SlideShare a Scribd company logo
1 of 2
Professional Profile
Land and Consents Surveyor
Matthew Anderson has over 2 years’ experience as a land officer dealing with land owners,
land agents, environmental agencies / contractors and solicitors. Matthew has worked on
some major projects for his client including 11kV rebuilds, 11kV and 33kV D poles as well as
schemes that are currently breaching health and safety regulations.
Matthew also has extensive knowledge of the countryside and environmental awareness.
Previous to being a land officer; Matthew studied Countryside, Conservation and Wildlife
Management for 4 years and moved onto Countryside Management at degree level at the
University of Greenwich for a final 2 years. This knowledge gives Matthew a great advantage
on site and in the office as Matthew arranges and manages ecological surveys from start
through to completion on his schemes where applicable, he also assists and supports his
colleagues on their surveys.
Key Skills
 Environmental Awareness
 Flora and Fauna Identification
 Project Planning
 Negotiation
Project Experience
Newick 09, 11kV Rebuild- UK Power Networks
The 11kv line consisting of 76 spans crossing the Newick area in East Sussex had been
programmed for a refurbishment by his client; Matthew had been given the responsibility of
obtaining consents for the scheme to be carried out over a timescale of three weeks.
Matthew had negotiated with a difficult land owner and their land agent to agree access
routes by carrying out a record of state and condition, This meant Matthew had gained the
trust of the landowner and land agent as well as giving them the security that their land
would be reinstated.
Matthew had also agreed access routes with a very large land owner in the area, he
managed the scheme professionally so the timing of the works would coincide with the large
game shoot which occurred for three months of the year, This land owner also had
government stewardship schemes in place on the land, this meant the rebuild on the land
would need to be carried out in sections to reduce damage and to give the land time to
recover, Matthew managed this scheme professionally and successfully with minimal
compensation claims received by his department.
Hoaden Court Farm, 11kV Rebuild and network reinforcement, part overhead and
part underground- UK Power Networks
Matthew had the responsibility of getting consents for the reinforcement of the network by
installing an 11kv cable in an existing easement strip and dealing with very difficult
landowners and their representatives. Matthew was also responsible for getting consents for
the 11kv overhead rebuild included in this reinforcement. Matthew had dealt with the scheme
professionally and carefully through to completion.
33kV-11kV D pole consents- UK Power Networks
These schemes required Matthew to get single site access forms and sometimes wayleave
agreements for poles that were decaying or decayed, Matthew was responsible for agreeing
access routes to the poles of which some were on an urgent basis, Matthew had also met
with land owners agents and other legal representatives on site to agree compensation
claims post construction.
Ashington- HV and LV overhead removal and LV cable installation. To eliminate
three ESQC’s- UK Power Networks
This scheme had been passed to Matthew after a number of health and safety issues had
been reported as well as voltage complaints in the area, the scheme involved the removal of
the LV overhead network to be replaced by LV underground cable, Matthew had to identify
and negotiate challenging cable routes with landowners, in total this scheme affected 18
properties. The scheme was ready for completion when a HV line removal scheme had
arisen which involved one of the same landowners, Matthew connected the schemes
together and identified another cable route to remove the health and safety issue from this
land owners property and agreed all consents with additional landowners in a small time
frame.
WSC Mountfield, 11kV rebuild and part undergrounding
This project was a UK Power Networks worst served customer scheme, of which involved an
11kv line refurbishment and an unused substation removal, Matthew had to liaise with land
owners and companies of which had strict on site safety regulations and environmental
policies to follow when the works are carried out on site. The scheme involved large
amounts of network undergrounding due to ESQC issues, Matthew handled the scheme
professionally through to completion.

