SAFETY MANAGEMENT PLAN
KATKONA 1&2 MINE ,KATKONA SUB AREA
1.BAIKUNTHPUR AREA
South Eastern Coalfield Limited
Coal India Limited
A Maharatna Company
2017
2. 2
S.N. CONTENTS PAGE NO.
1 Mission of Coal India 3
2 Vision of Coal India 3
3 Safety Policy of Coal India 3
4 Safety organization of Coal India 5
5 History of Katkona 1&2 Mine 6
6 Mine Working Plan 19
7 Mine Accident Analysis 19
8 System of Statutory Inspection & Records 26
9 Workplace Risks Assessment & Control 31
10 Principle Hazards Management Plan(PHMPs) 57
11 Emergency Organization plan including TARP 64
12 Emergency Exercise Event Log
13 Arrangement for training & upgradation of skill 80
14 Contractual Management Plan 81
15 List of Training / Refresher Training Conducts
16 Benefits of SMP 82
17 List of developed Standard Opperating Procedures 84
18. List of developed Code Of Practices
3. 3
1. MISSION OF COAL INDIA
To produce and market the planned quantity of coal and coal products efficiently and economically in
an eco-friendly manner with due regard to safety, conservation and quality.
2. VISION OF COAL INDIA
To emerge as a global player in the primary energy sector committed to provide energy security to
the country by attainting environmentally & sustainably growth through best practices from mine to
market.
3. SAFETY POLICY OF COAL INDIA
• Operating and system will be planned and designed to eliminate or materially reduce mining
hazards.
• Implement Statutory Rules and Regulations strenuous efforts made for achieving superior
standards of safety.
• To bring about improvement in working conditions by suitable changes in technology.
• Provide materialand monetary resources needed for the smooth and efficient execution of Safety
Plans.
• Deploy safety personnel wholly for accident for accident prevention work.
• Organize appropriate forums with employee’s representatives for Joint consultations on safety
matters and secure their motivation and commitment in Safety Management.
• Prepare annual Safety Plan and long term Safety Plan at beginning of every calendar year, unit-
wise and for the company, to effort improved safety in operations as per respective geo-mining
needs to prepare the units for onset of monsoon, to fulfil implementation of decisions by
Committee on Safety in Mines and Safety Conferences and to take measures for overcoming
accident proneness as may be reflected through study of accident analysis, keeping priority in
sensitive areas of roof-falls, haulage, explosives, mining machinery etc.
• Set up a frame work for execution of Safety Policy and Plans through the General Manager of
Areas, Agents, Managers, Other safety personnel of the units.
• Multi-level monitoring of the implementation of the Safety Plans through Internal Safety
Organization at the company headquarters and Area Safety Officers at area level.
• All senior executives at all levels of management, will continue to inculcate a safety consciousness
and develop involvement in practicing safety towards accident prevention in their functioning.
• Institute continuous education, training, in-door class, retraining all employees with the accent
placed on development of safety oriented skills.
• Continue efforts to better the living conditions and help of the employees both in and outside
the mines.
Safety Monitoring Agencies at Different Levels in CIL
1. Workmen’s Inspectors:-- As per Mine Rules 1955.
2. Safety Committee at Mine Level:--As per Mine Rule 1955.
3. Area Level Tripartite Committee.
4. Tripartite Safety Committee at Subsidiary Head Quarter Level.
5. Coal India Safety Board at Corporate Level.
6. Standing Committee on Safety in Coal Mines.
7. Different Parliamentary Committee.
4. 4
COAL INDIA LIMITED :: A MAHARATNA COMPANY
4. Organizational Structure for Safety in Coal India Ltd :
5. 5
5. HISTORY OF KATKONA MINE
5. 1 GENERAL INFORMATION :-
1. NAME OF THE MINE : KATKONA 1&2 INCLINE
2. MINE CODE : 010527
3. AREA : BAIKUNTHN PUR AREA
4. LOCATION LONGITUDE : 23° 20’ 00”
LATITUDE : 82 41’ 30”
RAILWAY STATION : KATORA
N.HEIGHWAY : KATNI-GUMALA (NH.78)
MINE ADDRESS : KATKONA 1&2 INCLINE
: POST – KATKONA
: POLICE ST. – PATNA
: TAHSIL - BAIKUNTHPUR
: DISTRICT - KOREA
: STATE_ CHATTISGARTH
: PIN CODE _ 497331
4. DATE OF OPENING OF MINE 15th
May,1963
5. LEASE HOLD AREA 1033.729 HECT.
6. HISTORY OF OWNERSHIP - since 1973 under WCL and
from 1987 under SECL
7. DISPUTE OF BOUNDARY - NOT ANY
8. MANPOWER ON ROLL - 399 (UP TO March- 2017)
U/g- 341 and Surface- 52
9. TARGET OF MINE - 246000 T / Year
6. 6
5.2 GEOLOGICAL AND MINING CONDITION :-
The Katkona 1&2 Incline was located at a distance of about 240 KM from the office of the Director of Mines
Safety, Bilaspur Region, Bilaspur and the mine was about 9 KM away from Patna (situated in Katni - Gumla
National Highway No. 78 ) in Katkona village, Baikunthpur, Tahsil, Korea District, Chhattisgarh State. The
nearest Railway Station was Katora Railway Station located about 9 KM away form the mine.
1)Date of Opening: - The mine was opened on 15 th may 1963 and after drivage of two drifts the work was
suspended in 1964 . The mine was restarted in the year 1973 and coal production started from 1974.
2)Change of Ownership :-The mine was opened on 15 th may 1963 and after drivage of two drifts the work
was suspended in 1964 by N.C.D.C. . The mine was restarted in the year 1973 after nationalization of coal
mines by C.M.A.L. and coal production started from 1974 by M/S CMAL. Then ownership was transferred to
WCL with effect from 1.11.1975 to 31.03.1986 and ultimately from 1.04.1986 it came under S.E.C.L.
3)Size of the mine:-
The mine area is 1033.729 Hect. The extent of the mine working along dip rise is about 2.0 km and
along strike is 4.50km.
4)Adjoining Mines:-
The Katkona 1&2 Inclines is surrounded by
(a). Towards North - Reserve forest
(b). Towards east side by Pandavpara Colliery where seam II and seam III is
being worked .
(c ) .Towards South - Reserve forest
(d). Towards west - Reserve forest
Barriers against adjoining mines were adequate.
5)Seam Description:- There were four number of workable seams exist in the leasehold property of the mine,
out of which Khajura Seam ( No.V seam) was the top most seam and the seam was workable in the property
through Katkona Incline No. 3&4, a separate mine. ChamatSeam( No. IIIseam) was the Middle seam, being
worked by another mine,i.e. Katkona 1&2 Incline mine. Khond seam, No. II Seam was Virgin which was lying
about 20 mt below from seam no. III. Katkona seam, No.I seam was the bottom most seam of the property
which was also developed through Katkona No.1&2 Incline mine.
7. 7
6) Details of the strata section indicating nature of strata and various seams as found in
borehole no. NCKT-6 is shown below :-
NCKT-6
Soil 1.52m
FG SS 16.6 m
shale 1.35 m
Seam V 4.3 m( Being worked by Katkona 3&4 Incline)
MGSS 26.13m
seam IV 0.9 m
CG-SS 102.1m
Seam III 1.6 m (Being developed by Katkona 1&2 Incline)
MGSS 10.8m
Seam II 0.7 m ( Virgin)
MGSS 33.7m
Seam I 3.5 m ( Developed by Katkona 1&2 incline and now standing on pillar)
Not to scale
7) The technical details of different workable seams were as follows:-
S.
N.
Seam
Thickness in
Meters
Gradient
Gassiness Depth
Mini--mum
InMtr
Maxi--mum
1. Katkona Seam
(No. I Seam)
2 to 5.0 mt. 1 in 3.35 Deg –I 20.0 254.0
2. Khond Seam
(No.II Seam)
0.9 to 2.0 mt. 1 in 3.16 Deg-- I 20.0 277.0
2. Chamat Seam
(No.III Seam)
1.5 to 1.6 mt. 1 in 25 Deg –I 20.0 256.0
8. 8
3. Khajura Seam
(No. V Seam)
2.0 to 4.0 mt. 1 in 40 Deg –I 15.0 157.0
8) Major Faults:- Following faults exist within the mine boundary of Katkona 1&2 Inclines the details of which wer
as under :-
Sr
no.
Name of
Faults
Location Width Throw Orientation
1. F-1 Rise side of the property Not known 45 mt up throw West to East
2 F-4 Dip side of the property Not known 140 t0 275
mt up throw
West to North
3.
F-7
Dip side of the property Not known 200 to 270 mt
down throw
West to North
4. F-8 Dip side of the property Not known 70-100mt
up throw
West to North
5. F-8A Dip side of the property Not known 05- 15 mt
up throw
West to East
6. F-9 Dip side from F-8 Not known 10 mt down
Throw
West to North
7. F-10 West side mine
boundary to middle
of the property
Not known 40 - 70 mt
up throw
West to east
.8. F-11 West side mine boundary Not known 40 - 70 mt
down throw
West to south
9. F-12 West side mine boundary Not known 80 mt
down throw
West to south
10. F- 13 Middle to dip of the property Not known 5 to 30 mt
down throw
West to North
11. F-14 From F-13 to Main dip /20 L Not known 5 to 20 mt
down throw
West to East
12. F- 15 Dip of 11 level west to
Main dip /20 L
Not known 5 mt
down throw
West to East
13. F-16 Middle of the property Not known 10 to 35 mt West to East
9. 9
down throw
14. F-17 Main dip / 15 L- 16L Not known 17 mt up throw West to East
15. F-18 14 L comp. dip to 33 x /10 L Not known 05 to 10 mt
down throw
West to East
16. F-19 13 L/ M. Dip to 10 x /13 L Not known 05 mt up throw East to west
17. F-20 From F-8A to dip of the
Eastern property
Not known 05 mt to30 mt
up throw
West to East
18 F-21 Eastern dip side of the
Property
Not known 05 mt to30 mt
up throw
West to East
19. F-22 Eastern dip side of the
Property
Not known 10 mt to15 mt
up throw
West to East
20. F-23 26 x dip 32 level Not known 05 mt up throw West to East
21. F- 24 17 Level / 51 x to
eastern mine boundary
Not known 05 mt to10 mt
up throw
West to East
22. F-25 22 Level / 52 x to
eastern mine boundary
Not known 05 mt
up throw
West to East
23. F-26 32 Level / 15 x to
eastern mine boundary
Not known 05 mt to 10 mt
up throw
West to East
24. F-27 10 L/ 41 x to rise side eastern
boundary
Not known 05 mt to 35 mt
up throw
West to East
25. F-28 Eastern mine boundary
from F-27
Not known 10 mt to 20 mt
up throw
West to East
Out of these faults, fault F-17 was encountered in 19 dip off 12L in seam I from where entry to seam III was
done by crossing the fault without any strata or other mining problem.
9). Entries: -
There were three entries for Katkona 1&2 Inclines. The detail of these three entries were as under:-
Name of incline
Length Gradient Size Purpose
No. 1 Incline 270.0 mt. 1 in 7.26 4.5 x 2.0
Used as travelling road and
coal transport and in takeairway.
10. 10
No. 2 Incline 240.0 mt. 1 in 7.25 4.5 x 2.0 Used as return airway &
material transport.
No. 5 Incline 60.0 mt. 1 in 6.0 4.5 x 2.0 Used for coal & material through
haulage, intake and escape Route
also.
10) Method of Work: -
Out of 4 nos. workable Seams available within mine boundary Seam I ( Katkona) and Seam III ( Chamat)
was being worked at Katkona 1&2 incline. Two underground mines e.g. Katkona 1&2 incline and Katkona
3&4 incline existed in same leasehold property of the mine.The upper most seam V ( Khajura) was being
worked by Katkona 3&4 inclines above seam III . Seam II ( Khond) was virgin. The overlying Seam V was
120.0 to 140.0 mt.above Seam III and developed by board & pillar method, average size of pillar varied from
20 mt. x 20 mt. to 35mt x 35 mtcentre to centre and average thickness of Seam I was 2.0 to 5.0 mt , that of
Seam II was 0.90 to 2.00 mt and seam III was 0.90 to 2.50 mt . Coal was being directly loaded onto
poneybelt by extra low height SDLs , And then by a series of belt conveyors coal carry up to UG strata
Bunker . from where through a ROM belt coal carry up to surface bunker and then from surface bunker coal
transported up to Katora Siding by contract tippers.
11) Degree of Mechanisation:-
Bord and Pillar development with solid blasting of coal in seam III was being practiced in the mine. Loaded
tubs from the working districts were being hauled by a series of conveyor belts to underground bunker, from
bunker to surface bunker coal was being transported by conveyor belt.
12) Present Working Panels:-
Presently following districts were being worked at Katkona 1&2 incline .
S1.
No.
Name Method of
Work
Mode of
Transport
SSR Approval no.
& date
Average no.
Of persons
Deployed
1. Panel 21L/64X
(3SDL, 0UDM)
Development Belt conveyor S.N.. 4031
dated - 12/9/2013
45
2.
