2011 Defense Trade Show

Bid Protests and Debriefings

             Presented By:
        Jackson Wyatt Moore, Jr.

     Smith, Anderson, Blount, Dorsett,
         Mitchell & Jernigan, LLP
             (919) 821-6688
          jmoore@smithlaw.com

                                                                 www.smithlaw.com
                                         ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
www.smithlaw.com




             Government Contracts Are
                Heavily Regulated
    • United States a Sovereign, not a Private Party
       – Authority to Act for Government: FAR 2.101; 1.602-1;
         DFARS 252.201-7000
    • Federal Acquisition Regulation (“FAR”).
       – Issued by DoD, NASA, GSA.
    • FAR Supplements.
       – Department of Defense Supplement (“DFARS”).
       – Supplements for Army (“AFARS”), Air Force (“AAFARS”),
         Navy/Marine Corps (“NMCFARS”).


                                            ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
2
www.smithlaw.com




        Government Contracting Sources:
               FAR/DFAR/ etc.
    • Acquisition Central: Acquisition.gov/far

    • FAR Aggregator: farsite.hill.af.mil

    • Where in Federal Contracting: www.wifcon.com




                                                 ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
3
www.smithlaw.com




      A definition of “Bid Protest”
    “[A] [written] action by an interested party objecting to a
    solicitation by a Federal agency for bids or proposals for
    a proposed contract or to a proposed award or the award
    of a contract or any alleged violation of statute or
    regulation in connection with a procurement or a
    proposed procurement.”

               28 U.S.C. §1491(b)(1); FAR 33.101.


                                           ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
4
www.smithlaw.com




      Reasons to Protest a Bid or Award
    • Get the contract.
    • Make a point.
    • Keep contract in the interim if you are an
      incumbent.
    • Do you really want to sue your (potential) client?



                                      ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
5
www.smithlaw.com




                       Can you protest?
    • What is your basis?
       – Specification deficiencies.
       – Winner not qualified for set-aside.
           • Priority to HUBZone contractor vs. 8(a) and SDVO.
           • Mission Critical Solutions v. United States (Mar. 3, 2010).
       – Agency awarded to a non-responsive or non-responsible
         bidder.
           • Evaluation deficiencies (unequal treatment, etc.).
           • Organizational Conflicts of interest .
           • Technical merits (hard).
       – Other reasons
                                                        ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
6
www.smithlaw.com




                 “Interested Party”
    An interested party is an “actual or prospective bidder or
    offeror whose direct economic interest would be affected by
    the award of the contract or failure to award the contract.”

    31 U.S.C.   3551(2); 4 C.F.R.    21.




                                              ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
7
www.smithlaw.com




                  “Interested Party”
    • Did you submit a bid?

    • A subcontractor to a disappointed bidder is not a bidder
      and cannot protest the bid of another. Eagle Design &
      Management, Inc. v. U.S. and Circle Solutions, Inc.,
      No. 04-1200C (Court of Federal Claims, Sept.16, 2004)




                                          ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
8
www.smithlaw.com




                  “Interested Party”
    • Would you win if you prevail on the protest?

    • Protester must show it had a substantial chance of
      receiving the award but for the agency’s error in the
      procurement process. Rex Service Corp. v. United
      States, 448 F.3d 1305 (Fed. Cir. 2006).




                                           ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
9
www.smithlaw.com




                     Time Marches On
     • Timeframes very short. 4 C.F.R. § 21.2.
        – Improper solicitation? Protest before proposal deadline.
        – Other protests? Generally 10 days after basis of protest
          known
        – Size Protests? 5 working days after bid opening or after
          receipt of notification of awardee (for RFPs and RFQs)

     • Timeframes to request debriefing very short.
        – 3 days after notice of exclusion from competition or notice of
          contract award. 48 C.F.R. §15.505.
                                                 ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
10
www.smithlaw.com




                      Where do I file?
     •   Agency.
     •   Government Accountability Office/Comptroller General.
     •   Court of Federal Claims.
     •   Agency, who forwards to the SBA (for size protests).




