SlideShare a Scribd company logo
1 of 28
ABESIT
PRESENTATION BY : RADHEY LAL
Roll No. : 1429040081
Section : 4th Year, ME-B2
Seminar
presentation
PRESENTED TO : Mr. Amit gupta
NTPC Dadri
CHP (Coal Handling Plant) Department
Presentation on :
Diagram of a typical coal-fired thermal power station
About NTPC
 NTPC, the largest power Company in India, was setup in 1975 to
accelerate power development in the country.
 NTPC has installed capacity of 41,684 MW.
 NTPC ranked 300th in the ‘2013, Forbes Global 2000’ ranking of the
World’s biggest companies.
 NTPC plans to become a 128,000 MW company by 2032.
 It has 16 coal based power stations (23,395 MW)
 7 gas based power stations (3,955 MW)
 4 power stations in Joint Ventures (1,794 MW).
 NTPC has been awarded NO-1,best workplace in India among large
organization and the best PSU for the year 2010.
History
 NTPC Dadri plant and township are property of ntpc ltd and
were built around 1988-1990.
 It was commissioned in 1991.
NTPC Dadri is a branch of National Thermal Power Corporation,
which is a public sector now. It is about 20 km from Ghaziabad
via Badalpur, Mahawar, Bamabawar, and Akilpur Jagir.
Continued..
Capacity
 NTPC Dadri is a unique power plant of NTPC group which has both
coal based thermal plant and gas based thermal plant of 1820 MW
and 817 MW respectively and 5 MW solar plant .
 Coal based :
Stage Unit Number
Installed
Capacity (MW)
Date of
Commissioning
1st
1 210 1991 October
2 210 1992 December
3 210 1993 March
4 210 1994 March
2nd
5 490 2010 January
6 490 2010 July
Total Six 1820
 Gas based :
NTPC dadri also produces electricity by gas. The details of gas power plant
are given below in the table.
Stage Unit Number
Installed
Capacity
(MW)
Date of
Commissioning
Gas Turbine
/ Steam
Turbine
1st
1 130.19 1992 March GT
2 130.19 1992 May GT
3 130.19 1992 June GT
4 130.19 1992 November GT
5 154.51 1993 February ST
6 154.51 1993 March ST
Total six 829.78
Total capacity of the plant is 2649 MW.
NTPC distributes to:
 Its mainly distributes most of its electricity to Delhi.
 And it also distributes some part of it electricity to Uttar Pradesh,
Uttarakhand and Haryana .
NTPC Dadri gets:
 Coal from Piparwar Mines ,Jharkhand .
 Gas from GAIL Hajira-Bijapur-Jagdispur (HBL) pipeline.
 Water from Upper Ganges Canal.
CHP (Coal Handling Plant)
 The role of CHP is to meet the demand of coal.
 It is the responsibility of CHP to take care of coal from Piparwar Mines ,
Jharkhand which is approx. 1250 Km away from the plant to the combustion
chamber/boiler.
 The CHP also takes care of the quality of coal . It ensures that the best quality
of coal should go for combustion.
 It also takes care of storing of coal in bunkers & reclaiming it at the time of
requirement.
 It also take cares that the calorific valve of coal should not lost during storage.
 It fulfil the need of coal according to the units operating or load.
 The function of coal handling plant is automatic feeding of coal to the boiler
furnace.
 The CHP department also takes care of Locomotives, track, and their
maintenance.
Coal Used :
 The daily coal usage in NTPC Dadri is 26000 tonnes at full
load.
 The coal used in stage 1 unit is 14000 tonnes.
 The coal used in stage 2 unit is 12000 tonnes.
 The coal grade used in NTPC is of grade 12.
COAL TRANSPORTATION
 Source of coal : Piparwar Mines ,Jharkhand)
 Means of transportation : Railway
Distance : 1250Km
Type of coal : Grade 12
C.V(calorific value) : 4600 kcal/kg.