More Related Content

Similar to Matthew Anderson- Professional Profile

Resume R_McCray FEB 2016
Resume R_McCray FEB 2016Resume R_McCray FEB 2016
Resume R_McCray FEB 2016
Robert McCray
 
CV john Halpin 6.4latest 30-01-17
CV john Halpin 6.4latest 30-01-17CV john Halpin 6.4latest 30-01-17
CV john Halpin 6.4latest 30-01-17
John William Halpin
 
Colgreen North Shore presentation-1.8a.13
Colgreen North Shore presentation-1.8a.13Colgreen North Shore presentation-1.8a.13
Colgreen North Shore presentation-1.8a.13
Graeme Donaldson
 
G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15
Greg Clifford
 
Reed Smith EME Environmental Law Services
Reed Smith EME Environmental Law ServicesReed Smith EME Environmental Law Services
Reed Smith EME Environmental Law Services
Adam Hedley
 
Example Sponsor Development Risk Assessment Report
Example Sponsor Development Risk Assessment ReportExample Sponsor Development Risk Assessment Report
Example Sponsor Development Risk Assessment Report
Ronald Moore
 
Electrical Resume Michael L Roesch 4Jan16 - Copy
Electrical Resume Michael L Roesch 4Jan16 - CopyElectrical Resume Michael L Roesch 4Jan16 - Copy
Electrical Resume Michael L Roesch 4Jan16 - Copy
Michael Roesch
 
dave resume sept 2015
dave resume sept 2015dave resume sept 2015
dave resume sept 2015
Dave Hoover
 
Construction Manager Resume
Construction Manager ResumeConstruction Manager Resume
Construction Manager Resume
Jack Dickerson
 
Combine cover letter and resume
Combine cover letter and resumeCombine cover letter and resume
Combine cover letter and resume
Rich St.Cyr
 

Similar to Matthew Anderson- Professional Profile (20)

Resume R_McCray FEB 2016
Resume R_McCray FEB 2016Resume R_McCray FEB 2016
Resume R_McCray FEB 2016
 
Case Study Solibra
Case Study SolibraCase Study Solibra
Case Study Solibra
 
CV john Halpin 6.4latest 30-01-17
CV john Halpin 6.4latest 30-01-17CV john Halpin 6.4latest 30-01-17
CV john Halpin 6.4latest 30-01-17
 
Colgreen North Shore presentation-1.8a.13
Colgreen North Shore presentation-1.8a.13Colgreen North Shore presentation-1.8a.13
Colgreen North Shore presentation-1.8a.13
 
My project list - James W. Kendrick
My project list - James W. KendrickMy project list - James W. Kendrick
My project list - James W. Kendrick
 
G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15
 
Project Experience
Project ExperienceProject Experience
Project Experience
 
Reed Smith EME Environmental Law Services
Reed Smith EME Environmental Law ServicesReed Smith EME Environmental Law Services
Reed Smith EME Environmental Law Services
 
CV~PW~02-02-16 Opus
CV~PW~02-02-16 OpusCV~PW~02-02-16 Opus
CV~PW~02-02-16 Opus
 
Example Sponsor Development Risk Assessment Report
Example Sponsor Development Risk Assessment ReportExample Sponsor Development Risk Assessment Report
Example Sponsor Development Risk Assessment Report
 
Electrical Resume Michael L Roesch 4Jan16 - Copy
Electrical Resume Michael L Roesch 4Jan16 - CopyElectrical Resume Michael L Roesch 4Jan16 - Copy
Electrical Resume Michael L Roesch 4Jan16 - Copy
 
dave resume sept 2015
dave resume sept 2015dave resume sept 2015
dave resume sept 2015
 
Ed resume 2017.docx current
Ed resume   2017.docx currentEd resume   2017.docx current
Ed resume 2017.docx current
 
CV_Jamie Allen
CV_Jamie AllenCV_Jamie Allen
CV_Jamie Allen
 
Construction Manager Resume
Construction Manager ResumeConstruction Manager Resume
Construction Manager Resume
 
Wind Farm Forum 2015: Ecological Risk Mitigation for the Australian Wind Indu...
Wind Farm Forum 2015: Ecological Risk Mitigation for the Australian Wind Indu...Wind Farm Forum 2015: Ecological Risk Mitigation for the Australian Wind Indu...
Wind Farm Forum 2015: Ecological Risk Mitigation for the Australian Wind Indu...
 
