SlideShare a Scribd company logo
1 of 19
Download to read offline
The Foundation Examination
Multiple Choice
40 minutes Paper
Instructions
1. All 50 questions should be attempted.
2. All answers are to be marked on the answer grid provided.
3. Please use a pencil and NOT ink to mark your answers in the
Answer sheet provided.
4. There is only one correct answer per question.
5. You have 40 minutes for this paper.
6. You must get 25 or more correct to pass.
Candidate Number: .....................................…
© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV Foundation Examination
1 Which resources does the Value Ratio consider?
a) Money and time only
b) Money, time and quality only
c) Money, people, time, quality and materials only
d) Money, people, time, energy and materials only
2 Which statement describes Management of Value (MoV)?
a) A framework designed to minimise costs
b) A collective term for many processes that are aimed at maximising value
c) A means to establish objectives for an organisation
d) A management approach to encourage teamwork
3 Which statement regarding Management of Value is true?
a) It focuses exclusively on minimizing an organization’s costs
b) It ensures that all individual stakeholder needs are met
c) It supports decision-making based on maximizing value for money
d) It focuses on products rather than functions
2© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV Foundation Examination
4 For which combination of the following situations would an operational MoV Study normally be
considered advantageous?
1. A project has just been commissioned for use.
2. There is a need to improve existing service operations.
3. Once a project has successfully delivered its output.
4. There is a need to retain a service without end users.
a) 1, 2, 3
b) 1, 2, 4
c) 1, 3, 4
d) 2, 3, 4
5 Which is an example of delivering a tangible return on investment?
a) Completion of a project
b) A programme delivering a reduction in operating costs
c) MoV processes being followed
d) Expenditure of a project budget
6 Which is NOT one of the seven MoV principles?
a) Align with organizational objectives
b) Focus on deliverables and outputs
c) Learn from experience and improve
d) Tailor to suit the subject
3© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV Foundation Examination
7 Why should MoV activities align with an organization’s objectives or portfolio strategy?
a) Because MoV is the mechanism for delivering the outputs which will help an organization to
meet its objectives
b) To ensure that measures to maximize value in one area do NOT adversely impact on value
across the wider organization
c) To ensure that MoV activities can be carried out irrespective of the broader organizational
strategy
d) To ensure that there is an overlap of objectives between projects within a programme
8 Which questions does a Function Diagram answer when relating Value Drivers to project
objectives?
a) How and why
b) Who and what
c) When and who
d) How and what
9 Identify the missing word in the following sentence.
MoV reconciles the views of different stakeholders to maximise value by [ ? ] consensus on
differing expectations
a) brokering
b) requiring
c) preventing
d) measuring
4© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV Foundation Examination
10 What an essential responsibility for senior management when establishing MoV?
a) Defining the roles of each team member in an MoV study
b) Identifying key MoV Study stakeholders
c) Monitoring improvements in value
d) Actively backing the use of MoV in the organization
11 Which would NOT normally appear in a Business Case?
a) Expected Benefits
b) Expected Timescales
c) Project Team
d) Procurement Strategy
12 What is the main objective of conducting an MoV Study at the beginning of a potential
programme?
a) To establish the requirements for the MoV Project Plan
b) To strengthen existing information in order to decide whether or not to authorize the initiation of
a programme
c) To describe the purpose of a series of MoV Studies throughout a project
d) To test early models or prototypes before a design is fixed
5© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV Foundation Examination
13 Which is a key process used to gather information for an MoV Study?
a) Consult Stakeholders
b) Benchmark Competitors
c) Maintain Confidentiality
d) Examine the whole project
14 Which is a selection criterion for an MoV study team member?
a) Is available to join the Study
b) Has the skill and other abilities to contribute positively to a Study
c) Represents an important stakeholder
d) Has a passionate interest in the outputs of the Study
15 What is good practice to strengthen objectivity in a well-balanced MoV study team?
a) Motivating interaction between team members
b) Demonstrating knowledge of the issues and skills in providing a solution
c) Involving people who represent all critical disciplines and stakeholders views
d) Involving experienced people who are NOT otherwise involved in the project
6
© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV Foundation Examination
16 Which would be undertaken in the Process Information process?
a) Collate information gathered to date and document the analyses already conducted
b) Meet with key stakeholders to gain consensus on MoV Study objectives
c) Decide to implement part of a Value Improving Proposal
d) Review cost estimates to check for double counting
17 Why is team-building particularly important during an MoV Study?
a) MoV Study participants should collaborate
b) MoV requires a high-performance team to achieve results
c) MoV Studies often must be completed within tight timescales
d) MoV Studies expect all participants to add value
18 Which statement applies when establishing an MoV study team?
a) Each team member should have an interest in every aspect of the project
b) In the early stages of a project it is NOT necessary to involve all major stakeholders
c) The Study Leader should be responsible for selecting all roles of the study team
d) Team members should be selected for their skills and other abilities to contribute to a Study
7© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV Foundation Examination
19 Which is NOT a way of assessing performance impact?
a) Reviewing dependencies on the project schedule
b) Monitoring benefits realized
c) Reviewing achievement of Key Performance Indicators
d) Monitoring throughput or output per employee
20 Which statement concerning an assessment of Time Impact in a Value Improving Proposal is
true?
a) If a Value Improving Proposal takes a long time to implement it will normally delay the project
b) The time required for project management, holidays, and sickness should be included in the
assessment
c) It is essential to involve a professional scheduler to estimate duration and resource
requirements
d) Saving time through any Value Improving Proposal will reduce the overall duration of the project
21 Which statement regarding Function Analysis is true?
a) It focuses mainly on the identification of product components
b) It aims to stimulate creative ideas
c) It aims to minimize costs
d) It identifies potential solutions before defining functions in detail
8© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV Foundation Examination
22 Why is it important to tailor MoV to suit the subject?
a) To ensure the right level of resources are used
b) To ensure that it is applied to the same level on all projects and programmes
c) To eliminate the use of formal Studies where possible
d) To limit the unnecessary adherence to the Principles
23 Which is part of the Development or Presentation phases of the Value Engineering Job Plan?
a) Agree the implementation plan
b) Prepare a workshop handbook
c) Monitor progress of the implementation plan
d) Brainstorm ideas to improve value
24 Which is NOT a use of Value Profiling?
a) Testing key stakeholder agreement about requirements
b) Determining the relative importance of key stakeholders
c) Assisting with assessing improvements in performance
d) Assisting with assessing improvements in value
9© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV Foundation Examination
25 Which value index indicates the poorest performance and therefore has the most improvement
potential?
a) 50
b) 280
c) 600
d) 900
26 Which statement regarding the Value Index is true?
a) It shows how well a project satisfies its objectives
b) It must have a range between 1 and 10
