Progressing CBM
Development in Indonesia
- An Industry Perspective -
Mohd. Radzif Mohamed
VICO CBM Commercial Manager
IndoGAS Conference
27th – 29th January 2015
1
VICO Overview
• VICO is a 50:50 JV between BP and ENI
• VICO has operated the Sanga Sanga conventional oil
and gas PSC since 1968 with first LNG in 1977
• CBM PSC awarded November 2009 for 30 years
• Sanga Sanga CBM PSC has met all PSC
commitments & spent $250m to date
• Exploration complete, appraisal in progress
• First CBM rig & horizontal wells in Indonesia
• First CBM gas delivery to Bontang in 2011
• First CBM Gas Sales delivery to PLN in 2013
• Conventional & CBM PSC share infrastructure
SEM 201
MWP #1
Exploration Wells
Appraisal Programme
2
Coring (Using
Conventional Wells
2010 2011 2012 2013 2014
Resource Appraisal
PSC signed
Re-completed Mut 78 (old oil
well)- first CBM well
Drilling MWP#1, first
purpose drilled CBM
wells
Micro-seismic on
MWP#2 fracs
First LRP
First Hydraulic rig on
MWP#3
CBM to Power
Mut 205 Well Head
Compressor Trial
First CBM horizontals
in Indonesia
VICO CBM Achievements
3
Indonesia CBM Resources
4
• Resource potential in Indonesia estimated at over 450TCF
• 54 CBM PSC’s awarded since 2008 with 22 in Sumatra and 34 in
Kalimantan
• SKKMigas estimate and using latest data from operators, resource base of
130 to 140 TCF for CBM in Indonesia in licensed PSCs (more in unlicensed
areas)
NOTE – Conventional Proved Reserves for Indonesia approximately 100 TCF
(2014 BP statistical review)
Energy Demand/Supply
5
• Strong GDP growth is driving increased domestic demand in
Indonesia but domestic production is falling - decline in
conventional oil & gas production
• Likely that Indonesia will become a net importer of gas - CBM
production could help fill the demand gap or imports will increase
CBM In Indonesia
• Has CBM been successful in Indonesia?
– Initial GoI CBM Roadmap? 500 100  8.9 MMSCFD
– Many have left – BP, Exxon, Total, Santos, etc
– Current investor sentiments at a low – No recent CBM PSC
awards
– Well behind on Exploration Commitment – less than 20%
– Regulatory and fiscal environment unsuited for CBM
– Good CBM potential but still needs to prove produceability
and commerciality
 How do we make CBM a SUCCESS 
6
7
Indonesian CBM industry is still in its infancyMaturity
Exploration time to commercialisation
UNITED STATES
• Resources: 700 TCF
• Main Basin: San Juan,
Black Warrior
• Annual Production: 1.65
TCF (2012)
• Start exploration: 1950’s
• Commercialisation start:
1980’s
• Wells drilled: 30,000
• Cost per well: US$ 200-
300 Thousand
252
BCF/
Year
UNITED STATES
• Fiscal incentives:
• Unregulated selling price
• Tax credits (initial stage)
• Land owner royalties
• Light handed regulation
AUSTRALIA
• Resources: 250 TCF
• Main Basin: Bowen, Surat
• Start exploration: 1950’s
• Commercialisation start: 1990’s
• Wells drilled: 1,300 (2010)
• Cost per well: US$ 1.2 Million
• Fiscal incentives:
• Favorable fiscal regime
• Unregulated selling price
• Government mandates Power
Companies to utilize power
generated from gas
CHINA
• Resources: 1300 TCF
• Produced basin: Qinshui
• Annual Production: 21 BCF (2012)
• Start exploration: 1990’s
• Commercialisation start: 2009
• Wells drilled: 2,000
• Fiscal incentives:
• Price reforms
• Preferential power tariff
• Tax reliefs
• Low government take
INDONESIA
• Resources: 140 TCF
(based on active
working areas)
• Main basin: Kutai,
South Sumatera
• Annual Production: 450
MCF (2013)
• Start exploration: 2008
• No Commerc. yet
• Wells drilled: 84
Annual Production
8
ADVISORY
BOARD
EXECUTIVE
DIRECTOR
Work Group
Fiscal
Work Group
Technology
Work Group
Policy &
Regulations
ESDM LITBANG
LEMIGAS
Ministerial
Policy Brief
& Model
Agreement
3Q 2014 1Q 2015 1Q 2015
Government & Industry
Initiative
INDUSTRY
Government
of Indonesia
9
Led by
Mohd Radzif
Mohamed
What Does Indonesia Need
• Consider aggressive short term incentives.
• Access to the high value gas market in Indonesia,
consistent with Domestic LNG Price
• A significant reduction in the overall regulatory regime
• Fiscal policy for the support of CBM.
• A “one stop shop” in the Government for all permitting
• Improved POD requirements for CBM
10
~ Terima Kasih ~
11

