SlideShare a Scribd company logo
1 of 5
Download to read offline
Name: Address:
Laurence Marchant Wynchlode House
Pinstock Lane
Gedney
PE12 0BT
Education:
School - JFS Free School
8 ‘O’ Levels, English, Maths, History, Geography, Chemistry, Physics, Biology & Art
University – University of West London
DMS
Career:
London Underground
Date Entered Service: July 1991
Role:
Revenue Control Inspector
Date Entered current Role 01st December 2003
Date: July 1993 to December 2003
I started with London Underground as a revenue protection inspector in July 1993, after 2
years I became part of the new Tout Squad, this comprised of 20 police officers and 20
revenue protection inspectors, this was a 1 year project and was a very successful squad
with a 98% conviction rate. We saved London Underground over £2 million pounds in
lost revenue during the project life.
At the end of the project I transferred to 55 Broadway and worked on a number of office
based projects.
From there I relocated to Ealing Common Depot where I developed and managed the
Minor Works Process and looked after a £4m budget for SSR, (Sub Surface Railway).
I had a staff of 3 persons. The work consisted of ensuring the best price for work
requested by the GSM of the line.
Date: December 2003 to November 2012
At the beginning of December 2003 I joined the Connect project as Building Control
Manager. This work comprised of ensuring that all work carried out for LUL Connect by
is contractors conformed to all then current legislation and LU standards. I carried out
site visits to inspect the work to ensure that it had been carried out to the correct standard
required by LU. I also managed the small works process whereby items that were not to
the correct LU / Legal standards, mainly in the Fire and Power disciplines had to be
corrected. This process would normally take around eight weeks for each item. I put
together a programme and funding that meant I had 36 contraventions corrected in 30
weeks.
At the completion of this part of the project my role changed to managing the handover
of assets to the InfraCo’s. This was a very complex role as I had to ensure that all assets
had the correct certification and met all legal requirements such as CER’s being one hour
compliant, and that all documents were to the standard required by the individual
InfraCo’s and included all the relevant information to maintain the rooms and the
equipment I them.
In order to ensure that all aspects were captured visualisation boards were used, this
meant that it was easy to track all disciplines and very quickly see which tasks had been
completed.
Once the procedure had been completed for the Metronet InfraCo the process was
repeated for Tublines. This occasion discussions resulted in a smarter handover from
lessons learnt and negotiations reduced the maintenance cost to LU from £8m to £1.2m
per year.
At this time I the process of bringing the Connect New Radio system live on the stations.
This entailed ensuring that testing at each station was carried out to the correct procedure
and reached the standard required. The first set of stations were brought in on a line
bases, this meant that some stations were running a dual radio system. This was not an
ideal situation so the process was changed to a group of station going live on the same
day. This proved to be very effective. The entire Connect system went live as per the
programme. Before each line could go live with the old radio system shut down the HRI
and the Fire Brigade had to be shown that the system was robust. I devised a system
where all the information required by the two authorities could be taken to them.
On the successful completion of all stations using the new Connect radio system I started
to manage the process of removing all the redundant radio equipment from each station.
During this process it was found that the Northern line radio and radio dating back to pre
legacy were not part of the contractual arrangement for removal. Discussions with
various contractors came to the conclusion that the cost to remove this redundant
equipment would be in the region of £250k - £350k. Negotiating this with our main
contractor I reduced the cost to LU to £150k
Towards the completion of this part of the Connect Project I started to manage the
Refresh Project. This part of Connect identifies and replaces all life expired equipment. It
is a complex project as new equipment has to be identified tested to meet LU and
contractual standards. The equipment is then installed in place tested and commissioned.
The commissioning process includes presenting to the Change Control Board both
technically and none technically the effect on the operational railway and how risk is
managed and alleviated.
During this process I am managing the relocation of seven GPS antennas which have
been identified as at risk due to their current location. I also assist with the Airwave
project as and when required.
Role Volunteer Work for Stroke Association
November 2013 – Present
I am the treasurer of the Spalding Group of the Stroke Association, covering usual duties
and assisting in the running of the group.
I am also increasing the awareness of stroke prevention and awareness in the
Lincolnshire
Summary of current experience
• Proficient with Microsoft Office Suite software
• Hold Quaff 54. Lucas Card, Lift & Escalator permit, Track Accustomed, Depot
Area A for Neasden and Northumberland Park Depots license.
• Achieved all targets set for the last 12 months P & D
• Sourced a 10 year storage deal with Yellow Box Company for the storage of
redundant radio equipment that must be stored in a secure environment until 2020
• Negotiated with Thales cost of removing redundant radio equipment on Northern
Line from £250,000 to £150,000 then a further £10,000 worth of work carried out
at no cost to LU
• Negotiated with Tublines the cost of maintenance of non radio equipment
installed on stations managed by them from £8.5m to £2.7 m.
• Managed the English Heritage procedure for all sites involved with the Connect
Project
• Managed the Building Control Process for Connect / Metronet
• Managed the minor Works process during the later stages of Connect completing
34 separate tasks in 30 weeks at a very large saving to LU Connect, successfully
bringing the close out of all remaining issues.
• Managed the completion of the Connect radio system on stations and brought the
system live line by station groups and line
• Managed the successful handover of assets from Connect to LU Metronet
• Managing the Connect Refresh Project starting with the Central and Jubilee lines
• Managing the safe removal of all redundant legacy radio, video and transmission
equipment
• Managing the swop over of 125 dual antenna to Cojot antennas
• Managing the Relocation of a number of GPS antennas over the network
• Carry out site visits for SSR Projects to confirm/allocate space for equipment
• Carry out site surveys to ensure that negative power applications can be submitted
with correct information
• Managing numerous sites for correct installation of relocated Connect equipment
by other projects
• Assisting with Airwave Project
• Testing of the Connect Train radio on the new SSR & VLU Stock
• Worked on several disciplines within the Connect Project since 2003, (new build,
station and train radio, English Heritage procedure, LU fire procedure)
• Working knowledge of Connect Radio System – often consulted by colleagues for
advice and/or site assistance to test coverage etc
• Knowledge of LU Operational Working systems
• Knowledge of most LU Stations
• Knowledge of English Heritage Procedure
• Knowledge of LU Fire Procedure
• Working Knowledge of both SSR and VLU new train radio system.
• Experience in managing small team of 2 contractors during the enabling stages of
Connect
• Managed the assurance process for Fire Compliance for all Connect new build
rooms
• Excellent site knowledge across the London Underground and Network Rail
networks.
• Excellent knowledge of the Connect installations and associated history of the
site.
• Good experience of analysing and negotiating commercial maintenance
agreements at all levels, inclusive of small contracts for the maintenance of UPS
systems to large contracts for the maintenance of all enabling assets with
Metronet and Tube Lines.
• Experience of using visualisation management to manage projects.
• Experience in undertaking site snagging on new installations.
• Skilled in obtaining permits to work for LU buildings.
• Experienced in managing a variety of different sized projects.
• Skilled in building good relationships with the contractor and other LU functions.
• Good knowledge of LUL standards.
• Experience of Network Rail processes.
• Knowledge and experience of LUL processes for CCB.