                                           ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
11
www.smithlaw.com




                     Agency Protest
     • Least formal, least expensive
     • Protester can request an independent review of the
       merits of its agency protest at a level above the CO.
       55.103(d)(4).
     • Note: agency protest does extend deadline for filing
       GAO protest, but review of the protest does not extend
       deadline. 33.103(d)(5); 4 C.F.R. 21.2(a)(3)



                                          ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
12
www.smithlaw.com




                       Agency Protest
     • Format:
        – State prominently it is a “protest”
        – Addressed to Contracting Officer or designated official
        – Detailed fact and legal statement, including how protester
          has been harmed
        – Copies of relevant documents
        – A showing that the protest is timely
        – A showing that the protester an “interested party”
        – A request for ruling and a statement of the requested relief.
        FAR 33.103(d)
                                                 ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
13
www.smithlaw.com




                       Agency Protest
     • Relief
        – Before award: correct the deficiency
        – After award:
           • Void contract (rare)
           • Terminate Contract for Convenience
           • Permit Award to stand
           • Direct a Re-evaluation
           • Award cost of pursuing protest, including fees.
        FAR 33.102; 4 C.F.R. Section 21.8

                                                ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
14
www.smithlaw.com




      GAO (Comptroller General) Protests
     • Procedures: 31 U.S.C. 3551; 4 CFR 21.
     • Strict timing deadlines
        – Comply or risk dismissal
        – File before GAO’s close of business, or the protest will be
          dated the next day (important for pre-award protests)
        – File Before bid opening for solicitation improprieties
        – Within 10 days after protest basis known for any other basis.
        – Within 10 days after debriefing (when requested)
     • Must send copy to agency within one day after filing
       within GAO. 4 C.F.R. 21.1(e)
                                                ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
15
www.smithlaw.com




      GAO (Comptroller General) Protests
     • A Protest Can Stay of the Contract (absent compelling
       circumstances):
        – Protest before award prohibits agency from
           awarding contract.
        – Protest within 10 calendar days of award or within
           five days after a debriefing date is offered to the
           protester, the Contracting Officer must suspend
           contract performance or terminate the contract.
            • Notice must come from the GAO, not the protester.

                                               ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
16
www.smithlaw.com




      GAO (Comptroller General) Protests
     • Content similar to Agency protests, and can ask for:
        – a protective order,
        – written document discovery, and
        – a hearing
     • Detailed statement of facts (not speculation)
     • After receipt, GAO will contact agency and ask for a
       detailed report and documents. 4 C.F.R. 21.3(a).
     • Agency report due within 30 days of GAO’s notice.
       Copies must go to protestor and intervenors.
                                            ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
17
www.smithlaw.com




       GAO (Comptroller General) Protests
     • GAO can hold a hearing, though these are rare.
     • Decision is issued within 100 days of date of filing of
       the protest with the GAO. 4 C.F.R. 21.9(a).
     • Remedies:
        – GAO makes recommendations:
            • Refrain from exercising options under contract,
              recompete, issue a new solicitation, terminate, award a
              contract that complies with the law, or any of the above.
        – Costs may be awarded to the protester
                                                 ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
18
www.smithlaw.com




      GAO (Comptroller General) Protests
     • Agency has 60 days to implement
       recommendations or report failure to comply
     • Contracting Agency has “sound discretion” to
       remedy the procurement impropriety that formed
       the basis of the GAO recommendation. ST
       Aerospace Engines Pte. Ltd. B-275725, B-
       275725.3 (1997).

                                    ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
19
www.smithlaw.com




         Court of Federal Claims Protests
     • Only court forum (versus agency forum) to pursue a
       preaward or postaward protest. 28 U.S.C. 1491(b).
     • Party can file with COFC after bringing a GAO protest
       or instead of the GAO protest
     • COFC not bound by GAO decision, but it is given
       deference.




                                          ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
20
www.smithlaw.com




         Court of Federal Claims Protests
     • No automatic stay: protestor must move for a
       temporary restraining order.
     • COFC will hold an initial status conference
     • Protective Orders may be sought to protect confidential
       information from disclosure.
     • Depositions and discovery is allowed.
     • Summary judgments or “paper trials” are typical


                                           ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
21
www.smithlaw.com




         Court of Federal Claims Protests
     • COFC must decide whether agency’s actions were
       arbitrary, capricious, and abuse of discretion, or
       otherwise violative of the law
     • Protestor must show:
        – “Significant error” in the procurement process
        – Error resulted in “competitive prejudice” to the protestor:
          without the error, there was a “substantial chance” the
          protestor would have won the award. Alfa Laval Separation,
          Inc. v. United States, 175 F.3d 1365 (Fed. Cir. 1999).


                                               ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
22
www.smithlaw.com




                        Size Protests
     • A Business is “other than small” for a particular size
       standard set out in the procurement. 13 C.F.R.
       121.1001 through 121.1007.
     • Protest filed with contracting officer. CO will forward to
       SBA. 13 CFR 121.1003.
     • Protest must be in writing specify reason and present
       evidence for claiming business is “other than small”.