c) It forms the basis for developing the Value Drivers
d) It shows whether a project delivers value for money
27 Which statement regarding the Value for Money Ratio is FALSE?
a) It enables project resources to be focused on areas offering the greatest value
b) It should only be used at the outset of a project
c) It can be used to monitor progress throughout a project
d) It can be used to inform option selection
10© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV Foundation Examination
28 Which is NOT one of the phases in the Value Engineering Job Plan?
a) Development
b) Creative
c) Implementation
d) Cost
29 Which statement regarding the Value for Money Ratio is true?
a) It enables resources to be deployed where they will provide greatest value
b) It considers only monetary benefits
c) It only applies at the start of a project
d) It should NOT take into account the Value Index
30 What is shown on a Value Tree?
a) All of the required product outputs for a project and the relationship between them
b) All of the cost elements and how they relate to project value
c) The relationship between, and the hierarchy of, Value Drivers
d) What project activities are required to realise desired project objectives
11© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV Foundation Examination
31 Why is discounted cash flow analysis (DCF) useful in MoV Studies?
a) It calculates total cost by adding together initial capital costs, periodic capital costs over the
lifecycle, and regular costs such as staff or consumables for operations
b) It is a reliable and rigorous method for comparing alternative options which involve large capital
cost more than 25 years in the future
c) It enables comparison of Projects which involve different cash flow timing
d) It is designed to ensure that Value Improving Proposals will generate positive cash flows in
each year
32 Which technique is used to select the most promising option for further analysis from a small
number of options?
a) Value Tree
b) Evaluation Matrix
c) Value Driver
d) Value Improving Proposal
33 Which statement regarding Discounted Cash Flow Analysis is true?
a) It shows the effect of discounting prices to increase sales
b) It uses the Net Present Value to show the current value of a proposed investment
c) It adds together project costs without considering when the costs are incurred
d) It is used over a time period of more than ten years
12
© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV Foundation Examination
34 Which describes the ‘paired comparison technique’ as applied in an MoV Study?
a) A method which combines the two most important Value Drivers and evaluates their combined
importance
b) A method which combines the two most useful Value Improvement Proposals and evaluates
their combined effectiveness
c) A method which achieves consensus by requiring team members to work in pairs when
preparing to make decisions
d) A method which assesses the relative weighting of attributes by requiring team members to
compare the relative performance of two items at a time
35 Which combination of the following criteria would influence the choice of weighting technique to
use in an MoV Study?
1. Minimize the contributors ability to bias results
2. Eliminate any measure of subjectivity
3. Enable prioritization of Value Drivers
4. Focus on guidance rather than establishing facts
a) 1, 2, 3
b) 1, 2, 4
c) 1, 3, 4
d) 2, 3, 4
36 What technique is BEST for generating a large number of ways to improve value and stimulate
innovation?
a) Brainstorm in open discussion to trigger ideas and record the best ideas
b) Brainstorm using the Function Analysis model as a guide to focus creative thinking
c) Use creative thinking to evaluate each idea as it is identified, reject the unsuitable, and
maximize innovative ideas
d) Maintain live and visible records which assess the financial impact of each idea identified in
order to maintain focus on innovative ideas
13© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV Foundation Examination
37 Which technique produces diagrams representing information flows, roles and principal
controls in order to understand how an organization works?
a) Benchmarking
b) Root Cause Analysis
c) Process Mapping
d) Discounted Cash Flow Analysis
38 Which is an output of an Option Evaluation Matrix?
a) Value Driver
b) Criterion Weight
c) Value for Money
d) Option Cost
39 What question does Root Cause Analysis primarily ask to establish the root cause of a
problem?
a) What
b) When
c) Why
d) Who
14© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV Foundation Examination
40 Which is a technique for generating a large volume of ideas?
a) Brainstorming
b) Option Evaluation Matrix
c) Discounted Cash Flow
d) Function Analysis
41 In what sequence would the following steps occur in the generic MoV Project Plan?
1. Gather and analyze information
2. Define the MoV Study objectives
3. Provide training, if necessary, to enable the participants to contribute effectively
a) 2, 1, 3
b) 1, 2, 3
c) 3, 1, 2
d) 2, 3, 1
42 Which statement regarding MoV activities is true?
a) They should only be conducted at the start of a project
b) Their effectiveness should be reviewed at the end of a project
c) Lessons learned from a project should NOT affect ‘business as usual’ activities
d) In a programme environment, MoV activities should only be carried out at the programme level
15
© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV Foundation Examination
43 Who should establish the Value Profile for a Project?
a) The MoV Study Leader
b) The Project Owners and End Users
c) The Project Delivery Team
d) The MoV Study Leader and Project Delivery Team
44 What should an MoV Study Leader do to gain a better understanding of an organization’s
business drivers?
a) Understand the organization’s culture
b) Understand what the organization does
c) Understand the organization’s market proposition
d) Understand the organization’s jargon
45 Which question is used to provoke a step change in Value?
a) What alternative product can we deliver?
b) Which component should be replaced?
c) How else can we perform the required function?
d) What cheaper product would be acceptable?
16© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV Foundation Examination
46 Which is generally true for MoV scenarios?
a) Only the best individual Value Improvement Proposals are implemented
b) Individual Value Improvement Proposals are grouped to show the aggregate effect over the
whole project
c) The Value Index of each scenario is maximized
d) The Value for Money Ratio of each scenario is maximized
47 Which statement concerning resource allocation is true?
a) Ways of increasing resource allocation should be considered when a Value Driver is relatively
unimportant and few resources are required to fulfil it
b) Ways of increasing resource allocation should be considered when a Value Driver is relatively
important and few resources are allocated to fulfil it
c) Resource allocation should be in direct proportion to the Value Profile for a product
d) The Cost/Worth method provides an indicator of whether resource allocation provides good
value
48 Why should the plan for implementing Value Improving Proposals be monitored?
a) MoV requires creation of a Benefits Management System
b) It records the person responsible for implementing each Value Improving Proposal
c) It ensures expected improvements in value are actually realized
d) MoV studies are commonly run on tight budgets
17
© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV Foundation Examination
49 Which is NOT likely to be an instruction to an MoV Study Leader who works in business
operations?
a) Proceed with the MoV Study once the project has delivered its outputs and has been
commissioned for use
b) Examine the need to improve existing service operations
c) Initiate an MoV Study whenever organizational circumstances change
d) Conduct an MoV Study with the aim of retaining the business operations which do NOT have
end users
50 Which activity should be done first when embedding MoV in an organization?
a) Assign roles and responsibilities
b) Capture and analyze data
c) Develop Study Leaders Handbook
d) Develop MoV Policy
18
© AXELOS Limited 2012
All rights reserved.
Reproduction of this material requires the permission of AXELOS Limited.
The swirl logo™ is a trade mark of AXELOS Limited
MoV® is a registered trade mark of AXELOS Limited
M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
MoV foundation sample paper