8L/74X
(3SDL, 1UDM) Development Belt Conveyor --------do --------- 50
3. Stone Drifting
Seam-I to Seam -II
In Process By SDL As per Requirement 16
11. 11
5.3 INUNDATION:-
(i) Rivers:
No river existed within the mine boundary of Katkona 1&2 Inclines.
(ii) Nullah :- Surface area mostly consisted of forest land in hilly terrain. Few seasonal nullah/ rain cuts existed within
the property as shown on the plan however there was no danger of inundation from the surface water.
(iii) Ponds:-
There was no pond etc. over the property of Katkona 1&2 Incline.
(iv) Railways:-
No Railway siding existed within the property.
(v) C.H.P.:-
Coal handling arrangement in the mine was achieved by providing twin overhead bunkers of 100 tonne
capacity each on the surface, with truck loading arrangement underneath. Coal coming out of the mine by
belt conveyor installed in incline no.1 was directly fed to these bunkers.
(vi) Dwellings:-There were no dwellings existed over the property.
(vii) Roads:No road was passing over the workings .
(viii) H.T. Lines:- 3.3 KV SECL H.T. Line exist on the east side of no. 2 incline from Katkona
surfacesub station to Katkona 3&4 incline surface sub station. Development workings existed
below this HT line.
5.4 SEAM WISE DETAILS OF MINE:-
1) No./ Name of Seams being worked.
Sl.No No.Name
Of Seam
Depth of Working
Weather the seam is in the
state of open
Maximum Minimum
01 No.I Seam
Katkona
254 Mts 20 Mts. Development
02 No.II Seam
Khond
223 Mts. 61 Mts. Virgin
03 No.III Seam
Chamat.
202 Mts. 20 Mts. Development
Section of the Strata ( Attach a bore hole section) Attached.
12. 12
Direction and average dip of the Seams.
Seam I 1in3.35, N 9° 20’ E
Seam II 1in 3.14, N 8° 45’ E
Seam III 1in 3.14 , N 3° 14’ E
1) Details of Outlets
Inclines are as followes :-
Incline
No.
Length Width Height Gradient Connected to Purpose
No.1 270M 4.5M 2.0
M.
1in 7.26 Seam I
Traveling/Belt
Road/ Intake
airway
No.2 240M
4.5
M
2.0M 1 in7.25 Seam I
Material
Transport
Haulage/Retu
rn airway
No.5 60M 4.5
M 2.0
M
1 in 6.0 Seam I Intake airway
Special Geological Features, Disturbances ( Major, Fault, Dyke, Sills, Fissures, Pot
Holes.)
There are several faults encountered in the mine from 0.5 Mts. To 15 Mts
throw. Beyond present working there are several major faults within the
leasehold boundary varies from 10 Mts. To 280 Mts. Throw. Several
small dykes frequently appeared in Seam III Chamat and Seam I Katkona,
thickness varies form 0.5 Mts. To 1.50 Mts.
5) Total Reserve
As per 1986 Geological Report .
SEAM Grade
Range
Thickness
Mts.
Reserve in Million Te.
Geological Mineable Extractable
III SC II 0.90-2.50 07.50 05.15 03.00
II B/D 0.90-2.00 04.00 02.40 01.20
I SC I 2.00-5.00 11.00 09.34 07.00
5.5 GRADE OF COAL:-
SEAM Grade Range Thickness
Mts.
Reserve in Million Te.
Geological Mineable Extractable
13. 13
III SC-II 0.90 to 2.50 7.50 5.15 3.00
II B/D 0.90 to 2.00 4.00 2.40 1.20
I SC-I 2.00 to 5.00 11.00 9.34 7.00
d. Content of coal are as given table :-
Name of the
Seam
Volatile matter Fixed carbon Moisture Ash
III 34% -35% 49% 2 %- 4% 14% -20%
II 34% – 35% 49% 2 %- 4% 14 %-20%
I 32% 53% 2% - 4% 14%– 20%
Nature of roof & Floor.
(Up to 2.0 M Thickness) Sand stone
SeamII Overlying Virgin, connected
Seam III.through 02 drift only
Present working Seam I - Development
3 Nos. of panel was depillared and
sealed off. No Active or sealed off Fire.
5.6 INFLAMABLE GAS :-
The seam is Degree I gassy Mine, chances of gas is rare.
Gas Measurement Instrument present in Katkona Mine:-
Sr.No. Name Of Instrument Quantity
1. Methanometer 6
2. Micro Clip CH4 Detector 3
3. Micro Clip CO Detector 1
4. Multi Gas Detector Micro 1
5. Toxymeter 1
6. Flame safety lamp 7
14. 14
7. Anemometer 1
8. Barometer 1
5.7 FIRE:-
There is no spontaneous heating. As precautionary measures continuous measurement of CO in air return
done. Regular inspection and checking of old working, sectionalisation stopping and ventilation stopping are
done by competent persons. Fallen coal accumulated in the old working areas and return air way is regularly
done.
5.8 MACHINERY, PLANT AND EQUIPEMENT:-
1. No. OF SDL :- 6 On Roll EIMCO ELECON
2.NO. OF UDM :- 1 EIMCO ELECON + 1 SIPLEX
3.NO. OF HAULAGE :- 1 MMEC + 4 BOLDRUM + 2 ENDLESS
4.NO. OF PUMP :- 4
5.MMV :- 1
6.AUXILLARY FAN :- 2
5.9 DETAILS OF MAIN MECHANICAL VENTILATOR AND PARAMETERS
S.N. Specification of fan & motor Results
1 Name of Manufacturer VOLTAS
2 Model No. PV-200
3 Type of fan Axial Flow Fan
4 Fan capacity 5000 Cum/Min.
5 Water gauge 50 mm
6 Blade angle setting & Nos. 15 degree. And Nos of Blades.8
7 Motor rating 90KW
8 Operating voltage 550Volts
9 Power Factor 0.91
10 Motor RPM 1480
11 Nos of Belts 8 Nos
12 Diameter of Fan 2.00 Mts
13 Fan RPM 720
15. 15
DETAILS OF VENTILATION PARAMETERS
1 Air quantity delivered by the fan 3100 Cum/Min.
2 Water Gauge 40mm
3 Current drawn 45Amp
4 Over all efficiency 74 %
5 Return Air Quantity 3300 Cu. M/Min
6. MINE WORKING PLAN:- Enclosed
7. ACCIDENT ANALYSIS OF KATKONA 1&2 INCLINE:-
ACCIDENT statistics since 2000 to march 2017
YEAR FATAL SERIOUS REPORTATBLE
2004 NiL 01 04
2005 NiL NiL 05
2006 NiL 01 03
2007 NiL NiL 06
2009 NiL NiL 01
2010 NiL NiL 01
2011 Nil 1 1
2012 Nil Nil 2
2013 Nil Nil Nil
2014 Nil Nil 4
2015 Nil Nil 1
2016 Nil Nil 2
March 2017
16. 16
a. FATAL ACCIDENT (Since 1986 to AUGUST 2016 ):-
Sl
No.
Year No. of
Accident
No. of Person Total
M/Shift
Worked
In the
Year
Total
Coal
Production
Total
Empoy
Ment
Death
Rate
Per
1000
Person
Employed
Killed Seriously
Injured
1 1994 01 01 01 NIL N.A. N.A.
FATAL CLASSIFICATION BY CAUSE:-
SL.
No.
Year No. of Person Classification of Accident by Cause
Killed Seriously
Injured
Fall of
Roof
Fall
Of
Side
Haulage Explosive Machinery
01 1994 01 NiL NiL 01 NiL NiL Nil
b. SERIOUS ACCIDENT (Since 2006- AUGUST 2016 ):-
S.L.
No.
Year
No.OfAccident
No.OfPERSON
SeriouslyInjured
Injury Rate Classification of Accident by
cause
Per3Lakh
ManShift
Emplo
Yed
PerMillion
Tonne
Produc
Tion
Per1000
Persons
Employee
yed
FallofRoof
FallOf
Roof
Haulage
Explosie
Mach.Inery/
Misc
1 2006 Nil Nil - - - - - - -
2 2007 Nil Nil - - - - - - -
3 2008 Nil Nil - - - - - - - -
4 2009 Nil Nil - - - - - - - -
5 2010 Nil Nil - - - - - - - -
6 2011 1 1
7 2012 Nil - - - - - - - - -
8 2013 Nil -
9 2014 Nil -
10 2015 Nil -
17. 17
11 2016 Nil -
12 2017
SERIOUS ACCIDENT PLACEWISE SERIOUS:-
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
Development Face 01
Haulage Road 02 03 01 01
Other Working Place
Other Traveling
Roadway
TIME WISE SERIOUS
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
7.00AM TO
3.00PM
02 01
-
-
- 1
3.00 PM TO
11.00 AM
01 01 01 01
-
-
-
11.00 PM TO
7.00 AM
01 01
-
-
-
18. 18
MONTH WISE SERIOUS
AGE WISE SERIOUS ACCIDENT :-
YEAR 18 TO 30 AGE 31 TO 40 AGE 41 TO 50 AGE 51 TO 60 AGE
2011 01 01 01
2012 01
2013
2014 01 01 01
2015 01
2016
March 2017
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
2000 01 01 01
2001
2002
2003 01 02
2004 01
2005
2006 01
2007
2008 - - - - - - - - - - -
2009 - - - - - - - - - - - -
2010 - - - - - - - - - - - -
2011 1
2012 - - - - - - - - - - - -
19. 19
c. REPORTABLE ACCIDENT ANALYSIS :-
AGEWISE REPORTABLE:-
Age 11 12 13 14 15 16 March 17
21 TO 30 - - - - -
31 -40 1 - - -
41 TO 50
01
- 2 1 1
51 TO 60 - 2 -
MONTHWISE REPORTABLE ACCIDENT :-
Year JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
2000 01 01
2001 01 01 01 02 01
2002 01 01 01 02 01 01
2003 02 01
2004 01 01 01 01
2005 02 01 01 01
2006 01 01 01
2007 01 01 02 01 01
2008 01 01 01 01 01
2009 01
2010 01 - - - - - - - - - - -
2011 01
2012
2013
2014 1 1
2015
2016 1 1
March
2017
20. 20
PLACEWISE REPORTABLE:-
Years 2000 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 March
17
Development
Face
02 01 02 01 01 03 01
01 1 1
Haulage Road 02 02 03 03 02 01 01 01 02 01
Other Working
Place
01 01 01
01 01 01 1
Depillaring 01
Traveling
Roadway
01 01 01
3 1 1
CAUSEWISE REPORTABLE:-
2010 2011 2012 2013 2014 2015 2016 2017
Fall of object 1
Fall of person on the level 2 3 1
Transport machine 1 1
Electricity
Other Machinery
Fall of Ground
Miscellaneous 1 1
TIME WISE REPORTABLE
2010
2011
2012
2013
2014
2015
2016
2017
7.00AM TO 3.00PM 01 02 04 1 1
3.00 PM TO
11.00 AM
01 1
11.00 PM TO
7.00 AM
21. 21
8. SYSTEM OF STATUTORY INSPECTION AND RECORDS:-
The statutory inspection in the mine is done three shifts (First, Second and Night) by Mining sirdar, Overman
and shift Incharge of Relay A, B,C. In general shift, District Incharge of both the district and Production
Incharge look after the requirement of materials for safety and Production. Ventilation Officer Dusting
Incharge inspect around the mine especially old workings, (isolation, sectionalisation and ventilation )
stopping including air crossing. Safety Officer visits the mine and promote safe practice among the
concerned mine employee and report to Manager about his visit stating that the provisions of Mine acts,
Rules and daily visit the mine and fulfill the requirement of machine and materials used for safety and
production.
Regular Back Shift Inspection is practiced by sr. Officers of the mine. All types of report and records like
Shot Firers, Mining Sirdar, Overman Report Books, manager’s Diary, Electrical Supervisor Log Book ,
Workman Inspector Report Book , Haulage Line Inspection report Book etc required by the statutory are
being maintained.
