Steel Melting Shop
The basic function of SMS is to produce hot metal from Ferro scrap
and providing input material to ingot mould and caster for taking a
shape. Slag is also an output of SMS which are used by cement
industries for cement making.
Basic highlights of SMS:
 Electric Arc Furnace (EAF)
 Transformer rating of this furnace is 25 MVA for stainless steel
furnace and 18.75 MVA for the non stainless steel furnace.
 One heat requires 3 hours to complete.
 After tapping the molten metal is sent to VOD/VAD/LD directly.
 In VAD the molten metal is degassed to removed the Hydrogen or
Oxygen from the metal to reduce their amount to an acceptable
ppm level.
VAD Furnace Ladle Furnace
VOD Furnace AOD Furnace
CONTINUOUS CASTING SHOP(CCS)
Through continuous casting route mainly stailess steel slabs are
produced. In ASP there was a twin caster i.e. slab cum bloom caster
which culd be used either as single strand slab caster or double strand
bloom caster in operation.
For continuous casting there is mould where the liquid metal is to be
poured.Before the ladle comes inside the mould some biscuit and
chocolate size bar is placed to give the shape of the slab.
Casting can be sequential or in batch . In sequential casting 2 or more
then 2 ladles are brought to turret for casting one by one.But in batch
only one ladle is cast.
BLOOMING AND BILLET MILL (BBM)
In ASP, Blooming & Billet Mill plays a major role. Here the
primary rolling mill is use to compress the soaking pits. In this process
the soaking pit is use at temperature 1180-1800 C.
BBM consists of Blooming Mill, Billet Mill & Soaking pits. This
mill produces blooms, billets, squares, rounds, & slabs of various sizes
& can handle all grades of alloy steel produced at SMS. At 1st in pit
furnace a metal shape is heated and then it passed between two rollers.
In roller operation the crossection of the specimen is gradually
decreased.
CONDITIONING SHOP
COOLING LUD
HOTSAW
BILLETSHEAR
650 mm BILLETMILL 2
700 mm BILLETMILL 1
BLOOMSHEAR
LD SCARFING MACHINE
900 mm TWO HIGH REVERSING MILL
SOAKING PITFURNACE
FROMSMS & CCS
MAJOR CONTROLLERS IN B.B.M.:
 Pit temperature controller.
 Fuel controller.
BLOOMING & BILLET MILL
FORGE SHOP
The forge shops have two type of forging presses for producing
compact steel forgings. One is computerized forging press & another
one is manual forging press which have 2 T capacity.
In forging shop there is two heating chamber for heating the
material before forging process. 1st chamber is use for gradually
increasing the temperature of the specimen. Here the specimen doesn’t
reaches the particular temperature which is not suitable for the forging.
And the 2nd chamber is use for reheating the specimen. The total
heating time is 6hrs. After that the specimen is ready for the forging.
USE OF FORGING:
It is use for making a specimen of required shape. By the forging
press we get a final product of good surface finish. In forging process
rectangular shape can be change in circular shape & also vice-versa.
After processing in this shop the material is then sent to Heat Treatment
and Finishing shop.
SECTION:
 Press Bay
 Hammer Bay
INPUT MATERIAL:
Blooms of various sizes.
CONTROLLING PARAMETERS OF FURNACE:
 Metal temperature.
 Fuel flow.
 Combustion flow.
 Compressed air flow.
 Furnace pressure.
PRODUCTS:
Rounds, squares, die block, flats, rings etc.
Diagram of Forging Press machine
Forging Hammer Reheating Furnace
Forging Pressure Forging Roll
PLATE MILL
The ingots are rolled at Blooming and Billet Mill for producing blooms, billets,
rounds and slabs in a variety of steel grades & sizes. The rolled slabs are further
rolled in Plate mill to produce plates. Today thermomechanical rolling is the
most important production process for the manufacture of high strength plates.
In this method the temperatures are exactly set for finish rolling and for cooling.
CONDITIONING SHOP
Detection and removal of surface defects like cracks and making
materials ready for further processing a/c to customer’s needs.In
the conditioning shop, the surface defect of the products are
removed prior to shipping further rolling or forging in order to
meet the required quality standard of the finished product. The
further processing is known as conditioning. This shop is equipped
with slow cooling boxes and bogie.Hearth type dispositioning
furnaces for treatment of products received from BBM.Other
facilities include straightening machines,saw and flame cutting
machines elaborate inspection and testing arrangements for spark
and spectro testing for quality control.
INPUT MATERIALS:
Products from-
 Forge shop
 BBM
 Bar mill
There are two types of conditioning shops:
1.CONDITIONING SHOP 1
Normal cooling Box cooling Grinding
Cutting Furnace cooling
2.CONDITIONING SHOP 2:
In this shop materials come from continuous casting shop.
HEAT TREATMENT AND FINISHING SHOP
Here different types of heat treatment arrangements such as for oil
quenching, water quenching are present in order to impart specific
properties to the alloy steel as per customer’s requirement.
BOILER HOUSE
This unit provides steam for the entire plant. Steam is used
in vaccuam creation system consisting of converging and
diverging nozzles. The water to be sent to boiler is first
demineralised by passing it through cation exchanger and
anion exchanger. This is done to prevent scaling by
deposition of minerals on inner surface of boiler which
reduces the life of boiler considerably. The water sent to the
boiler is checked regularly in a chemical laboratory.
MECHANICAL REPAIR SHOP(MRS)
This is the Mechanical repairing shop which is support the
production of the plant as well as looking after breakdown and
preventive maintenance of equipment.
It has Four Sections. Eg; i) Overhauling & Fitting, ii) Winding ,
iii) Testing & iv) Preventive & Breakdown Maintenance.
* Overhauling & Fitting Section :
This section repairs the motor, generator etc, after careful
inspection of all parts & repair it accordingly.
* Welding Section : -
Welding of AC Motor of both Squirrel Cage & Slip Ring upto the
capacity of 225 KW, 415V. 1480 RPM can be done.
* Testing Section :
At Testing section all DC & AC Motors upto the capacity of 100
KW can be Tested.
* Preventive & Breakdown Maintenance : -
Maintains Lathe, Drill, Planning, Copy planning , Welding
etc, for uninterrupted production & to ensure equipment
availability.