More Related Content

What's hot

The ultimate fast-track guide to PRINCE2 for PMP credential holders
The ultimate fast-track guide to PRINCE2 for PMP credential holdersThe ultimate fast-track guide to PRINCE2 for PMP credential holders
The ultimate fast-track guide to PRINCE2 for PMP credential holdersAlison Wood
 
Taklimat Ringkas Program AQPC IC and IQPC Bali 2019
Taklimat Ringkas Program AQPC IC and IQPC Bali 2019Taklimat Ringkas Program AQPC IC and IQPC Bali 2019
Taklimat Ringkas Program AQPC IC and IQPC Bali 2019Parman Ambo
 
2017 | E-Brochure | Professional Project Management - PPM (3 Days) | Project ...
2017 | E-Brochure | Professional Project Management - PPM (3 Days) | Project ...2017 | E-Brochure | Professional Project Management - PPM (3 Days) | Project ...
2017 | E-Brochure | Professional Project Management - PPM (3 Days) | Project ...Dcolearning
 
2021| PMFT | E-BROCHURE
2021| PMFT | E-BROCHURE2021| PMFT | E-BROCHURE
2021| PMFT | E-BROCHUREDcolearning
 
Prince2 & PMBOK Comparison Demystified
Prince2 & PMBOK Comparison DemystifiedPrince2 & PMBOK Comparison Demystified
Prince2 & PMBOK Comparison DemystifiedCTE Solutions Inc.
 
