SlideShare a Scribd company logo
1 of 12
lng
1at the
1g out
rank-
Jigh/
orma -
atten-
a list
analy -
Jribed
~scan
alita-
fect
1g-edge
1es for
e>deling
rts and
luanti-
and
course
atio n
1t's
1 might
if it
t. The
ke this
lly,
exam-
' s firm
•ability
a ted
,vith
Probability (P) times Outcome = EMV
P=.20 *
< P=.80
$300,000 = +$60,000
-$40,000 = -$32,000
-$50,000 = -$10,000
-$ 20,000 = - $2,000
$60, 000 = $42,000
~
*
Project 2 *
P= .70
Project 1 's EMV = $60,000- $32, 000 = $28, 000
Proj ect 2's EMV = -$10,000- $2,000 + $42, 000 = $30,000
FIGURE 11-7 Expected monetary value (EMV) example
no reimburse ment if it is not awarded the contract. The sum of
the probabilities for
outcomes for each project must equal one (for Project 1, 20
percent plus 80 percent) .
Probabilities are normally determined based on expert judgme
nt. Cliff or other people
in his firm should have some sense of their likelihood of
winning certain projects.
Figure 11-7 also shows probabilities and outcomes for Project
2. Suppose there is a
20 percent probability that Cliffs firm will lose $ 50,000 on
Project 2, a 10 percent probabili-
ty that it will lose $20,000, and a 70 percent probability that it
will earn $60,000. Again,
experts would ne ed to estimate these dollar amounts and
probabilities.
To calculate the expected monetary value (EJvfV) for each proj
ect, multiply the proba-
bility by the outcome value (or each potential outcome for each
project and sum the results.
To calculate expected monetary value for Project 1, going from
left to right, multiply the
probability by the outcome for each branch and sum the results.
In this example, the EMV
for Proj ect 1 is $28, 000.
.2($300 ,000) + .8( -$40 ,000) = $60,000- $32,000 = $28 ,000
The EMV for Project 2 is $30,000 .
.2 ( -$50 ,000 ) + .1(-$20 ,000) + .7($60,000) = -$1 0 ,000-$2
,000 + .$42,000
= $30,000
Beca use the EMV provides an estimate for the total dollar
value of a decision , you wa nt
to have a pos itive number; the higher the EMV, the bette r.
Since the EJvfV is positive for
both Projects 1 and 2 , Clift"s firm would expec t a positive
outcome from eac h and could bid
0n both proj ects. If it had to choose between the two proj ects ,
perhaps because of limited
resources , Clift"s firm should bid on Project 2 because it has a
higher EMV.
443
Project Risk Management
consulting costs might be expanded in the description to say
that the organiza-
tion might be able to negotiate lower-than-average costs for a
particular consul-
tant because the consultant really e njoys working for that
company in that
particular location.
• The categor:y under which the risk event falls: For example,
defective server
might fall under the broader category of technology or hardware
technology.
• The root cause of the risk: The root cause of the defective
server might be a
defective power supply.
• Triggers for each risk: Triggers are indicators or symptoms of
actual risk
events. For example, cost overruns on early activities may be
symptoms of poor
cost estimates . Defective products may be symptoms of a low-
quality supplier.
Documenting potential risk symptoms for projects also helps the
project team
identify more potential risk events .
• Potential responses to each risk: A potential response to the
risk event of a
defective server might be the. inclusion of a clause in a contract
with the supplier
to replace a defective server within a certain time period at a
negotiated cost.
• The risk owner or person who will own or take responsibility
for the risk: For
example, a certain person might be in charge of any server-
related risk events
and managing response strategies.
• The probability of the risk occurring: There might be a high,
medium, or low
probability of a certain risk event occurring. For example, the
risk might be low
that the server would actually be defective .
• The impact to the project if the risk occurs: There might be a
high , medium,
or low impact to project success if the risk event actually
occurs. A defective
server might have a high impact on successfully completing a
project on time.
• The status of the 1isk: Did the risk event occur? Was the
response strategy com-
pleted? Is the risk no longer relevant to the project? For
example , a contract
clause may have been completed to address the risk of a
defective server.
TABLE 11-5 Sample risk register
437
No. Rank R1sk Description Category Root Tnggers Potential
Risk Probability Impact Status
R44 1
R21 2
R7 3
Cause Responses Owner
For example, the following data might be entered for the first
risk in the register as fol-
lows. Notice that Cliffs team is taking a very proactive
approach in managing this risk.
• No.: R44
• Rank: 1
• Risk: New customer
• Description: We have never done a project for this
organization before and
don't know too much about them. One of our company's
strengths is building
Project Risk Management
2. Review a document related to risk management, such as
Microsoft's Security Risk Manage-
ment Guide available from the companion Web site for this text.
Does this guide address
most of the topics related to risk management planning as
described in this text? Document
your analysis in a two-page paper.