Statutory Records maintained at Katkona Incline Katkona Sub Area; Baikunthpur Area : SECL
Reg.No. Period Records to be maintained Exam, maint Sign
36(3) Authorization book and list of competent persons. Manager
41(8) Enquiry of fatal and serious accidents Manager
41(3)a Requisition book report to Owner, Agent for supply of materials Manager
49(1)(b) Surveyor’s daily facts about mine boundary, doubts about
accuracy of plans
Surveyor
63(4) List of plans Survey instruments and field book Surveyor
91(3) Rope record construction make date of installation and re-
capping
Roper splicer
103A Violation / Contravention recording register spot violation. Manager
114(2)(iii) Record of dangerous occurrence and examination before re-
admitting
manager
118(2) Permissions to light fire in U/G Manager
119(1)(a) Examination before persons are readmitted into the mine after
fire fighting
Manager
141(3)(b) Examination after dewatering VO
22. 22
145(1)(d) Particulars of gas determination VO
160(4) Copy of License of Magazine Magazine In-Char
164A(5)(b) Inspection of vehicle used for bulk transport of Explosives. Engineer
134 Standing orders for withdrawal of persons in the event of
stoppage of MMV
Manager
47(b) Hourly Observation of pressure Gauge and speed indicator of main fan
and recording
Fan Operator/VO
41(1)b Daily Under Manager’s Inspection Report Under Manager
41(1)b Daily Manager’s Inspection Report Manager
41-4(3) Daily Work performed by safety officer SO
42-4(3) Daily Work performed ventilation officer V.O
43(9) Daily Over man’s report of inspection OM
44&113(3)(d) Daily Mining Sirdar’s report of inspection MS
45&179(b) Daily Shot firer’s report book SF
56(b) Daily Record of explosives received /stored and issued Magazine Clerk
56(d) Daily Record of explosives issued to shot firer and return Magazine Clerk
93(1)(c) Daily Examination of haulage engine brake wheel etc. Mech.fitter
123A(1A)(d)(i) Daily Record of areas cleaned of coal dust and treated with
incombustible dust
Dust In-charge
123B(8) Daily Record of collection of dust samples and results of analysis of
dust
Sampling Incharge
131(5) Daily Log book examination and maintenance of electrical apparatus Engineer
155(2) Daily Examination of safety lamps immediately before belowground for
use
Lamp room Fitter
155(3) Daily Examination of safety lamps on after use Lamp room I/C
23. 23
142(5)3&4deg Daily Occurrence of inflammable or noxious gases VO
156(2) Daily Issue and return record of safety Lamps Lamp room Fitter
162(3) Daily Records of Transit slip Magazine In-Char
162(4) Daily Explosive issue and return record Magazine In-Char
70(1) Weekly Examination of outlet shaft Incline etc. Overman
89(3)(d) Weekly Examination of buffer, tub repair drawbar fitter safety catch
coupling chain etc.
Tub repair fitter
93(1)(b) weekly Examination of haulage track. Overman
94 Weekly Examination of haulage/travelling roadway loading to all out-lets
of the mine
Overman
118A(3)(c) Weekly Idle day inspection All Overman
118A(3)122(5) Weekly Inspection of fire stopping and isolation stopping VO
143(3&2deg) Weekly Inspection of unused working for presence of inflammable or
noxious gases
VO
133(3) Weekly Examination of main mechanical ventilation Mech. Forman
155(4) weekly Through examination of every flame Safety Lamps in use Lamp room I/C
186(5) weekly Inspection of all plants & machineries Foreman
187(2) weekly Examination of surface fence Overman
136(6) Fortnight Examination of air crossing ventilation stopping on doors etc. VO
133(4) Monthly Air measurement record V.O
4 Monthly Monthly return (production machinery man days and hours of
work)
Manager
76(1) Quarterly Register of reportable injuries Form ˝J ̋ Manager
116(3) Quarterly Log book effectiveness of detection in every electric system Engineer
24. 24
169(2)(c)(i) Quarterly Record of overhaul of Explosive Electric Sup.
76(2) Annually Register of minor injuries Form ̋ K ˝ Manager
111(1) Yearly Annual return of mine Manager
5 Annual Annual return(Employment explosives, out-put, leave wags) Form
III
Manager
29 P 20th
Feb Annual return of medical examination Form T Manager
105, 1/ 1960 Inspection of working beneath important surface features. All Overman
163,33of
1964
Physical verification of stock of explosive with the record
maintained
Blasting officer
108(1) SSR Development working within 10m of face and function of
roadways immediately out bye of the development faces.
All Overman
108 Code of standing orders for organization of support works Manager
119(3) Scheme for the provision and maintenance of the fighting
arrangements for prevention detection dealing and control of file.
V.O
120(1) File fighting plans V.O.
134 Standing orders of action to be taken in the even of fan stoppage V.O.
199A(1) Emergency plan of action for use in time of emergency Manager
29 s Action taken on workmen’s inspector inspection(15days) Manager
29 r Action taken to implement the recommendation of PSC Manager
77 A Issued of identity Token to every person employed at the mine Manager
108(1) S.S.R. for disturb zone Manager
29 G Medical examination of all persons employed at the mine Form O Manager
29 R2 Workman Inspector Report WI
29 U & 29 V Safety Committee accommodation S.O.
42(3) List of first Aider at the mine S.O.
44(3) List of First Aid station provided in the mine District Incharge
47(2) Posting of weekly day of rest Manager
48(1) Notice of work Form ˝V˝ Manager
49(4) Register of compensation day of rest Form ̋F ˝ OS/Manager
53(1) Register of leave account n Form ˝G ̋ & ̋ H ˝ OS
54 Information regarding leave with wages ˝ L ̋ OS
59 Register of overtime work ̋T ˝ Manager
69(4) Proceeding of canteen managing committee meeting Canteen Incharge
25. 25
71 Canteen Accounts book Canteen Incharge
73(2) Welfare Officers day in day record Welfare Officer
77 Register of persons employed at mine Form ˝ B ̋ W.O
78(1)(a) Register of persons employed in U.G Form ̋ C ˝ MTK
78(1) (c ) Register of persons employed on above ground Form ˝ C ̋ MTK
79 Posting of abstracts bye-laws and notices Vth Schedule Manager
TERMINOLOGY OF SAFETY MANAGEMENT PLAN (SMP)
Safety Management Plan (SMP):
SMP is a working document which outlines all the action to be carried out to ensure safety and health
at the workplace based on ‘Risk Assessment’ exercise to be done by a team consisting of workers and mine
management beside others.
Hazards:
It is source of potential harm/situation with a possible to cause loss.
Risk:
It is the change of something happing that will have an impact upon objectives. It is measured in terms
of Likelihood and Consequences.
Consequence;
It is the size of loss or damage and it indicates the magnitude or amount of severity of risk. In terms of
health and safety, it is the degree of harm that could be caused to people exposed to the hazard, the potential
severity of injuries or ill health and /or the number of people who could be potentially affected.
Likelihood:
It is used as a qualitative description of probability and frequency.
Risk Management :
Risk Management is a systematic application of management policies, procedures and practices to the
task of Identifying, Analyzing , Accessing , Treating , and monitoring the risks at workplaces.
Risk Assessment;
Risk Assessment is logical and systematic method of identifying, analyzing and evaluating Potential
Hazards in a particular process/ operation. Hazards are quantified in terms of numbers.
26. 26
Risk Control:
Implementation of strategies to prevent or control hazards.
Risk Management Process
1. Establishing Context:- This means to clearly define the particular task, issue or situation and underlying
hazards that one is trying to resolve as a part of risk management activities. By doing so the risk assessment team
understands what the issue is, where the issue is located and what specifically will be covered.
2. Hazard Identification:- This is the first and the most important step of Risk Management process. Hazards
are best identified by variety of technique that may include-Consultation with mine worker, Inspections, Accident
& incident report, manufacture booklet, safety audits, checklists etc.
3. Risk Analysis:- Analysis risk is the process of adding meaning to the identified hazards i.e. what loss event
could be associated with the identified hazard.
4. Evaluating Risk:- This is done to provide an estimate of resultant risk, in terms of consequences and
likelihood. Most commonly Risk Grid Matrix is used to provide a qualitative measure of the risk magnitude.
5. Treating Risk:- For this Hierarchy of controls is used to identify where we are putting our effort for
controlling risk. The elimination being most effective and PPE & action reliable on human behaviour are least
effective.
6. Auditing & Monitoring of Risk Control Measures :- Reviewing the effectiveness of programmes within
the Safety Management Plan. This should be an on-going process. Both internal and external audits should be
considered. This should be show whether policies, regulations and expectations are being met or where systems.
7. Review: - Once the control measures have been implemented it is important to review them as soon as they
have been implemented and periodically afterwards to verify their effectiveness.
8. Communication: - It is the key ensure that the hazard identification and risk management is fully effective.
Communicate
&
Consult
Establish Context
Identify the Hazard
Analyse the Risks
Treat Risk
Evaluate Risk
Monitor
& Review
Auditing & Monitoring
of Risk Control
Measures
27. 27
Methodology Followed for Preparation of SMP
Following are the step by step methodology followed while preparation of ‘Safety Management Plan’ (SMP)
including the Risk Assessment and Risk Management.
C
o
m
m
u
n
i
c
a
t
i
o
n
Assemble the Team/Formation of multi-disciplinary team
Define the Operation/Activities
Identifying the Hazard in each operations
Access the Risk by considering consequences and likelihood
Framing control measures
Time bound ‘Action Plan’ with responsibilities for implementation of control measures
Ensure resources made available for implementation of control measures
Monitoring of implementation status of ‘Control Measures’
Auditing and Review the Process
Quantity and Prioritize Risk
Monitoring effectiveness of ‘Control Measures’
28. 28
Treatment Control and Action Plan
Examine the high priority risks. Consider the potential to reduce or eliminate the risk by using the Hierarchy
of Controls.
Least Effective
Controls
Hierarchy of controls.
1. ELIMANATE : - Remove the hazards or the need to perform the hazardous activity all-together.
100% Effective
2. SUBSITITUTE:- Hazardous substance, process, equipment, work method for safer
75% Effective
3. ENGINEERING /ISOLATION: - Redesign, enclose, or isolate/separate people from the
hazards by use of lock out system or use of barriers/distance /time.
50% Effective
4. ADMINISTRATIVE: - Training, rules, procedures, safe systems of work
20-30% Effective
5. PPE: - Include eye/face/skin/foot/ head/ respiratory/ hearing/fall protection and
contingencies such as firefighting equipments. 5% Effective
6. SAFE BEHAVIOUR: Situational awareness/ alertness and compliance with rules and procedure,
instructions.
Can’t say/Unpredictable
Most
Effective
29. 29
Safety and Health Policy of Katkona 1&2 Incline
1. To plan and design all the operation in such a way as to eliminate the mining hazards.
2. To implement the statutory Regulation and Rules and to make strenuous efforts for achieving superior
standard of safety.
3. To give priority to safety and health factor over economic factors.
4. To regard safe working as taking precedence over improvisation and unsafe practices.
5. To bring about improvement in working condition by suitable change in technology.
6. To provide all materials and monitory resource needed for the smooth and efficient execution of the safety
plans.
7. To prove for a “safety suggestion scheme” and the careful consideration of a submission and
implementation thereof.
8. To institute continuous education, training and re-training of all employees for Development of safety
oriented skill.
9. To make continuous efforts for the better living condition and health of all the employees both in and
outside the mine.
10. To organize appropriate forums with employees representative, for joint consultation on safety matters.
11. To provide for medical examination of all employees
12. To appoint workmen’s Inspector to monitor the safety of mine and to locate unsafe condition/ practices and
have them corrected.
13. To furnish work places free from recognize hazards cause death injuries or illness.
14. To monitor the performance of supervisors by their safety records.
15. To provide for the maximum use by all the employee of protective equipment and safety devices to
minimize the accidents.
16. To investigate and discuss all the incident /accident by the safety committee and apply effective remedies.
17. To ensure the prevention, suppression, treatment, collection and removal of the harmful dust at all time and
to provide and consistently use the dust suppression equipment, both at the surface and underground.
18. To ensure good illumination and sanitary facilities.
31. 31
Possible Degree of Consequences
While identifying hazards in a classified sector, number of workers who may be exposed need
to be taken in account to ascertain possible degree of consequences in the event of a mishap in
following manner:-
TABLE -1
Serial
No.
Percentage of work persons employed Impact assessment of exposure
1. >40 Maximum
2. 20-40 High
3. 10-20 Medium
4. 5-10 Low
5. <5 Very Low
REVISITING OF SMP:-
The SMP may be revisited when;
1) Geo- Mining conditions changed; or
2) Mining process is changed or altered; or
3) New equipement is introduced in the mining process; or
4) Incident of near miss is reported; or
5) Accident takes place.
33. 33
KATKONA 1&2 INCLINE
Now it is required manage the Risk up to acceptable levels which are inherently involved in above said operation
U/G Mine
Production
System
Production
Sub-System
Production
Facilitating Sub-
System
Elements of
Production
Facilitating Sub-
System
Elements
Production
Sub-System
Coal
Loading
Operation
Coal Winning
(Drilling &
Blasting
Operations
Systematic Coal Production at High Productivity
with Safety and healthy work environment
Production
Coal
Evacuacing
(Transportation
)
Ground
Control
Machine
Maintenance
Ventilation/
Environment
Material
Supply
Others
34. 34
PROCESS TO CALCULATE RISK SCORE FOR A HAZARD
Using the equations in Section 6.2.3. of DGMS Cir. No.02/2002 , the following values has been
used to calculate Risk Score for a Hazard.
Risk Score = Consequence x Likelihood
Risk Score = Consequence x Probability x Exposure
Scale for Consequence
• Several dead 5
• One dead 1
• Significant chance of fatality 0.3
• One permanent disability/less chance of fatality 0.1
• Many lost time injuries 0.01
• One lost time injury 0.001
• Small injury 0.0001
Scale for Exposure
• Continuous 10
• Frequent (daily) 5
• Seldom(Weekly) 3
• Unusual (Monthly) 2.5
• Occasional 2
• Once in 5 years 1.5
• Once in 10 years 0.5
• Once in 100 years 0.02
Scale for Probability
• May well be expressed 10
• Quite possible 7
• Unusual but possible 3
• Only remotely possible 2
• Conceivable but unlikely 1
• Practically impossible 0.5
• Virtually impossible 0.1
Risk = Consequence x Probability x Exposure(CPE) for Maximum –
Maximum Risk – 5*10*10 = 500
Hazard identified as High Risk when (Risk>200)
Hazard identified as Risk requiring Management Action whe (Risk<200 and >20)
Hazard identified as Low Risk but to be reviewed when (Risk<20)
35. 35
Hazard Identification Process
The process of identifying hazards is possibly the most important part of the whole risk assessment
process. Objective is to ensure that all of the possible hazards are identified. Hazards are only discounted
when they have been assessed not to pose a risk. Normally the best process is to proceed step by step
through a task. A number of other processes can also be utilised-
• Previous experience of accidents or occurrence in the mine.
