SlideShare a Scribd company logo
1 of 38
Qualification of
HVAC systems
Case studies
• physical / technical tests
• risk analysis calibration
• risk analysis computerized systems

1
Table of Contents
1. Introduction

Figure slide 1: Silica gel and structure of
zeolite used as adsorbent for
dehumification of clean rooms to protect
products which are sensitive against
moisture exposion

2. HVAC design requirements
3. HVAC construction requirements

4. General HVAC qualification activities (DQ, IQ, OQ, PQ)
5. Physical / technical OQ and PQ tests for HVAC systems
6. Case study risk analysis for measurement and control unsits for HVAC
systems
7. Case study risk analysis computerized systems validation for HVAC systems
8. Summary

2
Introduction
 In pharmaceutical primary as well as in secondary manufacturing HVAC
systems are a major factor for the observance of cleanliness and product
purity.
 No wonder that the qualification activities of HVAC systems with their
measurement and control and computerized units are cost intensive and a
great deal of time.
 The key issues to keep HVAC qualification in quality, time, and costs are
 the understanding of interfaces beween product purity / characteristic, cleanliness zones,
HVAC functions and clean rooms requirements.
 the structured identification of critical functions and operations, the objective evaluation,
and the definition of appropriate measures (design, qualification, calibration, and
validation activities) in a documented way.

3
Introduction
 These key issues are the reason for the following seminar topics
listed below.
 Design and construction requirements of HVAC systems with their functions
and units.
 General HVAC qualification steps to ensure a sufficient scope and structered
approach,
 Specific physical and technical tests such as filter leak tests, measurement of
room difference pressures, temperature and humidity, capability study of
dehumification function.
 Method and practice of risk analysis to cover potential risks and to define the
scope and approach of calibration and computerized systems validation in
relation to HVAC systems.

4
HVAC design requirements
 The complexity resulting from the different requirements for air
quality in the various cleanliness zones, make it recommendable to
define up-front the following process criteria:
 Critical room parameters which affect product or materials (i.e. humidity) and
the corresponding acceptance limit.
 Which process operations present a reasonable potential for contamination.
 Which process or operations are not affected by room conditions (e.g. closed
systems).
 Potential sources of room contamination (outdoor air, process equipment /
operation, HVAC components, failure of HVAC functions...).
 Equipment failure modes (fans, room / zone fail safe modes, interlocks, user
action in the event of failure).

5
HVAC design requirements
 In establishing design criteria for critical parameters, consideration
should be given to operating ranges which will assist in the definition
of the tightness of control range of these parameters.
 The following tables will give
a conception for relevant
parameters in conjunction
with cleanliness zones used
in secondary manufacturing.

Process
tolerance

Action limit

Figure: The picture demonstrates
the relation of process, operation
ranges, limits, and tolerances.

Process range

Process limits

Process limits

Alert limit

Range of measurement and control unit

6
HVAC design requirements
 Typical parameters and ranges for the design of HVAC systems under
consideration of cleanliness zoning concept (table).
 If cleanliness zoning
requirements are different
Room
Room
relative
to product specific reRoom
Room air
relative
pressure in
Zone:
temperature
changes in
quirements the relevant parahumidity in
Pa:
in °C:
h :
%:
meters with their ranges,
to barometric
reference
tolerances, and limits should
be fixed and documented.
A
N/A (a)
40,0 ± 10,0
(a)
N/A (a)
-1

Example:
Products which are sensitive
to moisture (e.g. effervescence tablets).
In this case the setpoint, tolerances,
and limits of the dehumidification
is the major factor for
the conditioning.

B

22,0 ± 4,0

45,0 ± 15,0

30 - 90

30 - 45

C/1

22,0 ± 4,0

45,0 ± 15,0

20 - 50

20 - 30

D/2

22,0 ± 5,0

45,0 ± 15,0

5 - 30

10 - 15

E/3

20,0 ± 8,0

45,0 ± 15,0

4 – 10 (b)

0

4

Not defined

Not defined

Not defined

Not defined

(a) The driving factor in zone A is the laminar air speed of 0,45 ms-1 ± 0,09 ms-1 (b) Optional

7
HVAC design requirements
 Example layout
effervescents factory
Figure: The picure shows
humidity controlled areas.
Typically, exposed humiditysensitive products require
humidity control to 30,0 to 50,0
%, but different values are not
uncommen (e.g. effervescence
products). Process range can
also range to 10,0 % to 20,0 %
rel. humidity depending on
process and mixture of
components (acid / alkaline
gradient).

8
HVAC construction requirements
 In case of humidity sensitiveness a
dehumidification unit has to be
integrated / installed.
 Such a unit selected should not adversely
contaminate the product. Cooling coils generate
large quantities of condensate which must
drained properly to avoid microbial
contamination. Provisions should also be made
that no condensate droplets can be entrained
into the air stream passing throug the cooling
coils.
 Liquid and dry type desiccant systems should be
evaluated for potential carry-over of dessicant
into the supply air stream and the effect of such
carry-over on the exposed product.