More Related Content

What's hot

Supply chain management
Supply chain managementSupply chain management
Supply chain managementRavi Shekhar
 
Steel Authority of India Ltd bokaro
Steel Authority of India Ltd bokaroSteel Authority of India Ltd bokaro
Steel Authority of India Ltd bokaroSuman Sourabh
 
Kuldeep ritika ppt on bokaro steel plant
Kuldeep ritika  ppt on bokaro steel plantKuldeep ritika  ppt on bokaro steel plant
Kuldeep ritika ppt on bokaro steel plant1996kuldeep
 
Training at sail bokaro
Training at sail bokaroTraining at sail bokaro
Training at sail bokaroGAURAV VERMA
 
PSM INTERNSHIP 2
PSM INTERNSHIP 2PSM INTERNSHIP 2
PSM INTERNSHIP 2Asim Aslam
 
Internship report Of Pakistan Steel Mill
Internship report Of Pakistan Steel MillInternship report Of Pakistan Steel Mill
Internship report Of Pakistan Steel MillSyed Ghufran Hassan
 
Industrial training report- Visakhapatnam Steel Plant.
Industrial training report- Visakhapatnam Steel Plant. Industrial training report- Visakhapatnam Steel Plant.
Industrial training report- Visakhapatnam Steel Plant. Ishankamal Mitra
 
Ppt on bokaro steel plant
Ppt on bokaro steel plantPpt on bokaro steel plant
Ppt on bokaro steel plantPrashant Kumar
 
SAIL ROURKELA SINTER PLANT
SAIL ROURKELA SINTER PLANTSAIL ROURKELA SINTER PLANT
SAIL ROURKELA SINTER PLANTAshish Kholia
 
Steel Plant Internship and ICOMM Telecom limited
Steel Plant Internship and ICOMM Telecom limitedSteel Plant Internship and ICOMM Telecom limited
Steel Plant Internship and ICOMM Telecom limitedNaveen Teja
 
Sinter Plant,Lime & Dolo Plant industrial Training Report
Sinter Plant,Lime & Dolo Plant industrial Training ReportSinter Plant,Lime & Dolo Plant industrial Training Report
Sinter Plant,Lime & Dolo Plant industrial Training ReportShani Kumar Singh
 
Bhilai Steel Plant - Internship Report
Bhilai Steel Plant - Internship ReportBhilai Steel Plant - Internship Report
Bhilai Steel Plant - Internship ReportAmul Raj
 