                                             ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
23
www.smithlaw.com




                       Size Protests
     • SBA has 10 days to make size determination and notify
       contracting officer unless the SBA obtains more time.
       FAR 19.302.
     • SBA may ask challenged business for more
       information; failing to provide may result in an “other
       than small” determination. 13 CFR 121.1008(d).
     • Results of size determinations are entered into SBA
       database.


                                           ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
24
www.smithlaw.com




            Protest Basis: Timeliness
     • Case Study: Ball Aerospace (2010).
        – Air Force RFQ’d a Blanket Purchase Agreement:
           • RFQ for services; some on a fixed price and some hourly.
           • RFQ but did not require vendors to estimate number of hours
             needed to perform requirements in statements of work.
           • RFQ required vendors to provide pricing based on unit pricing only.
        – AT&T’s price was 57% lower; Ball complained the evaluation
          of vendor’s price and technical quotes was flawed.
        – Result: Protest Denied as untimely.
           • Agency Must Evaluate Proposals considering cost the government.
           • But, a post-award challenge to the evaluation scheme is untimely.
        – GAO Protest B-402148 (Jan. 25, 2010).
                                                    ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
25
www.smithlaw.com




      Protest Basis: Non-Responsive Bids
     • Case Study: Irving Burton (2010).
        – Task Order Proposal Request from Army said:
           • proposals limited to 30 single-sided pages.
           • attachments limited to 10 single-sided pages each.
        – Winner’s Proposal Exceeded the Page Limits.
        – Result: Protest Sustained.
           • Agency Should Have Evaluated Proposal After Removing the
             Excess Pages.
        – In re: Irving Burton Associates: GAO Protest B-401983.3
          (Mar. 29, 2010).

                                                      ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
26
www.smithlaw.com




                    Protest Basis: OCI
     • Case Study: CACI (2011).
        – OCI claim related to DoD RFP for Records System:
            • BAH’s proposal $9.7 MM, almost $3MM than CACI’s.
            • CACI claimed BAH had access to CACI confidential information
              when BAH was a “support contractor” for the DPRIS system.
            • Contracting officer determined that BAH did not have “unequal
              access to information” that gave an unfair advantage.
        – Result: Protest Overruled.
            • CACI could point to no specific information that would have given
              BAH an unfair advantage in competing for the award.
            • CACI could not show that BAH improperly obtained confidential
              CACI information: CACI should have controlled its own information.
        – In re: CACI, inc.: GAO Protest B-403064.2 (Jan. 28, 2011).
                                                     ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
27
www.smithlaw.com




          Authority to Change Contract
     • Only contracting officer may enter into,
       administer, amend or terminate contracts.
        – FAR 1.601(a).
        – DFAR 252.201-7000(b).
     • Changes that are not in writing and approved by
       Contracting Officer might not be enforced.


                                      ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
28
www.smithlaw.com




           Authority to Change Contract
     • Case Study: CATH-dr/Balti Joint Venture (2007).
        – Construction project for the Navy.
        – Contractor told to:
            • Direct all suggested changes to the Resident Officer in Charge of
              Contracts, who also was the Project Manager.
            • Perform no work outside the contract without written authorization
              from the ROICC/PM.
        – Court: ROICC/PM was not the Contracting Officer and
          therefore could not change construction contract.
        – CATH-dr/Balti Joint Venture, 497 F.3d 1339 (Fed. Cir. 2007).
                                                        ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
29
www.smithlaw.com




                           Debriefings
     • FAR encourages debriefings.
        – Often changes protest deadlines
        – Encourages talking between bidders and agencies
        – Helps to improve future bids.
     • Always request a timely debriefing
        – In writing to CO within three days of award
        – Use information for future procurements or a bid protest
     • Even if untimely, ask for a debriefing.

                                                ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
30
Questions?

   Jackson Moore
jmoore@smithlaw.com
   (919) 821-6688




                                          www.smithlaw.com
                  ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.