9

Figure: Simplified picture of a small
dehumidification unit (cooling coils).
HVAC construction requirements
 General structure of a HVAC system
used in sterile manufacturing
of parenterals. Critical process steps
are covered by laminar air flow units.

Figure: In general the HVAC system includes several
basic units such as fresh / exhaust air, and air
conditioning units with their fans, filters, and
measurement and control instrumentation

 10
HVAC construction requirements
 Dehumidification method by adsorptive separation

Figures: The exchange of humidity happens in the slow rotating adsorption-rotor
(charched with silica gel).The humidity load will be desorbed by a countercurrent heated
air flow. The loaded air can be exhaust. There are different types available (heat recovery
unit or with integrated condenser). The adsorption process is frequently reversal and
continuous. Pictures authorized by Munters GmbH

 11
HVAC construction requirements
 Dehumidification by adsorption:
 Continuous working dehumidification (adsorbed layer / adsorbent made of silica or
zeolites). Simultaneous adsorption and regeneration.
 Supply with dry air flow ranges from 50 m3h-1 to 80.000 m3h-1.
 Adsorption as well as desorption results are a function of
 temperature of air to dehumidification unit,
 stable pressure conditions inside dehumidification unit,
 humidity load of inlet air (fresh air / recirculated air rate),
 angle velocity / revolutions per minute (adsorbed layer / rotor)
 and contact time with adsorbent as a function of air flow rate.

 Additional requirements are the proper insulation of the conditioned rooms, and
measures to eliminate electrostatic differential potential.

 12
General HVAC qualification activities (DQ, IQ, OQ, PQ)
 General acceptance criteria DQ: The design and its documentation
comply with user and GMP requirements. Chronology and trace
ability are covered. The main contents of the concept, basic, and
detail engineering are documented.

Figure: The DQ part of
Sulzers validation
structure matrix for clean
rooms and HVAC
systems

Clean rooms
HVAC

 13
General HVAC qualification activities (DQ, IQ, OQ, PQ)
 The IQ will bring the documented evidence that the as it is on site to
be installed system with its components, measurement and control
units and instrumentation, hardware / software(modules) complies
with the specification.
 The OQ will bring the documented
evidence that the operational
functions with its specific
parameters, ranges and limits
comply with the functional
requirements and specifications.
Figure: The IQ / OQ part of
Sulzers validation structure matrix
for clean rooms and HVAC
systems

Clean rooms
HVAC

 14
Physical / technical OQ and PQ tests for HVAC systems
 In addition to these
general tests (e.g.
power failure and
recovery tests,
verification of
functions and
sequences, verification of alarms
and interlocks...)
typical HVAC specific
tests has to be
performed.

Unidirectional
airflow / LAF:

Test:

Turbulent /
mixed airflow:

Differential pressure on filters

1

1

Room differential pressure

N/A

2, 3

Airflow velocity / uniformity

2, 3

Optional

Airflow volume / rate

2

2

Parallelism

2

N/A

Air flow patterns

Optional

Optional

Filter leak test / challenge test

2

2

Recovery

N/A

2

Room classification (airborne particle)

2

2

Particle fall out

Optional

Optional

Temperature, humidity

N/A

2, 3

1 := As built (ideally used to perform IQ); 2:= At rest (ideally used to perform OQ); 3:= Operational (ideally used to perform PQ)

 15
Physical / technical OQ and PQ tests for HVAC systems
 Determination of differential pressure on filters
 This preliminary test is performed to detect initial defects of filters,
 and to verify the pressure differential (for a defined flow) meets the value
specified by the vendor,
 and finally, where applicable, set the correct value of the alarm as indicated by
the vendor for triggering a filter replacement.

 Differential pressure between rooms
 This measurement consists in measuring with a calibrated manometer the
differential pressure existing between the inside of a clean room and the
surrounding areas as defined in the specifications.
 This determination should be made under various operational conditions such
as day mode, night mode, opening of doors, etc. to identify also situations when
the pressure differential can not be met and as a consequence the product may
be at risk.

 16
Physical / technical OQ and PQ tests for HVAC systems
 Determination of air flow velocity
 This verification is used to determine average airflow velocity and uniformity of
velocity within a clean room, clean zone or unidirectional flow work zone.
 This method is not recommended for non-unidirectional airflow cleanliness
zones; in that case the measurement of airflow volumes should be performed
instead.
 The airflow velocity is measured at a distance of 30 cm from the supply source
using an anemometer (therma / vane-type). The number of individual
measurements should be at least equal to 3 per m2. The duration of each
measurement should not less than 15 s.
 The uniformity of air flow velocity is defined as being the relative standard
deviation of the velocity, expressed as a percentage of the mean as follows:
Uniformity = standard deviation / average velocity * 100.
 The relative standard deviation (or uniformity) should not exceed 15 %, except
where otherwise specified.

