SlideShare a Scribd company logo
1 of 23
Module 1 - Introduction
• Definition of project
• Project management
• Project life cycle
• Project types
• Project overruns
• Role, responsibilities, demands on project manager
Projects
• Any new structure, plant, process, system or software,
large or small, or the replacement, refurbishing,
renewal or removal of an existing one
• Every new design of car, aircraft, ship, refrigerator,
computer, crane, steel mill, refinery, production line,
sewer, road, bridge, dock, dam, power station, control
system, building or software package is a project.
Use of ‘Project’ for all these is logical because each is
• An investment of resources for an objective
• A cause of irreversible change
• Novel to some degree
• Concerned with the future
• Related to an expected result
• Criterion to invest in a project is that the goods or
services produced are more valuable than the
predicted cost of the project
• Project usually has a defined date of completion
• The work for project is a period of intense engineering
and other activities but is short in duration relative to
the subsequent working life of the investment
‘Project’ - Definitions
• ‘a temporary endeavor undertaken to create a unique product or
service’
• ‘a discrete undertaking with defined objectives often including time,
cost and quality goals’
• ‘a unique set of coordinated activities, with definite starting and
finishing points, undertaken by an individual or organization to meet
specific objectives with defined schedule, cost and performance
parameters’
‘Project’ - Characteristics
• It is temporary – having a start and finish
• Is unique in some way
• Has specific objectives
• Is the cause and means of change
• Involves risk and uncertainty
• Involves the commitment of human, material and
financial resources
Project Management
•PM implies some form of control over the
planned process of explicit change
•PM is the management of change, but explicitly
planned change, such that from the initial
concept, the change is directed towards the
unique creation of a functioning system
PM - Definition
•‘the art of directing and coordinating human and
material resources through the life of a project
by using modern management techniques to
achieve predetermined goals of scope, cost,
time, quality and participant satisfaction’
• ‘the planning, organization, monitoring and control of
all aspects of a project and all the motivation of all
involved to achieve project objectives safely and
within agreed time, cost and performance criteria’
• ‘ the planning, monitoring and control of all aspects of
a project and the motivation of all those involved to
achieve the project objectives on time and to cost,
quality and performance’
Project Life Cycle
• Each project has a beginning and an end
• Nature & scale of activities change at each stage
• Duration of the stages vary from project to project
• Stages can also overlap
Project Types
1. Civil Engineering, Construction, Petrochemical, Mining and
Quarrying
2. Manufacturing Projects
3. Management Projects
Civil Engineering, Construction, Petrochemical,
Mining and Quarrying
• These spring to mind most readily whenever industrial projects are
mentioned
• They incur special risks and problems of organization
• Require massive capital investment and rigorous management of
progress finance and quality
Manufacturing Projects
• Aims to produce a piece of equipment or machinery, ship, aircraft,
land vehicle or some other item of specially designed hardware
Management Projects
• Every company can expect to need project management expertise at
least once in its lifetime
• These are projects that arise when companies
a) relocate their headquarters,
b) develop and introduce a new computer system
c) Launch a marketing campaign
d) Prepare a feasibility report
e) Restructure the organisation
Project Overruns
• Project Overrun (Cost increase or budget overrun) means a budget
deficit that occurs in a result of unexpected costs
• Reasons:-
a) Underestimation of project costs
b) Overlooking project risks
c) Project Creep – Changing work content while the project is already
in progress
d) Poor performance of team members
Project Manager
• PM will take responsibility for planning, implementing and completing
the project
• Selection of project manager is one of the two or three most
important decisions concerning the project
Attributes, Skills & Qualities of PM
• A strong technical background
• A hard nosed manager
• A mature individual
• Someone who is currently available
• Someone on good terms with senior executives
• A person who can keep the project team happy
• One who has worked in several different departments
The best PM is the one who
can get the job done!!!!
• Hard workers are easy to find
• What is rare is the individual whose focus is one the
completion of a difficult job
• This drive to complete the tasks is the most important
• The PM must be competent in the science of project
management, but this is not sufficient
• The PM must also have technical competence in some
aspects of the work being performed on the project
Four major skills for PM
(with a powerful bias towards work completion)
• Credibility – Technical & Administrative
• Sensitivity – PM needs to sense interpersonal conflicts on the project
team or between team members and outsiders
• Leadership and Management style – PM must capitalize on people’s
strengths, cover their weaknesses, know when to take over and when
to give the team its head, know when to punish, when to
communicate, when to reward and when to remain silent
• Ability to handle stress
Responsibilities of PM
• Responsibility to the parent organization
• Responsibility to the project and client
• Responsibility to the members of the project team
• To prepare a preliminary budget and schedule
• To help select people to serve on the project team
• To get to know the client
• To make sure that proper facilities are available
• To ensure that any supplies required in the project life are
available
• To take care of routine details necessary to get the project
moving