More Related Content

Similar to Debriefs and Protest Process

Procedural Issues in Bad Faith Litigation
Procedural Issues in Bad Faith LitigationProcedural Issues in Bad Faith Litigation
Procedural Issues in Bad Faith Litigation
Rachel Hamilton
 
BobTataBio.PDF
BobTataBio.PDFBobTataBio.PDF
BobTataBio.PDF
Bob Tata
 
Florida Homeowner\'s Construction Recovery Fund - A Homeowner\'s Last Resort
Florida Homeowner\'s Construction Recovery Fund - A Homeowner\'s Last ResortFlorida Homeowner\'s Construction Recovery Fund - A Homeowner\'s Last Resort
Florida Homeowner\'s Construction Recovery Fund - A Homeowner\'s Last Resort
wsunter
 
Federal Procurement Updates June 2010
Federal Procurement Updates June 2010Federal Procurement Updates June 2010
Federal Procurement Updates June 2010
fkenniasty
 
Cigna Corp. v. Amara Revisited
Cigna Corp. v. Amara RevisitedCigna Corp. v. Amara Revisited
Cigna Corp. v. Amara Revisited
Rachel Hamilton
 

Similar to Debriefs and Protest Process (20)

Morse IPO Slides Joint Defense Of Ip Litigation November 2009
Morse IPO Slides Joint Defense Of Ip Litigation November 2009Morse IPO Slides Joint Defense Of Ip Litigation November 2009
Morse IPO Slides Joint Defense Of Ip Litigation November 2009
 
Statutory class actions developments and strategies
Statutory class actions developments and strategiesStatutory class actions developments and strategies
Statutory class actions developments and strategies
 
Privacy Law Update Darren Chaker
Privacy Law Update Darren ChakerPrivacy Law Update Darren Chaker
Privacy Law Update Darren Chaker
 
Darren chaker privacy_law
Darren chaker privacy_lawDarren chaker privacy_law
Darren chaker privacy_law
 
Starting a Franchise | Jones Day | Doing Business 2.0
Starting a Franchise | Jones Day | Doing Business 2.0Starting a Franchise | Jones Day | Doing Business 2.0
Starting a Franchise | Jones Day | Doing Business 2.0
 
C. Lee Lott - Baker Donelson Employee (Counsel/Advisor To Mississippi Governo...
C. Lee Lott - Baker Donelson Employee (Counsel/Advisor To Mississippi Governo...C. Lee Lott - Baker Donelson Employee (Counsel/Advisor To Mississippi Governo...
C. Lee Lott - Baker Donelson Employee (Counsel/Advisor To Mississippi Governo...
 
Procedural Issues in Bad Faith Litigation
Procedural Issues in Bad Faith LitigationProcedural Issues in Bad Faith Litigation
Procedural Issues in Bad Faith Litigation
 
BobTataBio.PDF
BobTataBio.PDFBobTataBio.PDF
BobTataBio.PDF
 
Cutting Edge Employment Law Issues
Cutting Edge Employment Law IssuesCutting Edge Employment Law Issues
Cutting Edge Employment Law Issues
 
Justin Chiarodo: Government Contracts & Insurance Issues: How Prepared is You...
Justin Chiarodo: Government Contracts & Insurance Issues: How Prepared is You...Justin Chiarodo: Government Contracts & Insurance Issues: How Prepared is You...
Justin Chiarodo: Government Contracts & Insurance Issues: How Prepared is You...
 
Florida Homeowner\'s Construction Recovery Fund - A Homeowner\'s Last Resort
Florida Homeowner\'s Construction Recovery Fund - A Homeowner\'s Last ResortFlorida Homeowner\'s Construction Recovery Fund - A Homeowner\'s Last Resort
Florida Homeowner\'s Construction Recovery Fund - A Homeowner\'s Last Resort
 
Georgia Tennessee Hot issues
Georgia Tennessee Hot issuesGeorgia Tennessee Hot issues
Georgia Tennessee Hot issues
 
Federal Procurement Updates June 2010
Federal Procurement Updates June 2010Federal Procurement Updates June 2010
Federal Procurement Updates June 2010
 
Top 10 Business Law Cases of the Year (2015)
Top 10 Business Law Cases of the Year (2015)Top 10 Business Law Cases of the Year (2015)
Top 10 Business Law Cases of the Year (2015)
 
Report & Recommendation Denying Preliminary Injunction - MDFL
Report & Recommendation Denying Preliminary Injunction - MDFLReport & Recommendation Denying Preliminary Injunction - MDFL
Report & Recommendation Denying Preliminary Injunction - MDFL
 
Maria addison
Maria addisonMaria addison
Maria addison
 
Developments in Whistleblower Law
Developments in Whistleblower LawDevelopments in Whistleblower Law
Developments in Whistleblower Law
 