3. Research risk management software. Are many products
available? What are the main
advantages of using them in managing projects? What are the
main disadvantages? Write
a two-page paper discussing your findings, and include at least
three references.
4. Suppose your organization is deciding which of four projects
to bid on. Information on each
is in the table below. Assume that all up-front investments are
not recovered, so they are
shown as negative profits. Draw a diagram and calculate the
EMV for each project. Write a
few paragraphs explaining which projects you would bid on. Be
sure to use the EMV informa-
456 tion and your personal risk tolerance to justify your answer.
Chapter 11
Project 1 50 percent Sl20,000
50 percent -$50,000
Project 2 30 percent s 100' 000
40 percent s 50,000
30 percent -860,000
Project 3 70 percent s 20,000
:10 percent -S 5,000
Project -l 30 percent s 40,000
JO percent s 30,000
20 percent $ 20,000
20 percent -850,000
5. Find an example of a company that took a big risk on an
information technology project
and succeeded. In adrJition, lind an example of a company that
took a big risk and
failed. Summarize each project and situation in a two-page
paper where you should also
discuss whether you believe that anything besides luck makes a
difference between suc-
cess and failure.
Tony and his team identified some risks during the first month
of the Recreation and Well-
ness Intranet Project. However, all they did was document them
in a list. They never ranked
them or developed any response strategies. Since several
problems have been occurring
on the project, such as key team members leaving the company,
users being uncooperative,
and team members not providing good status information, Tony
has decided to be more pro-
active in managing risks. He also wants to address positive as
well as negative risks.
i. Create a risk register for the project, using Table i 1-5 and the
data below it as a guide.
Identity six potential risks, including risks related to the
problems described above.
Include negative and positive risks.
Plot the six risks on a probability/impact matrix, using Figure
11-7. Also assign a numeric
value for the probability and impact of each risk on meeting the
main project objective.
use a scale of 1 to 10 in assigning the values, with 1 being low
and 10 being high. For
a simple risk factor calculation, multiply these two values (the
probability score and the
impact score). Add a column to your risk register to the right of
the impact column called
Risk Score. Enter the new data in the risk register. Write your
rationale for how you
determined the scores for one of the negative risks and one of
the positive risks.
Develop a response strategy for one of the negative risks and
one of the positive risks.
Enter the information in the risk register. Also write a separate
paragraph describing
what specific tasks would need to be done to implement the
strategy. Include time and
cost estimates tor each strategy, as well.
ion Web Site
· the companion Web site for this text
(www.cengage.com/mis/schwalbe) to access:
References cited in the text and additional suggested readings
for each chapter
Template files
Lecture notes
Interactive quizzes
Pod casts
Links to general project management Web sites
And more
See the Preface of this text for additional information on
accessing the companion Web site.
Key Terms
brainstorming -a technique by which a group attempts to
generate ideas or find a solution for
a specific problem by amassing ideas spontaneously and without
judgment
contingency allowances- provisions held by the project sponsor
or organization to reduce the
risk of cost or schedule overruns to an acceptable level; also
called contingency reserves
contingency plans - predefined actions that the project team will
take if an identified risk
event occurs
contingency reserves- provisions held by the project sponsor or
organization to reduce the
risk of cost or schedule overruns to an acceptable level; also
called contingency
allowances
decision tree- a diagramming analysis technique used to help
select the best course of action
in situations in which future outcomes are uncertain
Delphi technique- an approach used to derive a consensus
among a panel of experts, to
make predictions about future developments
expected monetary value (EMV)- the product of the risk event
probability and the risk
event's monetary value
fallback plans- plans developed for risks that have a high
impact on meeting project
objectives, to be implemented if attempts to reduce the risk are
not effective
flowcharts - diagrams that show how various elements of a
system relate to each other
457
Project Risk Management
Unit V Mini Project
Analyze the Running Case on pages 456-457 of the textbook,
The Recreation and Wellness Intranet Project.
· Complete Tasks 1-3 of the case, and use Excel and/or
screenshots as necessary to display your data.
· Summarize your findings in a 700 word minimum, APA
formatted, Word document.
· Any Excel documents and/or screenshots created to display
your tasks need to be copied and pasted into the Word document
at the end of the summary, and the assignment should be
submitted as one document.