• Work process evaluation.
• Consultation with employees who may have experience in the job.
• Off-side specialists with experience at other mine sites (consultants).
• Fault tree analysis to determine underlying issues and hazards that might not be
evident at first glance.
• Safety statistics for this or other mines.
• Significant incident, near-miss or accident reports
• Inspections in the mine.
Tools of Risk Management
Following documents has been considered for consideration of team,
• Minutes of safety committee meeting
• Workmen’s Inspection report
• Contraventions pointed out by regulators and action taken report
• Safety officer’s inspection report
• Report (s) submitted by Internal Safety Organization, if any
• Previous risk assessment document, if any
• Report (s) on accidents and near misses
Assemble Identify Determine
Review Hazards
Review Ranking
RankDetermine
Initiate
37. 37
TABLE -3
Hazard Identification
HAZARDS IDENTIFIED HIGH RISK
(Risk>200)
Requiring immediate attention
S.N. Description of Hazard
Percentage
of Workers
exposed
Cons. Prob. Exposure
Total
(C*P*E)
1 Roof and Side Fall (Strata Control) 50% 5 10 10 500
2
Moving machinery (including illegal man-
riding on SDL etc.)
70% 5 10 10 500
3
Existing Mine Fire-potential for explosion/
Spontaneous Combustion
70% 5 7 10 350
4
Inundation/Waterlogged Workings surface
water
40% 5 7 10 350
5 Ventilation/ Mine Gases 70% 5 7 10 350
6
Lack of skilled persons/using unskilled persons
in specified jobs
30% 5 7 10 350
7 Survey-incorrect mine plan 70% 5 7 10 350
8 Improper Survey instruments 70% 5 7 10 350
OTHER HAZARDS IDENTIFIED AS RISKS
REQUIRING MANAGEMENT ACTION
(Risk<200 and >20)
OTHER HAZARDS IDENTIFIED AS LOW
RISK BUT TO BE REVIEWED
(Risk<20)
S.N. Description of Hazard
Percentage
of Workers
exposed
Cons. Prob. Exposure
Total
(C*P*E)
1 Blasting 20% 1 10 10 100
2 Haulage & transport failure 10% 1 10 10 100
3 Unauthorized Entry to mine workings 10% 1 10 10 100
4 Lack of illumination 10% 1 10 10 100
5 Electricity 20% 1 10 10 100
6 Material Handling 20% 1 10 10 100
S.N. Description of Hazard
Percentage
of Workers
exposed
Cons. Prob. Exposure
Total
(C*P*E)
1 Respirable Dust 20% 0.1 10 10 10
38. 38
TABLE – 4 Summarized Hazard Identification
Major Hazard Categories Identified
(01) Strata Control
(02) Machinery
(03) Inundation
(04) Mine Fires
(05) Mine Gases
(06) Electricity
(07) Blasting & Use of Explosives
(08) Haulage & Transportation
(09) Spontaneous Combustion
(10) Occupational Health
(11) Emergency Reponse
TABLE -5 Categorization of Identified Risks
S.N. Major Hazard Sub Category of Hazard
1 Strata Control • Roof fall (Strata control)
• Side fall
• Lack of skilled persons/using unskilled persons
• Improper survey instruments
• Surface blasting and vibrations
• Lack of illumination
2 Machinery
• Lack of skilled persons/using unskilled persons
• Winding (Shaft)
• Boilers
• Lack of illumination
• Moving machinery (including illegal man-riding on SDL etc.)
3 Inundation • Waterlogged workings
• Survey-incorrect mine plan
• Improper survey instruments
• Lack of skilled persons/using unskilled persons
2 Noise 20% 0.1 10 10 10
3 Inadequate Ventilation 60% 0.1 10 10 10
4 Slippery Roadway 70% 0.1 10 10 10
5 Improper travelling roadway 70% 0.1 10 10 10
39. 39
• Inundation from surface source
• Surface blasting and vibrations
• Drivages not to plan
4 Mines Fires • Existing Mine Fire
• Lack of skilled persons/using unskilled persons
• Surface blasting and vibrations
• Unauthorized entry to mine workings
• Coal dust –explosion
• Inadequate –Ventilation
5 Mine Gases • Mine Gases
• Fire damp
• Coal dust- explosion
• Inadequate Ventilation
6 Electricity • Electricity
• Lack of skilled persons/using unskilled persons
7 Blasting & Use of Explosives • Blasting
• Lack of skilled persons/using unskilled persons
• Coal dust - explosion
• Drivages not to plan
8 Haulage & Transportation • Lack of illumination
• Haulage & transport failure
• Moving machinery (including illegal man-riding on SDL etc.
• Material handling
9 Spontaneous Combustion • Spontaneous Combustion
10 Occupational Health • Respirable dust
• Noise
• Lack of illumination
11 Emergency Response • Improper travelling roadway
Development of worksheet for Risk Assessment, Control and Audit
As per DGMS (Tech.) (S&T) Circular No.05, Dated -2 April 2016
The template of worksheet for risk assessment , control and audit exercise may include , among others,
document number, title, name of the mine, company, date conducted, location, etc. followed by the list of
assessment team members and facilitators, as below:
Risk Assessment – Mine Ventilation / inundation/ in underground coal/metal mines
Name of the Mine : Katkona 1&2 Incline Name of Company : SECL
Date Conducted :
Location : Katkona 1&2 Incline
1. RA/SCUG
Risk Assessment: Strata Control in Underground Coal Mines
Name of the Mine : Katkona 1&2 Incline Name of Company : SECL
Date Conducted :
41. 41
SCH-19 Inadequate design of
supports
Failure to account for
multiple seam interaction
effects.
05 05 03 75
SCH-20 Roof fall in
development workings
Non adherence to support
plan in prior
developments. (Problems
05 03 07 105 Progressive strata
dilation in old
developed
1 2 3 4 5 6 7 8
SCH-1 Lack of knowledge on
procedures
Documents available are
sketchy and not adequate.
05 10 10 500 Workshop on
development of
Safety
Management plan
need to be
conducted
SCH-2 Lack of knowledge on
procedures.
Workers and supervisors
not trained to follow
procedures.
05 10 10 500 Specialised
refresher training
required.
SCH-3 Lack of knowledge on
procedures.
Surveillance to implement
procedures.
05 10 10 500 Specialised
process (es) to be
devised.
SCH-4 Roof fall in freshly
exposed roof of
development workings
Poor supervision of
mining operations
05 10 10 500
SCH-5 Roof fall in freshly
exposed roof of
development workings
Poor workmanship in
installing supports.
05 10 07 350
SCH-6 Roof fall in freshly
exposed roof of
development workings.
Inadequate support
density for weak and
incompetent roof strata.
05 10 07 350
SCH-7 Roof fall in freshly
exposed roof of
development workings.
Inferior quality of support
material.
05 10 07 350 Quality of roof
bolts, bearing
plates, cement
capsules, etc.
SCH-8 Roof fall in
development workings.
Presence of slip planes in
roof.
05 05 07 175
SCH-9 Side fall in
development workings.
Weak and incompetent
sides.
05 05 07 175
SCH-10 Roof fall in
development workings
Delay in supply of roof
support material in
development workings.
05 05 07 175 Material indented
but not received in
time.
SCH-11 Roof fall in
development workings
Delay in erection of
supports in development
workings.
05 05 07 175 Deficient work
culture and lack
of discipline.
SCH-12 Roof fall in
development workings
Orientation of roadways
parallel to cleat.
05 05 07 175
SCH-13 Side fall in
development workings
Orientation of roadways
parallel to cleat.
05 05 07 175
SCH-14 Roof fall in
development workings
Excessive roadways with
due to poor drilling and
blasting.
05 05 03 75
SCH-15 Roof fall in
development workings
Workings not supported
according to support plan.
05 10 07 350 Poor supervisions.
SCH-16 Roof fall in
development workings
Inordinate time interval
between development and
extraction of coal panels.
05 05 03 75 Proper planning
schedule (short &
long term) not in
place.
SCH-17 Roof fall in
development workings
Development workings
are not vertically co
incident (Seam to seam)
05 05 03 75
SCH-18 Roof fall in
development workings
Support plan based on
deficient geological data
and other parameters.
05 05 03 75 Support design
not based on
prescribed
Geotechnical
classification
system.
42. 42
of the past) galleries.
SCH-21 Roof fall in
development workings
Effect of weathering. 05 03 03 45
SCH-22 Inadequate design of
supports.
Inadequate data for
decision making.
05 10 02 100
SCH-23 Inadequate design. Wrong sequence of
designed extraction.
05 03 03 45
SCH-24 Roof fall in mine
workings.
Lack of knowledge of
support personnel.
05 03 03 45
SCH-25 Side fall in mine
workings.
Formation of pillars with
sharp corners.
01 05 03 15
SCH-26 Side fall in mine
workings.
Improper selection of side
supports.
01 05 03 15
SCH-27 Roof fall in
development workings.
Shortage of support
personnel.
05 05 03 75
SCH-28 Roof fall in mine
workings.
Effect of weathering. 05 03 03 45
SCH-29 Roof fall in mine
workings.
Water seepage-brought
strata.
02 01 1.5 03
SCH-30 Roof fall in mine
workings.
Support hardware (roof
bolts, bearing plates) used
not as per approved
specifications.
05 10 03 150
SCH-31 Roof fall in mine
workings.
Cement capsules do not
confirm to prescribed
quality standards.
05 10 03 150
SCH-32 Roof fall in mine
workings.
Improper tensioning of
roof bolts.
01 10 03 30
SCH-33 Roof fall in
development workings.
Short holes drilled not as
per prescribed pattern.
01 05 03 15
SCH-34 Roof fall in
development workings.
Overcharging of Shot
holes.
01 05 03 15
SCH-35 Roof fall in
development workings.
Guidelines for solid
blasting not followed.
01 05 07 35
SCH-36 Roof fall in
development workings.
Presence of water in the
immediate roof.
01 05 03 15
SCH-37 Inadequate mine
design.
Short term production
planning with deficient
parameters.
01 10 07 70
SCH-38 Side fall in mine
workings.
Increased height of mine
galleries.
01 10 03 30
SCH-39 Inadequate mine
design.
Inappropriate pillar size. 0.3 10 03 09
SCH-40 Inadequate mine
design.
Effect of thickness of
parting not taken into
consideration.
05 10 01 50
SCH-41 Inadequate mine
design.
Failure to account for
interaction from adjacent
workings. (Underground)
05 10 01 50
SCH-42 Inadequate mine
design.
Failure to account for
interaction from
underlying or overlying
workings. (Underground)
05 10 01 50
TABLE: RA/MV-2
Risk Assessment: Mine Ventilation (MV) in Underground Coal Mines
Name of Mine : Katkona 1&2 Incline Date Conducted:
Name of the Company : S.E.C.L. Location:
Assessment Team
43. 43
S.N. Name Designation
01 Shri D.Singh Mine Manager (MM)
02 Shri Manoj Kumar Colliery Engineer (CE)
03 Shri P.F.Patel Safety Officer (SO)
04 Shri B.K.Singh Ventilation Officer (VO)
05 Shri K.K.Vishwakarma Assistant Manager (AM)
06. Shri S.K.Pandey Manager (M)
07. Shri K.A.Ansari AM (M)
08. Shri Dharmesh AM (M)
09. Shri S.K.Sinha SOE(M)
10 Shri G.S.Patel Sr.Surveyor (SUR)
11 Dr. R.R.Singh Medical Officer (MO)
12 Shri O.P.Gupta Surveyor (SUR)
13 Shri D.Sengupta Workman Inspector (Mining)(WIM)
14 Shri M.A.Siddqui Workman Inspector (Mechanical) (WIME)
15 Shri A.L.Gupta Workman Inspector (Electrical) (WIE)
16 Shri Ajay Singh Overman (OM)
17 Shri Amrit Mahato Mining Sirdar (MS)
18 Shri Shivcharan Foreman (Mechanical) (FMM)
19 Shri Ramesh Bhagat Foreman (Electrical) (FME)
20 Shri Dhaniram Electrical Supervisor (ES)
21 Shri Jawahar Safety Committee Member/Machenical Fitter
22 Shri Raghrai Safety Committee Member/SDL Operator
Facilitators (May Include)
S.N. Name Designation
01 Shri A.K. Dubey Nodal Officer , ISO
02 Shri M.Yadav Area Safety Officer
Hazard identified as regards to Mine Ventilation in mechanized Board & Pillar mining.
(Note : This assessment is based on loss of good quality air in working faces, not injury to persons.)