A VOCATIONAL TRAINNING REPORT_aman
A  VOCATIONAL TRAINNING REPORT_amanA  VOCATIONAL TRAINNING REPORT_aman
A VOCATIONAL TRAINNING REPORT_amanAMAN KESARI
 
Pankaj kumar ppt on bokaro steel plant for civil
Pankaj kumar ppt on bokaro steel plant for civilPankaj kumar ppt on bokaro steel plant for civil
Pankaj kumar ppt on bokaro steel plant for civil1996kuldeep
 
A presentation of summer internship in rourkela steel plant
A presentation of summer internship in rourkela steel plantA presentation of summer internship in rourkela steel plant
A presentation of summer internship in rourkela steel plantEnigmatic Deepak
 

What's hot (20)

Supply chain management
Supply chain managementSupply chain management
Supply chain management
 
Steel Authority of India Ltd bokaro
Steel Authority of India Ltd bokaroSteel Authority of India Ltd bokaro
Steel Authority of India Ltd bokaro
 
Sail presentation
Sail presentationSail presentation
Sail presentation
 
Kuldeep ritika ppt on bokaro steel plant
Kuldeep ritika  ppt on bokaro steel plantKuldeep ritika  ppt on bokaro steel plant
Kuldeep ritika ppt on bokaro steel plant
 
Training at sail bokaro
Training at sail bokaroTraining at sail bokaro
Training at sail bokaro
 
PSM INTERNSHIP 2
PSM INTERNSHIP 2PSM INTERNSHIP 2
PSM INTERNSHIP 2
 
Internship report Of Pakistan Steel Mill
Internship report Of Pakistan Steel MillInternship report Of Pakistan Steel Mill
Internship report Of Pakistan Steel Mill
 
Industrial training report- Visakhapatnam Steel Plant.
Industrial training report- Visakhapatnam Steel Plant. Industrial training report- Visakhapatnam Steel Plant.
Industrial training report- Visakhapatnam Steel Plant.
 
Ppt on bokaro steel plant
Ppt on bokaro steel plantPpt on bokaro steel plant
Ppt on bokaro steel plant
 
Vniimetmash
VniimetmashVniimetmash
Vniimetmash
 
SAIL ROURKELA SINTER PLANT
SAIL ROURKELA SINTER PLANTSAIL ROURKELA SINTER PLANT
SAIL ROURKELA SINTER PLANT
 
sail bokaro
sail bokarosail bokaro
sail bokaro
 
Steel Plant Internship and ICOMM Telecom limited
Steel Plant Internship and ICOMM Telecom limitedSteel Plant Internship and ICOMM Telecom limited
Steel Plant Internship and ICOMM Telecom limited
 
Sinter Plant,Lime & Dolo Plant industrial Training Report
Sinter Plant,Lime & Dolo Plant industrial Training ReportSinter Plant,Lime & Dolo Plant industrial Training Report
Sinter Plant,Lime & Dolo Plant industrial Training Report
 
Chandan me
Chandan meChandan me
Chandan me
 
Bhilai Steel Plant - Internship Report
Bhilai Steel Plant - Internship ReportBhilai Steel Plant - Internship Report
Bhilai Steel Plant - Internship Report
 
A VOCATIONAL TRAINNING REPORT_aman
A  VOCATIONAL TRAINNING REPORT_amanA  VOCATIONAL TRAINNING REPORT_aman
A VOCATIONAL TRAINNING REPORT_aman
 
Autoclave
AutoclaveAutoclave
Autoclave
 
Pankaj kumar ppt on bokaro steel plant for civil
Pankaj kumar ppt on bokaro steel plant for civilPankaj kumar ppt on bokaro steel plant for civil
Pankaj kumar ppt on bokaro steel plant for civil
 
A presentation of summer internship in rourkela steel plant
A presentation of summer internship in rourkela steel plantA presentation of summer internship in rourkela steel plant
A presentation of summer internship in rourkela steel plant
 

Similar to asp report

iron and steel plant
iron and steel plantiron and steel plant
iron and steel plantKumar Gaurav
 
Stainless Steel Castings, Steel Casting Manufacturer, Steel Casting Manufactu...
Stainless Steel Castings, Steel Casting Manufacturer, Steel Casting Manufactu...Stainless Steel Castings, Steel Casting Manufacturer, Steel Casting Manufactu...
Stainless Steel Castings, Steel Casting Manufacturer, Steel Casting Manufactu...Natarajan CV
 