More Related Content

What's hot

Managing energy risk in africa presentation
Managing energy risk in africa   presentationManaging energy risk in africa   presentation
Managing energy risk in africa presentationEgmont Ottermann
 
Item #11 ppt 2018 SMP Contract
Item #11   ppt 2018 SMP ContractItem #11   ppt 2018 SMP Contract
Item #11 ppt 2018 SMP Contractahcitycouncil
 
The Evolution of London's Business Improvement Districts
The Evolution of London's Business Improvement DistrictsThe Evolution of London's Business Improvement Districts
The Evolution of London's Business Improvement Districtsfutureoflondon
 
Gary Cochrane - Bounty Mining
Gary Cochrane - Bounty MiningGary Cochrane - Bounty Mining
Gary Cochrane - Bounty MiningInforma Australia
 
Hunterenergyplan
HunterenergyplanHunterenergyplan
HunterenergyplanHunterGas
 

What's hot (7)

Managing energy risk in africa presentation
Managing energy risk in africa   presentationManaging energy risk in africa   presentation
Managing energy risk in africa presentation
 
Item #11 ppt 2018 SMP Contract
Item #11   ppt 2018 SMP ContractItem #11   ppt 2018 SMP Contract
Item #11 ppt 2018 SMP Contract
 
The Evolution of London's Business Improvement Districts
The Evolution of London's Business Improvement DistrictsThe Evolution of London's Business Improvement Districts
The Evolution of London's Business Improvement Districts
 
Gary Cochrane - Bounty Mining
Gary Cochrane - Bounty MiningGary Cochrane - Bounty Mining
Gary Cochrane - Bounty Mining
 
Steering committee draft policy note 2 (1)
Steering committee draft policy note 2 (1)Steering committee draft policy note 2 (1)
Steering committee draft policy note 2 (1)
 
Hunterenergyplan
HunterenergyplanHunterenergyplan
Hunterenergyplan
 
Tyres ifo presentation -6-11-12
Tyres   ifo presentation -6-11-12Tyres   ifo presentation -6-11-12
Tyres ifo presentation -6-11-12
 

Viewers also liked

Kegiatan hulu migas x
Kegiatan hulu migas xKegiatan hulu migas x
Kegiatan hulu migas ximamncahyo
 
Optimalisasi Tata Kelola Industri Hulu Migas Nasional yang Efektif dan Akuntabel
Optimalisasi Tata Kelola Industri Hulu Migas Nasional yang Efektif dan AkuntabelOptimalisasi Tata Kelola Industri Hulu Migas Nasional yang Efektif dan Akuntabel
Optimalisasi Tata Kelola Industri Hulu Migas Nasional yang Efektif dan AkuntabelPublish What You Pay (PWYP) Indonesia
 
Bahan Presentasi Pendadaran Prawira dan Daud
Bahan Presentasi Pendadaran Prawira dan DaudBahan Presentasi Pendadaran Prawira dan Daud
Bahan Presentasi Pendadaran Prawira dan DaudUniversitas Sriwijaya
 
Minyak Dan Gas Bumi
Minyak Dan Gas BumiMinyak Dan Gas Bumi
Minyak Dan Gas Bumialspril
 
Teknik eksplorasi
Teknik eksplorasiTeknik eksplorasi
Teknik eksplorasioilandgas24
 

Viewers also liked (8)

Sumber minyak bumi
Sumber minyak bumiSumber minyak bumi
Sumber minyak bumi
 
Kegiatan hulu migas x
Kegiatan hulu migas xKegiatan hulu migas x
Kegiatan hulu migas x
 
Optimalisasi Tata Kelola Industri Hulu Migas Nasional yang Efektif dan Akuntabel
Optimalisasi Tata Kelola Industri Hulu Migas Nasional yang Efektif dan AkuntabelOptimalisasi Tata Kelola Industri Hulu Migas Nasional yang Efektif dan Akuntabel
Optimalisasi Tata Kelola Industri Hulu Migas Nasional yang Efektif dan Akuntabel
 