Coal requirement : 26,000 MT/Day
Type of wagon : 1. Track Hopper
2. Wagon Tippler
Transportation of Coal
 The coal is transported by Railway. From the mines to the Dadri
Railway Station the coal is transported by Indian Railway.
 But from Dadri station to the plant the coal is transported by NTPC
own Locomotives .
 For this purpose NTPC has 6 Locomotives.
Unloading
There are two types of wagon for unloading of coal which are given below:
 Wagon Tippler
 Track Hoper
The coal is unloaded from a box type wagon by tilting it by 150deg angle.
In this type wagons have opening at sides from which coal is unloaded.
This is a slow process and usually takes 6-7 hours for unloading of
train (16-17 wagons).
In this the wagons are bottom open type.
The compressed air is used for unloading.
This is a fast process & whole train is unloaded in 1 hour.
The opening shown in the figure are 25cm wide.
The coal after passin through these opening goes
to the Hopper from where it goes to the conveyer belt.
Hopper
After coal is unloaded it goes in the hoppers from where
it goes to the conveyor belt which leading to the
crusher.
From hopper it is goes to conveyor by pedal feeder.
In this video you watch how hopper looks like $ how
conveyor is moving .
Crusher House
 Crusher house is used to crush the coal to a size of 20mm.
 It crushes the coal by hammering action which converts the 250mm coal into
20mm coal.
 Before coal goes to the crusher it passes through a vibrating mechanism
named Gizzly Feeder which separates the 20mm or less than 20mm coal and
sends it directly on the conveyor on which the coal comes after crushing in 20
mm.
 After crusher house coal goes to the mills in which the coal is further reduced
into the size of 70 microns which is like baby powder.
 Then the powdered coal goes in the furnace.
Outer part of crusher Inside view of crusher
Crusher
4/11/2018 19
Hammer
30 mm Rotor
Coal
General Layout Of CHP
4/11/2018 20
Wagon Tippler Crusher House
Bunkers
Tripper Trolley
Conv. Belts Vibrating
Screens
Crushers
Feeder Surge
Hopper
Hopper
Operational Cycle
Bunkering Cycle
Stacking Cycle
Reclaiming Cycle
4/11/2018 21
Bunkering Cycle
4/11/2018 22Bunkers
From W/T
Bunkering
Belts
Surge Hopper
Vibrating Feeder
Crusher House
Crusher
Stacking Cycle
4/11/2018 23
Bunkers
Stacking Belts
Crushed
Yard
From W/T
Crusher House
Bunkering
Belts
By-Passed Coal
Coal Is not required if
bunker is full or Due any
maintenance
Reclaiming Cycle
4/11/2018 24
Bunkers
Reclaiming Belts
Crushed
Yard
Non-
Crushed
Yard
From W/T
Crusher House
Bunkering
Belts
If Outer Supply of coal
Is Not Present
Stacked Coal
Conveyor Belt
 The speed of conveyor belt is 2.4 m/s
before going to the crusher and 2.7 m/s
after coming from crusher.
 The conveyor belt system of Ntpc is
23Km long.
 Protection System
 Interlocking
 Pull cord switch
 Belt sway switch
 Magnetic Separator
 Metal detector
4/11/2018 25
Protection System
 Pull cord switch : Pull cord switch is
used as a safety switch to stop
the conveyor emergency.
 Belt sway switch : The switch allows smooth
running of conveyor and protects it from over
swaying due to uneven loading of material.
Protection System
 Suspended Magnet is a powerful magnet which is
suspended above the conveyor belt used to remove
ferrous elements from coal.
 Magnetic Separator is used to remove metal particle
from coal conveyed through conveyor belt .
 Non Ferrous Metal Detector is used to detect non ferrous
metal from coal
moving on conveyor belt.
4/11/2018 27
Thank You