 17
Physical / technical OQ and PQ tests for HVAC systems
 Measurement of air volume and uniformity – air exchange rate
 This procedure / verification is used to determine average airflow volume and
uniformity of volume wihin a clean room, clean zone or unidirectional flow work
zone.
 The airflow volume is measured from each terminal filter or supply diffuser by
using an electronic microanemometer with an appropriate airflow hood in a
manner that includes all of the air issuing from each single source.
 The uniformity should not exceed 15 %, except where otherwise specified.
 Total air volume will, in turn, be used to determine the air exchange rate (room
air volume per hour) for the clean room, as defined: Air exchange rate = total
airflow volume / volume of the room.

 18
Physical / technical OQ and PQ tests for HVAC systems
 Airflow parallelism test
 The purpose of the test is to verify the parallelism of air flow throuout the work
zone of a unidirectional airflow and wether the clean room is capable of limiting
the dispersion of internally generated contamination.
 The measurement is made using a isokinetic smoke generator and defining the
offset distance between the smoke streamline and the theoretical straight line
coming from the smoke outlet and parallel to the specified unidirectional airflow.
 The number of individual measurements should be equal to 1 / 10 m2.
 The angle of the offset should not exceed 14°.
 To be valid, such tests must be documented using video techniques.

 19
Physical / technical OQ and PQ tests for HVAC systems
 Determination of airflow patterns
 This verification is above all valuable for demonstrating the interactions of
airflow and equipment during the OQ phase, and for demonstrating the
effectiviness of aerodynamic barriers.
 This test should be considered as an alternative to differential pressure
between rooms (slide 16) and is particularly recommended for the initial
qualification of cleanliness zones (HVAC or clean rooms) where aerodynamic
barriers are employed instead of physical barriers and where therefore
acceptable differential pressures can not be achieved.
 The test consists of a visualisation of the air flow patterns, using a smoke or
other visible aerosol and is designed to show evidence that all air flows are as
expected.
 In addition it is also recommended for the initial qualification in the at rest mode
of all types of clean room to demonstrate absence of non desirable dead zones,
backflows, leaks or turbulances which may contaminate a critical part of a clean
zone. To be valid, such tests must be documented using video techniques.

 20
Physical / technical OQ and PQ tests for HVAC systems
 Filter installation leak test (challange test)
 These verifications are performed to confirm that HEPA and ULPA filters are
properly installed by verifying the absence of by-pass leakage in the installation
(frame, gasket seal, and filter bank framework) and that the filters are free of
defects and small leaks in the filter medium and frame seal.
 These tests are required for unidirectional airflows, but have only limited value
for non-unidirectional airflow systems.
 Tests are performed by introducing an aerosol challange upstream of the filters
and scanning immediatly downstream of the filters and support frame or
sampling in a downstream duct.
 In rooms with turbulent airflow, the filter installation leak test can be substituted
by in-situ vergification of the integral particle penetration value through the filter.
See VDI 2083, Blatt3 for further information.

 21
Physical / technical OQ and PQ tests for HVAC systems
 Determination of the recovery time
 This test is not recommended for unidirectional airflows. It is performed to
determine whether the clean room or clean zone is capable of returning to its
specified cleanliness class within a finite time, after being expoused to a source
of airborne particulate challange in form of smoke or aerosol.
 The result of this test is an important information for correct operation of the
system, because it defines also the minimum „hold“ time which should be taken
into account after power failure, start (recovery), mode change. See VDI 2083,
Blatt 3 for further infomation.

 Determination of room classification (airborne particle count
mapping)
 This test is performed to determine that the completed clean room can meet the
cleanliness class specified.

 22
Physical / technical OQ and PQ tests for HVAC systems
 The test consists in measuring the concentration of particles of a well defined
size in the clean room in order to prove with a defined confidence limit, that the
clean room complies with the cleanliness class.
 In case of unidirectional airflows, the sample points should include test points
located immediately upstream of the work activity level.
 All sample points must comply with the class limit.
 Fore more and detailed information refer US Fed. Std 209E / ISO 14644-1.
 If not performed in the operational mode, in the case of cleanliness zones
belonging to class A and B, this test must be repeated to take into account
generation of particles by operator, equipment or process. The main purpose is
then to identify worst case locations which should also be taken into account
when installing probes for continuous particle monitoring.

 23
Physical / technical OQ and PQ tests for HVAC systems
 Particle fallout test
 These tests are done by allowing a small test surface to collect natural particles
that settle out in the clean room area. The particles on the plate are counted
with a surface particle detection instrument and a particle-deposition rate is
determined.
 These verification could also be used in multipurpose / multi-product facilities to
support a demonstration of absence of croos contamination.

 Temperature level and uniformity test
 The purpose is to demonstrate the capability of the clean room / HVAC system
to maintain air temperature wihin the specified limits and over a certain period
of time.
 The result of this test can also be used to support qualification of the location of
fixed installed temperature monitoring devices.

 24
Physical / technical OQ and PQ tests for HVAC systems
 Humidity level and uniformity test
 The purpose of this test is to demonstrate the capability of the clean room
(HVAC system with (de)humidification units) to maintain air humidity levels
within the specified limits and over a certain period of time.
 The result of these tests can also be used to support
qualification of the location of fixed installed
humidity monitoring devices.