More Related Content

Similar to PEEM 2.pptx

Lecture 1- Introduction.pptx
Lecture 1- Introduction.pptxLecture 1- Introduction.pptx
Lecture 1- Introduction.pptxPrabin Pandit
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptxProfDrAnbalaganChinn
 
Chapter-1-Introduction.pdf
Chapter-1-Introduction.pdfChapter-1-Introduction.pdf
Chapter-1-Introduction.pdfssuser8bc44e
 
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesOm lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesvideoaakash15
 
Fundamentals of aviation project management
Fundamentals of aviation project managementFundamentals of aviation project management
Fundamentals of aviation project managementPartha Chakraborty
 
BASICS OF PROJECT MANAGEMENT
BASICS OF PROJECT MANAGEMENTBASICS OF PROJECT MANAGEMENT
BASICS OF PROJECT MANAGEMENTNiruban Projoth
 
Project Management
Project ManagementProject Management
Project ManagementXubitech
 
Software Project Management Basics
Software Project Management BasicsSoftware Project Management Basics
Software Project Management BasicsAmarjeet Singh
 
Role of project management in construction industry by Engineer Muhammad Kama...
Role of project management in construction industry by Engineer Muhammad Kama...Role of project management in construction industry by Engineer Muhammad Kama...
Role of project management in construction industry by Engineer Muhammad Kama...Kamal787
 
Project Management
Project ManagementProject Management
Project ManagementAtif Rehmat
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
INTRODUCTION TO PROJECT MANAGMENT
INTRODUCTION TO PROJECT MANAGMENT INTRODUCTION TO PROJECT MANAGMENT
INTRODUCTION TO PROJECT MANAGMENT Harihara puthiran
 

Similar to PEEM 2.pptx (20)

Lecture 1- Introduction.pptx
Lecture 1- Introduction.pptxLecture 1- Introduction.pptx
Lecture 1- Introduction.pptx
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx
 
PME UNIT-3.pptx
PME UNIT-3.pptxPME UNIT-3.pptx
PME UNIT-3.pptx
 
Chapter-1-Introduction.pdf
Chapter-1-Introduction.pdfChapter-1-Introduction.pdf
Chapter-1-Introduction.pdf
 
Project Managemet Basics
Project Managemet BasicsProject Managemet Basics
Project Managemet Basics
 
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesOm lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
 
Fundamentals of aviation project management
Fundamentals of aviation project managementFundamentals of aviation project management
Fundamentals of aviation project management
 
BASICS OF PROJECT MANAGEMENT
BASICS OF PROJECT MANAGEMENTBASICS OF PROJECT MANAGEMENT
BASICS OF PROJECT MANAGEMENT
 
Pe ch 1
Pe ch   1Pe ch   1
Pe ch 1
 
Project Management
Project ManagementProject Management
Project Management
 
PM Related Info
PM Related InfoPM Related Info
PM Related Info
 
Pm
PmPm
Pm
 
Software Project Management Basics
Software Project Management BasicsSoftware Project Management Basics
Software Project Management Basics
 
Project cycle
Project cycleProject cycle
Project cycle
 
Role of project management in construction industry by Engineer Muhammad Kama...
Role of project management in construction industry by Engineer Muhammad Kama...Role of project management in construction industry by Engineer Muhammad Kama...
Role of project management in construction industry by Engineer Muhammad Kama...
 
