
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptx
 
Circular failure
Circular failureCircular failure
Circular failure
 
Chapter 4.2 coffer dam, well foundation-final1
Chapter 4.2   coffer dam, well foundation-final1Chapter 4.2   coffer dam, well foundation-final1
Chapter 4.2 coffer dam, well foundation-final1
 
Breakwater construction
Breakwater constructionBreakwater construction
Breakwater construction
 
Bombardem breakwaters
Bombardem breakwatersBombardem breakwaters
Bombardem breakwaters
 
Dams and spillways
Dams and spillwaysDams and spillways
Dams and spillways
 
Break waters
Break watersBreak waters
Break waters
 
Ay 2020 2021 fe supply key
Ay 2020 2021 fe supply keyAy 2020 2021 fe supply key
Ay 2020 2021 fe supply key
 
Oguk fpso network side shell repairs on-station.
Oguk fpso network   side shell repairs on-station.Oguk fpso network   side shell repairs on-station.
Oguk fpso network side shell repairs on-station.
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU2. CAISSONS (ACE) 2160601 GTU
2. CAISSONS (ACE) 2160601 GTU
 

Mp14 Barge Salvage Survey Final

  • 1. MP14 Barge Salvage Survey Tuesday, March 31, 2009 Location: 30 01 03.47N 089 54 21.67W, Acergy (Michound Slip) N.O. Description of Casualty: Sunken, Total immersion, Damaged Concrete barge 90’ x 60’ x 12’ main-deck displacement hull with eight two- 90’ 60’ 12’ main- two- column concrete bents supporting an upper concrete deck stringer. stringer. New Construction weight: nominally 1105 short tons Last known dead-weight (taken from 9.5 draft): 1616 short tons dead-
  • 2. Orientation of casualty: • Reference marks are located at each corner of the main deck with mud-line elevations at corners of barge. Elevation of the water surface at time of survey was +1.25’. Beginning at the South-East corner of the casualty • (DC-1) elevation was -9.75’ (water depth 11’) mud-line depth was - 22.25’ (water depth 23.5’) moving clock-wise to South-West Corner • (DC-2) elevation was -27.75’ (water depth 29’), mud-line elevation was -33.75’ (water depth 35’), moving clock-wise to North-West corner • (DC-3) elevation was -37.75’ (water depth 39’) and mud-line elevation was -36.75’ (water depth 38’). Moving clock-wise to North- East corner • (DC-4) elevation was -19.75’ (water depth 21’) and mud-line elevation was -28.25 (water depth 29.5’).
  • 3.
  • 5. DC-2 DC-1
  • 7. Note open hatch at DC-3 and excavated bottom profile
  • 8. DC-2 DC-1
  • 9. Three dimensional drawing shows present mud-line Details thre dimensional re in relationship to casualty interior Presents 3-dimensional relationship of mud-line to casualty
  • 10. Obstruction Beneath Casualty • The barges was then referenced in fifteen feet increments beginning at DC-1 to DC-4 (the shore-ward 90’ side) and began jetting 70’ long sections of 2” diameter conduit beneath the barge to determine if jetting lifting bands beneath the casualty would be a viable option. From corner DC1 (South to North): • 0+15’: Encountered solid obstruction at 37’ penetration. Divers attempted to adjust angle slightly Southward and encountered solid obstruction at 40’ penetration. A third conduit was attempted at a greater angle and conduit deflected off solid and exited the front of casualty 15’ from corner rather than exiting the opposing side of the casualty. • 0+30: Divers inserted conduit and encountered solid obstruction at 32’ penetration. A second attempt was made with similar results. • 0+45’ (center-line): Divers encountered solid obstruction at 26’ penetration. • 0+60’: divers encountered solid obstruction at 20’ penetration. • 0+75’: divers encountered solid obstruction at 12’ penetration. • After a consultation with Wayne Fillingame (Acergy), it was noted that a previous tenant had disposed of two concrete bridge deck sections in the vicinity of the casualty and that the casualty is resting atop of one or both of them, there-by precluding the use of lifting bands beneath the casualty by conventional means.
  • 11.
  • 12. Internal Inspection • Divers entered the casualty at an open access point located in the North- West quadrant (DC-3, lowest elevation) and determined a depth of siltation average of 6.75’ inside that quadrant. Since the majority of the main-deck is beneath the natural mud-line, this was not unexpected information. Divers deployed an air-lift to remove mud from inside this quadrant to survey potential damage to the side-walls and deck, Four primary areas of damage were noted, including: • North Side wall hole nominally 12” x undetermined length • West Side wall and deck has apparent collision damage that is detailed in attached sketch, measuring: – Deck has hole extending seven feet inboard by fourteen feet long – Side-wall has hole and fractured area six feet by fourteen feet Side- • Near centerline west hatch (sealed by salvage patch) has deck surrounding it heavily fractured and holed by apparent compressed air • North-west deck shows heavy spall and fractured concrete with exposed rebars at juncture to side-wall and indications of deck separation. • All mud removed from inside this quadrant by air-lifting was replenished through deck and side-wall damage in under 12 hours.