 The function and sequences of dehumidification
units must be carefully tested (main functions
see slide 12).
Figure: Mobile measurement
device for the acquisition of
humidity data.

 25
Case studies risk analysis
The FMEA is a tool for Quality Management that combines the technology and
experience of specialists in identifying failure modes.
In the Pharmaceutical Industry the regulatories of Good Manufacturing Practice
(GMP) demand a high level on quality assurance system and documentation.
Therefore the main intention of the FMEA is to
 identify
 evaluate
 and cover
GMP critical functions and process conditions
in a systematic, documented,
and objective way.

 26
Case studies risk analysis
 Typical applications in the Pharmaceutical Industry are
 qualification of technical equipment,
 calibration of measurement and control installations,
 validation of processes and computerized systems.

 In conjunction with an increasing uncertainty
 what,
 when,
 and how

to qualify, calibrate and maintain.

 27
Case studies risk analysis
In general, FMEA is the tool
 to prevent
 to confirm and
 to solve problems.

Entstehung von 75 % der Fehler

Behebung von 80 %
der Fehler

60
Fehlerbehebungskurve

55
50
45

Fehlerentstehungkurve

40
35

25

Fehlerquote

30

Failure removal costs

20
15
10

Design
incl.. DQ

Construction:
constructive
changes
...

Qualification:
redesign
new construction
delay of production
...

Production:
costs of delay
costs maintenance
loss of image
loss of market shares
...

5
0

Phases of project

 28

Planung

Konstruktion

Qualifizierung

Produktion

Figures: Most of the failures come into being
in a early project phase (design and
construction) and must be repaired cost
intensive in a late project phase. The FMEA
is a usefull tool to identify, evaluate and cover
potential failures.
Case studies risk analysis
A guide for a successfull FMEA used in Pharmaceutical Industry
 Systematic way of identification
 Objective way of evaluation
 Define criteria for evaluation.
 Form a team with speacialist‘s competence and the courage to make decisions.
 Set a trigger (yes/no) for decision of recommended actions.

 Define appropriate protective measures.
 Set a high level of documentation (create forms for
FMEA-documentation and recommended actions).

 29
Case studies risk analysis
 A potential risk is the hidden, unforeseen
occurrence of a failure with considerable
consequences.
 A potential risk is composed of
several factors:

D

S

 the occurence propability (O) that a
potential failure occur,
 the severity (S) of effects,
 the detection propability (D) that a
failure will be detected.

RPN = f(O, S, D)

O

 A potential risk is described by the risk priority number (RPN) as the
product of O, S, D.
Figure: Several factors of a risk potential.

 30
Case studies risk analysis
The FMEA involves four essential steps:

Start

1

 Identification of the potential failure with its
causes and effects.

Identify

2/4
(Re-) Evaluate

 Evaluation of the potential risk with the several
factors O, S, D and calculation of the risk
priority number (RPN).

no
Critical?

yes
3
Define
corrective
actions

 Establishing protective measures.
 Re-evalution of the improved conditions.

 31

Figure: Decision tree of
FMEA

End
Case study risk analysis for measurement and control unsits for
HVAC systems
 Objective 1: Reducing monitoring activities / costs and cover safty and
availability.
 Objective 2: Understanding interfaces between HVAC, clean room monitoring.
Find a logical / conclusive approach for calibration of HVAC / monitoring
instrumentation.
 Approach:
 The process parameter is leaving the normal prozess range in which the product quantity
and quality is covered into alert range. What is the occurance propability and the
consequences / sefirity for product quality? How can the detection propability evaluated
(e.g. respond other measurement and control unsits?
 The process parameter is crossing the limit to the action range. What is the occurance
propability and the consequences / sefirity for product quality? How can the detection
propability evaluated (e.g. respond other measurement and control unsits?

 32
Case study risk analysis for measurement and control unsits for
HVAC systems

Figure: Relation between normal prozess range, alert
range, and action range

 33
Case study risk analysis for measurement and control unsits for
HVAC systems
a ir in

a ir o u t

e q u ip m e n t# 5 2 5 4
3

m e a s u rin g & c o n tro l in s t a lla tio n s P L 3 :
PD SA 6190, PD SA 6265, M SA6187

2

m e a s u rin g & c o n tro l in s t a lla tio n s P L 2 :
T C 6 1 6 3 , T C 6 1 8 5 , M C 6 1 8 6 , P D A 6 1 4 5 , P S A 6 1 6 0 /1 /2 , T C
6 1 6 3 , P D IC 6 1 9 5 , P D A 6 2 6 0

P

f r e s h / e x h a u s t a ir u n it
e q u ip m e n t# .: 5 2 5 4

T
M

1

M

3

2

Figure(s): Evaluated
measurement and control
units of a HVAC unit

P

PDI

T

C le a n r o o m E .2 1 6
C la s s B

1

m e a s u rin g & c o n tro l in s t a lla tio n s P L 3 :
M 6516, S 1528, S 1538, S 1548, S 1566, S 1576
m e a s u rin g & c o n tro l in s t a lla tio n s P L 2 :
TC 6515, TC 6555, PD 6596, PD 6599, PD I 6571, PD I
6 5 7 2 , P D I 6 5 7 3 ...

m e a s u rin g & c o n tro l in s t a lla tio n s P L 1 :
T I 1 5 2 0 , T I 1 5 5 7 , T I1 5 5 8 , T I 1 5 6 7 , T I 1 5 6 8 , T I 1 5 7 7

e q u ip m e n t# 5 2 6 0

S
Q (L K Z )
Q ( P a r t .)