More Related Content

What's hot

NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)Rajan Kumar Choudhary
 
Ntpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILENtpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILERanjan kumar
 
NTPC MECANICAL SUMMER REPORT
NTPC MECANICAL  SUMMER REPORTNTPC MECANICAL  SUMMER REPORT
NTPC MECANICAL SUMMER REPORTAnkur Pal
 
GANESH KUMAR RAM PPT ON TTPS LALPANIA
GANESH KUMAR RAM PPT ON TTPS LALPANIAGANESH KUMAR RAM PPT ON TTPS LALPANIA
GANESH KUMAR RAM PPT ON TTPS LALPANIA1996kuldeep
 
Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)abdul mohammad
 
ntpcaniketautosaved-140928202317-phpapp01
ntpcaniketautosaved-140928202317-phpapp01ntpcaniketautosaved-140928202317-phpapp01
ntpcaniketautosaved-140928202317-phpapp01Aneek Mahata
 
Vocational training report
Vocational training reportVocational training report
Vocational training reportATUL RAJ
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
 
CONTROL AND INSTRUMENTATION OF POWER PLANT
CONTROL AND INSTRUMENTATION OF POWER PLANTCONTROL AND INSTRUMENTATION OF POWER PLANT
CONTROL AND INSTRUMENTATION OF POWER PLANTSubarna Poddar
 
Ppt on tenughat thermal power plant
Ppt on tenughat thermal power plantPpt on tenughat thermal power plant
Ppt on tenughat thermal power plantAbhinaw kapoor
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training reportsanjeevps12345
 

What's hot (20)

NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
 
Ntpc training ppt
Ntpc training pptNtpc training ppt
Ntpc training ppt
 
Ntpc training ppt
Ntpc training pptNtpc training ppt
Ntpc training ppt
 
Ntpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILENtpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILE
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
 
NTPC MECANICAL SUMMER REPORT
NTPC MECANICAL  SUMMER REPORTNTPC MECANICAL  SUMMER REPORT
NTPC MECANICAL SUMMER REPORT
 
TTPS
TTPSTTPS
TTPS
 
GANESH KUMAR RAM PPT ON TTPS LALPANIA
GANESH KUMAR RAM PPT ON TTPS LALPANIAGANESH KUMAR RAM PPT ON TTPS LALPANIA
GANESH KUMAR RAM PPT ON TTPS LALPANIA
 
Report ON NTPC DADRI .BY ....EMAM
Report ON NTPC DADRI  .BY ....EMAMReport ON NTPC DADRI  .BY ....EMAM
Report ON NTPC DADRI .BY ....EMAM
 
Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)
 
ntpcaniketautosaved-140928202317-phpapp01
ntpcaniketautosaved-140928202317-phpapp01ntpcaniketautosaved-140928202317-phpapp01
ntpcaniketautosaved-140928202317-phpapp01
 
Vocational training report
Vocational training reportVocational training report
Vocational training report
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
project -2
project -2project -2
project -2
 
ntpc unchahar
ntpc unchaharntpc unchahar
ntpc unchahar
 
CONTROL AND INSTRUMENTATION OF POWER PLANT
CONTROL AND INSTRUMENTATION OF POWER PLANTCONTROL AND INSTRUMENTATION OF POWER PLANT
CONTROL AND INSTRUMENTATION OF POWER PLANT
 
FIELD EXPERIENCE RK
FIELD EXPERIENCE RKFIELD EXPERIENCE RK
FIELD EXPERIENCE RK
 
Ppt on tenughat thermal power plant
Ppt on tenughat thermal power plantPpt on tenughat thermal power plant
Ppt on tenughat thermal power plant
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training report
 
report on ntpc plant
report on ntpc plantreport on ntpc plant
report on ntpc plant
 

Similar to Training chp

Coal Fired Thermal Power Plants
Coal Fired Thermal Power Plants Coal Fired Thermal Power Plants
Coal Fired Thermal Power Plants Arnab Nandi
 
report on adani UPCL
report on adani UPCLreport on adani UPCL
report on adani UPCLAquib Nadaf
 
Steam thermal power plant(panki)
Steam thermal power plant(panki)Steam thermal power plant(panki)
Steam thermal power plant(panki)Ranjeet Kumar
 