  • 14. DC-3 DC-4 Note depth of casualty below existing bottom contour at corner DC-3
  • 15. Ground Reaction Forces • The DC-3 quadrant is resting in a depression created by dredging during the previous salvage attempt with the natural mud-line elevation sloped from -27’ to the reference point DC-3 elevation of -37.75. This is a critical component because, without this dredged depression, most of the barge would be completely below the mud-line with the deepest point being 10’ below the mud-line at DC-3. The initial dredging depression created a mud- line elevation lower than the deck surface of the barge but has subsequently slumped material back into the depression to an elevation slightly covering the DC-3 quadrant and consistently replacing any sediments removed from inside the casualty by ingress through large damage openings in the North-west side-wall, North-West Deck, West center-line deck opening, and the North Side-wall (all beneath the existing mud-line except the center-line access). • Actual ground reaction is extrapolated at 88 pounds per square ft. across the bottom of the casualty based on laboratory results of samples taken from each of the four corners. Overcoming the reaction (soil suction) for initial movement will require an additional force of 237.6 Tons above total dead-weight. This reaction component will go away once initial movement is achieved.
  • 16. DC-3 Note open hatches in deck and sediment above deck at North-west corner DC-4
  • 17. Summary • This casualty is immersed on a descending mud bank near parallel to the shore-line with a 14º Port to starboard list and a 16º diagonal (port bow to starboard stern) trim. Average depth of mud surrounding the casualty is 5.5’ with corner DC-1 being 12.5’ above the mud-line and corner DC-3 being 1’ below the mud-line. Most of the DC-3 quadrant (the only quadrant penetrated during the inspection) is filled with sediment to an approximate level surface, estimated at minimally1200 cubic yards, if consistent through-out the plane of the entire barge interior (we would assume this to be so). • Quadrant DC-3 is heavily damaged on both side-walls and deck and is not capable of supporting the forces anticipated to gain buoyancy and will have to be carefully planned by weight and dimension, to maintain structural integrity necessary to lift. • Solid obstruction beneath the barge is probably a remnant bridge deck section (per Wayne Fillingame, Acergy). This obstruction eliminates the possibility of jetting lifting bands beneath the casualty by conventional methods. There remains an option of directional boring beneath the casualty to insert rigging but this method is both costly and inefficient and severely limits load distribution of the rigging slings by size.
  • 18. Salvage/Removal Options 350 Ton Chain Pullers
  • 19. Wreck in Place • Due to the amount of structural steel (rebars) in the casualty and the depth and consistency of the sediments surrounding the casualty, demolition by breaking would be virtually impossible to guarantee substantial removal without permitting for bucket dredging. Previous removal attempts by Pearl River Navigation of a similar concrete barge near this location were eventually abandoned after removing an estimated 30-40% of the casualty.
  • 20. Refloat • A previous salvage attempt of this casualty conducted by Offshore Marine Offshore Contractors, utilizing pump capacity in excess of 15,000 gpm (per Steve Pemberton, owner of Fast-flow Pumps Inc.) combined with compressed air injection rather than Fast- than ambient air intake, resulted in a partial refloat of one end of the casualty before air pressure fractured numerous areas of deck surface and separated portions of the deck from the side-walls. This is in evidence by heavy spall and exposed rebars at the side- juncture of the deck to the side-walls through-out the casualty and by a severely side- through- damaged area of the deck surrounding the Southern end of the centerline deck centerline access 3’ x 5’ that had been sealed by a salvage patch. 3’ 5’ • While it may be possible to patch this casualty to a point where a refloat could be achieved, several factors need to be accounted: • Substantial ground reaction from the present attitude (beneath the existing mud- the mud- line) will require a considerable amount of dredging around the casualty and some means of slowing re-ingress for the duration of the salvage operations. re- • Near complete removal of all sediment inside the casualty will be required to reduce be both the static and dynamic loads prior to refloat. • There is heavy potential of severe damage as yet unidentified which may include the which bottom of the casualty that would eliminate the possibility of refloat. refloat. • With these factors in mind, I would estimate less than a 30% probability of probability successful salvage by conventional refloat.