PMP vs Prince2 vs PMI-ACP
PMP vs Prince2 vs PMI-ACPPMP vs Prince2 vs PMI-ACP
PMP vs Prince2 vs PMI-ACPEdureka!
 
Agile certified exam outline
Agile certified exam outlineAgile certified exam outline
Agile certified exam outlinedhanyap2
 
Cmmaao pmi-test plan v1b
Cmmaao pmi-test plan v1bCmmaao pmi-test plan v1b
Cmmaao pmi-test plan v1bmission_vishvas
 
Test plan v1b cmmaao pmi pmp
Test plan v1b cmmaao pmi pmpTest plan v1b cmmaao pmi pmp
Test plan v1b cmmaao pmi pmppmicmmaao
 
Comparing PRINCE2 and the PMBok
Comparing PRINCE2 and the PMBokComparing PRINCE2 and the PMBok
Comparing PRINCE2 and the PMBokSimon Buehring
 
Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...
Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...
Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...Lviv Startup Club
 
Pmp project management professional
Pmp   project management professionalPmp   project management professional
Pmp project management professionalZabeel Institute
 
Prince2 Agile Frukostmöte
Prince2 Agile FrukostmötePrince2 Agile Frukostmöte
Prince2 Agile FrukostmöteLars Lundgren
 
Project management in_practice_a_guideline_and_toolbox_for_successful_projects
Project management in_practice_a_guideline_and_toolbox_for_successful_projectsProject management in_practice_a_guideline_and_toolbox_for_successful_projects
Project management in_practice_a_guideline_and_toolbox_for_successful_projectsPamelaRosaleschicago
 

What's hot (17)

The ultimate fast-track guide to PRINCE2 for PMP credential holders
The ultimate fast-track guide to PRINCE2 for PMP credential holdersThe ultimate fast-track guide to PRINCE2 for PMP credential holders
The ultimate fast-track guide to PRINCE2 for PMP credential holders
 
ince2pri
ince2priince2pri
ince2pri
 
Taklimat Ringkas Program AQPC IC and IQPC Bali 2019
Taklimat Ringkas Program AQPC IC and IQPC Bali 2019Taklimat Ringkas Program AQPC IC and IQPC Bali 2019
Taklimat Ringkas Program AQPC IC and IQPC Bali 2019
 
2017 | E-Brochure | Professional Project Management - PPM (3 Days) | Project ...
2017 | E-Brochure | Professional Project Management - PPM (3 Days) | Project ...2017 | E-Brochure | Professional Project Management - PPM (3 Days) | Project ...
2017 | E-Brochure | Professional Project Management - PPM (3 Days) | Project ...
 
2021| PMFT | E-BROCHURE
2021| PMFT | E-BROCHURE2021| PMFT | E-BROCHURE
2021| PMFT | E-BROCHURE
 
Prince2 & PMBOK Comparison Demystified
Prince2 & PMBOK Comparison DemystifiedPrince2 & PMBOK Comparison Demystified
Prince2 & PMBOK Comparison Demystified
 
PMP vs Prince2 vs PMI-ACP
PMP vs Prince2 vs PMI-ACPPMP vs Prince2 vs PMI-ACP
PMP vs Prince2 vs PMI-ACP
 
Agile certified exam outline
Agile certified exam outlineAgile certified exam outline
Agile certified exam outline
 
Cmmaao pmi-test plan v1b
Cmmaao pmi-test plan v1bCmmaao pmi-test plan v1b
Cmmaao pmi-test plan v1b
 
Test plan v1b cmmaao pmi pmp
Test plan v1b cmmaao pmi pmpTest plan v1b cmmaao pmi pmp
Test plan v1b cmmaao pmi pmp
 
Comparing PRINCE2 and the PMBok
Comparing PRINCE2 and the PMBokComparing PRINCE2 and the PMBok
Comparing PRINCE2 and the PMBok
 
Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...
Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...
Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...
 
ppm-brochure
ppm-brochureppm-brochure
ppm-brochure
 
Pmp project management professional
Pmp   project management professionalPmp   project management professional
Pmp project management professional
 
Prince2 Agile Frukostmöte
Prince2 Agile FrukostmötePrince2 Agile Frukostmöte
Prince2 Agile Frukostmöte
 