More Related Content

Similar to lng 1at the 1g out rank-Jigh orma -atten-a li.docx

Unit 2 [IT504 Critical Concepts and Competencies for the IT P.docx
Unit 2 [IT504 Critical Concepts and Competencies for the IT P.docxUnit 2 [IT504 Critical Concepts and Competencies for the IT P.docx
Unit 2 [IT504 Critical Concepts and Competencies for the IT P.docxdickonsondorris
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templatesHoa PN Thaycacac
 
Risk 3 simplelearn-exam2-ans
Risk 3 simplelearn-exam2-ansRisk 3 simplelearn-exam2-ans
Risk 3 simplelearn-exam2-ansMohamed Saeed
 
اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222nashaat algrara
 
Risk Management Plan Project NameLast UpdatedOverviewPro.docx
Risk Management Plan Project NameLast UpdatedOverviewPro.docxRisk Management Plan Project NameLast UpdatedOverviewPro.docx
Risk Management Plan Project NameLast UpdatedOverviewPro.docxhealdkathaleen
 
10.9 STORE-DRIVEN FORECASTS. The Home Depot is a lead.docx
10.9  STORE-DRIVEN FORECASTS. The Home Depot is a lead.docx10.9  STORE-DRIVEN FORECASTS. The Home Depot is a lead.docx
10.9 STORE-DRIVEN FORECASTS. The Home Depot is a lead.docxhyacinthshackley2629
 
Risk Management ProcessTraining Session Victor Allen.docx
Risk Management ProcessTraining Session Victor Allen.docxRisk Management ProcessTraining Session Victor Allen.docx
Risk Management ProcessTraining Session Victor Allen.docxSUBHI7
 
Project Management And The Major Areas Of Projects Management
Project Management And The Major Areas Of Projects ManagementProject Management And The Major Areas Of Projects Management
Project Management And The Major Areas Of Projects ManagementMiles Priar
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptxKamranKhan353531
 
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Pedram Danesh-Mand
 
Project Risk Management Plan © 2015 by Jones & Bartl.docx
Project Risk Management Plan © 2015 by Jones & Bartl.docxProject Risk Management Plan © 2015 by Jones & Bartl.docx
Project Risk Management Plan © 2015 by Jones & Bartl.docxAASTHA76
 
RegisterRisk Register#RiskImpact on ProjectCost $LikelihoodImpact .docx
RegisterRisk Register#RiskImpact on ProjectCost $LikelihoodImpact .docxRegisterRisk Register#RiskImpact on ProjectCost $LikelihoodImpact .docx
RegisterRisk Register#RiskImpact on ProjectCost $LikelihoodImpact .docxaudeleypearl
 
Risk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ansRisk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ansMohamed Saeed
 
Use of Causeand Effect Diagrams for Risk Management
Use of Causeand Effect Diagrams for Risk ManagementUse of Causeand Effect Diagrams for Risk Management
Use of Causeand Effect Diagrams for Risk ManagementProcept Associates
 
How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownAcumen
 

Similar to lng 1at the 1g out rank-Jigh orma -atten-a li.docx (20)

Unit 2 [IT504 Critical Concepts and Competencies for the IT P.docx
Unit 2 [IT504 Critical Concepts and Competencies for the IT P.docxUnit 2 [IT504 Critical Concepts and Competencies for the IT P.docx
Unit 2 [IT504 Critical Concepts and Competencies for the IT P.docx
 
Risk analysis
Risk analysisRisk analysis
Risk analysis
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templates
 
Risk 3 simplelearn-exam2-ans
Risk 3 simplelearn-exam2-ansRisk 3 simplelearn-exam2-ans
Risk 3 simplelearn-exam2-ans
 