DASAR GEOLOGI TEKNIK
DASAR GEOLOGI TEKNIKDASAR GEOLOGI TEKNIK
DASAR GEOLOGI TEKNIK
 
Bahan Presentasi Pendadaran Prawira dan Daud
Bahan Presentasi Pendadaran Prawira dan DaudBahan Presentasi Pendadaran Prawira dan Daud
Bahan Presentasi Pendadaran Prawira dan Daud
 
Minyak Dan Gas Bumi
Minyak Dan Gas BumiMinyak Dan Gas Bumi
Minyak Dan Gas Bumi
 
Tahapan eksplorasi
Tahapan eksplorasiTahapan eksplorasi
Tahapan eksplorasi
 
Teknik eksplorasi
Teknik eksplorasiTeknik eksplorasi
Teknik eksplorasi
 

Similar to IndoGAS 2015 Presentation - Progressing CBM Development in Indonesia - An Industry Perspective by Mohd Radzif Mohamad

Nemaska Lithium Corporate Presentation Jan 04 2016 FINAL
Nemaska Lithium Corporate Presentation Jan 04 2016 FINALNemaska Lithium Corporate Presentation Jan 04 2016 FINAL
Nemaska Lithium Corporate Presentation Jan 04 2016 FINALVictor Cantore
 
16. NECS 2016 _ Energy - Expanding the oil &; gas potential for north east- M...
16. NECS 2016 _ Energy - Expanding the oil &; gas potential for north east- M...16. NECS 2016 _ Energy - Expanding the oil &; gas potential for north east- M...
16. NECS 2016 _ Energy - Expanding the oil &; gas potential for north east- M...FICCINorthEast
 
Erhc south africa conference october 2013 final
Erhc south africa conference october 2013 finalErhc south africa conference october 2013 final
Erhc south africa conference october 2013 finalDan Keeney
 
10 Factors that May Affect the Future of Subsea Production
10 Factors that May Affect the Future of Subsea Production10 Factors that May Affect the Future of Subsea Production
10 Factors that May Affect the Future of Subsea ProductionLife Cycle Engineering
 
Candax Energy Corporate Presentation
Candax Energy Corporate PresentationCandax Energy Corporate Presentation
Candax Energy Corporate PresentationCompany Spotlight
 
Andalusia Bumi Energi
Andalusia Bumi EnergiAndalusia Bumi Energi
Andalusia Bumi EnergiHCI-IT
 
Gas - Dominant Energy of the Future by Babs Omotowa
Gas - Dominant Energy of the Future by Babs OmotowaGas - Dominant Energy of the Future by Babs Omotowa
Gas - Dominant Energy of the Future by Babs OmotowaE. Daniel
 
Oil & gas sector schotland
Oil & gas sector schotlandOil & gas sector schotland
Oil & gas sector schotlandhollanduktrade
 
Kirloskar brother ltd. Kirloskarvadi
Kirloskar brother ltd. KirloskarvadiKirloskar brother ltd. Kirloskarvadi
Kirloskar brother ltd. KirloskarvadiSubin Suresh
 
Waste-to-energy plants - public private partnership Singapore
Waste-to-energy plants - public private partnership SingaporeWaste-to-energy plants - public private partnership Singapore
Waste-to-energy plants - public private partnership SingaporeZhou HE (贺舟)
 
Unlocking the Economic Potential of South Africa's Oceans
Unlocking the Economic Potential of South Africa's OceansUnlocking the Economic Potential of South Africa's Oceans
Unlocking the Economic Potential of South Africa's OceansDr Lendy Spires
 
Panel 4. CCS technology - Takaya Watanabe, MHI
Panel 4. CCS technology - Takaya Watanabe, MHIPanel 4. CCS technology - Takaya Watanabe, MHI
Panel 4. CCS technology - Takaya Watanabe, MHIGlobal CCS Institute
 
Fuel gap for Power Sector priyank
Fuel gap for Power Sector  priyankFuel gap for Power Sector  priyank
Fuel gap for Power Sector priyankPRIYANK JAIN
 
22.03.2011 Oyu Tolgoi (OT) and Tavan Tolgoi (TT)-developing Mongolia’s world-...
22.03.2011 Oyu Tolgoi (OT) and Tavan Tolgoi (TT)-developing Mongolia’s world-...22.03.2011 Oyu Tolgoi (OT) and Tavan Tolgoi (TT)-developing Mongolia’s world-...
22.03.2011 Oyu Tolgoi (OT) and Tavan Tolgoi (TT)-developing Mongolia’s world-...The Business Council of Mongolia
 
Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...
Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...
Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...Lynn Aziz
 
Managing fuel supply & uncertainty in India
Managing fuel supply & uncertainty in IndiaManaging fuel supply & uncertainty in India
Managing fuel supply & uncertainty in IndiaIPPAI
 

Similar to IndoGAS 2015 Presentation - Progressing CBM Development in Indonesia - An Industry Perspective by Mohd Radzif Mohamad (20)

Nemaska Lithium Corporate Presentation Jan 04 2016 FINAL
Nemaska Lithium Corporate Presentation Jan 04 2016 FINALNemaska Lithium Corporate Presentation Jan 04 2016 FINAL
Nemaska Lithium Corporate Presentation Jan 04 2016 FINAL
 
Gdmp model workshop 2 - overview of model
Gdmp model workshop   2 - overview of modelGdmp model workshop   2 - overview of model
Gdmp model workshop 2 - overview of model
 
Premier oil13a pres
Premier oil13a presPremier oil13a pres
Premier oil13a pres
 
16. NECS 2016 _ Energy - Expanding the oil &; gas potential for north east- M...
16. NECS 2016 _ Energy - Expanding the oil &; gas potential for north east- M...16. NECS 2016 _ Energy - Expanding the oil &; gas potential for north east- M...
16. NECS 2016 _ Energy - Expanding the oil &; gas potential for north east- M...
 
Erhc south africa conference october 2013 final
Erhc south africa conference october 2013 finalErhc south africa conference october 2013 final
Erhc south africa conference october 2013 final
 
10 Factors that May Affect the Future of Subsea Production
10 Factors that May Affect the Future of Subsea Production10 Factors that May Affect the Future of Subsea Production
10 Factors that May Affect the Future of Subsea Production
 
Candax Energy Corporate Presentation
Candax Energy Corporate PresentationCandax Energy Corporate Presentation
Candax Energy Corporate Presentation
 
Andalusia Bumi Energi
Andalusia Bumi EnergiAndalusia Bumi Energi
Andalusia Bumi Energi
 
IRON SAND
IRON SANDIRON SAND
IRON SAND
 
Gas - Dominant Energy of the Future by Babs Omotowa
Gas - Dominant Energy of the Future by Babs OmotowaGas - Dominant Energy of the Future by Babs Omotowa
Gas - Dominant Energy of the Future by Babs Omotowa
 
Oil & gas sector schotland
Oil & gas sector schotlandOil & gas sector schotland
Oil & gas sector schotland
 
Kirloskar brother ltd. Kirloskarvadi
Kirloskar brother ltd. KirloskarvadiKirloskar brother ltd. Kirloskarvadi
Kirloskar brother ltd. Kirloskarvadi
 
Waste-to-energy plants - public private partnership Singapore
Waste-to-energy plants - public private partnership SingaporeWaste-to-energy plants - public private partnership Singapore
Waste-to-energy plants - public private partnership Singapore
 
Unlocking the Economic Potential of South Africa's Oceans
Unlocking the Economic Potential of South Africa's OceansUnlocking the Economic Potential of South Africa's Oceans
Unlocking the Economic Potential of South Africa's Oceans
 
Panel 4. CCS technology - Takaya Watanabe, MHI
Panel 4. CCS technology - Takaya Watanabe, MHIPanel 4. CCS technology - Takaya Watanabe, MHI
Panel 4. CCS technology - Takaya Watanabe, MHI
 
Fuel gap for Power Sector priyank
Fuel gap for Power Sector  priyankFuel gap for Power Sector  priyank
Fuel gap for Power Sector priyank
 
22.03.2011 Oyu Tolgoi (OT) and Tavan Tolgoi (TT)-developing Mongolia’s world-...
22.03.2011 Oyu Tolgoi (OT) and Tavan Tolgoi (TT)-developing Mongolia’s world-...22.03.2011 Oyu Tolgoi (OT) and Tavan Tolgoi (TT)-developing Mongolia’s world-...
22.03.2011 Oyu Tolgoi (OT) and Tavan Tolgoi (TT)-developing Mongolia’s world-...
 
Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...
Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...
Infrastructure Developments In Indonesia - Key Improvements and Priority Proj...
 