3

0421

0431

0432

2

p ro c e s s
s te p s

p ro c e s s
s te p s

m e a s u rin g & c o n tro l in s t a lla tio n s P L 2 :
n o n e , c le a n r o o m m o n ito r in g

1

m e a s u rin g & c o n tro l in s t a lla tio n s P L 1 :
n o n e , c le a n r o o m m o n ito r in g

P = p r e s s u r e d iffe r e n c e
T = te m p e ra tu re

p ro c e s s
s te p s

M = m o is tu r e
S = a ir v e lo c ity

c r it ic a l ( a s e p t ic ) p r o c e s s s t e p s in E . 2 1 6 ( la m in a r a ir f lo w p r o t e c t e d )

m e a s u rin g & c o n tro l in s t a lla tio n s P L 3 :
c l e a n r o o m m o n i t o r i n g s y s t e m ( o b je c t # 5 2 6 1 ) i n c l u d e s
Q ( L K Z ) 6 4 2 0 , Q (P a r t.) 6 4 1 0 , Q (P a r t.) 6 4 1 1 , Q ( L K Z ) 6 4 2 1 ,
Q ( P a rt.)6 4 1 2 , Q ( P a rt.)6 4 1 3 , Q ( P a rt.)6 4 1 4 , P D 6 4 0 1 ,
PD 6402, PD 6403, PD 6000, T6409

Q ( P a r t. ) = p a r tic le c o u n t in th e a ir
Q ( L K Z ) = c o u n t o f m ic r o o r g a n is m s in th e a ir

 34

distance to cleanroom class B

e q u ip m e n t# 5 2 5 1

T

s u b u n it# 0 5 1 0

level of protection (redundance, calibration period...)

a ir c o n d it io n in g u n it
e q u ip m e n t # 5 2 5 1

P

m e a s u rin g & c o n tro l in s t a lla tio n s P L 1 :
PD I 6121, PD SA 6155, TS 6175, TC 6225, PD I 6261, TI
1110, TI 1126, TI 1152, TI 1153, TI 1161, TI 1167, TI 1168,
P I 1 2 2 9 , P I 1 2 3 1 , P I 1 2 3 3 , P D S A 6 1 3 5 , P D I, 6 1 4 6 , P D S A
6 1 5 5 , P D S A 6 1 7 0 , T S 6 1 7 5 , ...
Case study risk analysis for measurement and control unsits for
HVAC systems
 Result of FMEA case study: Out of nearly 60 Measurement and
control units
 44 % have only to be adjusted. No calibration activities are required.
 26 % have to be adjusted and initial calibrated. No periodic calibration activities
are required.
 30 % (because of redundant design of clean room monitoring system) have to
be adjusted, initial and periodic calibrated.

 Reduction in costs: nearly 10.000,00 DM only because of reduced
initial calibration.

 35
Case study risk analysis computerized systems validation for
HVAC systems
 Approach:

Figure: Level of process
steps and level of
computerized function

B

D

E
P
(U roze
ni ß
t O fu
pe nkt
ra ion
tio e
ns n
)

C

C6

C1

B. Geis, xxxBRG_CSVEbenen_1_0

 36

C2

C4

C5

F
te un
r i s kt
ie ion
r te
sS
y

st

C3

em

A

co
m
pu

 Each essential process step
(e.g. A...E) will divided in the
functions of the computerized
system. Derive from reverse
function it is possible to identify
potential failures in a
systematic way.
 Because of that the CSV risk
analysis will cover the unit
operations as well as the
computerized system.
Figure: FMEA form used for CSV risk
analysis of clean room monitoring system

Case study risk analysis computerized systems validation for
HVAC systems

confidential

confidential

 37
Summary
 The key for a successful HVAC qualification are
 the understanding of interfaces beween product purity / characteristic,
cleanliness zones, HVAC functions and clean rooms requirements,
 the knowledge concerning general and HVAC specific tests,
 and the structured identification of critical functions and operations, the
objective evaluation, and the definition of appropriate measures (design,
qualification, calibration, and validation activities) in a documented way.