Project management
Project managementProject management
Project management
 
Project Management
Project ManagementProject Management
Project Management
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
INTRODUCTION TO PROJECT MANAGMENT
INTRODUCTION TO PROJECT MANAGMENT INTRODUCTION TO PROJECT MANAGMENT
INTRODUCTION TO PROJECT MANAGMENT
 
Session 2 mod 2 proj mgt
Session 2 mod 2 proj mgtSession 2 mod 2 proj mgt
Session 2 mod 2 proj mgt
 

More from PradeepTalwelkar (20)

PEEM 5.pptx
PEEM 5.pptxPEEM 5.pptx
PEEM 5.pptx
 
PEEM 4.pptx
PEEM 4.pptxPEEM 4.pptx
PEEM 4.pptx
 
PEEM 3.pptx
PEEM 3.pptxPEEM 3.pptx
PEEM 3.pptx
 
CEE 20.pptx
CEE 20.pptxCEE 20.pptx
CEE 20.pptx
 
CEE 19.pptx
CEE 19.pptxCEE 19.pptx
CEE 19.pptx
 
CEE 18.pptx
CEE 18.pptxCEE 18.pptx
CEE 18.pptx
 
CEE 17.pptx
CEE 17.pptxCEE 17.pptx
CEE 17.pptx
 
Cost & Asset Accounting.pptx
Cost & Asset Accounting.pptxCost & Asset Accounting.pptx
Cost & Asset Accounting.pptx
 
CEE 16.pptx
CEE 16.pptxCEE 16.pptx
CEE 16.pptx
 
CEE 15.pptx
CEE 15.pptxCEE 15.pptx
CEE 15.pptx
 
CEE 14.pptx
CEE 14.pptxCEE 14.pptx
CEE 14.pptx
 
CEE 13.pptx
CEE 13.pptxCEE 13.pptx
CEE 13.pptx
 
CEE 12.pptx
CEE 12.pptxCEE 12.pptx
CEE 12.pptx
 
CEE 11.pptx
CEE 11.pptxCEE 11.pptx
CEE 11.pptx
 
CEE 10.pptx
CEE 10.pptxCEE 10.pptx
CEE 10.pptx
 
CEE 8.pptx
CEE 8.pptxCEE 8.pptx
CEE 8.pptx
 
CEE 7.pptx
CEE 7.pptxCEE 7.pptx
CEE 7.pptx
 
CEE 6.pptx
CEE 6.pptxCEE 6.pptx
CEE 6.pptx
 
CEE 5.pptx
CEE 5.pptxCEE 5.pptx
CEE 5.pptx
 
CEE 4.pptx
CEE 4.pptxCEE 4.pptx
CEE 4.pptx
 

Recently uploaded

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 

Recently uploaded (20)