GANDHINAGAR THERMAL POWERPLANT
GANDHINAGAR THERMAL POWERPLANTGANDHINAGAR THERMAL POWERPLANT
GANDHINAGAR THERMAL POWERPLANTNiravDesai66
 
Coal handling plant
Coal handling plantCoal handling plant
Coal handling plantRohit Khatri
 
Dankuni Coal Complex
Dankuni Coal ComplexDankuni Coal Complex
Dankuni Coal ComplexKumar Saurabh
 
Surathgarh thermal powerplant
Surathgarh thermal powerplantSurathgarh thermal powerplant
Surathgarh thermal powerplantAAKASH DEEP SINGH
 
Black diamond logistic outlook
Black diamond logistic outlookBlack diamond logistic outlook
Black diamond logistic outlookAbhijat Dhawal
 
1.Steam Thermal Power Plant and Coal Handling
1.Steam Thermal Power Plant and Coal Handling1.Steam Thermal Power Plant and Coal Handling
1.Steam Thermal Power Plant and Coal HandlingNani Thirupathi
 
COAL HANDLING PLANT
COAL  HANDLING PLANTCOAL  HANDLING PLANT
COAL HANDLING PLANTpulak126
 
Themal power plant NTPC
Themal power plant NTPCThemal power plant NTPC
Themal power plant NTPCRahul Kurapati
 
TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant vishal patel
 
(Keshav) report file on kali sindh thermal power project, jhalawar
(Keshav) report file on kali sindh thermal power project, jhalawar(Keshav) report file on kali sindh thermal power project, jhalawar
(Keshav) report file on kali sindh thermal power project, jhalawarKeshav Meena
 
SURATGARH SUPER THERMAL POWER STATION
SURATGARH  SUPER  THERMAL POWER    STATION SURATGARH  SUPER  THERMAL POWER    STATION
SURATGARH SUPER THERMAL POWER STATION Sagar Sharma
 

Similar to Training chp (20)

Coal Fired Thermal Power Plants
Coal Fired Thermal Power Plants Coal Fired Thermal Power Plants
Coal Fired Thermal Power Plants
 
report on adani UPCL
report on adani UPCLreport on adani UPCL
report on adani UPCL
 
Steam thermal power plant(panki)
Steam thermal power plant(panki)Steam thermal power plant(panki)
Steam thermal power plant(panki)
 
Ntpc report harsh
Ntpc report  harshNtpc report  harsh
Ntpc report harsh
 
Nitin
NitinNitin
Nitin
 
GANDHINAGAR THERMAL POWERPLANT
GANDHINAGAR THERMAL POWERPLANTGANDHINAGAR THERMAL POWERPLANT
GANDHINAGAR THERMAL POWERPLANT
 
Coal handling plant
Coal handling plantCoal handling plant
Coal handling plant
 
Dankuni Coal Complex
Dankuni Coal ComplexDankuni Coal Complex
Dankuni Coal Complex
 
Surathgarh thermal powerplant
Surathgarh thermal powerplantSurathgarh thermal powerplant
Surathgarh thermal powerplant
 
Black diamond logistic outlook
Black diamond logistic outlookBlack diamond logistic outlook
Black diamond logistic outlook
 
Stps report
Stps reportStps report
Stps report
 
1.Steam Thermal Power Plant and Coal Handling
1.Steam Thermal Power Plant and Coal Handling1.Steam Thermal Power Plant and Coal Handling
1.Steam Thermal Power Plant and Coal Handling
 
COAL HANDLING PLANT
COAL  HANDLING PLANTCOAL  HANDLING PLANT
COAL HANDLING PLANT
 
Dankuni Coal Complex
Dankuni Coal ComplexDankuni Coal Complex
Dankuni Coal Complex
 
Sourish bhattacharyya
Sourish bhattacharyyaSourish bhattacharyya
Sourish bhattacharyya
 
Themal power plant NTPC
Themal power plant NTPCThemal power plant NTPC
Themal power plant NTPC
 
TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant
 
(Keshav) report file on kali sindh thermal power project, jhalawar
(Keshav) report file on kali sindh thermal power project, jhalawar(Keshav) report file on kali sindh thermal power project, jhalawar
(Keshav) report file on kali sindh thermal power project, jhalawar
 
NTPC Dadri Gas plant
NTPC Dadri Gas plantNTPC Dadri Gas plant
NTPC Dadri Gas plant
 
SURATGARH SUPER THERMAL POWER STATION
SURATGARH  SUPER  THERMAL POWER    STATION SURATGARH  SUPER  THERMAL POWER    STATION
SURATGARH SUPER THERMAL POWER STATION
 

Recently uploaded

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 

Recently uploaded (20)

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 

Training chp

  • 1. ABESIT PRESENTATION BY : RADHEY LAL Roll No. : 1429040081 Section : 4th Year, ME-B2 Seminar presentation PRESENTED TO : Mr. Amit gupta
  • 2. NTPC Dadri CHP (Coal Handling Plant) Department Presentation on :
  • 3. Diagram of a typical coal-fired thermal power station
  • 4. About NTPC  NTPC, the largest power Company in India, was setup in 1975 to accelerate power development in the country.  NTPC has installed capacity of 41,684 MW.  NTPC ranked 300th in the ‘2013, Forbes Global 2000’ ranking of the World’s biggest companies.  NTPC plans to become a 128,000 MW company by 2032.  It has 16 coal based power stations (23,395 MW)  7 gas based power stations (3,955 MW)  4 power stations in Joint Ventures (1,794 MW).  NTPC has been awarded NO-1,best workplace in India among large organization and the best PSU for the year 2010.
  • 5. History  NTPC Dadri plant and township are property of ntpc ltd and were built around 1988-1990.  It was commissioned in 1991. NTPC Dadri is a branch of National Thermal Power Corporation, which is a public sector now. It is about 20 km from Ghaziabad via Badalpur, Mahawar, Bamabawar, and Akilpur Jagir. Continued..
  • 6. Capacity  NTPC Dadri is a unique power plant of NTPC group which has both coal based thermal plant and gas based thermal plant of 1820 MW and 817 MW respectively and 5 MW solar plant .  Coal based : Stage Unit Number Installed Capacity (MW) Date of Commissioning 1st 1 210 1991 October 2 210 1992 December 3 210 1993 March 4 210 1994 March 2nd 5 490 2010 January 6 490 2010 July Total Six 1820
  • 7.  Gas based : NTPC dadri also produces electricity by gas. The details of gas power plant are given below in the table. Stage Unit Number Installed Capacity (MW) Date of Commissioning Gas Turbine / Steam Turbine 1st 1 130.19 1992 March GT 2 130.19 1992 May GT 3 130.19 1992 June GT 4 130.19 1992 November GT 5 154.51 1993 February ST 6 154.51 1993 March ST Total six 829.78
  • 8. Total capacity of the plant is 2649 MW.
  • 9. NTPC distributes to:  Its mainly distributes most of its electricity to Delhi.  And it also distributes some part of it electricity to Uttar Pradesh, Uttarakhand and Haryana . NTPC Dadri gets:  Coal from Piparwar Mines ,Jharkhand .  Gas from GAIL Hajira-Bijapur-Jagdispur (HBL) pipeline.  Water from Upper Ganges Canal.
  • 10. CHP (Coal Handling Plant)  The role of CHP is to meet the demand of coal.  It is the responsibility of CHP to take care of coal from Piparwar Mines , Jharkhand which is approx. 1250 Km away from the plant to the combustion chamber/boiler.  The CHP also takes care of the quality of coal . It ensures that the best quality of coal should go for combustion.  It also takes care of storing of coal in bunkers & reclaiming it at the time of requirement.  It also take cares that the calorific valve of coal should not lost during storage.  It fulfil the need of coal according to the units operating or load.  The function of coal handling plant is automatic feeding of coal to the boiler furnace.  The CHP department also takes care of Locomotives, track, and their maintenance.