Project management in_practice_a_guideline_and_toolbox_for_successful_projects
Project management in_practice_a_guideline_and_toolbox_for_successful_projectsProject management in_practice_a_guideline_and_toolbox_for_successful_projects
Project management in_practice_a_guideline_and_toolbox_for_successful_projects
 
Simulado Scrum master
Simulado Scrum masterSimulado Scrum master
Simulado Scrum master
 

Similar to MoV foundation sample paper

En p2 a_prac_2015_samplepaper1_questionbk_v6.0
En p2 a_prac_2015_samplepaper1_questionbk_v6.0En p2 a_prac_2015_samplepaper1_questionbk_v6.0
En p2 a_prac_2015_samplepaper1_questionbk_v6.0Matt Trigg
 
Establishing an Effective PMO
Establishing an Effective PMOEstablishing an Effective PMO
Establishing an Effective PMOBusiness Beam
 
Economics 430–Applied EconometricsHomework #2 (100 Points).docx
Economics 430–Applied EconometricsHomework #2 (100 Points).docxEconomics 430–Applied EconometricsHomework #2 (100 Points).docx
Economics 430–Applied EconometricsHomework #2 (100 Points).docxmadlynplamondon
 
Ad september 2014 exam final
Ad september 2014 exam   finalAd september 2014 exam   final
Ad september 2014 exam finalLo Wai
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1Daniel Hucks
 
APMP More MC Questions
APMP More MC QuestionsAPMP More MC Questions
APMP More MC QuestionsMonica Waters
 
Project management 3rd sem - smu mba solved assignments
Project management  3rd   sem - smu mba solved assignmentsProject management  3rd   sem - smu mba solved assignments
Project management 3rd sem - smu mba solved assignmentssmumbahelp
 
TOGAF-IntroAndPrelim_v0.1.pdf
TOGAF-IntroAndPrelim_v0.1.pdfTOGAF-IntroAndPrelim_v0.1.pdf
TOGAF-IntroAndPrelim_v0.1.pdfssuser200e7a1
 
Gsgm7523 strategic human resource management
Gsgm7523 strategic human resource managementGsgm7523 strategic human resource management
Gsgm7523 strategic human resource managementVivagan Elengovan
 
What is the business value of my project?
What is the business value of my project?What is the business value of my project?
What is the business value of my project?Joe Raynus
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and schedulingsmumbahelp
 
Project Management Silibus
Project Management SilibusProject Management Silibus
Project Management SilibusIzah Asmadi
 
Evaluation Report - The Many Faces of Collaboration
Evaluation Report - The Many Faces of CollaborationEvaluation Report - The Many Faces of Collaboration
Evaluation Report - The Many Faces of CollaborationAssociation of Colleges
 
Solution Challenge '24 GDSC Pillai College of Engineering
Solution Challenge '24 GDSC Pillai College of EngineeringSolution Challenge '24 GDSC Pillai College of Engineering
Solution Challenge '24 GDSC Pillai College of EngineeringAnandMenon54
 
Front-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas IndustryFront-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas IndustryDavid Pires
 

Similar to MoV foundation sample paper (20)

En p2 a_prac_2015_samplepaper1_questionbk_v6.0
En p2 a_prac_2015_samplepaper1_questionbk_v6.0En p2 a_prac_2015_samplepaper1_questionbk_v6.0
En p2 a_prac_2015_samplepaper1_questionbk_v6.0
 
Establishing an Effective PMO
Establishing an Effective PMOEstablishing an Effective PMO
Establishing an Effective PMO
 
Economics 430–Applied EconometricsHomework #2 (100 Points).docx
Economics 430–Applied EconometricsHomework #2 (100 Points).docxEconomics 430–Applied EconometricsHomework #2 (100 Points).docx
Economics 430–Applied EconometricsHomework #2 (100 Points).docx
 
Ad september 2014 exam final
Ad september 2014 exam   finalAd september 2014 exam   final
Ad september 2014 exam final
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
 
APMP More MC Questions
APMP More MC QuestionsAPMP More MC Questions
APMP More MC Questions
 
101 mba1 (1)
101 mba1 (1)101 mba1 (1)
101 mba1 (1)
 
Project management 3rd sem - smu mba solved assignments
Project management  3rd   sem - smu mba solved assignmentsProject management  3rd   sem - smu mba solved assignments
Project management 3rd sem - smu mba solved assignments
 
TOGAF-IntroAndPrelim_v0.1.pdf
TOGAF-IntroAndPrelim_v0.1.pdfTOGAF-IntroAndPrelim_v0.1.pdf
TOGAF-IntroAndPrelim_v0.1.pdf
 
AXELOS - MoV® - Management of Value - Foundation
AXELOS - MoV® - Management of Value - FoundationAXELOS - MoV® - Management of Value - Foundation
AXELOS - MoV® - Management of Value - Foundation
 
Gsgm7523 strategic human resource management
Gsgm7523 strategic human resource managementGsgm7523 strategic human resource management
Gsgm7523 strategic human resource management
 
What is the business value of my project?
What is the business value of my project?What is the business value of my project?
What is the business value of my project?
 