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 

PEEM 2.pptx

  • 1. Module 1 - Introduction • Definition of project • Project management • Project life cycle • Project types • Project overruns • Role, responsibilities, demands on project manager
  • 2. Projects • Any new structure, plant, process, system or software, large or small, or the replacement, refurbishing, renewal or removal of an existing one • Every new design of car, aircraft, ship, refrigerator, computer, crane, steel mill, refinery, production line, sewer, road, bridge, dock, dam, power station, control system, building or software package is a project.
  • 3. Use of ‘Project’ for all these is logical because each is • An investment of resources for an objective • A cause of irreversible change • Novel to some degree • Concerned with the future • Related to an expected result
  • 4. • Criterion to invest in a project is that the goods or services produced are more valuable than the predicted cost of the project • Project usually has a defined date of completion • The work for project is a period of intense engineering and other activities but is short in duration relative to the subsequent working life of the investment
  • 5. ‘Project’ - Definitions • ‘a temporary endeavor undertaken to create a unique product or service’ • ‘a discrete undertaking with defined objectives often including time, cost and quality goals’ • ‘a unique set of coordinated activities, with definite starting and finishing points, undertaken by an individual or organization to meet specific objectives with defined schedule, cost and performance parameters’
  • 6. ‘Project’ - Characteristics • It is temporary – having a start and finish • Is unique in some way • Has specific objectives • Is the cause and means of change • Involves risk and uncertainty • Involves the commitment of human, material and financial resources
  • 7. Project Management •PM implies some form of control over the planned process of explicit change •PM is the management of change, but explicitly planned change, such that from the initial concept, the change is directed towards the unique creation of a functioning system
  • 8. PM - Definition •‘the art of directing and coordinating human and material resources through the life of a project by using modern management techniques to achieve predetermined goals of scope, cost, time, quality and participant satisfaction’
  • 9. • ‘the planning, organization, monitoring and control of all aspects of a project and all the motivation of all involved to achieve project objectives safely and within agreed time, cost and performance criteria’ • ‘ the planning, monitoring and control of all aspects of a project and the motivation of all those involved to achieve the project objectives on time and to cost, quality and performance’
  • 10.
  • 11. Project Life Cycle • Each project has a beginning and an end • Nature & scale of activities change at each stage • Duration of the stages vary from project to project • Stages can also overlap
  • 12. Project Types 1. Civil Engineering, Construction, Petrochemical, Mining and Quarrying 2. Manufacturing Projects 3. Management Projects
  • 13. Civil Engineering, Construction, Petrochemical, Mining and Quarrying • These spring to mind most readily whenever industrial projects are mentioned • They incur special risks and problems of organization • Require massive capital investment and rigorous management of progress finance and quality
  • 14. Manufacturing Projects • Aims to produce a piece of equipment or machinery, ship, aircraft, land vehicle or some other item of specially designed hardware
  • 15. Management Projects • Every company can expect to need project management expertise at least once in its lifetime • These are projects that arise when companies a) relocate their headquarters, b) develop and introduce a new computer system c) Launch a marketing campaign d) Prepare a feasibility report e) Restructure the organisation
  • 16. Project Overruns • Project Overrun (Cost increase or budget overrun) means a budget deficit that occurs in a result of unexpected costs • Reasons:- a) Underestimation of project costs b) Overlooking project risks c) Project Creep – Changing work content while the project is already in progress d) Poor performance of team members
  • 17. Project Manager • PM will take responsibility for planning, implementing and completing the project • Selection of project manager is one of the two or three most important decisions concerning the project
  • 18. Attributes, Skills & Qualities of PM • A strong technical background • A hard nosed manager • A mature individual • Someone who is currently available • Someone on good terms with senior executives • A person who can keep the project team happy • One who has worked in several different departments
  • 19. The best PM is the one who can get the job done!!!!
  • 20. • Hard workers are easy to find • What is rare is the individual whose focus is one the completion of a difficult job • This drive to complete the tasks is the most important • The PM must be competent in the science of project management, but this is not sufficient • The PM must also have technical competence in some aspects of the work being performed on the project
  • 21. Four major skills for PM (with a powerful bias towards work completion) • Credibility – Technical & Administrative • Sensitivity – PM needs to sense interpersonal conflicts on the project team or between team members and outsiders • Leadership and Management style – PM must capitalize on people’s strengths, cover their weaknesses, know when to take over and when to give the team its head, know when to punish, when to communicate, when to reward and when to remain silent • Ability to handle stress
  • 22. Responsibilities of PM • Responsibility to the parent organization • Responsibility to the project and client • Responsibility to the members of the project team
  • 23. • To prepare a preliminary budget and schedule • To help select people to serve on the project team • To get to know the client • To make sure that proper facilities are available • To ensure that any supplies required in the project life are available • To take care of routine details necessary to get the project moving