More Related Content

Viewers also liked

Refrigeration Basics
Refrigeration BasicsRefrigeration Basics
Refrigeration Basics
Alvin Bene
 

Viewers also liked (8)

SVN CV
SVN CVSVN CV
SVN CV
 
Jocs olimpics
Jocs olimpicsJocs olimpics
Jocs olimpics
 
Refrigeration Basics
Refrigeration BasicsRefrigeration Basics
Refrigeration Basics
 
queue & its applications
queue & its applicationsqueue & its applications
queue & its applications
 
Design of Air conditioning System
Design of Air conditioning System   Design of Air conditioning System
Design of Air conditioning System
 
Hvac Basics
Hvac Basics Hvac Basics
Hvac Basics
 
Recent Trends in Airport Operations
Recent Trends in Airport OperationsRecent Trends in Airport Operations
Recent Trends in Airport Operations
 
Security Aspects in Aviation Sector
Security Aspects in Aviation SectorSecurity Aspects in Aviation Sector
Security Aspects in Aviation Sector
 

Similar to LMCV

Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
Crosstown TO
 
JARED MUTU C.V
JARED MUTU C.VJARED MUTU C.V
JARED MUTU C.V
Jared Mutu
 
Ron Williams CV Feb 2017
Ron Williams CV Feb 2017Ron Williams CV Feb 2017
Ron Williams CV Feb 2017
Ron Williams
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Crosstown TO
 
CV_PhilMorris_2015
CV_PhilMorris_2015CV_PhilMorris_2015
CV_PhilMorris_2015
Phil Morris
 
Raymond Pears.cv June 2015
Raymond Pears.cv June 2015Raymond Pears.cv June 2015
Raymond Pears.cv June 2015
raymond pears
 
JVBResume_KSA_ 4_14
JVBResume_KSA_ 4_14JVBResume_KSA_ 4_14
JVBResume_KSA_ 4_14
Jim Boucher
 

Similar to LMCV (20)