Dawn Thompson
Dawn ThompsonDawn Thompson
Dawn Thompson
 
Karthik Mahadevan
Karthik MahadevanKarthik Mahadevan
Karthik Mahadevan
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and scheduling
 
Project Management Silibus
Project Management SilibusProject Management Silibus
Project Management Silibus
 
Evaluation Report - The Many Faces of Collaboration
Evaluation Report - The Many Faces of CollaborationEvaluation Report - The Many Faces of Collaboration
Evaluation Report - The Many Faces of Collaboration
 
Rane
RaneRane
Rane
 
Solution Challenge '24 GDSC Pillai College of Engineering
Solution Challenge '24 GDSC Pillai College of EngineeringSolution Challenge '24 GDSC Pillai College of Engineering
Solution Challenge '24 GDSC Pillai College of Engineering
 
Front-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas IndustryFront-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas Industry
 

Recently uploaded

Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insightsseri bangash
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 

Recently uploaded (20)

Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insights
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 

MoV foundation sample paper

  • 1. The Foundation Examination Multiple Choice 40 minutes Paper Instructions 1. All 50 questions should be attempted. 2. All answers are to be marked on the answer grid provided. 3. Please use a pencil and NOT ink to mark your answers in the Answer sheet provided. 4. There is only one correct answer per question. 5. You have 40 minutes for this paper. 6. You must get 25 or more correct to pass. Candidate Number: .....................................… © AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
  • 2. MoV Foundation Examination 1 Which resources does the Value Ratio consider? a) Money and time only b) Money, time and quality only c) Money, people, time, quality and materials only d) Money, people, time, energy and materials only 2 Which statement describes Management of Value (MoV)? a) A framework designed to minimise costs b) A collective term for many processes that are aimed at maximising value c) A means to establish objectives for an organisation d) A management approach to encourage teamwork 3 Which statement regarding Management of Value is true? a) It focuses exclusively on minimizing an organization’s costs b) It ensures that all individual stakeholder needs are met c) It supports decision-making based on maximizing value for money d) It focuses on products rather than functions 2© AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
  • 3. MoV Foundation Examination 4 For which combination of the following situations would an operational MoV Study normally be considered advantageous? 1. A project has just been commissioned for use. 2. There is a need to improve existing service operations. 3. Once a project has successfully delivered its output. 4. There is a need to retain a service without end users. a) 1, 2, 3 b) 1, 2, 4 c) 1, 3, 4 d) 2, 3, 4 5 Which is an example of delivering a tangible return on investment? a) Completion of a project b) A programme delivering a reduction in operating costs c) MoV processes being followed d) Expenditure of a project budget 6 Which is NOT one of the seven MoV principles? a) Align with organizational objectives b) Focus on deliverables and outputs c) Learn from experience and improve d) Tailor to suit the subject 3© AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
  • 4. MoV Foundation Examination 7 Why should MoV activities align with an organization’s objectives or portfolio strategy? a) Because MoV is the mechanism for delivering the outputs which will help an organization to meet its objectives b) To ensure that measures to maximize value in one area do NOT adversely impact on value across the wider organization c) To ensure that MoV activities can be carried out irrespective of the broader organizational strategy d) To ensure that there is an overlap of objectives between projects within a programme 8 Which questions does a Function Diagram answer when relating Value Drivers to project objectives? a) How and why b) Who and what c) When and who d) How and what 9 Identify the missing word in the following sentence. MoV reconciles the views of different stakeholders to maximise value by [ ? ] consensus on differing expectations a) brokering b) requiring c) preventing d) measuring 4© AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
  • 5. MoV Foundation Examination 10 What an essential responsibility for senior management when establishing MoV? a) Defining the roles of each team member in an MoV study b) Identifying key MoV Study stakeholders c) Monitoring improvements in value d) Actively backing the use of MoV in the organization 11 Which would NOT normally appear in a Business Case? a) Expected Benefits b) Expected Timescales c) Project Team d) Procurement Strategy 12 What is the main objective of conducting an MoV Study at the beginning of a potential programme? a) To establish the requirements for the MoV Project Plan b) To strengthen existing information in order to decide whether or not to authorize the initiation of a programme c) To describe the purpose of a series of MoV Studies throughout a project d) To test early models or prototypes before a design is fixed 5© AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
  • 6. MoV Foundation Examination 13 Which is a key process used to gather information for an MoV Study? a) Consult Stakeholders b) Benchmark Competitors c) Maintain Confidentiality d) Examine the whole project 14 Which is a selection criterion for an MoV study team member? a) Is available to join the Study b) Has the skill and other abilities to contribute positively to a Study c) Represents an important stakeholder d) Has a passionate interest in the outputs of the Study 15 What is good practice to strengthen objectivity in a well-balanced MoV study team? a) Motivating interaction between team members b) Demonstrating knowledge of the issues and skills in providing a solution c) Involving people who represent all critical disciplines and stakeholders views d) Involving experienced people who are NOT otherwise involved in the project 6 © AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