 38

More Related Content

What's hot

Validación De Sistemas De Gases De Proceso
Validación De Sistemas De Gases De ProcesoValidación De Sistemas De Gases De Proceso
Validación De Sistemas De Gases De Proceso
Crown Cork & Seal
 
Hvac validation protocol
Hvac validation protocolHvac validation protocol
Hvac validation protocol
vivekccpr21
 
Support utilities validation.pptx (asmita magare)
Support utilities validation.pptx (asmita magare)Support utilities validation.pptx (asmita magare)
Support utilities validation.pptx (asmita magare)
magareasmi
 

What's hot (20)

Hvac
HvacHvac
Hvac
 
Validation of water
Validation of waterValidation of water
Validation of water
 
Validation of hvac
Validation of hvacValidation of hvac
Validation of hvac
 
Testing/Manufacture/Hepa Filter Test rig
Testing/Manufacture/Hepa Filter Test rig Testing/Manufacture/Hepa Filter Test rig
Testing/Manufacture/Hepa Filter Test rig
 
Validación De Sistemas De Gases De Proceso
Validación De Sistemas De Gases De ProcesoValidación De Sistemas De Gases De Proceso
Validación De Sistemas De Gases De Proceso
 
Hvac validation protocol
Hvac validation protocolHvac validation protocol
Hvac validation protocol
 
Validation of hvac system
Validation of hvac systemValidation of hvac system
Validation of hvac system
 
Support utilities validation.pptx (asmita magare)
Support utilities validation.pptx (asmita magare)Support utilities validation.pptx (asmita magare)
Support utilities validation.pptx (asmita magare)
 
Validation of compressed air and nitrogen
Validation of compressed air and nitrogenValidation of compressed air and nitrogen
Validation of compressed air and nitrogen
 
Vallidation 25
Vallidation 25Vallidation 25
Vallidation 25
 
A practical approach to pharmaceutical HVAC energy reduction
A practical approach to pharmaceutical HVAC energy reductionA practical approach to pharmaceutical HVAC energy reduction
A practical approach to pharmaceutical HVAC energy reduction
 
Workshop On Risk Assesment by Palash Ch Das
Workshop On Risk Assesment by Palash Ch DasWorkshop On Risk Assesment by Palash Ch Das
Workshop On Risk Assesment by Palash Ch Das
 
Quality assurance maintenance of hvac system in pharmaceutical industry
Quality assurance maintenance of hvac system in pharmaceutical industryQuality assurance maintenance of hvac system in pharmaceutical industry
Quality assurance maintenance of hvac system in pharmaceutical industry
 
Water system validation by- Akshay kakde
Water system validation by- Akshay kakdeWater system validation by- Akshay kakde
Water system validation by- Akshay kakde
 
Validation of HVAC pharma geeta TUBE (Utility Systems)
Validation of HVAC pharma geeta TUBE (Utility Systems)Validation of HVAC pharma geeta TUBE (Utility Systems)
Validation of HVAC pharma geeta TUBE (Utility Systems)
 
HVAC system
 HVAC system HVAC system
HVAC system
 
HVAC & Water in Pharmaceutical Manufacturing; From Theory to Application
HVAC & Water in Pharmaceutical Manufacturing; From Theory to ApplicationHVAC & Water in Pharmaceutical Manufacturing; From Theory to Application
HVAC & Water in Pharmaceutical Manufacturing; From Theory to Application
 
Protocol for compressed air validation
Protocol for compressed air  validationProtocol for compressed air  validation
Protocol for compressed air validation
 
Tài liệu hệ thống HVAC ( Phần 1b) Giới thiệu và tổng quan
Tài liệu hệ thống HVAC ( Phần 1b) Giới thiệu và tổng quan Tài liệu hệ thống HVAC ( Phần 1b) Giới thiệu và tổng quan
Tài liệu hệ thống HVAC ( Phần 1b) Giới thiệu và tổng quan
 
Validation Of System For Compressed Air Quality
Validation Of System For Compressed Air Quality   Validation Of System For Compressed Air Quality
Validation Of System For Compressed Air Quality
 

Viewers also liked

Hvac Presentation
Hvac PresentationHvac Presentation
Hvac Presentation
Choong KW
 
Electrical Work Patna_Technical Specification
Electrical Work Patna_Technical SpecificationElectrical Work Patna_Technical Specification
Electrical Work Patna_Technical Specification
Atul Chauhan
 
Risk Issues Environmental Monitoring of Cleanrooms
Risk Issues Environmental Monitoring of CleanroomsRisk Issues Environmental Monitoring of Cleanrooms
Risk Issues Environmental Monitoring of Cleanrooms
netomoney
 

Viewers also liked (14)

Tài liệu (Phần 3) | Hệ thống HVAC
Tài liệu (Phần 3) | Hệ thống HVAC Tài liệu (Phần 3) | Hệ thống HVAC
Tài liệu (Phần 3) | Hệ thống HVAC
 
WHO Guidance on HVAC Systems for Non Sterile Pharmaceuticals
WHO Guidance on HVAC  Systems for Non Sterile PharmaceuticalsWHO Guidance on HVAC  Systems for Non Sterile Pharmaceuticals
WHO Guidance on HVAC Systems for Non Sterile Pharmaceuticals
 
Hvac Presentation
Hvac PresentationHvac Presentation
Hvac Presentation
 
1MP from Comecer
1MP from Comecer1MP from Comecer
1MP from Comecer
 
ANALYSS OF RATES-VOLUME-II
ANALYSS OF RATES-VOLUME-IIANALYSS OF RATES-VOLUME-II
ANALYSS OF RATES-VOLUME-II
 
Heating and Cooling with Air Source Heat Pump and Air Handling Unit system fo...
Heating and Cooling with Air Source Heat Pump and Air Handling Unit system fo...Heating and Cooling with Air Source Heat Pump and Air Handling Unit system fo...
Heating and Cooling with Air Source Heat Pump and Air Handling Unit system fo...
 