Cigna Corp. v. Amara Revisited
Cigna Corp. v. Amara RevisitedCigna Corp. v. Amara Revisited
Cigna Corp. v. Amara Revisited
 
Remedies for breach of contract
Remedies for breach of contractRemedies for breach of contract
Remedies for breach of contract
 
Production, Privileges, and Practice PowerPoint
Production, Privileges, and Practice PowerPointProduction, Privileges, and Practice PowerPoint
Production, Privileges, and Practice PowerPoint
 

More from NC Military Business Center

Fort Bragg Small Business Outreach Event_March 18, 14
Fort Bragg Small Business Outreach Event_March 18, 14Fort Bragg Small Business Outreach Event_March 18, 14
Fort Bragg Small Business Outreach Event_March 18, 14
NC Military Business Center
 
FEDCON Summit: Bonding & Surety for Federal Construction Projects
FEDCON Summit: Bonding & Surety for Federal Construction ProjectsFEDCON Summit: Bonding & Surety for Federal Construction Projects
FEDCON Summit: Bonding & Surety for Federal Construction Projects
NC Military Business Center
 
FEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysFEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/Delays
NC Military Business Center
 
FEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysFEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/Delays
NC Military Business Center
 
FEDCON Summit: Department of Transportation Construction Opportunities
FEDCON Summit:  Department of Transportation Construction OpportunitiesFEDCON Summit:  Department of Transportation Construction Opportunities
FEDCON Summit: Department of Transportation Construction Opportunities
NC Military Business Center
 
FEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
FEDCON Summit: Labor Laws & Affirmative Action for Federal ContractsFEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
FEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
NC Military Business Center
 
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
NC Military Business Center
 
FEDCON Summit: Installation Energy Programs, Projects & Industry Experience
FEDCON Summit: Installation Energy Programs, Projects & Industry ExperienceFEDCON Summit: Installation Energy Programs, Projects & Industry Experience
FEDCON Summit: Installation Energy Programs, Projects & Industry Experience
NC Military Business Center
 
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
NC Military Business Center
 
FEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry PanelFEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry Panel
NC Military Business Center
 
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced AnalyticsHuman/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
NC Military Business Center
 

More from NC Military Business Center (20)

Camp Lejeune Small Business Outreach Event
Camp Lejeune Small Business Outreach EventCamp Lejeune Small Business Outreach Event
Camp Lejeune Small Business Outreach Event
 
MCAS Cherry Point Small Business Outreach Event
MCAS Cherry Point Small Business Outreach EventMCAS Cherry Point Small Business Outreach Event
MCAS Cherry Point Small Business Outreach Event
 
Spawar slides
Spawar slidesSpawar slides
Spawar slides
 
Fort Bragg Small Business Outreach Event_March 18, 14
Fort Bragg Small Business Outreach Event_March 18, 14Fort Bragg Small Business Outreach Event_March 18, 14
Fort Bragg Small Business Outreach Event_March 18, 14
 
FEDCON Summit: Bonding & Surety for Federal Construction Projects
FEDCON Summit: Bonding & Surety for Federal Construction ProjectsFEDCON Summit: Bonding & Surety for Federal Construction Projects
FEDCON Summit: Bonding & Surety for Federal Construction Projects
 
FEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysFEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/Delays
 
FEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/DelaysFEDCON Summit: Change Orders & Contract Disruptions/Delays
FEDCON Summit: Change Orders & Contract Disruptions/Delays
 
FEDCON Summit: Department of Transportation Construction Opportunities
FEDCON Summit:  Department of Transportation Construction OpportunitiesFEDCON Summit:  Department of Transportation Construction Opportunities
FEDCON Summit: Department of Transportation Construction Opportunities
 
FEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
FEDCON Summit: Labor Laws & Affirmative Action for Federal ContractsFEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
FEDCON Summit: Labor Laws & Affirmative Action for Federal Contracts
 
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
FEDCON Summit: Waste and Pollution Reduction Programs, Projects & Industry Ex...
 
FEDCON Summit: Installation Energy Programs, Projects & Industry Experience
FEDCON Summit: Installation Energy Programs, Projects & Industry ExperienceFEDCON Summit: Installation Energy Programs, Projects & Industry Experience
FEDCON Summit: Installation Energy Programs, Projects & Industry Experience
 
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
FEDCON Summit: Water, Wastewater and Stormwater Programs, Projects & Industry...
 
FEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry PanelFEDCON Summit: Environmental Engineering & Remediation Industry Panel
FEDCON Summit: Environmental Engineering & Remediation Industry Panel
 
FEDCON Summit: Marine Corps Installations East
FEDCON Summit: Marine Corps Installations EastFEDCON Summit: Marine Corps Installations East
FEDCON Summit: Marine Corps Installations East
 
FEDCON Summit: NCMBC Tools for Contractors
FEDCON Summit: NCMBC Tools for ContractorsFEDCON Summit: NCMBC Tools for Contractors
FEDCON Summit: NCMBC Tools for Contractors
 
FEDCON Summit: Public Private Ventures
FEDCON Summit: Public Private VenturesFEDCON Summit: Public Private Ventures
FEDCON Summit: Public Private Ventures
 
FEDCON Summit: Teaming Arrangements
FEDCON Summit: Teaming ArrangementsFEDCON Summit: Teaming Arrangements
FEDCON Summit: Teaming Arrangements
 
FEDCON Summit: Veterans Affairs
FEDCON Summit: Veterans AffairsFEDCON Summit: Veterans Affairs
FEDCON Summit: Veterans Affairs
 
Medical Technologies
Medical TechnologiesMedical Technologies
Medical Technologies
 
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced AnalyticsHuman/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
Human/Social Sciences/Cultural & Behavioral Dynamics and Advanced Analytics
 

Recently uploaded

Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Dipal Arora
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
amitlee9823
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
lizamodels9
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
amitlee9823
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
amitlee9823
 

Recently uploaded (20)

BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 

Debriefs and Protest Process

  • 1. 2011 Defense Trade Show Bid Protests and Debriefings Presented By: Jackson Wyatt Moore, Jr. Smith, Anderson, Blount, Dorsett, Mitchell & Jernigan, LLP (919) 821-6688 jmoore@smithlaw.com www.smithlaw.com ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.
  • 2. www.smithlaw.com Government Contracts Are Heavily Regulated • United States a Sovereign, not a Private Party – Authority to Act for Government: FAR 2.101; 1.602-1; DFARS 252.201-7000 • Federal Acquisition Regulation (“FAR”). – Issued by DoD, NASA, GSA. • FAR Supplements. – Department of Defense Supplement (“DFARS”). – Supplements for Army (“AFARS”), Air Force (“AAFARS”), Navy/Marine Corps (“NMCFARS”). ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 2
  • 3. www.smithlaw.com Government Contracting Sources: FAR/DFAR/ etc. • Acquisition Central: Acquisition.gov/far • FAR Aggregator: farsite.hill.af.mil • Where in Federal Contracting: www.wifcon.com ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 3
  • 4. www.smithlaw.com A definition of “Bid Protest” “[A] [written] action by an interested party objecting to a solicitation by a Federal agency for bids or proposals for a proposed contract or to a proposed award or the award of a contract or any alleged violation of statute or regulation in connection with a procurement or a proposed procurement.” 28 U.S.C. §1491(b)(1); FAR 33.101. ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 4
  • 5. www.smithlaw.com Reasons to Protest a Bid or Award • Get the contract. • Make a point. • Keep contract in the interim if you are an incumbent. • Do you really want to sue your (potential) client? ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 5
  • 6. www.smithlaw.com Can you protest? • What is your basis? – Specification deficiencies. – Winner not qualified for set-aside. • Priority to HUBZone contractor vs. 8(a) and SDVO. • Mission Critical Solutions v. United States (Mar. 3, 2010). – Agency awarded to a non-responsive or non-responsible bidder. • Evaluation deficiencies (unequal treatment, etc.). • Organizational Conflicts of interest . • Technical merits (hard). – Other reasons ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 6
  • 7. www.smithlaw.com “Interested Party” An interested party is an “actual or prospective bidder or offeror whose direct economic interest would be affected by the award of the contract or failure to award the contract.” 31 U.S.C. 3551(2); 4 C.F.R. 21. ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 7
  • 8. www.smithlaw.com “Interested Party” • Did you submit a bid? • A subcontractor to a disappointed bidder is not a bidder and cannot protest the bid of another. Eagle Design & Management, Inc. v. U.S. and Circle Solutions, Inc., No. 04-1200C (Court of Federal Claims, Sept.16, 2004) ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 8
  • 9. www.smithlaw.com “Interested Party” • Would you win if you prevail on the protest? • Protester must show it had a substantial chance of receiving the award but for the agency’s error in the procurement process. Rex Service Corp. v. United States, 448 F.3d 1305 (Fed. Cir. 2006). ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 9
  • 10. www.smithlaw.com Time Marches On • Timeframes very short. 4 C.F.R. § 21.2. – Improper solicitation? Protest before proposal deadline. – Other protests? Generally 10 days after basis of protest known – Size Protests? 5 working days after bid opening or after receipt of notification of awardee (for RFPs and RFQs) • Timeframes to request debriefing very short. – 3 days after notice of exclusion from competition or notice of contract award. 48 C.F.R. §15.505. ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 10
  • 11. www.smithlaw.com Where do I file? • Agency. • Government Accountability Office/Comptroller General. • Court of Federal Claims. • Agency, who forwards to the SBA (for size protests). ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 11
  • 12. www.smithlaw.com Agency Protest • Least formal, least expensive • Protester can request an independent review of the merits of its agency protest at a level above the CO. 55.103(d)(4). • Note: agency protest does extend deadline for filing GAO protest, but review of the protest does not extend deadline. 33.103(d)(5); 4 C.F.R. 21.2(a)(3) ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 12
  • 13. www.smithlaw.com Agency Protest • Format: – State prominently it is a “protest” – Addressed to Contracting Officer or designated official – Detailed fact and legal statement, including how protester has been harmed – Copies of relevant documents – A showing that the protest is timely – A showing that the protester an “interested party” – A request for ruling and a statement of the requested relief. FAR 33.103(d) ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 13
  • 14. www.smithlaw.com Agency Protest • Relief – Before award: correct the deficiency – After award: • Void contract (rare) • Terminate Contract for Convenience • Permit Award to stand • Direct a Re-evaluation • Award cost of pursuing protest, including fees. FAR 33.102; 4 C.F.R. Section 21.8 ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 14
  • 15. www.smithlaw.com GAO (Comptroller General) Protests • Procedures: 31 U.S.C. 3551; 4 CFR 21. • Strict timing deadlines – Comply or risk dismissal – File before GAO’s close of business, or the protest will be dated the next day (important for pre-award protests) – File Before bid opening for solicitation improprieties – Within 10 days after protest basis known for any other basis. – Within 10 days after debriefing (when requested) • Must send copy to agency within one day after filing within GAO. 4 C.F.R. 21.1(e) ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 15
  • 16. www.smithlaw.com GAO (Comptroller General) Protests • A Protest Can Stay of the Contract (absent compelling circumstances): – Protest before award prohibits agency from awarding contract. – Protest within 10 calendar days of award or within five days after a debriefing date is offered to the protester, the Contracting Officer must suspend contract performance or terminate the contract. • Notice must come from the GAO, not the protester. ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 16
  • 17. www.smithlaw.com GAO (Comptroller General) Protests • Content similar to Agency protests, and can ask for: – a protective order, – written document discovery, and – a hearing • Detailed statement of facts (not speculation) • After receipt, GAO will contact agency and ask for a detailed report and documents. 4 C.F.R. 21.3(a). • Agency report due within 30 days of GAO’s notice. Copies must go to protestor and intervenors. ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 17