Project mngmnt risks3.2
Project mngmnt risks3.2Project mngmnt risks3.2
Project mngmnt risks3.2
 
اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222
 
Risk Management Plan Project NameLast UpdatedOverviewPro.docx
Risk Management Plan Project NameLast UpdatedOverviewPro.docxRisk Management Plan Project NameLast UpdatedOverviewPro.docx
Risk Management Plan Project NameLast UpdatedOverviewPro.docx
 
10.9 STORE-DRIVEN FORECASTS. The Home Depot is a lead.docx
10.9  STORE-DRIVEN FORECASTS. The Home Depot is a lead.docx10.9  STORE-DRIVEN FORECASTS. The Home Depot is a lead.docx
10.9 STORE-DRIVEN FORECASTS. The Home Depot is a lead.docx
 
Proposed Exam
Proposed ExamProposed Exam
Proposed Exam
 
Risk Management ProcessTraining Session Victor Allen.docx
Risk Management ProcessTraining Session Victor Allen.docxRisk Management ProcessTraining Session Victor Allen.docx
Risk Management ProcessTraining Session Victor Allen.docx
 
Project Management And The Major Areas Of Projects Management
Project Management And The Major Areas Of Projects ManagementProject Management And The Major Areas Of Projects Management
Project Management And The Major Areas Of Projects Management
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptx
 
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
 
Risk Adjusted Estimating Techniques
Risk Adjusted Estimating TechniquesRisk Adjusted Estimating Techniques
Risk Adjusted Estimating Techniques
 
Project Risk Management Plan © 2015 by Jones & Bartl.docx
Project Risk Management Plan © 2015 by Jones & Bartl.docxProject Risk Management Plan © 2015 by Jones & Bartl.docx
Project Risk Management Plan © 2015 by Jones & Bartl.docx
 
RegisterRisk Register#RiskImpact on ProjectCost $LikelihoodImpact .docx
RegisterRisk Register#RiskImpact on ProjectCost $LikelihoodImpact .docxRegisterRisk Register#RiskImpact on ProjectCost $LikelihoodImpact .docx
RegisterRisk Register#RiskImpact on ProjectCost $LikelihoodImpact .docx
 
Risk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ansRisk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ans
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Use of Causeand Effect Diagrams for Risk Management
Use of Causeand Effect Diagrams for Risk ManagementUse of Causeand Effect Diagrams for Risk Management
Use of Causeand Effect Diagrams for Risk Management
 
How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us Down
 

More from SHIVA101531

Answer the following questions in a minimum of 1-2 paragraphs ea.docx
Answer the following questions in a minimum of 1-2 paragraphs ea.docxAnswer the following questions in a minimum of 1-2 paragraphs ea.docx
Answer the following questions in a minimum of 1-2 paragraphs ea.docxSHIVA101531
 
Answer the following questions using scholarly sources as references.docx
Answer the following questions using scholarly sources as references.docxAnswer the following questions using scholarly sources as references.docx
Answer the following questions using scholarly sources as references.docxSHIVA101531
 
Answer the following questions about this case studyClient .docx
Answer the following questions about this case studyClient .docxAnswer the following questions about this case studyClient .docx
Answer the following questions about this case studyClient .docxSHIVA101531
 
Answer the following questions using art vocabulary and ideas from L.docx
Answer the following questions using art vocabulary and ideas from L.docxAnswer the following questions using art vocabulary and ideas from L.docx
Answer the following questions using art vocabulary and ideas from L.docxSHIVA101531
 
Answer the following questions in a total of 3 pages (900 words). My.docx
Answer the following questions in a total of 3 pages (900 words). My.docxAnswer the following questions in a total of 3 pages (900 words). My.docx
Answer the following questions in a total of 3 pages (900 words). My.docxSHIVA101531
 
Answer the following questions No single word responses (at lea.docx
Answer the following questions No single word responses (at lea.docxAnswer the following questions No single word responses (at lea.docx
Answer the following questions No single word responses (at lea.docxSHIVA101531
 
Answer the following questions based on the ethnography Dancing Skel.docx
Answer the following questions based on the ethnography Dancing Skel.docxAnswer the following questions based on the ethnography Dancing Skel.docx
Answer the following questions based on the ethnography Dancing Skel.docxSHIVA101531
 