Abbreviations: HAZ: Hazard; CONS: Consequence; EXPS: Exposure; PROB: Probability,
HAZ
NO.
HAZARD MECHANISMS CALCULATED RISK COMMENTS
CON EXPS PROB RISK
RATING
1 2 3 4 5 6 7 8
MVH-1 Lack of knowledge on
procedures
Documents available are
sketchy and not
adequate.
05 10 10 500 Workshop on
development of Safety
Management plan
need to be conducted
MVH-2 Lack of knowledge on
procedures.
Workers and supervisors
not trained to follow
procedures.
05 10 10 500 Specialized refresher
training required.
MVH-3 Lack of knowledge on
procedures.
Surveillance to
implement procedures.
05 10 10 500 Specialized process
(es) to be devised.
44. 44
MVH-4 Air leakage in returns. Leakage through
ventilation doors/belt
doors.
05 05 07 175
MVH-5 Air leakage in returns. Leakage through
stoppings.
05 05 07 175
MVH-6 High resistance of
intake
Number of mine cars
present on haulage
system.
05 05 07 175
MVH-7 Reduced efficiency of
fan.
Slipping of V belts. 05 03 07 105
MVH-8 Air leakage trough
airlock.
Leakage through doors
and windows.
05 05 07 175
MVH-9 Improper distribution of
air to work faces.
Poor ventilation
planning.
05 05 07 175
MVH-10 Improper distribution of
air to work faces.
Poor workmanship in
installation of brattices
and ducting.
05 05 07 175 Specialized refresher
training required.
MVH-11 Improper distribution of
air to work faces.
Inadequate monitoring of
face ventilation.
05 05 07 175
MVH-12 Improper distribution of
air to work faces.
Attention not paid in
maintaining brattices and
ducts.
05 05 03 75 Deficient work culture
and poor discipline.
MVH-13 High resistance of
section intake.
Drivage of narrow
galleries.
05 05 03 75
MVH-14 Improper distribution of
air to work faces.
Use of damaged ducting. 05 05 07 175 Specialized refresher
training required.
MVH-15 Improper distribution of
air to work faces.
Reduction of cross
sectional area due to
poor erection of brattice.
05 03 07 105
MVH-16 Air leakage trough
airlock.
Short circuiting due to
poor door management
schedule.
05 03 07 105 Deficient work culture
and poor discipline.
MVH-17 Absorption of heat by
intake air.
Air picking up heat
unused workings.
05 05 03 75
MVH-18 Excessive amount of
water in intake airways.
Open water drains in
intakes.
01 05 07 35
MVH-19 Excessive quantities of
flammable gas(es).
Disruption to normal
ventilation
10 03 03 90 Additional
mechanisms to deal
with excessive
flammable gas levels
are covered by all
other mechanisms.
MVH-20 Scattered workings
faces.
Inadequate ventilation
planning.
05 03 03 45
MVH-21 High resistance of
intakes.
Accumulation of debris
in intakes.
05 05 03 75
MVH-22 Excessive quantities of
noxious gas(es).
Disruptions to normal
ventilation.
10 03 03 90 Additional
mechanisms to deal
with excessive
noxious gas levels are
covered by all other
mechanisms.
MVH-23 Air leakage into returns. Lack of reporting and
rectification of damage
to ventilation appliances.
05 05 03 75 Deficient work culture
and poor discipline.
MVH-24 Excessive water makes
in up cast shaft.
Water seepage from
shaft insets.
02 10 03 60
MVH-25 High resistance of
returns
Accumulation of debris
in returns.
05 05 03 75
MVH-26 High resistance of
intakes.
Unevenness of roadways
surfaces.
01 05 02 10
45. 45
MVH-27 Old workings open to
intake airways.
Poor routing of airways. 01 05 03 15
MVH-28 Improper distributions
of air to work faces.
Incorrect sitting of
auxiliary fans.
05 03 03 45
MVH-29 Air leakage into returns. Leakage through air
crossings.
05 05 07 175
MVH-30 Absorption of heat by
intake air.
Installed machines in
intakes.
01 03 02 06
MVH-31 Absorption of heat by
intake air.
Air picking up heat from
warmer water from open
boreholes from upper
seams.
01 03 02 06
MVH-32 Excessive amount of
water in intake airways.
Intermediate water
sumps in intakes.
0.3 03 02 1.8
MVH-33 High resistance of
returns.
Conveyance installed in
returns.
01 03 02 06
MVH-34 High resistance of
returns.
Zig sagging of air
current due to improper
planning.
0.3 05 02 03
MVH-35 Old workings open to
intake airways.
Non separation of old
workings from intake air.
01 05 03 15
MVH-36 Old workings open to
intake airways.
Damaged stopping
between old workings
and intakes.
01 05 03 15
MVH-37 Improper distribution of
air to faces.
Incorrect sitting of
Booster fan.
05 03 03 45
MVH-38 Excessive amount of
water in intake airways.
Leakage from water
pipes.
01 03 02 06
MVH-39 High resistance of
returns.
Air crossings of
inadequate cross
sectional area.
01 03 02 06
MVH-40 Reduced efficiency of
fan.
Voltage length of line of
extraction.
01 03 02 06
MVH-41 Scattered working
faces.
Excessive length of line
of extraction.
01 03 02 06
MVH-42 Improper distribution of
air work faces.
Excessive length of fan
ducting.
0.3 02 02 1.2
MVH-43 Improper distribution of
air work faces.
Excessive length of
brattice runs.
0.3 02 02 1.2
MVH-44 Reduction in area of fan
Evasee.
Accumulation of soot on
internal sides.
0.3 02 01 0.6
MVH-45 Reduced efficiency of
fan.
Improper setting of blade
angle.
0.3 03 02 1.8
MVH-46 Improper distribution of
air to faces.
Inadequate capacity of
auxiliary fans.
0.3 03 02 1.8
46. 46
TABLE: RA/IN-3
Risk Assessment: Inundation in Underground Coal Mines
Name of Mine : Katkona 1&2 Incline Date Conducted:
Name of the Company : S.E.C.L. Location:
Assessment Team
S.N. Name Designation
01 Shri D.Singh Mine Manager (MM)
02 Shri Manoj Kumar Colliery Engineer (CE)
03 Shri P.F.Patel Safety Officer (SO)
04 Shri B.K.Singh Ventilation Officer (VO)
05 Shri K.K.Vishwakarma Assistant Manager (AM)
06. Shri S.K.Pandey Manager(M)
07. Shri K.A.Ansari AM(M)
08. Shri Dharmesh AM(M)
09. Shri S.K.Sinha SOE(M)
10 Shri G.S.Patel Sr.Surveyor (SUR)
11 Shri D.Sengupta Workman Inspector (Mining) (WIM)
12 Shri M.A.Siddqui Workman Inspector (Mechanical)(WIME)
13 Shri A.L.Gupta Workman Inspector (Electrical)(WIE)
14 Shri Ajay Singh Overman (OM)
15 Shri Amrit Mahato Mining Sirdar (MS)
16 Shri Shivcharan Foreman (Mechanical) (FMM)
17 Shri Ramesh Bhagat Foreman (Electrical)(FME)
18 Shri Raghrai Safety Committee Member/SDL Operator
Facilitators (May Include)
S.N. Name Designation
01 Shri A.K. Dubey Nodal Officer , ISO
02 Shri M.Yadav Area Safety Officer
Hazard identified as regards to inundation in underground workings.
Abbreviations: HAZ: Hazard; CONS: Consequence; EXPS: Exposure; PROB: Probability
HAZ
NO.
HAZARD MECHANISMS CALCULATED RISK COMMENTS
CON EXPS PROB RISK
RATING
1 2 3 4 5 6 7 8
UNH-1 Lack of knowledge on
procedures
Documents available are
sketchy and not
adequate.
05 10 10 500 Workshop on
development of
safety management
plan need to be
conducted
47. 47
UNH-2 Lack of knowledge on
procedures.
Workers and supervisors
not trained to follow
procedures.
05 10 10 500
Specialised refresher
training required.
UNH-3 Lack of knowledge on
procedures.
Surveillance to
implement procedures.
05 10 10 500 Specialised process
(es) to be devised.
UNH-4 Sudden inrush of water in
underground mine
workings from surface.
Failure of coal pillars
due to existence of fire
in underground, allowing
connection cracks with
shallow surface rain
water accumulation and
flooding of underground.
05 10 07 350
UNH-5 Sudden inrush of water in
underground mine
workings from surface
Failure of embankment
constructed at river bank
due to heavy rain, and
entry of water from
surface through old
workings and subsidence
area to underground
mine workings
05 10 07 350
UNH-6 Sudden inrush of water
from workings of one
seam to another seam in
underground
Failure of dam
constructed in the
connection drift between
workings of two seams,
causing sudden inrush of
water from workings of
one seam to another
seam in underground.
05 10 07 350
UNH-7 Sudden inrush of water in
underground mine
workings from surface
Flooding of river due to
heavy rain and water
finding its way to
underground workings
through subsided area
over goaf or mine
entries.
05 05 07 175
UNH-8 Sudden inrush of water
from workings of same
seam or from one seam to
another seam in
underground
Barriers against water
logged old workings
failing under hydrostatic
pressure causing inrush
of water in underground
workings.
05 10 07 350
UNH-9 Sudden inrush of water
from workings of same
seam or from one seam to
another seam in
underground.
Sudden inrush of water
from old water logged
workings of same seam
or from one seam to
another seam in
underground due to
accidental connection.
05 05 02 50
UNH-10 Sudden inrush of water in
undergrounds mine
workings from surface.
Failure of river
bank/embankment due to
damage from mine
subsidence.
05 10 01 50
UNH-11 Sudden inrush of water in
underground workings
from adjacent strata.
Pillar failure or creep
allows goaf formation to
connect with subsidence
water body/aquifer.
05 10 01 50
UNH-12 Sudden inrush of water in
underground workings
from adjacent strata.
Roof fall in development
workings taps overlying
aquifer or subsurface
water accumulation.
05 1.5 02 15
UNH-13 Sudden inrush of water in
underground workings
from adjacent strata.
Mine workings intersect
geological structure
providing water flow
channel.
01 02 01 02
48. 48
UNH-14 Sudden inrush of water in
underground workings
from adjacent strata.
Existing mine workings
intersect open boreholes.
0.1 2.0 07 1.4
UNH-15 Sudden inrush of water
trapping mine workings in
underground.
Proper emergency
response protocol
including effective
communication from
surface to underground
not in place.
05 02 10 100 Workshop on
Emergency
Preparedness &
Response systems
needs to be
conducted.
UNH-16 Sudden inrush of water
trapping mine workers in
underground.
Lack of exposure and
practice of workers and
supervisors to follow
emergency response
protocol.
05 02 10 100
UNH-17 Sudden inrush of water
into present working
progressing towards old
water logged workings.
Not taking precautionary
majors while working
approaching towards old
water logged workings.
05 10 07 350
TABLE: RA/MF-4
Risk Assessment: Mine Fire (MF) in Underground Coal Mines
Name of Mine : Katkona 1&2 Incline Date Conducted:
Name of the Company : S.E.C.L. Location:
Assessment Team
S.N. Name Designation
01 Shri D.Singh Mine Manager (MM)
02 Shri Manoj Kumar Colliery Engineer (CM)
03 Shri P.F.Patel Safety Officer (SO)
04 Shri B.K.Singh Ventilation Officer (VO)
05 Shri K.K.Vishwakarma Assistant Manager (AM)
06. Shri S.K.Pandey Manager (M)
07. Shri K.A.Ansari AM(M)
08. Shri Dharmesh AM(M)
09. Shri S.K.Sinha SOE(M)
10 Shri G.S.Patel Sr.Surveyor (SUR)
11 Dr. R.R.Singh Medical Officer (MO)
12 Shri O.P.Gupta Surveyor (SUR)
13 Shri D.Sengupta Workman Inspector (Mining) (WIM)
14 Shri M.A.Siddqui Workman Inspector (Mechanical) (WIME)
15 Shri A.L.Gupta Workman Inspector (Electrical) (WIE)
16 Shri Ajay Singh Overman (OM)
17 Shri Amrit Mahato Mining Sirdar (MS)
18 Shri Shivcharan Foreman (Mechanical)(FMM)
19 Shri Ramesh Bhagat Foreman (Electrical) (FME)
20 Shri Dhaniram Electrical Supervisor (ES)
49. 49
21 Shri Jawahar Safety Committee Member/Machenical Fitter
22 Shri Raghrai Safety Committee Member/SDL Operator
Facilitators (May Include)
S.N. Name Designation
01 Shri A.K. Dubey Nodal Officer , ISO
02 Shri M.Yadav Area Safety Officer
Hazard identified as regards to Mine fire in underground mine
Abbreviations: HAZ: Hazard; CONS: Consequence; EXPS: Exposure; PROB: Probability,
HAZ
NO.
HAZARD MECHANISMS CALCULATED RISK COMMENTS
CON EXPS PROB RISK
RATING
1 2 3 4 5 6 7 8
MFH-1 Lack of knowledge on
procedures
Documents available are
sketchy and not adequate.
05 10 10 500 Workshop on
development of
Safety
Management
plan need to be
conducted
MFH-2 Lack of knowledge on
procedures.