  • 7. MoV Foundation Examination 16 Which would be undertaken in the Process Information process? a) Collate information gathered to date and document the analyses already conducted b) Meet with key stakeholders to gain consensus on MoV Study objectives c) Decide to implement part of a Value Improving Proposal d) Review cost estimates to check for double counting 17 Why is team-building particularly important during an MoV Study? a) MoV Study participants should collaborate b) MoV requires a high-performance team to achieve results c) MoV Studies often must be completed within tight timescales d) MoV Studies expect all participants to add value 18 Which statement applies when establishing an MoV study team? a) Each team member should have an interest in every aspect of the project b) In the early stages of a project it is NOT necessary to involve all major stakeholders c) The Study Leader should be responsible for selecting all roles of the study team d) Team members should be selected for their skills and other abilities to contribute to a Study 7© AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
  • 8. MoV Foundation Examination 19 Which is NOT a way of assessing performance impact? a) Reviewing dependencies on the project schedule b) Monitoring benefits realized c) Reviewing achievement of Key Performance Indicators d) Monitoring throughput or output per employee 20 Which statement concerning an assessment of Time Impact in a Value Improving Proposal is true? a) If a Value Improving Proposal takes a long time to implement it will normally delay the project b) The time required for project management, holidays, and sickness should be included in the assessment c) It is essential to involve a professional scheduler to estimate duration and resource requirements d) Saving time through any Value Improving Proposal will reduce the overall duration of the project 21 Which statement regarding Function Analysis is true? a) It focuses mainly on the identification of product components b) It aims to stimulate creative ideas c) It aims to minimize costs d) It identifies potential solutions before defining functions in detail 8© AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
  • 9. MoV Foundation Examination 22 Why is it important to tailor MoV to suit the subject? a) To ensure the right level of resources are used b) To ensure that it is applied to the same level on all projects and programmes c) To eliminate the use of formal Studies where possible d) To limit the unnecessary adherence to the Principles 23 Which is part of the Development or Presentation phases of the Value Engineering Job Plan? a) Agree the implementation plan b) Prepare a workshop handbook c) Monitor progress of the implementation plan d) Brainstorm ideas to improve value 24 Which is NOT a use of Value Profiling? a) Testing key stakeholder agreement about requirements b) Determining the relative importance of key stakeholders c) Assisting with assessing improvements in performance d) Assisting with assessing improvements in value 9© AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
  • 10. MoV Foundation Examination 25 Which value index indicates the poorest performance and therefore has the most improvement potential? a) 50 b) 280 c) 600 d) 900 26 Which statement regarding the Value Index is true? a) It shows how well a project satisfies its objectives b) It must have a range between 1 and 10 c) It forms the basis for developing the Value Drivers d) It shows whether a project delivers value for money 27 Which statement regarding the Value for Money Ratio is FALSE? a) It enables project resources to be focused on areas offering the greatest value b) It should only be used at the outset of a project c) It can be used to monitor progress throughout a project d) It can be used to inform option selection 10© AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
  • 11. MoV Foundation Examination 28 Which is NOT one of the phases in the Value Engineering Job Plan? a) Development b) Creative c) Implementation d) Cost 29 Which statement regarding the Value for Money Ratio is true? a) It enables resources to be deployed where they will provide greatest value b) It considers only monetary benefits c) It only applies at the start of a project d) It should NOT take into account the Value Index 30 What is shown on a Value Tree? a) All of the required product outputs for a project and the relationship between them b) All of the cost elements and how they relate to project value c) The relationship between, and the hierarchy of, Value Drivers d) What project activities are required to realise desired project objectives 11© AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
  • 12. MoV Foundation Examination 31 Why is discounted cash flow analysis (DCF) useful in MoV Studies? a) It calculates total cost by adding together initial capital costs, periodic capital costs over the lifecycle, and regular costs such as staff or consumables for operations b) It is a reliable and rigorous method for comparing alternative options which involve large capital cost more than 25 years in the future c) It enables comparison of Projects which involve different cash flow timing d) It is designed to ensure that Value Improving Proposals will generate positive cash flows in each year 32 Which technique is used to select the most promising option for further analysis from a small number of options? a) Value Tree b) Evaluation Matrix c) Value Driver d) Value Improving Proposal 33 Which statement regarding Discounted Cash Flow Analysis is true? a) It shows the effect of discounting prices to increase sales b) It uses the Net Present Value to show the current value of a proposed investment c) It adds together project costs without considering when the costs are incurred d) It is used over a time period of more than ten years 12 © AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
