2. TRANSPOTATION AND INSTALLATION SERVICES FOR
ST-PIP’S JACKET AND ITS APPURTENANCES
SCOPE OF WORK:
T&I
SCOPE
JACKET weight 2378 Ton
with launching method.
4 Piles OD 1829mm
Total weight is 1567 Tons
03 conductors OD 762mm
Total weight is 270 Tons
01 Drilling deck
Weight 22ton
3. 3
MILESTONE COMPLETION OF T&I SERVICES FOR ST-PIP’S JACKET AND ITS
APPURTENANCES
STT Description
Key Milestone
Sub Contract
Actual
Milestone
01-01 Effective Date 27 Apr 2015 27 Apr 2015
01-04a
MCD of ST-PIP’s Jacket and its
appurtenance
15 Aug 2015 15 Aug 2015
02-07 ST-PIP’s Jacket ready for Sail-away 31 Aug 2015 03 Sep 2015
02-08
Mobilization at Offshore Site of
installation Spread
05 Sep 2015 04 Sep 2015
02-09
Complete piling and Conductors
installation for ST-PIP’s Jacket
29 Sep 2015 01 Oct 2015
02-10 Handover of ST-PIP Jacket 30 Sep 2015 3 Oct 2015
TRANSPOTATION AND INSTALLATION SERVICES FOR
ST-PIP’S JACKET AND ITS APPURTENANCES
MILESTONE COMPLETION: