SlideShare a Scribd company logo
1 of 34
In Pursuit of Perfection: Internal
Auditors the gatekeeper of
Business Ethics in Jamaica.
"Integrating Project Management Techniques for Internal
Auditing"
Cyberdyne Business Solutions
AGENDA
• Background
• Management Dilemma and Solutions
• Roles, Function and Reporting
Relationship of an Internal Auditor
• Project Management Overview
Cyberdyne Business Solutions
Definitions
• Business ethics are moral principles that
guide the way a business behaves. The
same principles that determine an
individual’s actions also apply to business.
Cyberdyne Business Solutions
Monitoring Of Construction
Contracts
• During the 2012 calendar year, the Construction Contracts
Division of the Office of the Contractor General (OCG)
monitored the Pre and Post Contract stages of three hundred
and sixty seven (367) contracts. As such, there was a 10.5%
decrease in the number of works contracts which were
monitored for the year 2012, in comparison to the previous
year in which four hundred and ten (410) contracts were
monitored.
• It must be noted that the NCC, during the year, endorsed a
total of one hundred and forty eight (148) works contracts
which had an aggregate value of J$10,314,568,600.00, of
which fifty-two (52) were monitored by the Construction
Contracts Division. (Harrison, 2012)
Cyberdyne Business Solutions
Monitoring Of Non-construction Contracts,
Licenses, Permits And
Concessions
• The Division monitored approximately six hundred (600)
opportunities/contracts during the calendar year 2012, in
comparison to six hundred and eighty-two (682) procurement
opportunities/contracts which were monitored in 2011. This
represents a twelve percent (12%) decrease in the number of
non-construction contracts and license which were monitored
over the corresponding period.
• Of the 600 opportunities/contracts which were monitored
during the year, four hundred and sixty three (463) represents
monitoring assignments which were carried forward from
2011. The remaining one hundred and thirty-seven (137) or
approximately twenty three percent (23%) represents new
monitoring assignments during 2012. (Harrison, 2012)
Cyberdyne Business Solutions
Problem Set
• A company has been working on the development
of an advance product for the last three years at a
cost of $2 Million. Under the original plans, the
project should have been completed and the
payback (new revenues and/or cost savings) should
have started six months ago. So far, the delay has
run an anticipated additional cost of $500,000, and,
with no end in sight, management is getting edgy.
Should it terminate the project or budget additional
funds to continue work?
Cyberdyne Business Solutions
Management Dilemma
Management Facts:
•Decision to continue supplying funds,
manpower and facilities or whether to kill the
project based on current status of project.
•No one has sufficient, reliable information
into what has been accomplished or what to
expect in the future
Cyberdyne Business Solutions
Solutions
• Experience has shown that skills and
methodology used in financial auditing are
adaptable to the review and audit needs of
development projects and technical work.
• Assessment based on technical
competence alone often fail to further
furnish management with the data
necessary for decision making. (Ross, 1976)
Cyberdyne Business Solutions
Definition of Internal Auditing
• According to Institute of Internal Auditors
(IIA) - "Internal auditing is an independent,
objective assurance and consulting activity
designed to add value and improve an
organization's operations. It helps an
organisation accomplish its objectives by
bringing a systematic, disciplined approach to
evaluate and improve the effectiveness of risk
management, control, and governance
processes." (Deloit, 2014)
Cyberdyne Business Solutions
Major roles and responsibilities
of internal audit function
• evaluates and provides reasonable assurance that risk
management, control, and governance systems are
functioning as intended and will enable the organization's
objectives and goals to be met
• reports risk management issues and internal controls
deficiencies identified directly to the audit committee and
provides recommendations for improving the
organization's operations, in terms of both efficient and
effective performance
• evaluates information security and associated risk
exposures. (Deloit, 2014).
Cyberdyne Business Solutions
Major roles and responsibilities
of internal audit function (cont.)
• evaluates regulatory compliance program with consultation
from legal counsel
• evaluates the organization's readiness in case of business
interruption
• maintains open communication with management and the
audit committee
• teams with other internal and external resources as
appropriate
• engages in continuous education and staff development
• provides support to the company's anti-fraud programs.
(Deloit, 2014)
Cyberdyne Business Solutions
Reporting Structure of
Internal Audit Function
• In most companies, the internal auditor traditionally
reported to either the Chief Financial Officer or the Chief
Risk Officer, though other may have existed in some
companies. Today, the internal auditor may either report
directly to the Audit Committee, or the Audit Committee
will have a role in hiring, firing, evaluating and
compensating the Chief Audit Officer. The Audit
Committee’s increasing role with regard to the internal
audit is being undertaken to help ensure the internal
auditor’s "independence" and objectivity.
• The relationship between the Audit Committee and the
internal audit function should be clearly defined and
addressed in the Audit Committee’s charter.
Cyberdyne Business Solutions
Project Overview
• Project - A project is temporary in that it has a
defined beginning and end in time, and therefore
defined scope and resources.
• Project Manager – A PM is assigned by an
organization to achieve the specified objectives of a
project within the competing project constraints. The
role of the project manager is different from a
functional manager or an operations manager.
Depending on the organizational structure, the project
manager may be reporting to a functional manager or
a program manager or a portfolio manager.
Cyberdyne Business Solutions
Organisation Type:
Functional
A hierarchical organization where each employee has one clear superior,
staff are grouped by areas of specialization, and managed by a person
with expertise in that area.
Cyberdyne Business Solutions
Organisation Type: Weak
A project manager (often called a project administrator under this type of
organization) with only limited authority is assigned to oversee the
cross-functional aspects of the project.
Cyberdyne Business Solutions
Organisation Type: Weak
Matrix
A project manager (often called a project administrator under this type of
organization) with only limited authority is assigned to oversee the
cross-functional aspects of the project. The functional managers
maintain control over their resources and project areas.
Cyberdyne Business Solutions
Organisation Type: Balanced
Matrix
A project manager is assigned to oversee the project. Power is shared equally
between the project manager and the functional managers.
Cyberdyne Business Solutions
Organisation Type: Strong
Matrix
A project manager is primarily responsible for the project. Functional managers
provide technical expertise and assign resources on an as-needed basis.
Because project resources are assigned as necessary there can be conflicts
between the project manager and the functional manager over resource
assignment.
Cyberdyne Business Solutions
Organisation Type:
Projectised
an organizational structure in which the project manager has full authority
to assign priorities, apply resources, and direct the work of persons
assigned to the project.
Cyberdyne Business Solutions
Defining Organisation
Structure
Cyberdyne Business Solutions
5 PROCESSES GROUPS
• Initiating –
– Formal process recognize a new project
– Stakeholders are identified
– Commitment is obtained
• Planning –
– The use of resources to plan and subsequently report
progress within the project environment
• Executing –
– The actual work on the tasks planned
• Controlling and Monitoring –
– To provide an understanding of the project’s progress so that
appropriate corrective actions can be taken
• Closing –
– Those processes performed to formally terminate all activities
of a project or phase, and transfer the completed product to
others or to close a cancelled project
Cyberdyne Business Solutions
10 Knowledge Areas
• Project Integration Management - All Areas
• Project Scope Management - Requirements
• Project Time Management - Schedule
• Project Cost Management - Budget
• Project Quality Management – Final product outcome
• Project Human Resource Management - People
• Project Communications Management – Info. Delivery
• Project Risk Management – Measure/ Countermeasures
• Project Procurement Management – Goods/services
• Project Stakeholder Management - Stakeholder Analysis
Cyberdyne Business Solutions
Project Integration
Management
• Primarily concerned with effectively
integrating the process among the project
management process groups that are
required to accomplish the project
objective within an organisation’s defined
procedure
Cyberdyne Business Solutions
Project Scope Management
• Scope Management is the process of
defining what work is required and then
making sure all of that work is done – and
only that work is done.
• Scope refers to all the work involved in
creating the deliverables of the project and
the process used to create them
Cyberdyne Business Solutions
Project Time Management
• Time management is an essentially significant
ability for any efficient project manager. Project
managers, who are successful in controlling the
schedule, are usually able to manage the
budget, since schedule has a direct influence on
the project budget. The most common reasons
of going over budget in projects are due to
improper management of schedule. -
Cyberdyne Business Solutions
Project Cost Management
• Project Cost Management includes those
processes involved in planning,
estimating, budgeting, monitoring and
controlling costs. The ultimate goal of
project cost management is to complete
the project within the approved budget.
Cyberdyne Business Solutions
Project Quality Management
• Quality is defined as the degree to which
the project fulfills its requirements
• Quality Management includes creating
and following policies and procedures to
ensure that a project meets from the
customers perspective
• A lack of attension to quality means
rework or defects
Cyberdyne Business Solutions
Project Human Resource
Management
• The Human Resource management
process takes time and effort to plan how
you will involve people, identify the team
members you will need, define everyone’s
roles, create reward systems, improve
team member’s performance individually
and a team, and track performance.
Cyberdyne Business Solutions
Project Communication
Management
• The Plan Communication Management
process considers how to store, maintain,
distribute, and retrieve information and
what will happen to all the project
information once the project is closed.
Cyberdyne Business Solutions
Project Risk Management
• Risk Management includes Risk
Management, Risk Identification, the
qualitative and quantitative analysis of risk
response, planning and monitoring and
control of risk response.
Cyberdyne Business Solutions
Project Procurement
Management
• Procurement is a formal process to obtain goods
and services.
• Private companies have a lot of flexibility in their
procurement practices.
• Government entities are spending public funds,
they have to comply with laws, rules, and
regulations that specifically govern each step of
the procurement process
Cyberdyne Business Solutions
Project Stakeholder
Management
• Identifies the people, groups, or
organisations that could impact or be
impacted by the project
• Analyse stakeholder expectations and
their impact on the project
• Develop appropriate management
strategies for effectively engaging
stakeholders in project decision and
execution.
Cyberdyne Business Solutions
Thank You
Cyberdyne Business Solutions
References
• ROSS, F. E. 1976. Technical Reviews and Audits: Keeping Track of Progress in
Development Projects. Management Review, 65, pg. 11.
• HARRISON, D. 2012. OFFICE OF THE CONTRACTOR-GENERAL ANNUAL
REPORT 2012. 18 Oxford rd. Kingston 10 Jamaica W.I.: pg. 857.
• DELOIT. 2014. Internal audit roles and responsibilities [Online]. Available:
http://www.deloitte.com/view/en_CN/cn/services/corgov/ic/iarr/index.htm?lgtog=lgtog.
• EL-NAGGAR, W., MBA & PMP. 2013. Project Scope Management
Based on PMBOK 5th Edition [Online]. Available:
http://www.slideshare.net/wnaggar/pmp-02-project-scope-management.
• MULCAHY, R. 2013. Rita Mulcahy's PMP Exam Prep, RMC
Publications; Eighth edition pg. 624.
Cyberdyne Business Solutions

More Related Content

What's hot

PMBOK 6th vs 5th Edition
PMBOK 6th vs 5th EditionPMBOK 6th vs 5th Edition
PMBOK 6th vs 5th EditionGoutama Bachtiar
 
Strategic Alignment of Projects
Strategic Alignment of ProjectsStrategic Alignment of Projects
Strategic Alignment of ProjectsTuan Yang
 
The Strategic Business Analyst: Aligning Projects with Organizational Goals
The Strategic Business Analyst: Aligning Projects with Organizational GoalsThe Strategic Business Analyst: Aligning Projects with Organizational Goals
The Strategic Business Analyst: Aligning Projects with Organizational GoalsCorporate Education Group (CEG)
 
Outsourcing and Managed Services - Developing a Common Language Between Suppl...
Outsourcing and Managed Services - Developing a Common Language Between Suppl...Outsourcing and Managed Services - Developing a Common Language Between Suppl...
Outsourcing and Managed Services - Developing a Common Language Between Suppl...Alan McSweeney
 
Show me the value: Enabling BCM Program Success through Lean thinking
Show me the value: Enabling BCM Program Success through Lean thinkingShow me the value: Enabling BCM Program Success through Lean thinking
Show me the value: Enabling BCM Program Success through Lean thinkingMilen Kutev
 
CobiT, Val IT & Balanced Scorecards
CobiT, Val IT & Balanced ScorecardsCobiT, Val IT & Balanced Scorecards
CobiT, Val IT & Balanced ScorecardsMichael Sim
 
Trends and local challenges
Trends and local challengesTrends and local challenges
Trends and local challengesPMILebanonChapter
 
P2C2 Group's Quick Tasks for IT Enterprise Management
P2C2 Group's Quick Tasks for IT Enterprise ManagementP2C2 Group's Quick Tasks for IT Enterprise Management
P2C2 Group's Quick Tasks for IT Enterprise ManagementJim Kendrick
 
Agile Program Management: Moving from Principles to Practice
Agile Program Management: Moving from Principles to PracticeAgile Program Management: Moving from Principles to Practice
Agile Program Management: Moving from Principles to PracticeGlen Alleman
 
Implementing agile iterative project delivery approach and achieving business...
Implementing agile iterative project delivery approach and achieving business...Implementing agile iterative project delivery approach and achieving business...
Implementing agile iterative project delivery approach and achieving business...Alan McSweeney
 
Business Case for BA's PMs
Business Case for BA's PMsBusiness Case for BA's PMs
Business Case for BA's PMsBrian Fariss
 
Project management chapter 4 - project integration management-1
Project management   chapter 4 - project integration management-1Project management   chapter 4 - project integration management-1
Project management chapter 4 - project integration management-1Eduardo Antero
 
Resume : "COBIT 5 for Business Benefits Realization"
Resume : "COBIT 5 for Business Benefits Realization"Resume : "COBIT 5 for Business Benefits Realization"
Resume : "COBIT 5 for Business Benefits Realization"asvary asvary
 
Sept 2008 Presentation Quality & Project Management
Sept 2008 Presentation Quality & Project ManagementSept 2008 Presentation Quality & Project Management
Sept 2008 Presentation Quality & Project ManagementHaroon Abbu
 
Cobit as IT Management Best Practice Framework
Cobit as IT Management Best Practice FrameworkCobit as IT Management Best Practice Framework
Cobit as IT Management Best Practice Frameworkjg20001234
 
Implementing Project Portfolio Management
Implementing Project Portfolio ManagementImplementing Project Portfolio Management
Implementing Project Portfolio Managementdlipper
 
The Key Role of Business Analysis in Project Success and Achieving Business V...
The Key Role of Business Analysis in Project Success and Achieving Business V...The Key Role of Business Analysis in Project Success and Achieving Business V...
The Key Role of Business Analysis in Project Success and Achieving Business V...Alan McSweeney
 
The Project Management Process - Week 10 Global Issues in IT projects
The Project Management Process - Week 10   Global Issues in IT projectsThe Project Management Process - Week 10   Global Issues in IT projects
The Project Management Process - Week 10 Global Issues in IT projectsCraig Brown
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governanceGlen Alleman
 
COBIT 4.0
COBIT 4.0COBIT 4.0
COBIT 4.0bluekiu
 

What's hot (20)

PMBOK 6th vs 5th Edition
PMBOK 6th vs 5th EditionPMBOK 6th vs 5th Edition
PMBOK 6th vs 5th Edition
 
Strategic Alignment of Projects
Strategic Alignment of ProjectsStrategic Alignment of Projects
Strategic Alignment of Projects
 
The Strategic Business Analyst: Aligning Projects with Organizational Goals
The Strategic Business Analyst: Aligning Projects with Organizational GoalsThe Strategic Business Analyst: Aligning Projects with Organizational Goals
The Strategic Business Analyst: Aligning Projects with Organizational Goals
 
Outsourcing and Managed Services - Developing a Common Language Between Suppl...
Outsourcing and Managed Services - Developing a Common Language Between Suppl...Outsourcing and Managed Services - Developing a Common Language Between Suppl...
Outsourcing and Managed Services - Developing a Common Language Between Suppl...
 
Show me the value: Enabling BCM Program Success through Lean thinking
Show me the value: Enabling BCM Program Success through Lean thinkingShow me the value: Enabling BCM Program Success through Lean thinking
Show me the value: Enabling BCM Program Success through Lean thinking
 
CobiT, Val IT & Balanced Scorecards
CobiT, Val IT & Balanced ScorecardsCobiT, Val IT & Balanced Scorecards
CobiT, Val IT & Balanced Scorecards
 
Trends and local challenges
Trends and local challengesTrends and local challenges
Trends and local challenges
 
P2C2 Group's Quick Tasks for IT Enterprise Management
P2C2 Group's Quick Tasks for IT Enterprise ManagementP2C2 Group's Quick Tasks for IT Enterprise Management
P2C2 Group's Quick Tasks for IT Enterprise Management
 
Agile Program Management: Moving from Principles to Practice
Agile Program Management: Moving from Principles to PracticeAgile Program Management: Moving from Principles to Practice
Agile Program Management: Moving from Principles to Practice
 
Implementing agile iterative project delivery approach and achieving business...
Implementing agile iterative project delivery approach and achieving business...Implementing agile iterative project delivery approach and achieving business...
Implementing agile iterative project delivery approach and achieving business...
 
Business Case for BA's PMs
Business Case for BA's PMsBusiness Case for BA's PMs
Business Case for BA's PMs
 
Project management chapter 4 - project integration management-1
Project management   chapter 4 - project integration management-1Project management   chapter 4 - project integration management-1
Project management chapter 4 - project integration management-1
 
Resume : "COBIT 5 for Business Benefits Realization"
Resume : "COBIT 5 for Business Benefits Realization"Resume : "COBIT 5 for Business Benefits Realization"
Resume : "COBIT 5 for Business Benefits Realization"
 
Sept 2008 Presentation Quality & Project Management
Sept 2008 Presentation Quality & Project ManagementSept 2008 Presentation Quality & Project Management
Sept 2008 Presentation Quality & Project Management
 
Cobit as IT Management Best Practice Framework
Cobit as IT Management Best Practice FrameworkCobit as IT Management Best Practice Framework
Cobit as IT Management Best Practice Framework
 
Implementing Project Portfolio Management
Implementing Project Portfolio ManagementImplementing Project Portfolio Management
Implementing Project Portfolio Management
 
The Key Role of Business Analysis in Project Success and Achieving Business V...
The Key Role of Business Analysis in Project Success and Achieving Business V...The Key Role of Business Analysis in Project Success and Achieving Business V...
The Key Role of Business Analysis in Project Success and Achieving Business V...
 
The Project Management Process - Week 10 Global Issues in IT projects
The Project Management Process - Week 10   Global Issues in IT projectsThe Project Management Process - Week 10   Global Issues in IT projects
The Project Management Process - Week 10 Global Issues in IT projects
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governance
 
COBIT 4.0
COBIT 4.0COBIT 4.0
COBIT 4.0
 

Similar to In persuit of perfection internal auditor the gate keepers of ethics in jamaican business

Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Managementmuhammadyasirsaeedqa
 
Mg6088 spm unit-1
Mg6088 spm unit-1Mg6088 spm unit-1
Mg6088 spm unit-1SIMONTHOMAS S
 
PMP selected topics and ideas
PMP selected topics and ideasPMP selected topics and ideas
PMP selected topics and ideasAhmad Hamid
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Managementmuhammadyasirsaeedqa
 
Using Project Management to Improve ROI Day 1 Event
Using Project Management to Improve ROI  Day 1 EventUsing Project Management to Improve ROI  Day 1 Event
Using Project Management to Improve ROI Day 1 EventEd Kozak
 
Article - Global Project Management
Article - Global Project ManagementArticle - Global Project Management
Article - Global Project ManagementGregory A. Garrett
 
Carlos Sousa\'s Professional Profile
Carlos Sousa\'s Professional ProfileCarlos Sousa\'s Professional Profile
Carlos Sousa\'s Professional Profilecarlos-sousa
 
PM-1 Overview.ppt
PM-1 Overview.pptPM-1 Overview.ppt
PM-1 Overview.pptnatisil1
 
Project management frame work part 1
Project management frame work part 1Project management frame work part 1
Project management frame work part 1Mohamed , PMP
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...GlobalSkillup
 
Setting up a project framework phase 1 june 20162
Setting up a project framework phase 1 june 20162Setting up a project framework phase 1 june 20162
Setting up a project framework phase 1 june 20162Project Management Solutions
 
Project audit and closure
Project audit and closureProject audit and closure
Project audit and closureVelita Furtado
 
Lec 01 - Introduction.pptx
Lec 01 - Introduction.pptxLec 01 - Introduction.pptx
Lec 01 - Introduction.pptxHamzaMessaoudi10
 
14. Developing Custom Processes For IT Projects
14. Developing Custom Processes For IT Projects14. Developing Custom Processes For IT Projects
14. Developing Custom Processes For IT ProjectsBhuWan Khadka
 
Challenging Aspects of Modern Project Management
Challenging Aspects of Modern Project ManagementChallenging Aspects of Modern Project Management
Challenging Aspects of Modern Project ManagementYamanta Raj Niroula, PMP
 
L Holution Srochure B Pervices V1
L Holution Srochure B Pervices V1L Holution Srochure B Pervices V1
L Holution Srochure B Pervices V1James McDermott
 
PMO 2.0 - Building PMO Capabilities
PMO 2.0 - Building PMO CapabilitiesPMO 2.0 - Building PMO Capabilities
PMO 2.0 - Building PMO CapabilitiesErin Jones
 

Similar to In persuit of perfection internal auditor the gate keepers of ethics in jamaican business (20)

Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Mg6088 spm unit-1
Mg6088 spm unit-1Mg6088 spm unit-1
Mg6088 spm unit-1
 
PMP selected topics and ideas
PMP selected topics and ideasPMP selected topics and ideas
PMP selected topics and ideas
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Using Project Management to Improve ROI Day 1 Event
Using Project Management to Improve ROI  Day 1 EventUsing Project Management to Improve ROI  Day 1 Event
Using Project Management to Improve ROI Day 1 Event
 
1 project management framework
1  project management framework1  project management framework
1 project management framework
 
Article - Global Project Management
Article - Global Project ManagementArticle - Global Project Management
Article - Global Project Management
 
Carlos Sousa\'s Professional Profile
Carlos Sousa\'s Professional ProfileCarlos Sousa\'s Professional Profile
Carlos Sousa\'s Professional Profile
 
PM-1 Overview.ppt
PM-1 Overview.pptPM-1 Overview.ppt
PM-1 Overview.ppt
 
Project management frame work part 1
Project management frame work part 1Project management frame work part 1
Project management frame work part 1
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
 
2. project scope management
2. project scope management2. project scope management
2. project scope management
 
Setting up a project framework phase 1 june 20162
Setting up a project framework phase 1 june 20162Setting up a project framework phase 1 june 20162
Setting up a project framework phase 1 june 20162
 
Project audit and closure
Project audit and closureProject audit and closure
Project audit and closure
 
Lec 01 - Introduction.pptx
Lec 01 - Introduction.pptxLec 01 - Introduction.pptx
Lec 01 - Introduction.pptx
 
14. Developing Custom Processes For IT Projects
14. Developing Custom Processes For IT Projects14. Developing Custom Processes For IT Projects
14. Developing Custom Processes For IT Projects
 
Challenging Aspects of Modern Project Management
Challenging Aspects of Modern Project ManagementChallenging Aspects of Modern Project Management
Challenging Aspects of Modern Project Management
 
L Holution Srochure B Pervices V1
L Holution Srochure B Pervices V1L Holution Srochure B Pervices V1
L Holution Srochure B Pervices V1
 
PMO 2.0 - Building PMO Capabilities
PMO 2.0 - Building PMO CapabilitiesPMO 2.0 - Building PMO Capabilities
PMO 2.0 - Building PMO Capabilities
 
INTRO.pptx
INTRO.pptxINTRO.pptx
INTRO.pptx
 

Recently uploaded

OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur fĂĽr Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur fĂĽr Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur fĂĽr Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur fĂĽr Container und Kubern...NETWAYS
 
WhatsApp đź“ž 9892124323 âś…Call Girls In Juhu ( Mumbai )
WhatsApp đź“ž 9892124323 âś…Call Girls In Juhu ( Mumbai )WhatsApp đź“ž 9892124323 âś…Call Girls In Juhu ( Mumbai )
WhatsApp đź“ž 9892124323 âś…Call Girls In Juhu ( Mumbai )Pooja Nehwal
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024eCommerce Institute
 
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Delhi Call girls
 
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfOpen Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfhenrik385807
 
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Hasting Chen
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...NETWAYS
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...NETWAYS
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@vikas rana
 
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara ServicesVVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara ServicesPooja Nehwal
 
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...NETWAYS
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkataanamikaraghav4
 
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrSaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrsaastr
 
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Kayode Fayemi
 
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxGenesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxFamilyWorshipCenterD
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Krijn Poppe
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfhenrik385807
 
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
LANDMARKS  AND MONUMENTS IN NIGERIA.pptxLANDMARKS  AND MONUMENTS IN NIGERIA.pptx
LANDMARKS AND MONUMENTS IN NIGERIA.pptxBasil Achie
 
Motivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfMotivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfakankshagupta7348026
 
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024eCommerce Institute
 

Recently uploaded (20)

OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur fĂĽr Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur fĂĽr Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur fĂĽr Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur fĂĽr Container und Kubern...
 
WhatsApp đź“ž 9892124323 âś…Call Girls In Juhu ( Mumbai )
WhatsApp đź“ž 9892124323 âś…Call Girls In Juhu ( Mumbai )WhatsApp đź“ž 9892124323 âś…Call Girls In Juhu ( Mumbai )
WhatsApp đź“ž 9892124323 âś…Call Girls In Juhu ( Mumbai )
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024
 
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
 
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfOpen Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
 
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@
 
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara ServicesVVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
 
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
 
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrSaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
 
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
 
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxGenesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
 
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
LANDMARKS  AND MONUMENTS IN NIGERIA.pptxLANDMARKS  AND MONUMENTS IN NIGERIA.pptx
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
 
Motivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfMotivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdf
 
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
 

In persuit of perfection internal auditor the gate keepers of ethics in jamaican business

  • 1. In Pursuit of Perfection: Internal Auditors the gatekeeper of Business Ethics in Jamaica. "Integrating Project Management Techniques for Internal Auditing" Cyberdyne Business Solutions
  • 2. AGENDA • Background • Management Dilemma and Solutions • Roles, Function and Reporting Relationship of an Internal Auditor • Project Management Overview Cyberdyne Business Solutions
  • 3. Definitions • Business ethics are moral principles that guide the way a business behaves. The same principles that determine an individual’s actions also apply to business. Cyberdyne Business Solutions
  • 4. Monitoring Of Construction Contracts • During the 2012 calendar year, the Construction Contracts Division of the Office of the Contractor General (OCG) monitored the Pre and Post Contract stages of three hundred and sixty seven (367) contracts. As such, there was a 10.5% decrease in the number of works contracts which were monitored for the year 2012, in comparison to the previous year in which four hundred and ten (410) contracts were monitored. • It must be noted that the NCC, during the year, endorsed a total of one hundred and forty eight (148) works contracts which had an aggregate value of J$10,314,568,600.00, of which fifty-two (52) were monitored by the Construction Contracts Division. (Harrison, 2012) Cyberdyne Business Solutions
  • 5. Monitoring Of Non-construction Contracts, Licenses, Permits And Concessions • The Division monitored approximately six hundred (600) opportunities/contracts during the calendar year 2012, in comparison to six hundred and eighty-two (682) procurement opportunities/contracts which were monitored in 2011. This represents a twelve percent (12%) decrease in the number of non-construction contracts and license which were monitored over the corresponding period. • Of the 600 opportunities/contracts which were monitored during the year, four hundred and sixty three (463) represents monitoring assignments which were carried forward from 2011. The remaining one hundred and thirty-seven (137) or approximately twenty three percent (23%) represents new monitoring assignments during 2012. (Harrison, 2012) Cyberdyne Business Solutions
  • 6. Problem Set • A company has been working on the development of an advance product for the last three years at a cost of $2 Million. Under the original plans, the project should have been completed and the payback (new revenues and/or cost savings) should have started six months ago. So far, the delay has run an anticipated additional cost of $500,000, and, with no end in sight, management is getting edgy. Should it terminate the project or budget additional funds to continue work? Cyberdyne Business Solutions
  • 7. Management Dilemma Management Facts: •Decision to continue supplying funds, manpower and facilities or whether to kill the project based on current status of project. •No one has sufficient, reliable information into what has been accomplished or what to expect in the future Cyberdyne Business Solutions
  • 8. Solutions • Experience has shown that skills and methodology used in financial auditing are adaptable to the review and audit needs of development projects and technical work. • Assessment based on technical competence alone often fail to further furnish management with the data necessary for decision making. (Ross, 1976) Cyberdyne Business Solutions
  • 9. Definition of Internal Auditing • According to Institute of Internal Auditors (IIA) - "Internal auditing is an independent, objective assurance and consulting activity designed to add value and improve an organization's operations. It helps an organisation accomplish its objectives by bringing a systematic, disciplined approach to evaluate and improve the effectiveness of risk management, control, and governance processes." (Deloit, 2014) Cyberdyne Business Solutions
  • 10. Major roles and responsibilities of internal audit function • evaluates and provides reasonable assurance that risk management, control, and governance systems are functioning as intended and will enable the organization's objectives and goals to be met • reports risk management issues and internal controls deficiencies identified directly to the audit committee and provides recommendations for improving the organization's operations, in terms of both efficient and effective performance • evaluates information security and associated risk exposures. (Deloit, 2014). Cyberdyne Business Solutions
  • 11. Major roles and responsibilities of internal audit function (cont.) • evaluates regulatory compliance program with consultation from legal counsel • evaluates the organization's readiness in case of business interruption • maintains open communication with management and the audit committee • teams with other internal and external resources as appropriate • engages in continuous education and staff development • provides support to the company's anti-fraud programs. (Deloit, 2014) Cyberdyne Business Solutions
  • 12. Reporting Structure of Internal Audit Function • In most companies, the internal auditor traditionally reported to either the Chief Financial Officer or the Chief Risk Officer, though other may have existed in some companies. Today, the internal auditor may either report directly to the Audit Committee, or the Audit Committee will have a role in hiring, firing, evaluating and compensating the Chief Audit Officer. The Audit Committee’s increasing role with regard to the internal audit is being undertaken to help ensure the internal auditor’s "independence" and objectivity. • The relationship between the Audit Committee and the internal audit function should be clearly defined and addressed in the Audit Committee’s charter. Cyberdyne Business Solutions
  • 13. Project Overview • Project - A project is temporary in that it has a defined beginning and end in time, and therefore defined scope and resources. • Project Manager – A PM is assigned by an organization to achieve the specified objectives of a project within the competing project constraints. The role of the project manager is different from a functional manager or an operations manager. Depending on the organizational structure, the project manager may be reporting to a functional manager or a program manager or a portfolio manager. Cyberdyne Business Solutions
  • 14. Organisation Type: Functional A hierarchical organization where each employee has one clear superior, staff are grouped by areas of specialization, and managed by a person with expertise in that area. Cyberdyne Business Solutions
  • 15. Organisation Type: Weak A project manager (often called a project administrator under this type of organization) with only limited authority is assigned to oversee the cross-functional aspects of the project. Cyberdyne Business Solutions
  • 16. Organisation Type: Weak Matrix A project manager (often called a project administrator under this type of organization) with only limited authority is assigned to oversee the cross-functional aspects of the project. The functional managers maintain control over their resources and project areas. Cyberdyne Business Solutions
  • 17. Organisation Type: Balanced Matrix A project manager is assigned to oversee the project. Power is shared equally between the project manager and the functional managers. Cyberdyne Business Solutions
  • 18. Organisation Type: Strong Matrix A project manager is primarily responsible for the project. Functional managers provide technical expertise and assign resources on an as-needed basis. Because project resources are assigned as necessary there can be conflicts between the project manager and the functional manager over resource assignment. Cyberdyne Business Solutions
  • 19. Organisation Type: Projectised an organizational structure in which the project manager has full authority to assign priorities, apply resources, and direct the work of persons assigned to the project. Cyberdyne Business Solutions
  • 21. 5 PROCESSES GROUPS • Initiating – – Formal process recognize a new project – Stakeholders are identified – Commitment is obtained • Planning – – The use of resources to plan and subsequently report progress within the project environment • Executing – – The actual work on the tasks planned • Controlling and Monitoring – – To provide an understanding of the project’s progress so that appropriate corrective actions can be taken • Closing – – Those processes performed to formally terminate all activities of a project or phase, and transfer the completed product to others or to close a cancelled project Cyberdyne Business Solutions
  • 22. 10 Knowledge Areas • Project Integration Management - All Areas • Project Scope Management - Requirements • Project Time Management - Schedule • Project Cost Management - Budget • Project Quality Management – Final product outcome • Project Human Resource Management - People • Project Communications Management – Info. Delivery • Project Risk Management – Measure/ Countermeasures • Project Procurement Management – Goods/services • Project Stakeholder Management - Stakeholder Analysis Cyberdyne Business Solutions
  • 23. Project Integration Management • Primarily concerned with effectively integrating the process among the project management process groups that are required to accomplish the project objective within an organisation’s defined procedure Cyberdyne Business Solutions
  • 24. Project Scope Management • Scope Management is the process of defining what work is required and then making sure all of that work is done – and only that work is done. • Scope refers to all the work involved in creating the deliverables of the project and the process used to create them Cyberdyne Business Solutions
  • 25. Project Time Management • Time management is an essentially significant ability for any efficient project manager. Project managers, who are successful in controlling the schedule, are usually able to manage the budget, since schedule has a direct influence on the project budget. The most common reasons of going over budget in projects are due to improper management of schedule. - Cyberdyne Business Solutions
  • 26. Project Cost Management • Project Cost Management includes those processes involved in planning, estimating, budgeting, monitoring and controlling costs. The ultimate goal of project cost management is to complete the project within the approved budget. Cyberdyne Business Solutions
  • 27. Project Quality Management • Quality is defined as the degree to which the project fulfills its requirements • Quality Management includes creating and following policies and procedures to ensure that a project meets from the customers perspective • A lack of attension to quality means rework or defects Cyberdyne Business Solutions
  • 28. Project Human Resource Management • The Human Resource management process takes time and effort to plan how you will involve people, identify the team members you will need, define everyone’s roles, create reward systems, improve team member’s performance individually and a team, and track performance. Cyberdyne Business Solutions
  • 29. Project Communication Management • The Plan Communication Management process considers how to store, maintain, distribute, and retrieve information and what will happen to all the project information once the project is closed. Cyberdyne Business Solutions
  • 30. Project Risk Management • Risk Management includes Risk Management, Risk Identification, the qualitative and quantitative analysis of risk response, planning and monitoring and control of risk response. Cyberdyne Business Solutions
  • 31. Project Procurement Management • Procurement is a formal process to obtain goods and services. • Private companies have a lot of flexibility in their procurement practices. • Government entities are spending public funds, they have to comply with laws, rules, and regulations that specifically govern each step of the procurement process Cyberdyne Business Solutions
  • 32. Project Stakeholder Management • Identifies the people, groups, or organisations that could impact or be impacted by the project • Analyse stakeholder expectations and their impact on the project • Develop appropriate management strategies for effectively engaging stakeholders in project decision and execution. Cyberdyne Business Solutions
  • 34. References • ROSS, F. E. 1976. Technical Reviews and Audits: Keeping Track of Progress in Development Projects. Management Review, 65, pg. 11. • HARRISON, D. 2012. OFFICE OF THE CONTRACTOR-GENERAL ANNUAL REPORT 2012. 18 Oxford rd. Kingston 10 Jamaica W.I.: pg. 857. • DELOIT. 2014. Internal audit roles and responsibilities [Online]. Available: http://www.deloitte.com/view/en_CN/cn/services/corgov/ic/iarr/index.htm?lgtog=lgtog. • EL-NAGGAR, W., MBA & PMP. 2013. Project Scope Management Based on PMBOK 5th Edition [Online]. Available: http://www.slideshare.net/wnaggar/pmp-02-project-scope-management. • MULCAHY, R. 2013. Rita Mulcahy's PMP Exam Prep, RMC Publications; Eighth edition pg. 624. Cyberdyne Business Solutions