  • 18. www.smithlaw.com GAO (Comptroller General) Protests • GAO can hold a hearing, though these are rare. • Decision is issued within 100 days of date of filing of the protest with the GAO. 4 C.F.R. 21.9(a). • Remedies: – GAO makes recommendations: • Refrain from exercising options under contract, recompete, issue a new solicitation, terminate, award a contract that complies with the law, or any of the above. – Costs may be awarded to the protester ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 18
  • 19. www.smithlaw.com GAO (Comptroller General) Protests • Agency has 60 days to implement recommendations or report failure to comply • Contracting Agency has “sound discretion” to remedy the procurement impropriety that formed the basis of the GAO recommendation. ST Aerospace Engines Pte. Ltd. B-275725, B- 275725.3 (1997). ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 19
  • 20. www.smithlaw.com Court of Federal Claims Protests • Only court forum (versus agency forum) to pursue a preaward or postaward protest. 28 U.S.C. 1491(b). • Party can file with COFC after bringing a GAO protest or instead of the GAO protest • COFC not bound by GAO decision, but it is given deference. ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 20
  • 21. www.smithlaw.com Court of Federal Claims Protests • No automatic stay: protestor must move for a temporary restraining order. • COFC will hold an initial status conference • Protective Orders may be sought to protect confidential information from disclosure. • Depositions and discovery is allowed. • Summary judgments or “paper trials” are typical ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 21
  • 22. www.smithlaw.com Court of Federal Claims Protests • COFC must decide whether agency’s actions were arbitrary, capricious, and abuse of discretion, or otherwise violative of the law • Protestor must show: – “Significant error” in the procurement process – Error resulted in “competitive prejudice” to the protestor: without the error, there was a “substantial chance” the protestor would have won the award. Alfa Laval Separation, Inc. v. United States, 175 F.3d 1365 (Fed. Cir. 1999). ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 22
  • 23. www.smithlaw.com Size Protests • A Business is “other than small” for a particular size standard set out in the procurement. 13 C.F.R. 121.1001 through 121.1007. • Protest filed with contracting officer. CO will forward to SBA. 13 CFR 121.1003. • Protest must be in writing specify reason and present evidence for claiming business is “other than small”. ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 23
  • 24. www.smithlaw.com Size Protests • SBA has 10 days to make size determination and notify contracting officer unless the SBA obtains more time. FAR 19.302. • SBA may ask challenged business for more information; failing to provide may result in an “other than small” determination. 13 CFR 121.1008(d). • Results of size determinations are entered into SBA database. ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 24
  • 25. www.smithlaw.com Protest Basis: Timeliness • Case Study: Ball Aerospace (2010). – Air Force RFQ’d a Blanket Purchase Agreement: • RFQ for services; some on a fixed price and some hourly. • RFQ but did not require vendors to estimate number of hours needed to perform requirements in statements of work. • RFQ required vendors to provide pricing based on unit pricing only. – AT&T’s price was 57% lower; Ball complained the evaluation of vendor’s price and technical quotes was flawed. – Result: Protest Denied as untimely. • Agency Must Evaluate Proposals considering cost the government. • But, a post-award challenge to the evaluation scheme is untimely. – GAO Protest B-402148 (Jan. 25, 2010). ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 25
  • 26. www.smithlaw.com Protest Basis: Non-Responsive Bids • Case Study: Irving Burton (2010). – Task Order Proposal Request from Army said: • proposals limited to 30 single-sided pages. • attachments limited to 10 single-sided pages each. – Winner’s Proposal Exceeded the Page Limits. – Result: Protest Sustained. • Agency Should Have Evaluated Proposal After Removing the Excess Pages. – In re: Irving Burton Associates: GAO Protest B-401983.3 (Mar. 29, 2010). ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 26
  • 27. www.smithlaw.com Protest Basis: OCI • Case Study: CACI (2011). – OCI claim related to DoD RFP for Records System: • BAH’s proposal $9.7 MM, almost $3MM than CACI’s. • CACI claimed BAH had access to CACI confidential information when BAH was a “support contractor” for the DPRIS system. • Contracting officer determined that BAH did not have “unequal access to information” that gave an unfair advantage. – Result: Protest Overruled. • CACI could point to no specific information that would have given BAH an unfair advantage in competing for the award. • CACI could not show that BAH improperly obtained confidential CACI information: CACI should have controlled its own information. – In re: CACI, inc.: GAO Protest B-403064.2 (Jan. 28, 2011). ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 27
  • 28. www.smithlaw.com Authority to Change Contract • Only contracting officer may enter into, administer, amend or terminate contracts. – FAR 1.601(a). – DFAR 252.201-7000(b). • Changes that are not in writing and approved by Contracting Officer might not be enforced. ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 28
  • 29. www.smithlaw.com Authority to Change Contract • Case Study: CATH-dr/Balti Joint Venture (2007). – Construction project for the Navy. – Contractor told to: • Direct all suggested changes to the Resident Officer in Charge of Contracts, who also was the Project Manager. • Perform no work outside the contract without written authorization from the ROICC/PM. – Court: ROICC/PM was not the Contracting Officer and therefore could not change construction contract. – CATH-dr/Balti Joint Venture, 497 F.3d 1339 (Fed. Cir. 2007). ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 29
  • 30. www.smithlaw.com Debriefings • FAR encourages debriefings. – Often changes protest deadlines – Encourages talking between bidders and agencies – Helps to improve future bids. • Always request a timely debriefing – In writing to CO within three days of award – Use information for future procurements or a bid protest • Even if untimely, ask for a debriefing. ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P. 30
  • 31. Questions? Jackson Moore jmoore@smithlaw.com (919) 821-6688 www.smithlaw.com ©2010 SMITH, ANDERSON, BLOUNT, DORSETT, MITCHELL & JERNIGAN, L.L.P.