Heavy engineering corporation project report
Heavy engineering corporation project reportHeavy engineering corporation project report
Heavy engineering corporation project reportAshish Raj
 
Complete Rolling Mill & Equipment Manufacturer ---Hani Tech
Complete Rolling Mill & Equipment Manufacturer ---Hani TechComplete Rolling Mill & Equipment Manufacturer ---Hani Tech
Complete Rolling Mill & Equipment Manufacturer ---Hani TechKerri Zhang
 
Steel Melting Shop (SMS)
Steel Melting Shop (SMS)Steel Melting Shop (SMS)
Steel Melting Shop (SMS)Gautham Reddy
 
PPT ON METAL AND STEEL FACTORY, ISHAPORE, (WEST BENGAL)
PPT ON METAL AND STEEL FACTORY, ISHAPORE, (WEST BENGAL)PPT ON METAL AND STEEL FACTORY, ISHAPORE, (WEST BENGAL)
PPT ON METAL AND STEEL FACTORY, ISHAPORE, (WEST BENGAL)MD SHAHID JAMIL
 
Cost reduction in melting-A SQC & 6Sigma Approach
Cost reduction in melting-A SQC & 6Sigma ApproachCost reduction in melting-A SQC & 6Sigma Approach
Cost reduction in melting-A SQC & 6Sigma ApproachArun Sadvi
 
Van gang dẻo hitachi
Van gang dẻo hitachiVan gang dẻo hitachi
Van gang dẻo hitachihongrubu
 
Van bướm tay quay, van bướm tay gạt, van cửa, Van gang dẻo hitachi, 0932 ...
Van bướm tay quay, van bướm tay gạt, van cửa, Van gang dẻo hitachi, 0932 ...Van bướm tay quay, van bướm tay gạt, van cửa, Van gang dẻo hitachi, 0932 ...
Van bướm tay quay, van bướm tay gạt, van cửa, Van gang dẻo hitachi, 0932 ...hongrubu
 
Summer intership
Summer intershipSummer intership
Summer intershipPrithvi Raj
 
Bhilai steel plant plate mill & mars 1
Bhilai steel plant  plate mill & mars 1Bhilai steel plant  plate mill & mars 1
Bhilai steel plant plate mill & mars 1Akhilesh Rathiya
 
Continious casting of steel
Continious casting of steelContinious casting of steel
Continious casting of steelbikiranjan
 
Industrial Training Report on Plate Mill
Industrial Training Report on Plate MillIndustrial Training Report on Plate Mill
Industrial Training Report on Plate MillShani Kumar Singh
 
Berr Process Equipment - 2018-001
Berr Process Equipment - 2018-001Berr Process Equipment - 2018-001
Berr Process Equipment - 2018-001Berr Industry
 
Lead acid battery manufacturing process
Lead acid battery manufacturing processLead acid battery manufacturing process
Lead acid battery manufacturing processImran Shahnawaz
 

Similar to asp report (20)

iron and steel plant
iron and steel plantiron and steel plant
iron and steel plant
 
Seminar-II
Seminar-IISeminar-II
Seminar-II
 
Stainless Steel Castings, Steel Casting Manufacturer, Steel Casting Manufactu...
Stainless Steel Castings, Steel Casting Manufacturer, Steel Casting Manufactu...Stainless Steel Castings, Steel Casting Manufacturer, Steel Casting Manufactu...
Stainless Steel Castings, Steel Casting Manufacturer, Steel Casting Manufactu...
 
Amit
AmitAmit
Amit
 
Heavy engineering corporation project report
Heavy engineering corporation project reportHeavy engineering corporation project report
Heavy engineering corporation project report
 
Complete Rolling Mill & Equipment Manufacturer ---Hani Tech
Complete Rolling Mill & Equipment Manufacturer ---Hani TechComplete Rolling Mill & Equipment Manufacturer ---Hani Tech
Complete Rolling Mill & Equipment Manufacturer ---Hani Tech
 
Steel Melting Shop (SMS)
Steel Melting Shop (SMS)Steel Melting Shop (SMS)
Steel Melting Shop (SMS)
 