Workers and supervisors
not trained to follow
procedures.
05 10 10 500 Specialized
refresher training
required.
MFH-3 Lack of knowledge on
procedures.
Surveillance to implement
procedures.
05 10 10 500 Specialized
process (es) to be
devised.
MFH-4 Coal spillage in the
conveyor roadways.
Cleaning of conveyor
roadway.
05 10 07 350
MFH-5 Coal spillage in the
conveyor roadways.
Improper conveyor
installation.
05 10 07 350
MFH-6 Coal spillage in the
conveyor roadways.
Improper maintenance of
conveyor systems.
05 10 07 350
MFH-7 Broken coal in mine
workings. (spalling)
Non adherence to
dimensions prescribed
while developing
roadways.
05 10 07 350
MFH-8 Broken coal in mine
workings. (spalling)
Poor side management by
bolting and wire netting.
05 10 07 350
MFH-9 Bed separation of coal
roof and spalling of
coal pillars.
Deficient periodic
inspection of mine
workings.
05 10 07 350
MFH-10 Heating in roadways. Oxidation of fallen coal in
roadway.
05 10 07 350
MFH-11 Heating of belt rollers
and gearbox.
Friction of Fresh air in
goaf through surface
cracks developed due to
subsidence.
05 10 07 350
MFH-12 Early indication
of spontaneous
combustion not
picked up.
Deficient monitoring of
mine atmosphere.
05 10 07 350
MFH-13 Inadequate ventilation Inadequate ventilation
network planning.
05 10 03 150
MFH-14 Inadequate ventilation Poor quantity and velocity
of air at workplaces.
05 10 03 150
MFH-15 Inadequate ventilation Non monitoring of efficacy
of ventilation networks.
05 10 03 150
MFH-16 Inadequate ventilation Workers and supervisors
engaged in conduct of
ventilation survey not
05 10 07 350
50. 50
adequately trained.
MFH-17 Cracks developed in
and around
sectionalisation
stopping’s with
passage of time
resulting leakage of air
through
sectionalisation
stopping’s
Poor maintenances of
sectionalisation stopping
05 10 07 350
MFH-18 Air leakage through
sectionalisation
stopping’s
Due to poor construction of
stoppings.
05 10 07 350
TABLE: RA/MM-5
Risk Assessment: Mine Machinery (MM) in Underground Coal Mines
(Transportation/ Use of Machinery in U/G Mine)
Name of Mine : Katkona 1&2 Incline Date Conducted:
Name of the Company : S.E.C.L. Location:
Assessment Team
S.N. Name Designation
01 Shri D. Singh Mines Manager (MM)
02 Shri Manoj Kumar Colliery Engineer (CM)
03 Shri P.F.Patel Safety Officer (SO)
04 Shri B.K.Singh Ventilation Officer (VO)
05 Shri K.K.Vishwakarma Assistant Manager (AM)
06 Shri Akhilesh Pandey Engineer(E&M)
08 Dr. R.R.Singh Medical Officer (MO)
09 Shri Omprakash Surveyor (SUR)
10 Shri D.Sengupta Workman Inspector (Mining) (WIM)
11 Shri M.A. Siddique Workman Inspector (Mechanical) (WIME)
12 Shri R.L.Gupta Workman Inspector (Electrical) (WIE)
13 Shri Ashwin Kumar Overman (OM)
14 Shri Amrut Kumar Mining Sirdar (MS)
15 Shri Shivcharan Foreman (Mechanical)(FMM)
16 Shri Awadha Kishor Foreman (Electrical)(FME)
17 Shri Dhaniram Electrical Supervisor (ES)
51. 51
18 Shri Jawahar Mechanical Fitter (MEF)
19 Shri Raghurai Safety Committee Member/ SDL operator
20 Shri Ramsudhir Safety Committee Member/Mech. Fitter
Hazard identification as regards to transportation of machines/use of machinery in u/g mine
Abbreviation:HAZ:Hazard;CONS: Consequence;EXPS:Exposure;PROB:Probability;SOP:Standard Operating Procedure.
HAZ No HAZARD MECHANICS CALCULATED RISK COMMENTS
CONS EXPS PROB RISK
RATING
1 2 3 4 5 6 7 8
UGTMM-
1
Lack of
knowledge on
procedure
Document available
are sketchy and not
adequate
05 10 10 500 Workshop on
development of
SMP needs to be
conducted.
UGTMM-
2
Lack of
knowledge on
procedure
Workers and
Supervisors not
trained to follow
procedures.
05 10 10 500 .Specialized
refresher training
required
UGTMM-
3
Lack of
knowledge on
procedure
Surveillance to
implement procedure
05 10 10 500
UGTMM-
4
Collision with
other moving
vehicles
Non adherence to
traffic rules &
driving of
vehicles/machines in
an unsafe manner.
05 05 07 175
UGTMM-
5
Uncontrolled
movement of
vehicles
resulting
collision to
side
Unauthorized driving
by untrained
personnel.
05 05 07 175
UGTMM-
6
While
reversing
collision with
Poor rear view
causing improper
assessment by
05 03 07 105
Facilitators (May Include)
S.N. Name Designation
01 Shri A.K. Dubey Nodal Officer , ISO
02 Shri M.Yadav Area Safety Officer
03 Shri S.S.Sinha SO(E&M)
52. 52
other vehicles operator
UGTMM-
7
While
reversing
causing
injury/death of
the spotter
/other
workman
present in the
vicinity.
Poor rear view
causing improper
assessment by driver.
05 03 07 105
UGTMM-
8
Uncontrolled
movement of
loaded vehicle
due to steep
gradient of
haul road
resulting in
toppling from
height.
Non maintenance of
haul road gradient as
per provisions of the
statute.
05 05 07 175
UGTMM-
9
Rolling of
boulder /fall of
rock pieces on
the machine.
Presence of
overhangs and loose
material in working
bench.
01 05 10 50
UGTMM-
10
Collision of
dumper with
excavator
while loading
of material.
Non-adherence to
SOP by dumper
driver /excavator
operator.
0.3 5 7 10.5
UGTMM-
11
Falling
material from
bucket of the
excavator to
lower bench.
Non-adherence to
SOP by excavator
operator.
01 05 07 35
UGTMM-
12
Uncontrolled
movement of
vehicle.
Poor maintenance of
the vehicle resulting
in brake failure.
05 03 03 45
UGTMM-
13
Falling of
loaded vehicle
to bottom
bench and
down the hill
roads.
Poor maintenance of
the adequate width of
benches and berms.
05 03 07 105
UGTMM-
14
Collision of
vehicles and
with other
machineries.
Poor illumination in
the haul roads and
working benches.
05 05 07 175
UGTMM-
15
Fire in
transport and
other
machineries.
Electrical short
circuit.
05 05 03 75
UGTMM-
16
Burn injury in
transportation
and other
machineries.
Inadvertent contact
of hands with hot
radiator/other other
parts of engine.
01 05 07 3.5
UGTMM-
17
Toppling of
the vehicle due
to insufficient
space in dump
Insufficient
supervision and
maintenance of the
dump yard.
05 03 07 75
53. 53
yard.
UGTMM-
18
Toppling of
the drilling
machine
during
marching from
one place to
another.
Non adherence of
SOP framed for
drilling by the
operator.
01 05 07 35
UGTMM-
19
Bursting of
hose during
drilling
operation
causing injury
to person(s)
Poor maintenance of
the drilling machine.
01 05 07 35
UGTMM-
20
Improper
loading of
material in the
dumper
causing injury
to person(s)
Non adherence of
SOP framed for
loading operation by
the operator.
0.3 05 07 10.5
TABLE: RA/ELE-6
Risk Assessment: Coal Mine Electrical Installations
Name of Mine : Katkona 1&2 Incline Date Conducted:
Name of the Company : S.E.C.L. Location:
Assessment Team
S.N. Name Designation
01 Shri D.Singh Mines Manager (MM)
02 Shri Manoj Kumar Colliery Engineer (CE)
03 Shri P.F.Patel Safety Officer (SO)
04 Shri B.K.Singh Ventilation Officer (VO)
05 Shri Akhilesh Pandey Electrical Engineer (EE)
06 Shri Dhaniram Electrical Supervisor (ES)
07 Shri A.L. Gupta Workman Inspector Electrical (WIE)
Hazard identified in coal mine electrical installations
Abbreviations: HAZ: Hazard; CONS: Consequence; EXPS: Exposure; PROB: Probability,
HAZ
NO.
HAZARD MECHANISMS CALCULATED RISK COMMENTS
CON EXPS PROB RISK
Facilitators (May Include)
S.N. Name Designation
01 Shri A.K. Dubey Nodal Officer , ISO
02 Shri M.Yadav Area Safety Officer
03 Shri S.S.Sinha Staff Officer (E&M)
54. 54
RATING
1 2 3 4 5 6 7 8
ELH-1 Lack of knowledge on
procedures
Documents/circuit drawings
available are sketchy and
not adequate.
05 10 10 500 Workshop on
development of
Safety
Management plan
need to be
conducted
ELH-2 Lack of adequate training
/ knowledge on operating
procedures.
Workers and supervisors not
trained to follow
procedures. Surveillance to
implement operations
operating procedures.
05 10 10 500 Specialized
refresher training
required.
ELH-3 Source of gas ignition due
to cap lamp.
Open sparking from cap
lamp due to improper
maintenance.
05 10 07 350
ELH-4 Source of gas ignition due
to open sparking from
cables.
Cables of appropriate type
are not installed in proper
manner.
05 10 07 350
ELH-5 Excess heating of the
electrical machineries.
(i) Improper setting of the
OC relay;
(ii) Core losses of the
machineries are relatively
high due to repeated
rewinding;
(iii) Heat generated due to
friction of moving parts
owing to worn out bearing;
and
(iv) Inadequate ventilation.
05 10 03 150
ELH-6 Flammable gas
accumulation at face.
Loss of ventilation caused
by loss of electricity supply.
05 10 07 350
ELH-7 Contact with bare
conductors of the
switchgears when live.
Operating procedure not
followed to prevent access
of live conductor. The door
interlocking not functional.
05 05 03 75
ELH-8 Contact with the bare
Over Head (OH) line and
the bushings of
transformers (CT/PT).
Non maintenance of
adequate vertical/horizontal
clearances of OH line, non
provision of anti-climbing
devices.
05 05 07 175
ELH-9 Contact with the
electrically charged body
due to insulation failure.
Insulation resistance
measurement and
monitoring plan is not
effective.
05 10 03 150
ELH-10 Non tripping of earth
leakage relay (ELR).
The setting of the ELR is
not proper. Effectiveness of
the relay not tested
periodically.
05 10 03 150
ELH-11 Contact with electrically
charged water pipe line.
Pipe lines are not earthed at
frequent intervals, damaged
cables / bare conductors
coming in contract with the
pipe line, the pipe line being
used as the neutral of the
supply system or for
earthing purposes.
05 2.5 03 37
ELH-12 Electrical shock due to
improper shutdown.
Permit to work/shutdown
and re-charging procedures
not followed adequately.
05 10 07 350
HAZ
NO.
HAZARD MECHANISMS CALCULATED RISK COMMENTS
CON EXPS PROB RISK
RATING
1 2 3 4 5 6 7 8
55. 55
ELH-13 Hazards due to use of
under rated
apparatus/switchgears and
cables.
(i) Rating of the apparatus/
switchgears/cables is not
calculated taking in to
consideration the duty cycle,
prospective level of fault
current, making and braking
capacity, factor of safety,
time current characteristics,
ambient temperature, future
load requirement and other
applicable factors at the
time of its
selections/requisition.
(ii) Type test reports are not
obtained at the time of
receipt of the apparatus /
switchgears at store, so as to
verify the rating to which it
is tested.
05 05 10 250
ELH-14 Physical injury due to
fatigue and attention
deficiency.
Working atmosphere is not
conducive.
01 10 03 30
ELH-15 Electrical Shock due to
non identification of
switchgears at front/back
and at the
incoming/outgoing/throug
h going.
Identification is made only
at the front of the
switchgear(s) / other
electrical installations.
05 05 07 175
ELH-16 Distinction of circuits of
different voltage not done.
The circuits/cables under
use at different voltage are
not identified throughout the
length.
05 10 07 350
ELH-17 Distinction of the
installations having
provision of more than
one incoming feeders not
done.
Precautions to work in the
installation having provision
of receiving supply from
two feeders are not taken.
05 10 10 500
ELH-18 Failure of apparatus due
to inadequate support &
ventilation
Inadequate support and
ventilation at location where
electrical
equipment/apparatus are
placed.
05 10 03 150
ELH-19 Damage of trailing cable
under use.
Pressing of trailing cable of
SDL/ drill machine during
reverse movement of SDL.
05 10 03 150
ELH-20 Self Protective devices for
persons working on
electric line not provided.
There is no efficient
mechanism to check the
health condition of the
Personal Protective
Equipment (PPE) from time
to time.
01 10 10 100
ELH-21 Guarding under the OH
line crossing the
road/other installations
not provided.
Guarding is not provided
under each OH line crossing
the roads. The guard wires
are not properly earthed.
05 10 07 350
ELH-22 Protection against lighting
surges not provided.
Lighting arresters are not
installed at both ends of the
Over Head (OH) lines and
electrically operated Heavy
Earth Moving Machinery
(HEMM).
05 10 10 500
HAZ
NO.
HAZARD MECHANISMS CALCULATED RISK COMMENTS
CON EXPS PROB RISK
RATING
1 2 3 4 5 6 7 8
56. 56
ELH-23 Accident due to unused
overhead lines.
These are not maintained in
a safe mechanical
condition/or not removed.
01 10 03 30
ELH-24 Open circuits of the
neutral in the restricted
neutral system of power
supply.
(i) Neutral failure fall safe
relay is not employed in all
the Trans Switch Unit
(TSU).
(ii) The functionality of the
neutral failure relay where
ever installed, is not tested
periodically.
05 10 07 350
ELH-25 Non-prevention of ingress
of moisture in to
motors/transformers/switc
hgear.
Interlocking of auxiliary
fans is not maintained in all
the working face due to non
provision of facilities in the
starter used for auxiliary
fan/inadequate length of
control cable.
05 10 07 350
ELH-26 Hazard due to non-
interlocking o auxiliary
fan.
Interlocking of auxiliary
fans is not maintained in all
the working face due to non
provision of facilities in the
starter used for auxiliary
fan/ inadequate length of
control cable.
05 10 07 350
ELH-27 Interlocking of Local
Methane Detector (LMD)
/proper placement of
LMD not done.
LMD’s not shifted with the
advance of face. Sometimes
the battery backup of LMD
is not operational.
05 10 07 350
ELH-28 Non operation of pilot
core relay.
Pilot core protection is not
maintained up to the
ON/OFF push button station
but up to foot switch.
05 10 07 350
ELH-29 Maintenance of Flame
Proof (FLP) features of
apparatus / switchgears.
Deficient.
No maintenance schedule
for checking the FLP
features of the apparatus &
switchgears.
05 10 07 350
ELH-30 Non-communication
between the surface Sub
Station & other
distributing centers.
Communication facilities
not provided at all the
distributing centers in the
mine.
01 10 10 100
TABLE: RA/OH-7
Risk Assessment: Air Borne Respirable Dust and Mine Occupational Health
Name of Mine : Katkona 1&2 Incline Date Conducted:
Name of the Company : S.E.C.L. Location:
Assessment Team
S.N. Name Designation
01 Shri D.Singh Mines Manager (MM)
02 Shri Manoj Kumar Colliery Engineer (CE)
03 Shri P.F.Patel Safety Officer (SO)
04 Shri B.K.Singh Ventilation Officer (VO)
05 Shri D. Senguta Sr.Overman (OM)
06 Shri R.S.Singh SPA
57. 57
Hazard identified in respect of Air Borne Respirable dust and mine occupational health services at a coal mine having part
underground workings.
( Hazard indicated health harm issues of mine workers)
Abbreviations: HAZ: Hazard; CONS: Consequence; EXPS: Exposure; PROB: Probability,
HAZ
NO.
HAZARD MECHANISMS CALCULATED RISK COMMENTS
CON EXPS PROB RISK
RATING
1 2 3 4 5 6 7 8
OH-1 Presence of airborne
respirable dust in mine
work faces.
-Dry drilling operations.
-Water injection system not
working in drilling
machine.
-Dust concentration in excess
of permissible limit.
05 10 07 350 Survey for airborne
respirable dust
required to be
conducted and dust
control measures to
be adopted as per
regulation 144 of
draft Coal Mines
Regulations, 2015
& DGMS circulars.
OH-2 Presence of airborne
respirable dust in haul
roads.
-Dust suppression system
non functional.
05 10 03 150
OH-3 Presence of airborne
respirable dust at
conveyor belt transfer
points.
-Water spraying arrangement
non functional.
05 10 03 150
OH-4 Presence of airborne
respirable dust at coal
loading points.
-Water spraying arrangement
non functional.
05 10 07 350
OH-5 Risk of Pneumoconiosis
to mine workers.
-Initial & Periodic Medical
examination not
Conducted in prescribed
manner.
- Chest radiographs not of
prescribed standard.
- Radiographs not screened
as per ILO
Classification.
- Rehabilitation measures not
taken.
05 10 03 150 Medical
examinations are
required to be
conducted under
Rule 29B of Mines
Rules, 1955 and
recommendations
of X th Conference
on Safety in Mines.
OH-6 Contact dermatitis hazard
exists.
Machine maintained
personnel coming in contact
with oil/grease and
acid/alkaline media during
maintenance work.
01 05 07 35
TABLE: RA/DB-8
Risk Assessment: Drilling & Blasting Operation (DB) in Underground Coal Mines
Name of Mine : Katkona 1&2 Incline Date Conducted:
Name of the Company : S.E.C.L. Location:
Facilitators (May Include)
S.N. Name Designation
01 Shri A.K. Dubey Nodal Officer , ISO
02 Shri M.Yadav Area Safety Officer
03 Shri S.Sharma CMO
58. 58
Assessment Team
S.N. Name Designation
01 Shri D.Singh Colliery Manager (MM)
02 Shri Manoj Kumar Colliery Engineer (CE)
03 Shri P.F.Patel Safety Officer (SO)
04 Shri B.K.Singh Ventilation Officer (VO)
05 Shri K.K.Vishwakarma Assistant Manager (AM)
06 Shri S.K.Pandey Manager (M)
08 Shri K.A.Ansari AM(M)
09 Shri Dharmesh AM(M)
10 Shri S.K.Sinha SOE(M)
11 Dr. R.R.Singh Medical Officer (MO)
12 Shri. G.S. Patel Sr.Surveyor (SUR)
13 Shri O.P.Gupta Surveyor (SUR)
14 Shri D.Sengupta Workman Inspector (Mining) (WIM)
15 Shri M.A.Siddqui Workman Inspector (Mechanical) (WIME)
16 Shri A.L.Gupta Workman Inspector (Electrical) (WIE)
17 Shri Ajay Singh Overman (OM)
18 Shri Amrit Mahato Mining Sirdar (MS)
19 Shri Shivcharan Foreman (Mechanical) (FMM)
20 Shri Ramesh Bhagat Foreman (Electrical) (FME)
21 Shri Dhaniram Electrical Supervisor (ES)
Hazard identified in respect of Drilling & Blasting Operation in Underground Coal Mines
( Hazard indicated health harm issues of mine workers)
Abbreviations: HAZ: Hazard; CONS: Consequence; EXPS: Exposure; PROB: Probability,
HAZ
NO.
HAZARD MECHANISMS CALCULATED RISK COMMENTS
CON EXPS PROB RISK
RATING
1 2 3 4 5 6 7 8
DB-1 Roof and side fall Because of poor dressing of
running faces.
1 10 10 100
DB-2 Roof and side fall Unsupported green roof 1 10 10 100
DB-3 Roof and side fall Geological disturbed working
faces.
1 10 10 100
Facilitators (May Include)
S.N. Name Designation
01 Shri A.K. Dubey Nodal Officer , ISO
02 Shri M.Yadav Area Safety Officer
59. 59
DB-4 Accumational of
Inflamable gas in bind
gallaries
Poor ventilation systems &
poor supervisions.
0.3 10 10 30
DB-5 Health hazard due to
heat humidity & dust
Poor ventilation system. 0.1 10 10 10 .
DB-6 Electrocution Poor electrical maintenance. 1 10 10 100
DB-7 Misfire Unscientific distribution of
delay number.
1 10 10 100
DB-8 Misfire Wrong hold direction 1 10 10 100
DB-9 Misfire Use of old detonator &
explosive
1 10 10 100
DB-10 Misfire While dealing with misfire
not standard procedure
adopted.
1 10 10 100
DB-11 Mishap in joining faces Poor supervision while
blasting in joining faces.
1 10 10 100
DB-12 Mishap in joining faces Faces running towards both
sides of joining faces.
1 10 10 100
DB-13 Mishap in joining faces Blasting Card system not
adopted.
1 10 10 100
DB-14 Inadvertent entry in
blasting zone
Poor supervision while
blasting.
1 10 10 100
DB-15 Inadvertent entry in
blasting zone
Blasting Card system not
adopted.
1 10 10 100
DB-16 Presence of
Inflammable gas in drill
holes
Faces not checked properly
before charging.
1 10 10 100
DB-17 Health hazards due to
blasting fumes and dust
Poor ventilation at LVC. 0.3 10 10 30
DB-18 Health hazards due to
blasting fumes & dust
Entered in the blasted faces
without giving sufficient time
for diluting fumes & dust.
0.3 10 10 30
TABLE: RA/RB-9
Risk Assessment: Roof Bolter operation in the mine
Name of Mine : Katkona 1&2 Incline Date Conducted:
Name of the Company : S.E.C.L. Location:
Assessment Team
S.N. Name Designation
01 Shri D.Singh Colliery Manager (MM)
02 Shri P.F.Patel Safety Officer (SO)
03 Shri K.K.Vishwakarma Assistant Manager (AM)
04 Shri S.K.Pandey Manager (M)
05 Shri K.A.Ansari AM(M)
06 Shri D.Sengupta Workman Inspector (Mining) (WIM)
07 Shri Ajay Singh Overman (OM)
60. 60
08 Shri Amrit Mahato Mining Sirdar (MS)
09 Shri Sadhu Singh UDM Operator
10 Shri Raju Das Driller
Hazard identified in respect of Drilling & Blasting Operation in Underground Coal Mines
( Hazard indicated health harm issues of mine workers)
Abbreviations: HAZ: Hazard; CONS: Consequence; EXPS: Exposure; PROB: Probability,
HAZ
NO.
HAZARD MECHANISMS CALCULATED RISK COMMENTS
CON EXPS PROB RISK
RATING
1 2 3 4 5 6 7 8
RB1 Pre-start Checking Damage Cable having
joints
0.3 5 7 10.5 Proper joint by
vulcanizing
RB-2 Pre-start Checking Health Effect from Dust 5 10 10 500 Water spraying
on scrubber
RB-3 Movement of Twin
Bolter
Collision due to Poor
Visibility along roadway
0.01 2.5 2 0.05 Provide lights
along roadway
RB-4 Movement of Twin
Bolter
Collision due to
Inadvertent entry of
person
0.3 2 2 1.2 AVA & other
warning signal
RB-5 Movement of Twin
Bolter
Projectile hit person or
dislodge support
0.01 2.5 7 0.175 Guard on tyre n
regular cleaning
of Road with
restriction of
unwanted
movement of
man
RB-6 Movement of Twin
Bolter
Injury due to Roof/side
fall
0.01 1.5 1 0.015 GRP bolting
with Tensile
Plastic Net
RB-7 Movement of Twin
Bolter
Injury due to
transportation of heavy
materials
0.00
1
5 1 0.005 Supply
materials to
nearby place
RB-8 Movement of Twin
Bolter
Pressing of cable/hose
pipe by tyre
0.00
01
2.5 7 0.00175 Cable hanged
on hooks with
discuss on
sequence of
work
RB-9 Drilling of holes in
the roof
Eye injury due to Dust 0.1 5 10 5 Suppression of
dust by wet
drilling
RB-9 Drilling of holes in
the roof
Injury due to Slipping of
capsule during upwards
Motion
0.00
01
5 3 0.0015 Careful
inserting of
capsule with
pipe
Facilitators (May Include)
S.N. Name Designation
01 Shri A.K. Dubey Nodal Officer , ISO
02 Shri M.Yadav Area Safety Officer
61. 61
RB-10 Drilling of holes in
the roof
Side fall at time of GRP 0.3 5 7 10.5 Plastic tensile
net with
proper dressing
RB-11 Drilling of holes in
the roof
Injury due to slippage of
poor quality Spanner
0.1 2.5 2 0.5 Use of standard
quality wrench
RB-12 Testing of roof bolt
installed
Fall of person or
machine on ground
0.3 2.5 3 2.25 Training for
skills
improvement
RB-13 Testing of roof bolt
installed
Injury to eye by
pressurized hydraulic oil
0.3 3 3 2.7 Worn out hoses
to, be replaced
arrange 1 spare
testing m/c
TABLE: RA/CT-10
Risk Assessment: Coal Transportation in underground and in surface of the mine
Name of Mine : Katkona 1&2 Incline Date Conducted:
Name of the Company : S.E.C.L. Location:
Assessment Team
S.N. Name Designation
01 Shri D.Singh Colliery Manager (MM)
02 Shri Manoj Kumar Colliery Engineer (CE)
03 Shri P.F.Patel Safety Officer (SO)
04 Shri B.K.Singh Ventilation Officer (VO)
05 Shri K.K.Vishwakarma Assistant Manager (AM)
06 Shri S.K.Pandey Manager (M)
08 Shri K.A.Ansari AM(M)
09 Shri Dharmesh AM(M)
10 Shri S.K.Sinha SOE(M)
11 Dr. R.R.Singh Medical Officer (MO)
12 Shri. G.S. Patel Sr.Surveyor (SUR)
13 Shri O.P.Gupta Surveyor (SUR)
14 Shri D.Sengupta Workman Inspector (Mining) (WIM)
15 Shri M.A.Siddqui Workman Inspector (Mechanical) (WIME)
16 Shri A.L.Gupta Workman Inspector (Electrical) (WIE)
17 Shri Ajay Singh Overman (OM)
18 Shri Amrit Mahato Mining Sirdar (MS)
19 Shri Shivcharan Foreman (Mechanical) (FMM)
20 Shri Ramesh Bhagat Foreman (Electrical) (FME)
21 Shri Dhaniram Electrical Supervisor (ES)
Facilitators (May Include)
62. 62
Hazard identified in respect of Drilling & Blasting Operation in Underground Coal Mines
( Hazard indicated health harm issues of mine workers)
Abbreviations: HAZ: Hazard; CONS: Consequence; EXPS: Exposure; PROB: Probability,
HAZ
NO.
