SlideShare a Scribd company logo
1 of 2
Download to read offline
 
Testing of New Control Enclosure Relays
www.siemens.com/smartgrid
IEC 61850 Protection and
Control Solutions
Panama City, Panama
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Modern Substation Engineering
As the demand for power continues to grow throughout
the world, our substations must be modified or upgraded
to account for these system changes. Panama has been
experiencing this growth, similar to many other
countries, and as a result recently installed four (4) 230kV
capacitor banks at one of its major substations. These
capacitors were set up to maintain local voltage levels,
and systematically support increased power demand.
Because of the critical nature of this substation a very
robust protection and control scheme was required which
included primary and secondary relaying. Both the
primary and secondary relays were to have identical
control functionality, similar protection and alarm
functions, and the ability to communicate with the local
HMI and the remote National Dispatch Center’s SCADA
system. Should failure of the primary relay occur, the
secondary relay would be able to maintain protection of
the feeder, provide control operations for the circuit
breaker, and communicate with the local HMI and SCADA
systems.
“The goal of every project is to
provide a solution that meets the
customer’s needs and exceeds
their expectations.”
Wunderlich-Malec Engineering, Inc.
Portsmouth, NH
Published by and copyright © 2014
Siemens AG
Infrastructure & Cities Sector
Smart Grid Division
Energy Automation
Humboldtstr. 59
90459 Nuremberg, Germany
For more information,
please contact our
Customer Support Center.
Phone: +49 180/524 70 00
Fax: +49 180/524 24 71
(Charges depending on provider)
E-mail: support.ic@siemens.com
Order No. ICXXXX-XXXX-XXXX | Printed in Germany | AL=N ECCN=N
Dispo XXXXX | c4bs No. XXXX | GB XXXXXX RP XXXXXX WS XX13X.X |
© XX.2014, Siemens AG
New Control Enclosure at Panama
Substation
New 115kV Capacitor Bank at Substation
Control Enclosure in
construction at the modern
Wunderlich-Malec Facility
Winslow, ME
 
Benefits for Wunderlich-Malec Engineering,
Inc.
During startup and commissioning the customer
requested modifications to the previously approved
interlocking as well as the protection and control scheme.
These changes were made by modifying logic within each
relay, and were then verified during testing.
If IEC 61850 protocol was not used, hard wiring changes
and additional auxiliary relays would have been required
adding weeks to the schedule while increasing startup
costs.
If modifications to the protection and control schemes are
required due to substation upgrades in the future,
changes can be accomplished and tested prior to any
required shutdowns. This results in significantly reducing
potential outage time, and minimizing the work performed
in energized control panels.
"The SIPROTEC 5 relays provided by Siemens helped us
achieve the best possible solution for our customer, and
allowed for a much more efficient testing and
commissioning process to meet everyone's needs."
Challenges for Wunderlich-Malec
Engineering, Inc.
Due to the level of complexity of the protection and
control scheme and quantity of alarms from the substation
circuit breakers, several I/O status states were required at
each relay location.
A traditional solution would be to hard wire each of the
states required, for example breaker status, into an input
(I/O) at each of these relays. This input could then be
mapped and programmed into the functionality of the
relay as required. This would require several auxiliary
relays, possibly adding additional relays, and the
installation of a substantial amount of hard wiring
between panels.
The main goal of this project was to ensure that the
primary and secondary relays had nearly identical
functionality, and if the primary relay were to fail all critical
alarms, control functionality and protection could be
maintained by the secondary relay only. Control of the
substation is normally performed from the remote
SCADA; therefore transfer of protection & control to the
secondary relay must be automatic and seamless, while
alerting the remote SCADA of the primary relay failure.
Our solution
By incorporating the use of IEC 61850 protocol GOOSE
messaging and Siemens SIPROTEC 5 relaying, I/O
status states (including breaker interlocking and trip
commands) could be communicated between relays
without the added costs and labor associated with
installing auxiliary relaying and cabling to each relay.
Breaker status, alarms, and control permissive states
were communicated to the SCADA system over Ethernet
using IEC 61850 MMS mapping.
 