Answer the following questions to the best of your ability1) De.docx
Answer the following questions to the best of your ability1) De.docxAnswer the following questions to the best of your ability1) De.docx
Answer the following questions to the best of your ability1) De.docxSHIVA101531
 
Answer the following questionDo you think it is necessary to .docx
Answer the following questionDo you think it is necessary to .docxAnswer the following questionDo you think it is necessary to .docx
Answer the following questionDo you think it is necessary to .docxSHIVA101531
 
Answer the following question. Use facts and examples to support.docx
Answer the following question. Use facts and examples to support.docxAnswer the following question. Use facts and examples to support.docx
Answer the following question. Use facts and examples to support.docxSHIVA101531
 
Answer the bottom questions  in apa format and decent answer no shor.docx
Answer the bottom questions  in apa format and decent answer no shor.docxAnswer the bottom questions  in apa format and decent answer no shor.docx
Answer the bottom questions  in apa format and decent answer no shor.docxSHIVA101531
 
Answer the following below using the EXCEL attachment. chapter 5.docx
Answer the following below using the EXCEL attachment. chapter 5.docxAnswer the following below using the EXCEL attachment. chapter 5.docx
Answer the following below using the EXCEL attachment. chapter 5.docxSHIVA101531
 
Answer the following prompts about A Germanic People Create a Code .docx
Answer the following prompts about A Germanic People Create a Code .docxAnswer the following prompts about A Germanic People Create a Code .docx
Answer the following prompts about A Germanic People Create a Code .docxSHIVA101531
 
Answer the following discussion board question below minumun 25.docx
Answer the following discussion board question below minumun 25.docxAnswer the following discussion board question below minumun 25.docx
Answer the following discussion board question below minumun 25.docxSHIVA101531
 
Answer the following questions about IT Project Management. What.docx
Answer the following questions about IT Project Management. What.docxAnswer the following questions about IT Project Management. What.docx
Answer the following questions about IT Project Management. What.docxSHIVA101531
 
Answer the following in at least 100 words minimum each1.Of.docx
Answer the following in at least 100 words minimum each1.Of.docxAnswer the following in at least 100 words minimum each1.Of.docx
Answer the following in at least 100 words minimum each1.Of.docxSHIVA101531
 
Answer the following questions(at least 200 words) and responses 2 p.docx
Answer the following questions(at least 200 words) and responses 2 p.docxAnswer the following questions(at least 200 words) and responses 2 p.docx
Answer the following questions(at least 200 words) and responses 2 p.docxSHIVA101531
 
Answer the following questions in a Word document and upload it by M.docx
Answer the following questions in a Word document and upload it by M.docxAnswer the following questions in a Word document and upload it by M.docx
Answer the following questions in a Word document and upload it by M.docxSHIVA101531
 
Answer the following questions in complete sentences. Each answer sh.docx
Answer the following questions in complete sentences. Each answer sh.docxAnswer the following questions in complete sentences. Each answer sh.docx
Answer the following questions in complete sentences. Each answer sh.docxSHIVA101531
 
ANSWER THE DISCUSSION QUESTION 250 WORDS MINDiscussion Q.docx
ANSWER THE DISCUSSION QUESTION 250 WORDS MINDiscussion Q.docxANSWER THE DISCUSSION QUESTION 250 WORDS MINDiscussion Q.docx
ANSWER THE DISCUSSION QUESTION 250 WORDS MINDiscussion Q.docxSHIVA101531
 

More from SHIVA101531 (20)

Answer the following questions in a minimum of 1-2 paragraphs ea.docx
Answer the following questions in a minimum of 1-2 paragraphs ea.docxAnswer the following questions in a minimum of 1-2 paragraphs ea.docx
Answer the following questions in a minimum of 1-2 paragraphs ea.docx
 
Answer the following questions using scholarly sources as references.docx
Answer the following questions using scholarly sources as references.docxAnswer the following questions using scholarly sources as references.docx
Answer the following questions using scholarly sources as references.docx
 
Answer the following questions about this case studyClient .docx
Answer the following questions about this case studyClient .docxAnswer the following questions about this case studyClient .docx
Answer the following questions about this case studyClient .docx
 
Answer the following questions using art vocabulary and ideas from L.docx
Answer the following questions using art vocabulary and ideas from L.docxAnswer the following questions using art vocabulary and ideas from L.docx
Answer the following questions using art vocabulary and ideas from L.docx
 