Sngpl
SngplSngpl
Sngpl
 
Managing fuel supply & uncertainty in India
Managing fuel supply & uncertainty in IndiaManaging fuel supply & uncertainty in India
Managing fuel supply & uncertainty in India
 

IndoGAS 2015 Presentation - Progressing CBM Development in Indonesia - An Industry Perspective by Mohd Radzif Mohamad

  • 1. Progressing CBM Development in Indonesia - An Industry Perspective - Mohd. Radzif Mohamed VICO CBM Commercial Manager IndoGAS Conference 27th – 29th January 2015 1
  • 2. VICO Overview • VICO is a 50:50 JV between BP and ENI • VICO has operated the Sanga Sanga conventional oil and gas PSC since 1968 with first LNG in 1977 • CBM PSC awarded November 2009 for 30 years • Sanga Sanga CBM PSC has met all PSC commitments & spent $250m to date • Exploration complete, appraisal in progress • First CBM rig & horizontal wells in Indonesia • First CBM gas delivery to Bontang in 2011 • First CBM Gas Sales delivery to PLN in 2013 • Conventional & CBM PSC share infrastructure SEM 201 MWP #1 Exploration Wells Appraisal Programme 2
  • 3. Coring (Using Conventional Wells 2010 2011 2012 2013 2014 Resource Appraisal PSC signed Re-completed Mut 78 (old oil well)- first CBM well Drilling MWP#1, first purpose drilled CBM wells Micro-seismic on MWP#2 fracs First LRP First Hydraulic rig on MWP#3 CBM to Power Mut 205 Well Head Compressor Trial First CBM horizontals in Indonesia VICO CBM Achievements 3
  • 4. Indonesia CBM Resources 4 • Resource potential in Indonesia estimated at over 450TCF • 54 CBM PSC’s awarded since 2008 with 22 in Sumatra and 34 in Kalimantan • SKKMigas estimate and using latest data from operators, resource base of 130 to 140 TCF for CBM in Indonesia in licensed PSCs (more in unlicensed areas) NOTE – Conventional Proved Reserves for Indonesia approximately 100 TCF (2014 BP statistical review)
  • 5. Energy Demand/Supply 5 • Strong GDP growth is driving increased domestic demand in Indonesia but domestic production is falling - decline in conventional oil & gas production • Likely that Indonesia will become a net importer of gas - CBM production could help fill the demand gap or imports will increase
  • 6. CBM In Indonesia • Has CBM been successful in Indonesia? – Initial GoI CBM Roadmap? 500 100  8.9 MMSCFD – Many have left – BP, Exxon, Total, Santos, etc – Current investor sentiments at a low – No recent CBM PSC awards – Well behind on Exploration Commitment – less than 20% – Regulatory and fiscal environment unsuited for CBM – Good CBM potential but still needs to prove produceability and commerciality  How do we make CBM a SUCCESS  6
  • 7. 7
  • 8. Indonesian CBM industry is still in its infancyMaturity Exploration time to commercialisation UNITED STATES • Resources: 700 TCF • Main Basin: San Juan, Black Warrior • Annual Production: 1.65 TCF (2012) • Start exploration: 1950’s • Commercialisation start: 1980’s • Wells drilled: 30,000 • Cost per well: US$ 200- 300 Thousand 252 BCF/ Year UNITED STATES • Fiscal incentives: • Unregulated selling price • Tax credits (initial stage) • Land owner royalties • Light handed regulation AUSTRALIA • Resources: 250 TCF • Main Basin: Bowen, Surat • Start exploration: 1950’s • Commercialisation start: 1990’s • Wells drilled: 1,300 (2010) • Cost per well: US$ 1.2 Million • Fiscal incentives: • Favorable fiscal regime • Unregulated selling price • Government mandates Power Companies to utilize power generated from gas CHINA • Resources: 1300 TCF • Produced basin: Qinshui • Annual Production: 21 BCF (2012) • Start exploration: 1990’s • Commercialisation start: 2009 • Wells drilled: 2,000 • Fiscal incentives: • Price reforms • Preferential power tariff • Tax reliefs • Low government take INDONESIA • Resources: 140 TCF (based on active working areas) • Main basin: Kutai, South Sumatera • Annual Production: 450 MCF (2013) • Start exploration: 2008 • No Commerc. yet • Wells drilled: 84 Annual Production 8
  • 9. ADVISORY BOARD EXECUTIVE DIRECTOR Work Group Fiscal Work Group Technology Work Group Policy & Regulations ESDM LITBANG LEMIGAS Ministerial Policy Brief & Model Agreement 3Q 2014 1Q 2015 1Q 2015 Government & Industry Initiative INDUSTRY Government of Indonesia 9 Led by Mohd Radzif Mohamed
  • 10. What Does Indonesia Need • Consider aggressive short term incentives. • Access to the high value gas market in Indonesia, consistent with Domestic LNG Price • A significant reduction in the overall regulatory regime • Fiscal policy for the support of CBM. • A “one stop shop” in the Government for all permitting • Improved POD requirements for CBM 10