  • 21. Intact Lift • Lifting the casualty intact is a viable option with a moderate to high probability of to success but would entail several factors: • Since the casualty is resting upon some type of solid structure, the possibility of lifting from beneath the barge with metal straps is not a viable or cost effective option. • While the static load, as constructed, should be only around 700-800 tons (while 700- immersed), The dynamic load would include the displaced weight of nominally 1200 of cubic yards of sediment inside the barge (648 tons displaced weight), and a ground weight), reaction force of nominally 237.6 tons. – Sediments inside the barge can be removed by divers and most of the points of ingress arrested but will require substantial time and costs for penetration diving operations. – Ground reaction forces can be greatly reduced by dredging but may require may permitting and other environmental costs and time-lines. time- • Lifting points on the casualty will have to be distributed along the side-walls side- equilaterally to allow for a maximum tension force of 200 tons per leg and would per require a minimum of ten chain-pullers to guarantee a high probability of success chain- (see Lifting-pin diagram). Lifting- – Would require four barges to distribute the loads safely – Equilateral distribution of the load may be affected by concrete damage as yet undiscovered on the casualty • Final disposition of the casualty would be limited to reefing or releasing the load to another location until patches could be installed in damaged areas and lifting point areas access holes to allow the barge to be refloated.
  • 22. Dragging to Shore • Dragging the casualty to shore utilizing chain-pullers, either intact or in sections, is also a viable option with the following considerations: • Shore soil compaction factored to determine the number of Manta-anchors necessary to dead-man the pullers • Installation of slide-beams beneath the leading edge of the casualty to insure a lesser degree of friction as well as to preclude the possibility of the casualty “bull-dozing” into the strata while being pulled • It may be possible to “Choke” the ends of the casualty with heavy chain by dredging but will need to be reinforced to prevent the chains from breaking into the concrete. • Ground reaction forces still have to be taken into account when estimating the number of pullers needed to drag the load to shore. Should this factor be in excess of the holding force of the manta-anchors, sectioning of the casualty would be required to reduce the weight of the load. • The casualty will be heavily damaged, probably beyond recovery, by this method and would require complete demolition and removal by truck or barge. • While this method is a viable option with a very high probability of success, the time- line is not predictable enough to allow as an option other than under a “Time and Materials” agreement.
  • 23. Sectional Removal • This method of removal has the highest probability of success of all the options considered with the additional advantage of moderately predictable costs and time-lines. The casualty would be cross- time- cross- sectioned into five roughly proportional sized sections (60’ x 18’) utilizing a “top-down” diamond wire (60’ 18’ top- down” saw (see attached sketch ). • An air-lift would be deployed by crane to excavate access at each point to be sectioned to allow the air- diver to attach each turning sheave to the side-wall of the casualty with the sheave extending below the side- bottom edge of the casualty. The sheave plates are attached utilizing four (4) 3/8” grade eight stud utilizing 3/8” bolts driven into the side-wall with an underwater powder-actuated fastener tool. The diamond wire is side- powder- then threaded from the work platform barge through the outside of one sheave, over the top of the of casualty and down to the second sheave and back to the saw unit located on the work platform barge. • Each end (side-wall) of a section will require two 6.25” diameter core-borings to act as a receiver for the (side- 6.25” core- lifting pins (see attached lifting pin drawing). Core drill is hydraulically operated and requires a single hydraulically 5/8” x 6” Red-head to attach to the side-wall. Three inch chain will be shackled to each lifting pin and 5/8” 6” Red- side- passed to a 250 ton hydraulic chain puller, mounted on a barge. Each piece will then be lifted between the two staging barges and towed to a pre-determined place for disposal. There are several advantages pre- to this method of removal: • Requires only two inland work barges (one with small crane) to assist with operations. assist • Requires minimal shore staging of operations • Requires minimal dredging or permits • Requires only four (4) chain-pullers, lifting pins, and chain shots chain- • Greatly reduced ground reaction forces – Reduced surface area – Renders interior sediments a means of egress • Offers increased disposal options • Engineering data supports load bearing design of lifting pins and attachments. and
  • 24. Appendices • Diagram of Lifting Pin • 200 Ton Chain Puller • 350 Ton Chain-puller • Diamond Wire-saw • Hydraulic Pile Cutter • Diamond Wire Routing Diagram
  • 25.
  • 27.