Answer the following questions in a total of 3 pages (900 words). My.docx
Answer the following questions in a total of 3 pages (900 words). My.docxAnswer the following questions in a total of 3 pages (900 words). My.docx
Answer the following questions in a total of 3 pages (900 words). My.docx
 
Answer the following questions No single word responses (at lea.docx
Answer the following questions No single word responses (at lea.docxAnswer the following questions No single word responses (at lea.docx
Answer the following questions No single word responses (at lea.docx
 
Answer the following questions based on the ethnography Dancing Skel.docx
Answer the following questions based on the ethnography Dancing Skel.docxAnswer the following questions based on the ethnography Dancing Skel.docx
Answer the following questions based on the ethnography Dancing Skel.docx
 
Answer the following questions to the best of your ability1) De.docx
Answer the following questions to the best of your ability1) De.docxAnswer the following questions to the best of your ability1) De.docx
Answer the following questions to the best of your ability1) De.docx
 
Answer the following questionDo you think it is necessary to .docx
Answer the following questionDo you think it is necessary to .docxAnswer the following questionDo you think it is necessary to .docx
Answer the following questionDo you think it is necessary to .docx
 
Answer the following question. Use facts and examples to support.docx
Answer the following question. Use facts and examples to support.docxAnswer the following question. Use facts and examples to support.docx
Answer the following question. Use facts and examples to support.docx
 
Answer the bottom questions  in apa format and decent answer no shor.docx
Answer the bottom questions  in apa format and decent answer no shor.docxAnswer the bottom questions  in apa format and decent answer no shor.docx
Answer the bottom questions  in apa format and decent answer no shor.docx
 
Answer the following below using the EXCEL attachment. chapter 5.docx
Answer the following below using the EXCEL attachment. chapter 5.docxAnswer the following below using the EXCEL attachment. chapter 5.docx
Answer the following below using the EXCEL attachment. chapter 5.docx
 
Answer the following prompts about A Germanic People Create a Code .docx
Answer the following prompts about A Germanic People Create a Code .docxAnswer the following prompts about A Germanic People Create a Code .docx
Answer the following prompts about A Germanic People Create a Code .docx
 
Answer the following discussion board question below minumun 25.docx
Answer the following discussion board question below minumun 25.docxAnswer the following discussion board question below minumun 25.docx
Answer the following discussion board question below minumun 25.docx
 
Answer the following questions about IT Project Management. What.docx
Answer the following questions about IT Project Management. What.docxAnswer the following questions about IT Project Management. What.docx
Answer the following questions about IT Project Management. What.docx
 
Answer the following in at least 100 words minimum each1.Of.docx
Answer the following in at least 100 words minimum each1.Of.docxAnswer the following in at least 100 words minimum each1.Of.docx
Answer the following in at least 100 words minimum each1.Of.docx
 
Answer the following questions(at least 200 words) and responses 2 p.docx
Answer the following questions(at least 200 words) and responses 2 p.docxAnswer the following questions(at least 200 words) and responses 2 p.docx
Answer the following questions(at least 200 words) and responses 2 p.docx
 
Answer the following questions in a Word document and upload it by M.docx
Answer the following questions in a Word document and upload it by M.docxAnswer the following questions in a Word document and upload it by M.docx
Answer the following questions in a Word document and upload it by M.docx
 
Answer the following questions in complete sentences. Each answer sh.docx
Answer the following questions in complete sentences. Each answer sh.docxAnswer the following questions in complete sentences. Each answer sh.docx
Answer the following questions in complete sentences. Each answer sh.docx
 
ANSWER THE DISCUSSION QUESTION 250 WORDS MINDiscussion Q.docx
ANSWER THE DISCUSSION QUESTION 250 WORDS MINDiscussion Q.docxANSWER THE DISCUSSION QUESTION 250 WORDS MINDiscussion Q.docx
ANSWER THE DISCUSSION QUESTION 250 WORDS MINDiscussion Q.docx
 

Recently uploaded

Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersChitralekhaTherkar
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptxPoojaSen20
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 

Recently uploaded (20)

Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of Powders
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptx
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 

lng 1at the 1g out rank-Jigh orma -atten-a li.docx

  • 1. lng 1at the 1g out rank- Jigh/ orma - atten- a list analy - Jribed ~scan alita- fect 1g-edge 1es for e>deling rts and luanti- and course atio n 1t's 1 might if it t. The
  • 2. ke this lly, exam- ' s firm •ability a ted ,vith Probability (P) times Outcome = EMV P=.20 * < P=.80 $300,000 = +$60,000 -$40,000 = -$32,000 -$50,000 = -$10,000 -$ 20,000 = - $2,000 $60, 000 = $42,000 ~ * Project 2 * P= .70 Project 1 's EMV = $60,000- $32, 000 = $28, 000 Proj ect 2's EMV = -$10,000- $2,000 + $42, 000 = $30,000 FIGURE 11-7 Expected monetary value (EMV) example
  • 3. no reimburse ment if it is not awarded the contract. The sum of the probabilities for outcomes for each project must equal one (for Project 1, 20 percent plus 80 percent) . Probabilities are normally determined based on expert judgme nt. Cliff or other people in his firm should have some sense of their likelihood of winning certain projects. Figure 11-7 also shows probabilities and outcomes for Project 2. Suppose there is a 20 percent probability that Cliffs firm will lose $ 50,000 on Project 2, a 10 percent probabili- ty that it will lose $20,000, and a 70 percent probability that it will earn $60,000. Again, experts would ne ed to estimate these dollar amounts and probabilities. To calculate the expected monetary value (EJvfV) for each proj ect, multiply the proba- bility by the outcome value (or each potential outcome for each project and sum the results. To calculate expected monetary value for Project 1, going from left to right, multiply the probability by the outcome for each branch and sum the results. In this example, the EMV for Proj ect 1 is $28, 000. .2($300 ,000) + .8( -$40 ,000) = $60,000- $32,000 = $28 ,000 The EMV for Project 2 is $30,000 . .2 ( -$50 ,000 ) + .1(-$20 ,000) + .7($60,000) = -$1 0 ,000-$2 ,000 + .$42,000 = $30,000
  • 4. Beca use the EMV provides an estimate for the total dollar value of a decision , you wa nt to have a pos itive number; the higher the EMV, the bette r. Since the EJvfV is positive for both Projects 1 and 2 , Clift"s firm would expec t a positive outcome from eac h and could bid 0n both proj ects. If it had to choose between the two proj ects , perhaps because of limited resources , Clift"s firm should bid on Project 2 because it has a higher EMV. 443 Project Risk Management consulting costs might be expanded in the description to say that the organiza- tion might be able to negotiate lower-than-average costs for a particular consul- tant because the consultant really e njoys working for that company in that particular location. • The categor:y under which the risk event falls: For example, defective server might fall under the broader category of technology or hardware technology. • The root cause of the risk: The root cause of the defective server might be a defective power supply.
  • 5. • Triggers for each risk: Triggers are indicators or symptoms of actual risk events. For example, cost overruns on early activities may be symptoms of poor cost estimates . Defective products may be symptoms of a low- quality supplier. Documenting potential risk symptoms for projects also helps the project team identify more potential risk events . • Potential responses to each risk: A potential response to the risk event of a defective server might be the. inclusion of a clause in a contract with the supplier to replace a defective server within a certain time period at a negotiated cost. • The risk owner or person who will own or take responsibility for the risk: For example, a certain person might be in charge of any server- related risk events and managing response strategies. • The probability of the risk occurring: There might be a high, medium, or low probability of a certain risk event occurring. For example, the risk might be low that the server would actually be defective . • The impact to the project if the risk occurs: There might be a high , medium, or low impact to project success if the risk event actually occurs. A defective server might have a high impact on successfully completing a project on time.
  • 6. • The status of the 1isk: Did the risk event occur? Was the response strategy com- pleted? Is the risk no longer relevant to the project? For example , a contract clause may have been completed to address the risk of a defective server. TABLE 11-5 Sample risk register 437 No. Rank R1sk Description Category Root Tnggers Potential Risk Probability Impact Status R44 1 R21 2 R7 3 Cause Responses Owner For example, the following data might be entered for the first risk in the register as fol- lows. Notice that Cliffs team is taking a very proactive approach in managing this risk. • No.: R44 • Rank: 1 • Risk: New customer • Description: We have never done a project for this organization before and don't know too much about them. One of our company's strengths is building