PPT ON METAL AND STEEL FACTORY, ISHAPORE, (WEST BENGAL)
PPT ON METAL AND STEEL FACTORY, ISHAPORE, (WEST BENGAL)PPT ON METAL AND STEEL FACTORY, ISHAPORE, (WEST BENGAL)
PPT ON METAL AND STEEL FACTORY, ISHAPORE, (WEST BENGAL)
 
Cost reduction in melting-A SQC & 6Sigma Approach
Cost reduction in melting-A SQC & 6Sigma ApproachCost reduction in melting-A SQC & 6Sigma Approach
Cost reduction in melting-A SQC & 6Sigma Approach
 
SMS PROJECT
SMS PROJECTSMS PROJECT
SMS PROJECT
 
final_report
final_reportfinal_report
final_report
 
Van gang dẻo hitachi
Van gang dẻo hitachiVan gang dẻo hitachi
Van gang dẻo hitachi
 
Van bướm tay quay, van bướm tay gạt, van cửa, Van gang dẻo hitachi, 0932 ...
Van bướm tay quay, van bướm tay gạt, van cửa, Van gang dẻo hitachi, 0932 ...Van bướm tay quay, van bướm tay gạt, van cửa, Van gang dẻo hitachi, 0932 ...
Van bướm tay quay, van bướm tay gạt, van cửa, Van gang dẻo hitachi, 0932 ...
 
Summer intership
Summer intershipSummer intership
Summer intership
 
Bhilai steel plant plate mill & mars 1
Bhilai steel plant  plate mill & mars 1Bhilai steel plant  plate mill & mars 1
Bhilai steel plant plate mill & mars 1
 
Continious casting of steel
Continious casting of steelContinious casting of steel
Continious casting of steel
 
Lecture 7 steel
Lecture 7 steelLecture 7 steel
Lecture 7 steel
 
Industrial Training Report on Plate Mill
Industrial Training Report on Plate MillIndustrial Training Report on Plate Mill
Industrial Training Report on Plate Mill
 
Berr Process Equipment - 2018-001
Berr Process Equipment - 2018-001Berr Process Equipment - 2018-001
Berr Process Equipment - 2018-001
 
Lead acid battery manufacturing process
Lead acid battery manufacturing processLead acid battery manufacturing process
Lead acid battery manufacturing process
 

asp report

  • 1. CONTENTS Introduction Steel Melting Shop Vacuum Arc Degassing Vacuum Oxygen Decarburization Ladle Furnace Argon Oxygen Decarburization Continuous Casting Shop Blooming and Billet Mill Forge Shop  Plate Mill Heat Treatment & Finishing Shop Conditioning Shop Mechanical Repair Shop Boiler House Conclusion
  • 2. Steel Melting Shop The basic function of SMS is to produce hot metal from Ferro scrap and providing input material to ingot mould and caster for taking a shape. Slag is also an output of SMS which are used by cement industries for cement making. Basic highlights of SMS:  Electric Arc Furnace (EAF)  Transformer rating of this furnace is 25 MVA for stainless steel furnace and 18.75 MVA for the non stainless steel furnace.  One heat requires 3 hours to complete.  After tapping the molten metal is sent to VOD/VAD/LD directly.  In VAD the molten metal is degassed to removed the Hydrogen or Oxygen from the metal to reduce their amount to an acceptable ppm level.
  • 3.
  • 4. VAD Furnace Ladle Furnace VOD Furnace AOD Furnace
  • 5. CONTINUOUS CASTING SHOP(CCS) Through continuous casting route mainly stailess steel slabs are produced. In ASP there was a twin caster i.e. slab cum bloom caster which culd be used either as single strand slab caster or double strand bloom caster in operation. For continuous casting there is mould where the liquid metal is to be poured.Before the ladle comes inside the mould some biscuit and chocolate size bar is placed to give the shape of the slab. Casting can be sequential or in batch . In sequential casting 2 or more then 2 ladles are brought to turret for casting one by one.But in batch only one ladle is cast.
  • 6.
  • 7. BLOOMING AND BILLET MILL (BBM) In ASP, Blooming & Billet Mill plays a major role. Here the primary rolling mill is use to compress the soaking pits. In this process the soaking pit is use at temperature 1180-1800 C. BBM consists of Blooming Mill, Billet Mill & Soaking pits. This mill produces blooms, billets, squares, rounds, & slabs of various sizes & can handle all grades of alloy steel produced at SMS. At 1st in pit furnace a metal shape is heated and then it passed between two rollers. In roller operation the crossection of the specimen is gradually decreased. CONDITIONING SHOP COOLING LUD HOTSAW BILLETSHEAR 650 mm BILLETMILL 2 700 mm BILLETMILL 1 BLOOMSHEAR LD SCARFING MACHINE 900 mm TWO HIGH REVERSING MILL SOAKING PITFURNACE FROMSMS & CCS
  • 8. MAJOR CONTROLLERS IN B.B.M.:  Pit temperature controller.  Fuel controller. BLOOMING & BILLET MILL FORGE SHOP The forge shops have two type of forging presses for producing compact steel forgings. One is computerized forging press & another one is manual forging press which have 2 T capacity. In forging shop there is two heating chamber for heating the material before forging process. 1st chamber is use for gradually
  • 9. increasing the temperature of the specimen. Here the specimen doesn’t reaches the particular temperature which is not suitable for the forging. And the 2nd chamber is use for reheating the specimen. The total heating time is 6hrs. After that the specimen is ready for the forging. USE OF FORGING: It is use for making a specimen of required shape. By the forging press we get a final product of good surface finish. In forging process rectangular shape can be change in circular shape & also vice-versa. After processing in this shop the material is then sent to Heat Treatment and Finishing shop. SECTION:  Press Bay  Hammer Bay INPUT MATERIAL: Blooms of various sizes. CONTROLLING PARAMETERS OF FURNACE:  Metal temperature.  Fuel flow.  Combustion flow.  Compressed air flow.  Furnace pressure. PRODUCTS: Rounds, squares, die block, flats, rings etc.
  • 10. Diagram of Forging Press machine Forging Hammer Reheating Furnace
  • 11. Forging Pressure Forging Roll PLATE MILL The ingots are rolled at Blooming and Billet Mill for producing blooms, billets, rounds and slabs in a variety of steel grades & sizes. The rolled slabs are further rolled in Plate mill to produce plates. Today thermomechanical rolling is the most important production process for the manufacture of high strength plates. In this method the temperatures are exactly set for finish rolling and for cooling.
  • 12. CONDITIONING SHOP Detection and removal of surface defects like cracks and making materials ready for further processing a/c to customer’s needs.In the conditioning shop, the surface defect of the products are removed prior to shipping further rolling or forging in order to meet the required quality standard of the finished product. The further processing is known as conditioning. This shop is equipped with slow cooling boxes and bogie.Hearth type dispositioning
  • 13. furnaces for treatment of products received from BBM.Other facilities include straightening machines,saw and flame cutting machines elaborate inspection and testing arrangements for spark and spectro testing for quality control. INPUT MATERIALS: Products from-  Forge shop  BBM  Bar mill There are two types of conditioning shops: 1.CONDITIONING SHOP 1 Normal cooling Box cooling Grinding Cutting Furnace cooling 2.CONDITIONING SHOP 2: In this shop materials come from continuous casting shop. HEAT TREATMENT AND FINISHING SHOP Here different types of heat treatment arrangements such as for oil quenching, water quenching are present in order to impart specific properties to the alloy steel as per customer’s requirement. BOILER HOUSE
  • 14. This unit provides steam for the entire plant. Steam is used in vaccuam creation system consisting of converging and diverging nozzles. The water to be sent to boiler is first demineralised by passing it through cation exchanger and anion exchanger. This is done to prevent scaling by deposition of minerals on inner surface of boiler which reduces the life of boiler considerably. The water sent to the boiler is checked regularly in a chemical laboratory. MECHANICAL REPAIR SHOP(MRS) This is the Mechanical repairing shop which is support the production of the plant as well as looking after breakdown and preventive maintenance of equipment. It has Four Sections. Eg; i) Overhauling & Fitting, ii) Winding , iii) Testing & iv) Preventive & Breakdown Maintenance. * Overhauling & Fitting Section : This section repairs the motor, generator etc, after careful inspection of all parts & repair it accordingly. * Welding Section : - Welding of AC Motor of both Squirrel Cage & Slip Ring upto the capacity of 225 KW, 415V. 1480 RPM can be done. * Testing Section : At Testing section all DC & AC Motors upto the capacity of 100 KW can be Tested.
  • 15. * Preventive & Breakdown Maintenance : - Maintains Lathe, Drill, Planning, Copy planning , Welding etc, for uninterrupted production & to ensure equipment availability.