 

More Related Content

What's hot

7SR23 High Impedance Bus Bar Protection Relay
7SR23 High Impedance Bus Bar Protection Relay7SR23 High Impedance Bus Bar Protection Relay
7SR23 High Impedance Bus Bar Protection Relayashwini reliserv
 
Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)Rohini Haridas
 
Generator Protection By - Er Rahul Sharma
Generator Protection By - Er Rahul Sharma Generator Protection By - Er Rahul Sharma
Generator Protection By - Er Rahul Sharma Rahul Ruddra
 
Loss of excitation
Loss of excitationLoss of excitation
Loss of excitationNTPC
 
Basics of overcurrent protection
Basics of overcurrent protectionBasics of overcurrent protection
Basics of overcurrent protectionSalim Palayi
 
instrument transformer
instrument transformerinstrument transformer
instrument transformerNishant Kumar
 
25 9-2014 design and development of micro-controller base differential protec...
25 9-2014 design and development of micro-controller base differential protec...25 9-2014 design and development of micro-controller base differential protec...
25 9-2014 design and development of micro-controller base differential protec...rajdoshi94
 
Presentation on Over-/under-voltage protection of electrical appliance
Presentation on Over-/under-voltage protection of electrical appliancePresentation on Over-/under-voltage protection of electrical appliance
Presentation on Over-/under-voltage protection of electrical applianceNishant Kumar
 
Generator protection gers
Generator protection gersGenerator protection gers
Generator protection gersHabudin Hassan
 
Substation equipment and its function 2
Substation equipment and its function 2Substation equipment and its function 2
Substation equipment and its function 2Zulfiqar Mangrio
 
RADIAL FEEDER PROTECTION PANEL DEVELOPMENT
RADIAL FEEDER PROTECTION PANEL DEVELOPMENTRADIAL FEEDER PROTECTION PANEL DEVELOPMENT
RADIAL FEEDER PROTECTION PANEL DEVELOPMENTHimanshu Paghdal
 
7UT63 Differential Protection Relay
7UT63 Differential Protection Relay7UT63 Differential Protection Relay
7UT63 Differential Protection Relayashwini reliserv
 
Generator Protection
Generator ProtectionGenerator Protection
Generator ProtectionPriten Vasa
 
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...jbpatel7290
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformerssiddharam kantoli
 
Protection Of Generator
Protection Of GeneratorProtection Of Generator
Protection Of GeneratorRahuldey1991
 

What's hot (20)

Overcurrent Protection
Overcurrent ProtectionOvercurrent Protection
Overcurrent Protection
 
7SR23 High Impedance Bus Bar Protection Relay
7SR23 High Impedance Bus Bar Protection Relay7SR23 High Impedance Bus Bar Protection Relay
7SR23 High Impedance Bus Bar Protection Relay
 
Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)
 
Generator Protection By - Er Rahul Sharma
Generator Protection By - Er Rahul Sharma Generator Protection By - Er Rahul Sharma
Generator Protection By - Er Rahul Sharma
 
Loss of excitation
Loss of excitationLoss of excitation
Loss of excitation
 
Basics of overcurrent protection
Basics of overcurrent protectionBasics of overcurrent protection
Basics of overcurrent protection
 
instrument transformer
instrument transformerinstrument transformer
instrument transformer
 
25 9-2014 design and development of micro-controller base differential protec...
25 9-2014 design and development of micro-controller base differential protec...25 9-2014 design and development of micro-controller base differential protec...
25 9-2014 design and development of micro-controller base differential protec...
 