CV~PW~02-02-16 Opus
CV~PW~02-02-16 OpusCV~PW~02-02-16 Opus
CV~PW~02-02-16 Opus
 
Moncrieff_Craig_CV
Moncrieff_Craig_CVMoncrieff_Craig_CV
Moncrieff_Craig_CV
 
Moncrieff_Craig_CV
Moncrieff_Craig_CVMoncrieff_Craig_CV
Moncrieff_Craig_CV
 
CL
CLCL
CL
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
 
Steve Lincoln CV
Steve Lincoln CVSteve Lincoln CV
Steve Lincoln CV
 
JARED MUTU C.V
JARED MUTU C.VJARED MUTU C.V
JARED MUTU C.V
 
Ron Williams CV Feb 2017
Ron Williams CV Feb 2017Ron Williams CV Feb 2017
Ron Williams CV Feb 2017
 
grobson cv
grobson cvgrobson cv
grobson cv
 
cv2016
cv2016cv2016
cv2016
 
Chet_FM 2 Rev
Chet_FM 2 RevChet_FM 2 Rev
Chet_FM 2 Rev
 
Caledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 finalCaledonia Fairbank Oakwood Open House Deck October 2017 final
Caledonia Fairbank Oakwood Open House Deck October 2017 final
 
CV_PhilMorris_2015
CV_PhilMorris_2015CV_PhilMorris_2015
CV_PhilMorris_2015
 
Western Cape Broadband Briefing to Cape Chamber ICT Committee
Western Cape Broadband Briefing to Cape Chamber ICT CommitteeWestern Cape Broadband Briefing to Cape Chamber ICT Committee
Western Cape Broadband Briefing to Cape Chamber ICT Committee
 
Driving Connectivity in the Scottish Islands: Droneways and Airmasts
Driving Connectivity in the Scottish Islands: Droneways and AirmastsDriving Connectivity in the Scottish Islands: Droneways and Airmasts
Driving Connectivity in the Scottish Islands: Droneways and Airmasts
 
Raymond Pears.cv June 2015
Raymond Pears.cv June 2015Raymond Pears.cv June 2015
Raymond Pears.cv June 2015
 
JVBResume_KSA_ 4_14
JVBResume_KSA_ 4_14JVBResume_KSA_ 4_14
JVBResume_KSA_ 4_14
 
Boo wind power in egypt
Boo wind power in egyptBoo wind power in egypt
Boo wind power in egypt
 