Validation Part2
Validation Part2Validation Part2
Validation Part2
 
Bihar Schedule of Rates ne 01-16-07-2012
Bihar Schedule of Rates ne 01-16-07-2012Bihar Schedule of Rates ne 01-16-07-2012
Bihar Schedule of Rates ne 01-16-07-2012
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
 
Hvac basics
Hvac basicsHvac basics
Hvac basics
 
Electrical Work Patna_Technical Specification
Electrical Work Patna_Technical SpecificationElectrical Work Patna_Technical Specification
Electrical Work Patna_Technical Specification
 
Risk Issues Environmental Monitoring of Cleanrooms
Risk Issues Environmental Monitoring of CleanroomsRisk Issues Environmental Monitoring of Cleanrooms
Risk Issues Environmental Monitoring of Cleanrooms
 
Plumbing labour rate 2015
Plumbing labour rate 2015Plumbing labour rate 2015
Plumbing labour rate 2015
 
NFPA 20
NFPA 20 NFPA 20
NFPA 20
 

Similar to Hvac manpreet singh naroo

USP 797/800 Cleanroom Compliance by Terra Universal
USP 797/800 Cleanroom Compliance by Terra UniversalUSP 797/800 Cleanroom Compliance by Terra Universal
USP 797/800 Cleanroom Compliance by Terra Universal
Terra Universal
 
GOOD MANUFACTURING PRAC.pptx microbiology for pharm d
GOOD MANUFACTURING PRAC.pptx  microbiology for pharm dGOOD MANUFACTURING PRAC.pptx  microbiology for pharm d
GOOD MANUFACTURING PRAC.pptx microbiology for pharm d
tehseenmalik450
 

Similar to Hvac manpreet singh naroo (20)

USP 797/800 Cleanroom Compliance by Terra Universal
USP 797/800 Cleanroom Compliance by Terra UniversalUSP 797/800 Cleanroom Compliance by Terra Universal
USP 797/800 Cleanroom Compliance by Terra Universal
 
Chap 43
Chap 43Chap 43
Chap 43
 
Sterile products manufacturing
Sterile products manufacturingSterile products manufacturing
Sterile products manufacturing
 
Clean Room Pharmaceutical Good Manufacturing Process.pdf
Clean Room Pharmaceutical Good Manufacturing Process.pdfClean Room Pharmaceutical Good Manufacturing Process.pdf
Clean Room Pharmaceutical Good Manufacturing Process.pdf
 
Clean Room Pharmaceutical_ GMP Procedures
Clean Room Pharmaceutical_ GMP ProceduresClean Room Pharmaceutical_ GMP Procedures
Clean Room Pharmaceutical_ GMP Procedures
 
IRJET - Review Paper on Air Conditioning System for Operation Theatre in Hosp...
IRJET - Review Paper on Air Conditioning System for Operation Theatre in Hosp...IRJET - Review Paper on Air Conditioning System for Operation Theatre in Hosp...
IRJET - Review Paper on Air Conditioning System for Operation Theatre in Hosp...
 
Sterile process validation
Sterile process validationSterile process validation
Sterile process validation
 
Bluon TdX 20 Compared to R-22 Testing Summary
Bluon TdX 20 Compared to R-22 Testing SummaryBluon TdX 20 Compared to R-22 Testing Summary
Bluon TdX 20 Compared to R-22 Testing Summary
 
Tiêu chuẩn HVAC cho dây chuyền sản xuất thuốc không tiệt trùng
Tiêu chuẩn HVAC cho dây chuyền sản xuất thuốc không tiệt trùng Tiêu chuẩn HVAC cho dây chuyền sản xuất thuốc không tiệt trùng
Tiêu chuẩn HVAC cho dây chuyền sản xuất thuốc không tiệt trùng
 
Design HVAC System for Hospital
Design HVAC System for Hospital Design HVAC System for Hospital
Design HVAC System for Hospital
 
Design of HVAC system for commercial building
Design of HVAC system for commercial buildingDesign of HVAC system for commercial building
Design of HVAC system for commercial building
 
IPC_PPT_CDT1-1_PCS & importance.ppt
IPC_PPT_CDT1-1_PCS & importance.pptIPC_PPT_CDT1-1_PCS & importance.ppt
IPC_PPT_CDT1-1_PCS & importance.ppt
 
Hvac System
Hvac SystemHvac System
Hvac System
 
GOOD MANUFACTURING PRAC.pptx microbiology for pharm d
GOOD MANUFACTURING PRAC.pptx  microbiology for pharm dGOOD MANUFACTURING PRAC.pptx  microbiology for pharm d
GOOD MANUFACTURING PRAC.pptx microbiology for pharm d
 