Presentation on Over-/under-voltage protection of electrical appliance
Presentation on Over-/under-voltage protection of electrical appliancePresentation on Over-/under-voltage protection of electrical appliance
Presentation on Over-/under-voltage protection of electrical appliance
 
Generator protection gers
Generator protection gersGenerator protection gers
Generator protection gers
 
Substation equipment and its function 2
Substation equipment and its function 2Substation equipment and its function 2
Substation equipment and its function 2
 
RADIAL FEEDER PROTECTION PANEL DEVELOPMENT
RADIAL FEEDER PROTECTION PANEL DEVELOPMENTRADIAL FEEDER PROTECTION PANEL DEVELOPMENT
RADIAL FEEDER PROTECTION PANEL DEVELOPMENT
 
7UT63 Differential Protection Relay
7UT63 Differential Protection Relay7UT63 Differential Protection Relay
7UT63 Differential Protection Relay
 
BUS BAR PROTECTION PPT BY:-R.K.PANDIT
BUS BAR  PROTECTION PPT BY:-R.K.PANDITBUS BAR  PROTECTION PPT BY:-R.K.PANDIT
BUS BAR PROTECTION PPT BY:-R.K.PANDIT
 
Bus Bar Protection
Bus Bar ProtectionBus Bar Protection
Bus Bar Protection
 
Generator Protection
Generator ProtectionGenerator Protection
Generator Protection
 
Overcurrent coordination
Overcurrent coordinationOvercurrent coordination
Overcurrent coordination
 
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformers
 
Protection Of Generator
Protection Of GeneratorProtection Of Generator
Protection Of Generator
 

Similar to WM Siemens IEC 61850 Flyer 081914

Remediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardRemediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardIJAPEJOURNAL
 
Distribution Automation based on IEC61850
Distribution Automation based on IEC61850Distribution Automation based on IEC61850
Distribution Automation based on IEC61850Nirmal Thaliyil
 
AMSC D-SVC™ Product Catalog
AMSC D-SVC™ Product CatalogAMSC D-SVC™ Product Catalog
AMSC D-SVC™ Product CatalogPaul Chang
 
IRJET- PLC Based Intelligent Control of Substation
IRJET- PLC Based Intelligent Control of SubstationIRJET- PLC Based Intelligent Control of Substation
IRJET- PLC Based Intelligent Control of SubstationIRJET Journal
 
VIZIMAX's Renewable Energy Production solutions
VIZIMAX's Renewable Energy Production solutionsVIZIMAX's Renewable Energy Production solutions
VIZIMAX's Renewable Energy Production solutionsGuillaume Leur
 
Nokia_Sub-station_Automation_White_Paper_EN
Nokia_Sub-station_Automation_White_Paper_ENNokia_Sub-station_Automation_White_Paper_EN
Nokia_Sub-station_Automation_White_Paper_ENJuan Boggiano
 
EasergyT300_Catalog_NRJED314621EN_022018.pdf
EasergyT300_Catalog_NRJED314621EN_022018.pdfEasergyT300_Catalog_NRJED314621EN_022018.pdf
EasergyT300_Catalog_NRJED314621EN_022018.pdfShantieHarunAlRosyid
 
Smarter Grid Solutions Company Overview
Smarter Grid Solutions Company OverviewSmarter Grid Solutions Company Overview
Smarter Grid Solutions Company OverviewSmarter Grid Solutions
 
IRJET- Automatic Load Balancing and Phase Balancing by PLC and Scada
IRJET-  	  Automatic Load Balancing and Phase Balancing by PLC and ScadaIRJET-  	  Automatic Load Balancing and Phase Balancing by PLC and Scada
IRJET- Automatic Load Balancing and Phase Balancing by PLC and ScadaIRJET Journal
 
GSM Based Fault Monitoring System (Project)
GSM Based Fault Monitoring System (Project)GSM Based Fault Monitoring System (Project)
GSM Based Fault Monitoring System (Project)Aishwary Verma
 
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...IRJET Journal
 
DETECTING POWER GRID SYNCHRONISATION FAILURE ON SENSING BAD VOLTAGE OR FREQUE...
DETECTING POWER GRID SYNCHRONISATION FAILURE ON SENSING BAD VOLTAGE OR FREQUE...DETECTING POWER GRID SYNCHRONISATION FAILURE ON SENSING BAD VOLTAGE OR FREQUE...
DETECTING POWER GRID SYNCHRONISATION FAILURE ON SENSING BAD VOLTAGE OR FREQUE...Pradeep Avanigadda
 
Joseph Staniowski - Design Project
Joseph Staniowski - Design ProjectJoseph Staniowski - Design Project
Joseph Staniowski - Design ProjectJoseph Staniowski
 