Combine cover letter and resume
Combine cover letter and resumeCombine cover letter and resume
Combine cover letter and resume
 
Cantrell Steve H
Cantrell Steve HCantrell Steve H
Cantrell Steve H
 
G1 Here Comes the Sun
G1 Here Comes the SunG1 Here Comes the Sun
G1 Here Comes the Sun
 
Ashraf Suleiman.
Ashraf Suleiman.Ashraf Suleiman.
Ashraf Suleiman.
 

Matthew Anderson- Professional Profile

  • 1. Professional Profile Land and Consents Surveyor Matthew Anderson has over 2 years’ experience as a land officer dealing with land owners, land agents, environmental agencies / contractors and solicitors. Matthew has worked on some major projects for his client including 11kV rebuilds, 11kV and 33kV D poles as well as schemes that are currently breaching health and safety regulations. Matthew also has extensive knowledge of the countryside and environmental awareness. Previous to being a land officer; Matthew studied Countryside, Conservation and Wildlife Management for 4 years and moved onto Countryside Management at degree level at the University of Greenwich for a final 2 years. This knowledge gives Matthew a great advantage on site and in the office as Matthew arranges and manages ecological surveys from start through to completion on his schemes where applicable, he also assists and supports his colleagues on their surveys. Key Skills  Environmental Awareness  Flora and Fauna Identification  Project Planning  Negotiation Project Experience Newick 09, 11kV Rebuild- UK Power Networks The 11kv line consisting of 76 spans crossing the Newick area in East Sussex had been programmed for a refurbishment by his client; Matthew had been given the responsibility of obtaining consents for the scheme to be carried out over a timescale of three weeks. Matthew had negotiated with a difficult land owner and their land agent to agree access routes by carrying out a record of state and condition, This meant Matthew had gained the trust of the landowner and land agent as well as giving them the security that their land would be reinstated. Matthew had also agreed access routes with a very large land owner in the area, he managed the scheme professionally so the timing of the works would coincide with the large game shoot which occurred for three months of the year, This land owner also had government stewardship schemes in place on the land, this meant the rebuild on the land would need to be carried out in sections to reduce damage and to give the land time to recover, Matthew managed this scheme professionally and successfully with minimal compensation claims received by his department.
  • 2. Hoaden Court Farm, 11kV Rebuild and network reinforcement, part overhead and part underground- UK Power Networks Matthew had the responsibility of getting consents for the reinforcement of the network by installing an 11kv cable in an existing easement strip and dealing with very difficult landowners and their representatives. Matthew was also responsible for getting consents for the 11kv overhead rebuild included in this reinforcement. Matthew had dealt with the scheme professionally and carefully through to completion. 33kV-11kV D pole consents- UK Power Networks These schemes required Matthew to get single site access forms and sometimes wayleave agreements for poles that were decaying or decayed, Matthew was responsible for agreeing access routes to the poles of which some were on an urgent basis, Matthew had also met with land owners agents and other legal representatives on site to agree compensation claims post construction. Ashington- HV and LV overhead removal and LV cable installation. To eliminate three ESQC’s- UK Power Networks This scheme had been passed to Matthew after a number of health and safety issues had been reported as well as voltage complaints in the area, the scheme involved the removal of the LV overhead network to be replaced by LV underground cable, Matthew had to identify and negotiate challenging cable routes with landowners, in total this scheme affected 18 properties. The scheme was ready for completion when a HV line removal scheme had arisen which involved one of the same landowners, Matthew connected the schemes together and identified another cable route to remove the health and safety issue from this land owners property and agreed all consents with additional landowners in a small time frame. WSC Mountfield, 11kV rebuild and part undergrounding This project was a UK Power Networks worst served customer scheme, of which involved an 11kv line refurbishment and an unused substation removal, Matthew had to liaise with land owners and companies of which had strict on site safety regulations and environmental policies to follow when the works are carried out on site. The scheme involved large amounts of network undergrounding due to ESQC issues, Matthew handled the scheme professionally through to completion.