DML CV 17
DML CV 17DML CV 17
DML CV 17
 
HASSAN ALI CV1
HASSAN ALI CV1HASSAN ALI CV1
HASSAN ALI CV1
 

LMCV

  • 1. Name: Address: Laurence Marchant Wynchlode House Pinstock Lane Gedney PE12 0BT Education: School - JFS Free School 8 ‘O’ Levels, English, Maths, History, Geography, Chemistry, Physics, Biology & Art University – University of West London DMS Career: London Underground Date Entered Service: July 1991 Role: Revenue Control Inspector Date Entered current Role 01st December 2003 Date: July 1993 to December 2003 I started with London Underground as a revenue protection inspector in July 1993, after 2 years I became part of the new Tout Squad, this comprised of 20 police officers and 20 revenue protection inspectors, this was a 1 year project and was a very successful squad with a 98% conviction rate. We saved London Underground over £2 million pounds in lost revenue during the project life. At the end of the project I transferred to 55 Broadway and worked on a number of office based projects. From there I relocated to Ealing Common Depot where I developed and managed the Minor Works Process and looked after a £4m budget for SSR, (Sub Surface Railway). I had a staff of 3 persons. The work consisted of ensuring the best price for work
  • 2. requested by the GSM of the line. Date: December 2003 to November 2012 At the beginning of December 2003 I joined the Connect project as Building Control Manager. This work comprised of ensuring that all work carried out for LUL Connect by is contractors conformed to all then current legislation and LU standards. I carried out site visits to inspect the work to ensure that it had been carried out to the correct standard required by LU. I also managed the small works process whereby items that were not to the correct LU / Legal standards, mainly in the Fire and Power disciplines had to be corrected. This process would normally take around eight weeks for each item. I put together a programme and funding that meant I had 36 contraventions corrected in 30 weeks. At the completion of this part of the project my role changed to managing the handover of assets to the InfraCo’s. This was a very complex role as I had to ensure that all assets had the correct certification and met all legal requirements such as CER’s being one hour compliant, and that all documents were to the standard required by the individual InfraCo’s and included all the relevant information to maintain the rooms and the equipment I them. In order to ensure that all aspects were captured visualisation boards were used, this meant that it was easy to track all disciplines and very quickly see which tasks had been completed. Once the procedure had been completed for the Metronet InfraCo the process was repeated for Tublines. This occasion discussions resulted in a smarter handover from lessons learnt and negotiations reduced the maintenance cost to LU from £8m to £1.2m per year. At this time I the process of bringing the Connect New Radio system live on the stations. This entailed ensuring that testing at each station was carried out to the correct procedure and reached the standard required. The first set of stations were brought in on a line bases, this meant that some stations were running a dual radio system. This was not an ideal situation so the process was changed to a group of station going live on the same day. This proved to be very effective. The entire Connect system went live as per the programme. Before each line could go live with the old radio system shut down the HRI and the Fire Brigade had to be shown that the system was robust. I devised a system where all the information required by the two authorities could be taken to them. On the successful completion of all stations using the new Connect radio system I started to manage the process of removing all the redundant radio equipment from each station. During this process it was found that the Northern line radio and radio dating back to pre
  • 3. legacy were not part of the contractual arrangement for removal. Discussions with various contractors came to the conclusion that the cost to remove this redundant equipment would be in the region of £250k - £350k. Negotiating this with our main contractor I reduced the cost to LU to £150k Towards the completion of this part of the Connect Project I started to manage the Refresh Project. This part of Connect identifies and replaces all life expired equipment. It is a complex project as new equipment has to be identified tested to meet LU and contractual standards. The equipment is then installed in place tested and commissioned. The commissioning process includes presenting to the Change Control Board both technically and none technically the effect on the operational railway and how risk is managed and alleviated. During this process I am managing the relocation of seven GPS antennas which have been identified as at risk due to their current location. I also assist with the Airwave project as and when required. Role Volunteer Work for Stroke Association November 2013 – Present I am the treasurer of the Spalding Group of the Stroke Association, covering usual duties and assisting in the running of the group. I am also increasing the awareness of stroke prevention and awareness in the Lincolnshire Summary of current experience • Proficient with Microsoft Office Suite software • Hold Quaff 54. Lucas Card, Lift & Escalator permit, Track Accustomed, Depot Area A for Neasden and Northumberland Park Depots license. • Achieved all targets set for the last 12 months P & D • Sourced a 10 year storage deal with Yellow Box Company for the storage of redundant radio equipment that must be stored in a secure environment until 2020 • Negotiated with Thales cost of removing redundant radio equipment on Northern Line from £250,000 to £150,000 then a further £10,000 worth of work carried out at no cost to LU • Negotiated with Tublines the cost of maintenance of non radio equipment installed on stations managed by them from £8.5m to £2.7 m.
  • 4. • Managed the English Heritage procedure for all sites involved with the Connect Project • Managed the Building Control Process for Connect / Metronet • Managed the minor Works process during the later stages of Connect completing 34 separate tasks in 30 weeks at a very large saving to LU Connect, successfully bringing the close out of all remaining issues. • Managed the completion of the Connect radio system on stations and brought the system live line by station groups and line • Managed the successful handover of assets from Connect to LU Metronet • Managing the Connect Refresh Project starting with the Central and Jubilee lines • Managing the safe removal of all redundant legacy radio, video and transmission equipment • Managing the swop over of 125 dual antenna to Cojot antennas • Managing the Relocation of a number of GPS antennas over the network • Carry out site visits for SSR Projects to confirm/allocate space for equipment • Carry out site surveys to ensure that negative power applications can be submitted with correct information • Managing numerous sites for correct installation of relocated Connect equipment by other projects • Assisting with Airwave Project • Testing of the Connect Train radio on the new SSR & VLU Stock • Worked on several disciplines within the Connect Project since 2003, (new build, station and train radio, English Heritage procedure, LU fire procedure) • Working knowledge of Connect Radio System – often consulted by colleagues for advice and/or site assistance to test coverage etc • Knowledge of LU Operational Working systems • Knowledge of most LU Stations • Knowledge of English Heritage Procedure
  • 5. • Knowledge of LU Fire Procedure • Working Knowledge of both SSR and VLU new train radio system. • Experience in managing small team of 2 contractors during the enabling stages of Connect • Managed the assurance process for Fire Compliance for all Connect new build rooms • Excellent site knowledge across the London Underground and Network Rail networks. • Excellent knowledge of the Connect installations and associated history of the site. • Good experience of analysing and negotiating commercial maintenance agreements at all levels, inclusive of small contracts for the maintenance of UPS systems to large contracts for the maintenance of all enabling assets with Metronet and Tube Lines. • Experience of using visualisation management to manage projects. • Experience in undertaking site snagging on new installations. • Skilled in obtaining permits to work for LU buildings. • Experienced in managing a variety of different sized projects. • Skilled in building good relationships with the contractor and other LU functions. • Good knowledge of LUL standards. • Experience of Network Rail processes. • Knowledge and experience of LUL processes for CCB.