TRANSFORMER HEALTH MONITORING SYSTEM
TRANSFORMER HEALTH MONITORING SYSTEMTRANSFORMER HEALTH MONITORING SYSTEM
TRANSFORMER HEALTH MONITORING SYSTEMIRJET Journal
 

Similar to WM Siemens IEC 61850 Flyer 081914 (20)

Remediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardRemediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazard
 
Schneider plc
Schneider plcSchneider plc
Schneider plc
 
Distribution Automation based on IEC61850
Distribution Automation based on IEC61850Distribution Automation based on IEC61850
Distribution Automation based on IEC61850
 
AMSC D-SVC™ Product Catalog
AMSC D-SVC™ Product CatalogAMSC D-SVC™ Product Catalog
AMSC D-SVC™ Product Catalog
 
IRJET- PLC Based Intelligent Control of Substation
IRJET- PLC Based Intelligent Control of SubstationIRJET- PLC Based Intelligent Control of Substation
IRJET- PLC Based Intelligent Control of Substation
 
VIZIMAX's Renewable Energy Production solutions
VIZIMAX's Renewable Energy Production solutionsVIZIMAX's Renewable Energy Production solutions
VIZIMAX's Renewable Energy Production solutions
 
SebKMT Cable Sheath testers & Fault Locators
SebKMT Cable Sheath testers & Fault LocatorsSebKMT Cable Sheath testers & Fault Locators
SebKMT Cable Sheath testers & Fault Locators
 
Nokia_Sub-station_Automation_White_Paper_EN
Nokia_Sub-station_Automation_White_Paper_ENNokia_Sub-station_Automation_White_Paper_EN
Nokia_Sub-station_Automation_White_Paper_EN
 
EasergyT300_Catalog_NRJED314621EN_022018.pdf
EasergyT300_Catalog_NRJED314621EN_022018.pdfEasergyT300_Catalog_NRJED314621EN_022018.pdf
EasergyT300_Catalog_NRJED314621EN_022018.pdf
 
Eraring_Energy_Case_Study
Eraring_Energy_Case_StudyEraring_Energy_Case_Study
Eraring_Energy_Case_Study
 
Smarter Grid Solutions Company Overview
Smarter Grid Solutions Company OverviewSmarter Grid Solutions Company Overview
Smarter Grid Solutions Company Overview
 
IRJET- Automatic Load Balancing and Phase Balancing by PLC and Scada
IRJET-  	  Automatic Load Balancing and Phase Balancing by PLC and ScadaIRJET-  	  Automatic Load Balancing and Phase Balancing by PLC and Scada
IRJET- Automatic Load Balancing and Phase Balancing by PLC and Scada
 
GSM Based Fault Monitoring System (Project)
GSM Based Fault Monitoring System (Project)GSM Based Fault Monitoring System (Project)
GSM Based Fault Monitoring System (Project)
 
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
Introduction of 132/11 kV Digitally Optimized Substation for Protection, Cont...
 
Gemini_3__3008_web
Gemini_3__3008_webGemini_3__3008_web
Gemini_3__3008_web
 
DETECTING POWER GRID SYNCHRONISATION FAILURE ON SENSING BAD VOLTAGE OR FREQUE...
DETECTING POWER GRID SYNCHRONISATION FAILURE ON SENSING BAD VOLTAGE OR FREQUE...DETECTING POWER GRID SYNCHRONISATION FAILURE ON SENSING BAD VOLTAGE OR FREQUE...
DETECTING POWER GRID SYNCHRONISATION FAILURE ON SENSING BAD VOLTAGE OR FREQUE...
 