  • 11. Coal Used :  The daily coal usage in NTPC Dadri is 26000 tonnes at full load.  The coal used in stage 1 unit is 14000 tonnes.  The coal used in stage 2 unit is 12000 tonnes.  The coal grade used in NTPC is of grade 12.
  • 12. COAL TRANSPORTATION  Source of coal : Piparwar Mines ,Jharkhand)  Means of transportation : Railway Distance : 1250Km Type of coal : Grade 12 C.V(calorific value) : 4600 kcal/kg. Coal requirement : 26,000 MT/Day Type of wagon : 1. Track Hopper 2. Wagon Tippler
  • 13. Transportation of Coal  The coal is transported by Railway. From the mines to the Dadri Railway Station the coal is transported by Indian Railway.  But from Dadri station to the plant the coal is transported by NTPC own Locomotives .  For this purpose NTPC has 6 Locomotives. Unloading There are two types of wagon for unloading of coal which are given below:  Wagon Tippler  Track Hoper
  • 14. The coal is unloaded from a box type wagon by tilting it by 150deg angle. In this type wagons have opening at sides from which coal is unloaded. This is a slow process and usually takes 6-7 hours for unloading of train (16-17 wagons).
  • 15. In this the wagons are bottom open type. The compressed air is used for unloading. This is a fast process & whole train is unloaded in 1 hour. The opening shown in the figure are 25cm wide. The coal after passin through these opening goes to the Hopper from where it goes to the conveyer belt.
  • 16. Hopper After coal is unloaded it goes in the hoppers from where it goes to the conveyor belt which leading to the crusher. From hopper it is goes to conveyor by pedal feeder. In this video you watch how hopper looks like $ how conveyor is moving .
  • 17. Crusher House  Crusher house is used to crush the coal to a size of 20mm.  It crushes the coal by hammering action which converts the 250mm coal into 20mm coal.  Before coal goes to the crusher it passes through a vibrating mechanism named Gizzly Feeder which separates the 20mm or less than 20mm coal and sends it directly on the conveyor on which the coal comes after crushing in 20 mm.  After crusher house coal goes to the mills in which the coal is further reduced into the size of 70 microns which is like baby powder.  Then the powdered coal goes in the furnace.
  • 18. Outer part of crusher Inside view of crusher
  • 20. General Layout Of CHP 4/11/2018 20 Wagon Tippler Crusher House Bunkers Tripper Trolley Conv. Belts Vibrating Screens Crushers Feeder Surge Hopper Hopper
  • 21. Operational Cycle Bunkering Cycle Stacking Cycle Reclaiming Cycle 4/11/2018 21
  • 22. Bunkering Cycle 4/11/2018 22Bunkers From W/T Bunkering Belts Surge Hopper Vibrating Feeder Crusher House Crusher
  • 23. Stacking Cycle 4/11/2018 23 Bunkers Stacking Belts Crushed Yard From W/T Crusher House Bunkering Belts By-Passed Coal Coal Is not required if bunker is full or Due any maintenance
  • 24. Reclaiming Cycle 4/11/2018 24 Bunkers Reclaiming Belts Crushed Yard Non- Crushed Yard From W/T Crusher House Bunkering Belts If Outer Supply of coal Is Not Present Stacked Coal
  • 25. Conveyor Belt  The speed of conveyor belt is 2.4 m/s before going to the crusher and 2.7 m/s after coming from crusher.  The conveyor belt system of Ntpc is 23Km long.  Protection System  Interlocking  Pull cord switch  Belt sway switch  Magnetic Separator  Metal detector 4/11/2018 25
  • 26. Protection System  Pull cord switch : Pull cord switch is used as a safety switch to stop the conveyor emergency.  Belt sway switch : The switch allows smooth running of conveyor and protects it from over swaying due to uneven loading of material.
  • 27. Protection System  Suspended Magnet is a powerful magnet which is suspended above the conveyor belt used to remove ferrous elements from coal.  Magnetic Separator is used to remove metal particle from coal conveyed through conveyor belt .  Non Ferrous Metal Detector is used to detect non ferrous metal from coal moving on conveyor belt. 4/11/2018 27