HAZARD MECHANISMS CALCULATED RISK COMMENTS
CON EXPS PROB RISK
RATING
1 2 3 4 5 6 7 8
UNH-1 Loading of coal Hit by bucket coz of
Movement of SDL in
gallery
0.3 5 7 10.5 Widen the
gallery to max
allowable limit
of width
UNH-2 Loading of coal Injury due run over 5 10 10 500 Obstruction
free path,
AVA & lights
provided
UNH-3 Loading of coal Getting pressed between
bucket and pillars
0.01 2.5 2 0.05 Code of
practices for
operating SDL
be implemented
strictly
UNH-4 Loading on belt by
SDL
Injury due to Spillages
from belt
0.3 2 2 1.2 Carefulness &
make awareness
UNH-5 Loading on trunk
at surface from
bunker &
weighing
Collision due to
Overcrowded trucks
1 10 7 70 Maintaining
queue
UNH-6 Loading on trunk
at surface from
bunker &
weighing
Hitting men present
nearby coz of Driving
trucks by unskilled
drivers/persons
0.3 10 3 9 Spot inspection
of persons
driving trucks
S.N. Name Designation
01 Shri A.K. Dubey Nodal Officer , ISO
02 Shri M.Yadav Area Safety Officer
63. 63
TABLE: RA/MECH-11
Risk Assessment: Mechanical work in the mine
Name of Mine : Katkona 1&2 Incline Date Conducted :
Name of the Company : S.E.C.L. Location:
Assessment Team
S.N. Name Designation
01 Shri D.Singh Colliery Manager (MM)
02 Shri Manoj Kumar Colliery Engineer (CE)
03 Shri P.F.Patel Safety Officer (SO)
04 Shri B.K.Singh Ventilation Officer (VO)
05 Shri K.K.Vishwakarma Assistant Manager (AM)
06 Shri S.K.Pandey Manager (M)
08 Shri K.A.Ansari AM(M)
09 Shri Dharmesh AM(M)
10 Shri S.K.Sinha SOE(M)
11 Dr. R.R.Singh Medical Officer (MO)
12 Shri. G.S. Patel Sr.Surveyor (SUR)
13 Shri O.P.Gupta Surveyor (SUR)
14 Shri D.Sengupta Workman Inspector (Mining) (WIM)
15 Shri M.A.Siddqui Workman Inspector (Mechanical) (WIME)
16 Shri A.L.Gupta Workman Inspector (Electrical) (WIE)
17 Shri Ajay Singh Overman (OM)
18 Shri Amrit Mahato Mining Sirdar (MS)
19 Shri Shivcharan Foreman (Mechanical) (FMM)
20 Shri Ramesh Bhagat Foreman (Electrical) (FME)
21 Shri Dhaniram Electrical Supervisor (ES)
Facilitators (May Include)
S.N. Name Designation
01 Shri A.K. Dubey Nodal Officer , ISO
02 Shri M.Yadav Area Safety Officer
64. 64
Hazard identified in respect of Drilling & Blasting Operation in Underground Coal Mines
( Hazard indicated health harm issues of mine workers)
Abbreviations: HAZ: Hazard; CONS: Consequence; EXPS: Exposure; PROB: Probability,
HAZ NO. HAZARD MECHANISMS CALCULATED RISK COMMENTS
CON EXPS PROB RISK
RATING
1 2 3 4 5 6 7 8
MECH-1 Haulage system Injury due to striking,
damage due to collision
by Sudden brake failure
5 2 7 70 Replacement of
brake at specified
interval with
Proper
maintenance & by
inspection
MECH-2 Haulage system Injury due to hit by
structure due to loose
Foundation base
5 1.5 1 7.5 Reinforcing
foundation by
props and Ensure
firm foundation
for haulage
installation
MECH-3 Haulage system Injury due uncontrolled
movement of tubs
0.1 2.5 2 0.5 Good quality
control units shall
be supplied &
used and Regular
maintenance &
replacing of units
MECH-4 Rope fitting Snapping of running
ropes
0.1 2 2 0.4 Timely rope
replacement of by
good quality
MECH-5 Rope fitting Snapping of tension
rope
0.1 2 2 0.4 Provide strong
fencing &
enough tension
MECH-6 Tub handling Injury due to Damaged
tubs
0.01 2.5 3 0.75 Use after proper
repair and handle
with safety
MECH-7 Tub handling Injury due to restricted
work place for repairing
0.01 2.5 3 0.75 Improve work
place
environment &
carry out repair
MECH-8 Tub handling Injury due to derailed
tubs
0.01 3 7 0.21 Proper track &
tub maintenance,
provision of re-
railers
MECH-9 SDL
maintenance
Injury due to hit by
slipping of spanner &
bolts while replacement
of tyre
0.01 2.5 2 0.05 Engage skilled
& experienced
persons with
compliance of the
safety procedures
MECH-
10
SDL
maintenance
Injury due to hit by
sudden fall of raised
bucket while repairing
0.01 3 1 0.03 In addition to
safety pin,
positive support
of adequate
capacity should
be fixed below
the bucket
66. 66
Hazard identified in respect of Drilling & Blasting Operation in Underground Coal Mines
( Hazard indicated health harm issues of mine workers)
Abbreviations: HAZ: Hazard; CONS: Consequence; EXPS: Exposure; PROB: Probability,
HAZ NO. HAZARD MECHANISMS CALCULATED RISK COMMENTS
CON EXPS PROB RISK
RATING
1 2 3 4 5 6 7 8
UNH-1 Transporting of
pump &
switches
Injury to back, hand/
leg while carrying
heavy items
0.3 5 7 10.5 Provide adequate
& skilled
manpower
UNH-2 Installation of
pumps
Injury due to fall of
heavy objects
5 10 10 500 Handling object
properly
UNH-3 Pipes laying
and connection
Stress & strain to person
for laying heavy/long
pipes
0.01 2.5 2 10.5 Engage skilled
person under
supervision
UNH-4 Changing pipes
or
packing/washers
Injury to hand/ fingers
coz of improper tools
0.3 2 2 1.2 Provide proper
tools
UNH-5 Operating pump
at dip side sump
Injury/damage due to
collapse retaining wall
0.01 2 7 0.14 Regular checking
& examination
UNH-6 Operating pump
in old working
areas
Suffocation and
asphyxiation due to
inadequate ventilation
0.3 10 7 21 Providing safety
lamp, lighting and
telephone at
pumping station
UNH-7 Travelling along
old galleries
Injury due to fall of
roof/ sides
0.1 10 3 3 For remotely
located pumps,
persons should
carry lamps
TABLE: CP/SCUG-1
Control Plan: Strata Control in underground coal mines
Name of Mine : Katkona 1&2 Incline Date Conducted:
Name of the Company : S.E.C.L. Location:
Assessment Team
S.N. Name Designation
01 Shri D.Singh Colliery Manager (MM)
02 Shri Manoj Kumar Colliery Engineer (CE)
03 Shri P.F.Patel Safety Officer (SO)
04 Shri B.K.Singh Ventilation Officer (VO)
05 Shri K.K.Vishwakarma Assistant Manager (AM)
06. Shri S.K.Pandey Manager (M)
07. Shri K.A.Ansari AM(M)
08. Shri Dharmesh AM(M)
09. Shri S.K.Sinha SOE(M)
10 Dr. R.R.Singh Medical Officer (MO)
67. 67
11 Shri. G.S. Patel Sr.Surveyor (SUR)
12 Shri O.P.Gupta Surveyor (SUR)
13 Shri D.Sengupta Workman Inspector (Mining) (WIM)
14 Shri M.A.Siddqui Workman Inspector (Mechanical) (WIME)
15 Shri A.L.Gupta Workman Inspector (Electrical) (WIE)
16 Shri Ajay Singh Overman (OM)
17 Shri Amrit Mahato Mining Sirdar (MS)
18 Shri Shivcharan Foreman (Mechanical) (FMM)
19 Shri Ramesh Bhagat Foreman (Electrical) (FME)
20 Shri Dhaniram Electrical Supervisor (ES)
21 Shri Jawahar Safety Committee Member/Machenical Fitter
22 Shri Raghrai Safety Committee Member/SDL Operator
Control Plan: Strata Control in underground coal mines
Abbreviations: Same as TABLE: CP/SCUG-1
Mechanism Control RSP/DGC/MG Procedure ERCI Res Comments
Roof fall in
freshly exposed
roof due to lack of
supervision
Efficient supervisions
to prevent roof fall in
the freshly exposed
area.
Reg. 124(7) Devise and implement an
integrated system of
supervision of green roof
area by Mining
Sirdar/Overman/Asst.
Manager.
Med MM. To be put in
place within
one month
(YF).
Roof fall due to
poor workmanship
in installation of
supports
1. Installation of
supports by efficient
and trained support
personnel.
2. Training of support
personnel.
Reg.124(7)
Rule(T)-09;
DGC-Legis
4/1975.
1. Devise and implement a
system for careful
selection of support
personnel.
2. Devise a schedule for
training and re-training of
support personnel at
prescribed interval.
Med
Med
MM &
Agent.
MM &
Agent.
1. Schedule to
be put in place
within one
month.
2. Training
may be
conducted
within one
month.
Roof side fall
resulting from
weak and
incompetent roof
strata.
Ascertain the
competence of strata
for an adequate roof
support design.
Reg124 (1)
a.
Structural mapping of
freshly exposed roof and
sides to identify
geological feature like slip
planes etc., which affects
the competence of roof
rock.
Low MM. System to be
put in place
within two
months.
Roof fall due to
Inferior quality of
support material.
Ensure supply of
prescribed quality of
support material.
Standing order
under
Reg.124(8);
DCG-Tech 3 of
1996& 2 of
1997
Establish a system of
procurement and supply
of support material
conforming to BIS
standards with a provision
of pre-checking for
quality.
Low MM &
Agent.
System to be
put in place
within one
month (YF).
Roof and side fall
in mine workings
due to deficient
support density.
Ensure installation of
supports as per
support plan.
124(5) Devise a system of
monitoring by supervisors
and managers to ascertain
whether supports are
Med. MM. System to be
put in place
within fifteen
days
68. 68
installed as per supports
plan.
(YF).
Support plan
based on deficient
geological data
and other
parameters
causing instability
of strata.
Ensure framing of
support design on the
basis of proper
geotechnical
investigations.
124(1)a. Classification of roof rock
by CMRI-ISM Geo-
mechanics classification
and support design
thereof.
Low MM. System to be
put in place
within one
month(YF).
Delay in supply of
support material
and non erection
of support
resulting in roof
fall.
Ensure timely supply
and erection of mine
supports.
Standing order
under
Reg.124(8)
Establish a system of
timely placing of indent
for supports followed by
supply of supports. Ensure
timely erection of
supports.
Med AM &
MM.
System to be
put in place
within one
month (YF).
Roof and side fall
due of adverse
orientation of
roadway vis-à-vis
prominent
geological
features like cleat
etc.
Orient proposed main
installations and
roadways strategically
in respect of
prominent geological
disturbances to reduce
strata stability
problems.
Reg.124(1) Main Planning & Design
Engineer in consultation
and under the guidance of
experts of an
academic/research
institute to decide
orientation of proposed
main installations and
roadways in mine plan.
Low MM &
Agent.
MM & Agent
may purse the
issue in a time
bound
manner.
TABLE: CP/MV-2
Control Plan: Mine Ventilation (MV) in underground coal mines
Name of Mine : Katkona 1&2 Incline Date Conducted:
Name of the Company : S.E.C.L. Location:
Assessment Team
S.N. Name Designation
01 Shri D.Singh Colliery Manager (MM)
02 Shri Manoj Kumar Colliery Engineer (CE)
03 Shri P.F.Patel Safety Officer (SO)
04 Shri B.K.Singh Ventilation Officer (VO)
05 Shri K.K.Vishwakarma Assistant Manager (AM)
06. Shri S.K.Pandey Manager (M)
07. Shri K.A.Ansari AM(M)
08. Shri Dharmesh AM(M)
09. Shri S.K.Sinha SOE(M)
10 Dr. R.R.Singh Medical Officer (MO)
11 Shri. G.S. Patel Sr.Surveyor (SUR)
12 Shri O.P.Gupta Surveyor (SUR)
13 Shri D.Sengupta Workman Inspector (Mining) (WIM)
14 Shri M.A.Siddqui Workman Inspector (Mechanical) (WIME)
15 Shri A.L.Gupta Workman Inspector (Electrical) (WIE)
16 Shri Ajay Singh Overman (OM)