  • 13. MoV Foundation Examination 34 Which describes the ‘paired comparison technique’ as applied in an MoV Study? a) A method which combines the two most important Value Drivers and evaluates their combined importance b) A method which combines the two most useful Value Improvement Proposals and evaluates their combined effectiveness c) A method which achieves consensus by requiring team members to work in pairs when preparing to make decisions d) A method which assesses the relative weighting of attributes by requiring team members to compare the relative performance of two items at a time 35 Which combination of the following criteria would influence the choice of weighting technique to use in an MoV Study? 1. Minimize the contributors ability to bias results 2. Eliminate any measure of subjectivity 3. Enable prioritization of Value Drivers 4. Focus on guidance rather than establishing facts a) 1, 2, 3 b) 1, 2, 4 c) 1, 3, 4 d) 2, 3, 4 36 What technique is BEST for generating a large number of ways to improve value and stimulate innovation? a) Brainstorm in open discussion to trigger ideas and record the best ideas b) Brainstorm using the Function Analysis model as a guide to focus creative thinking c) Use creative thinking to evaluate each idea as it is identified, reject the unsuitable, and maximize innovative ideas d) Maintain live and visible records which assess the financial impact of each idea identified in order to maintain focus on innovative ideas 13© AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
  • 14. MoV Foundation Examination 37 Which technique produces diagrams representing information flows, roles and principal controls in order to understand how an organization works? a) Benchmarking b) Root Cause Analysis c) Process Mapping d) Discounted Cash Flow Analysis 38 Which is an output of an Option Evaluation Matrix? a) Value Driver b) Criterion Weight c) Value for Money d) Option Cost 39 What question does Root Cause Analysis primarily ask to establish the root cause of a problem? a) What b) When c) Why d) Who 14© AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
  • 15. MoV Foundation Examination 40 Which is a technique for generating a large volume of ideas? a) Brainstorming b) Option Evaluation Matrix c) Discounted Cash Flow d) Function Analysis 41 In what sequence would the following steps occur in the generic MoV Project Plan? 1. Gather and analyze information 2. Define the MoV Study objectives 3. Provide training, if necessary, to enable the participants to contribute effectively a) 2, 1, 3 b) 1, 2, 3 c) 3, 1, 2 d) 2, 3, 1 42 Which statement regarding MoV activities is true? a) They should only be conducted at the start of a project b) Their effectiveness should be reviewed at the end of a project c) Lessons learned from a project should NOT affect ‘business as usual’ activities d) In a programme environment, MoV activities should only be carried out at the programme level 15 © AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
  • 16. MoV Foundation Examination 43 Who should establish the Value Profile for a Project? a) The MoV Study Leader b) The Project Owners and End Users c) The Project Delivery Team d) The MoV Study Leader and Project Delivery Team 44 What should an MoV Study Leader do to gain a better understanding of an organization’s business drivers? a) Understand the organization’s culture b) Understand what the organization does c) Understand the organization’s market proposition d) Understand the organization’s jargon 45 Which question is used to provoke a step change in Value? a) What alternative product can we deliver? b) Which component should be replaced? c) How else can we perform the required function? d) What cheaper product would be acceptable? 16© AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
  • 17. MoV Foundation Examination 46 Which is generally true for MoV scenarios? a) Only the best individual Value Improvement Proposals are implemented b) Individual Value Improvement Proposals are grouped to show the aggregate effect over the whole project c) The Value Index of each scenario is maximized d) The Value for Money Ratio of each scenario is maximized 47 Which statement concerning resource allocation is true? a) Ways of increasing resource allocation should be considered when a Value Driver is relatively unimportant and few resources are required to fulfil it b) Ways of increasing resource allocation should be considered when a Value Driver is relatively important and few resources are allocated to fulfil it c) Resource allocation should be in direct proportion to the Value Profile for a product d) The Cost/Worth method provides an indicator of whether resource allocation provides good value 48 Why should the plan for implementing Value Improving Proposals be monitored? a) MoV requires creation of a Benefits Management System b) It records the person responsible for implementing each Value Improving Proposal c) It ensures expected improvements in value are actually realized d) MoV studies are commonly run on tight budgets 17 © AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1
  • 18. MoV Foundation Examination 49 Which is NOT likely to be an instruction to an MoV Study Leader who works in business operations? a) Proceed with the MoV Study once the project has delivered its outputs and has been commissioned for use b) Examine the need to improve existing service operations c) Initiate an MoV Study whenever organizational circumstances change d) Conduct an MoV Study with the aim of retaining the business operations which do NOT have end users 50 Which activity should be done first when embedding MoV in an organization? a) Assign roles and responsibilities b) Capture and analyze data c) Develop Study Leaders Handbook d) Develop MoV Policy 18 © AXELOS Limited 2012 All rights reserved. Reproduction of this material requires the permission of AXELOS Limited. The swirl logo™ is a trade mark of AXELOS Limited MoV® is a registered trade mark of AXELOS Limited M_o_V-ExamPaper-1-GBP210FSample1-110412SamplePaper1