Smart grid Technology
Smart grid TechnologySmart grid Technology
Smart grid Technology
 
LayerZero Power Systems Corporate Brochure
LayerZero Power Systems Corporate BrochureLayerZero Power Systems Corporate Brochure
LayerZero Power Systems Corporate Brochure
 
Joseph Staniowski - Design Project
Joseph Staniowski - Design ProjectJoseph Staniowski - Design Project
Joseph Staniowski - Design Project
 
TRANSFORMER HEALTH MONITORING SYSTEM
TRANSFORMER HEALTH MONITORING SYSTEMTRANSFORMER HEALTH MONITORING SYSTEM
TRANSFORMER HEALTH MONITORING SYSTEM
 

WM Siemens IEC 61850 Flyer 081914

  • 1.   Testing of New Control Enclosure Relays www.siemens.com/smartgrid IEC 61850 Protection and Control Solutions Panama City, Panama                                 Modern Substation Engineering As the demand for power continues to grow throughout the world, our substations must be modified or upgraded to account for these system changes. Panama has been experiencing this growth, similar to many other countries, and as a result recently installed four (4) 230kV capacitor banks at one of its major substations. These capacitors were set up to maintain local voltage levels, and systematically support increased power demand. Because of the critical nature of this substation a very robust protection and control scheme was required which included primary and secondary relaying. Both the primary and secondary relays were to have identical control functionality, similar protection and alarm functions, and the ability to communicate with the local HMI and the remote National Dispatch Center’s SCADA system. Should failure of the primary relay occur, the secondary relay would be able to maintain protection of the feeder, provide control operations for the circuit breaker, and communicate with the local HMI and SCADA systems. “The goal of every project is to provide a solution that meets the customer’s needs and exceeds their expectations.” Wunderlich-Malec Engineering, Inc. Portsmouth, NH
  • 2. Published by and copyright © 2014 Siemens AG Infrastructure & Cities Sector Smart Grid Division Energy Automation Humboldtstr. 59 90459 Nuremberg, Germany For more information, please contact our Customer Support Center. Phone: +49 180/524 70 00 Fax: +49 180/524 24 71 (Charges depending on provider) E-mail: support.ic@siemens.com Order No. ICXXXX-XXXX-XXXX | Printed in Germany | AL=N ECCN=N Dispo XXXXX | c4bs No. XXXX | GB XXXXXX RP XXXXXX WS XX13X.X | © XX.2014, Siemens AG New Control Enclosure at Panama Substation New 115kV Capacitor Bank at Substation Control Enclosure in construction at the modern Wunderlich-Malec Facility Winslow, ME   Benefits for Wunderlich-Malec Engineering, Inc. During startup and commissioning the customer requested modifications to the previously approved interlocking as well as the protection and control scheme. These changes were made by modifying logic within each relay, and were then verified during testing. If IEC 61850 protocol was not used, hard wiring changes and additional auxiliary relays would have been required adding weeks to the schedule while increasing startup costs. If modifications to the protection and control schemes are required due to substation upgrades in the future, changes can be accomplished and tested prior to any required shutdowns. This results in significantly reducing potential outage time, and minimizing the work performed in energized control panels. "The SIPROTEC 5 relays provided by Siemens helped us achieve the best possible solution for our customer, and allowed for a much more efficient testing and commissioning process to meet everyone's needs." Challenges for Wunderlich-Malec Engineering, Inc. Due to the level of complexity of the protection and control scheme and quantity of alarms from the substation circuit breakers, several I/O status states were required at each relay location. A traditional solution would be to hard wire each of the states required, for example breaker status, into an input (I/O) at each of these relays. This input could then be mapped and programmed into the functionality of the relay as required. This would require several auxiliary relays, possibly adding additional relays, and the installation of a substantial amount of hard wiring between panels. The main goal of this project was to ensure that the primary and secondary relays had nearly identical functionality, and if the primary relay were to fail all critical alarms, control functionality and protection could be maintained by the secondary relay only. Control of the substation is normally performed from the remote SCADA; therefore transfer of protection & control to the secondary relay must be automatic and seamless, while alerting the remote SCADA of the primary relay failure. Our solution By incorporating the use of IEC 61850 protocol GOOSE messaging and Siemens SIPROTEC 5 relaying, I/O status states (including breaker interlocking and trip commands) could be communicated between relays without the added costs and labor associated with installing auxiliary relaying and cabling to each relay. Breaker status, alarms, and control permissive states were communicated to the SCADA system over Ethernet using IEC 61850 MMS mapping.