  • 7. Project Risk Management 2. Review a document related to risk management, such as Microsoft's Security Risk Manage- ment Guide available from the companion Web site for this text. Does this guide address most of the topics related to risk management planning as described in this text? Document your analysis in a two-page paper. 3. Research risk management software. Are many products available? What are the main advantages of using them in managing projects? What are the main disadvantages? Write a two-page paper discussing your findings, and include at least three references. 4. Suppose your organization is deciding which of four projects to bid on. Information on each is in the table below. Assume that all up-front investments are not recovered, so they are shown as negative profits. Draw a diagram and calculate the EMV for each project. Write a few paragraphs explaining which projects you would bid on. Be sure to use the EMV informa- 456 tion and your personal risk tolerance to justify your answer. Chapter 11 Project 1 50 percent Sl20,000 50 percent -$50,000
  • 8. Project 2 30 percent s 100' 000 40 percent s 50,000 30 percent -860,000 Project 3 70 percent s 20,000 :10 percent -S 5,000 Project -l 30 percent s 40,000 JO percent s 30,000 20 percent $ 20,000 20 percent -850,000 5. Find an example of a company that took a big risk on an information technology project and succeeded. In adrJition, lind an example of a company that took a big risk and failed. Summarize each project and situation in a two-page paper where you should also discuss whether you believe that anything besides luck makes a difference between suc- cess and failure. Tony and his team identified some risks during the first month of the Recreation and Well- ness Intranet Project. However, all they did was document them in a list. They never ranked them or developed any response strategies. Since several problems have been occurring on the project, such as key team members leaving the company, users being uncooperative, and team members not providing good status information, Tony has decided to be more pro- active in managing risks. He also wants to address positive as well as negative risks.
  • 9. i. Create a risk register for the project, using Table i 1-5 and the data below it as a guide. Identity six potential risks, including risks related to the problems described above. Include negative and positive risks. Plot the six risks on a probability/impact matrix, using Figure 11-7. Also assign a numeric value for the probability and impact of each risk on meeting the main project objective. use a scale of 1 to 10 in assigning the values, with 1 being low and 10 being high. For a simple risk factor calculation, multiply these two values (the probability score and the impact score). Add a column to your risk register to the right of the impact column called Risk Score. Enter the new data in the risk register. Write your rationale for how you determined the scores for one of the negative risks and one of the positive risks. Develop a response strategy for one of the negative risks and one of the positive risks. Enter the information in the risk register. Also write a separate paragraph describing what specific tasks would need to be done to implement the strategy. Include time and cost estimates tor each strategy, as well. ion Web Site · the companion Web site for this text (www.cengage.com/mis/schwalbe) to access:
  • 10. References cited in the text and additional suggested readings for each chapter Template files Lecture notes Interactive quizzes Pod casts Links to general project management Web sites And more See the Preface of this text for additional information on accessing the companion Web site. Key Terms brainstorming -a technique by which a group attempts to generate ideas or find a solution for a specific problem by amassing ideas spontaneously and without judgment contingency allowances- provisions held by the project sponsor or organization to reduce the risk of cost or schedule overruns to an acceptable level; also called contingency reserves contingency plans - predefined actions that the project team will take if an identified risk event occurs contingency reserves- provisions held by the project sponsor or organization to reduce the
  • 11. risk of cost or schedule overruns to an acceptable level; also called contingency allowances decision tree- a diagramming analysis technique used to help select the best course of action in situations in which future outcomes are uncertain Delphi technique- an approach used to derive a consensus among a panel of experts, to make predictions about future developments expected monetary value (EMV)- the product of the risk event probability and the risk event's monetary value fallback plans- plans developed for risks that have a high impact on meeting project objectives, to be implemented if attempts to reduce the risk are not effective flowcharts - diagrams that show how various elements of a system relate to each other 457 Project Risk Management Unit V Mini Project Analyze the Running Case on pages 456-457 of the textbook, The Recreation and Wellness Intranet Project. · Complete Tasks 1-3 of the case, and use Excel and/or screenshots as necessary to display your data. · Summarize your findings in a 700 word minimum, APA formatted, Word document.
  • 12. · Any Excel documents and/or screenshots created to display your tasks need to be copied and pasted into the Word document at the end of the summary, and the assignment should be submitted as one document.