Utilizing Energy Recovery and Optimizing Air
Utilizing Energy Recovery and Optimizing AirUtilizing Energy Recovery and Optimizing Air
Utilizing Energy Recovery and Optimizing Air
 
PID Tuning Rules
PID Tuning RulesPID Tuning Rules
PID Tuning Rules
 
Comparison of different controller strategies for Temperature control
Comparison of different controller strategies for Temperature controlComparison of different controller strategies for Temperature control
Comparison of different controller strategies for Temperature control
 
Air circulation maintenance industry for sterile and non sterile area
Air circulation maintenance  industry for sterile and non sterile areaAir circulation maintenance  industry for sterile and non sterile area
Air circulation maintenance industry for sterile and non sterile area
 
HVAC for clean rooms 120217
HVAC for clean rooms 120217HVAC for clean rooms 120217
HVAC for clean rooms 120217
 
Smart Process Distillation Application Improves Recovery And Saves Energy
Smart Process Distillation Application Improves Recovery And Saves EnergySmart Process Distillation Application Improves Recovery And Saves Energy
Smart Process Distillation Application Improves Recovery And Saves Energy
 

Hvac manpreet singh naroo

  • 1. Qualification of HVAC systems Case studies • physical / technical tests • risk analysis calibration • risk analysis computerized systems 1
  • 2. Table of Contents 1. Introduction Figure slide 1: Silica gel and structure of zeolite used as adsorbent for dehumification of clean rooms to protect products which are sensitive against moisture exposion 2. HVAC design requirements 3. HVAC construction requirements 4. General HVAC qualification activities (DQ, IQ, OQ, PQ) 5. Physical / technical OQ and PQ tests for HVAC systems 6. Case study risk analysis for measurement and control unsits for HVAC systems 7. Case study risk analysis computerized systems validation for HVAC systems 8. Summary 2
  • 3. Introduction  In pharmaceutical primary as well as in secondary manufacturing HVAC systems are a major factor for the observance of cleanliness and product purity.  No wonder that the qualification activities of HVAC systems with their measurement and control and computerized units are cost intensive and a great deal of time.  The key issues to keep HVAC qualification in quality, time, and costs are  the understanding of interfaces beween product purity / characteristic, cleanliness zones, HVAC functions and clean rooms requirements.  the structured identification of critical functions and operations, the objective evaluation, and the definition of appropriate measures (design, qualification, calibration, and validation activities) in a documented way. 3
  • 4. Introduction  These key issues are the reason for the following seminar topics listed below.  Design and construction requirements of HVAC systems with their functions and units.  General HVAC qualification steps to ensure a sufficient scope and structered approach,  Specific physical and technical tests such as filter leak tests, measurement of room difference pressures, temperature and humidity, capability study of dehumification function.  Method and practice of risk analysis to cover potential risks and to define the scope and approach of calibration and computerized systems validation in relation to HVAC systems. 4
  • 5. HVAC design requirements  The complexity resulting from the different requirements for air quality in the various cleanliness zones, make it recommendable to define up-front the following process criteria:  Critical room parameters which affect product or materials (i.e. humidity) and the corresponding acceptance limit.  Which process operations present a reasonable potential for contamination.  Which process or operations are not affected by room conditions (e.g. closed systems).  Potential sources of room contamination (outdoor air, process equipment / operation, HVAC components, failure of HVAC functions...).  Equipment failure modes (fans, room / zone fail safe modes, interlocks, user action in the event of failure). 5
  • 6. HVAC design requirements  In establishing design criteria for critical parameters, consideration should be given to operating ranges which will assist in the definition of the tightness of control range of these parameters.  The following tables will give a conception for relevant parameters in conjunction with cleanliness zones used in secondary manufacturing. Process tolerance Action limit Figure: The picture demonstrates the relation of process, operation ranges, limits, and tolerances. Process range Process limits Process limits Alert limit Range of measurement and control unit 6
  • 7. HVAC design requirements  Typical parameters and ranges for the design of HVAC systems under consideration of cleanliness zoning concept (table).  If cleanliness zoning requirements are different Room Room relative to product specific reRoom Room air relative pressure in Zone: temperature changes in quirements the relevant parahumidity in Pa: in °C: h : %: meters with their ranges, to barometric reference tolerances, and limits should be fixed and documented. A N/A (a) 40,0 ± 10,0 (a) N/A (a) -1 Example: Products which are sensitive to moisture (e.g. effervescence tablets). In this case the setpoint, tolerances, and limits of the dehumidification is the major factor for the conditioning. B 22,0 ± 4,0 45,0 ± 15,0 30 - 90 30 - 45 C/1 22,0 ± 4,0 45,0 ± 15,0 20 - 50 20 - 30 D/2 22,0 ± 5,0 45,0 ± 15,0 5 - 30 10 - 15 E/3 20,0 ± 8,0 45,0 ± 15,0 4 – 10 (b) 0 4 Not defined Not defined Not defined Not defined (a) The driving factor in zone A is the laminar air speed of 0,45 ms-1 ± 0,09 ms-1 (b) Optional 7
  • 8. HVAC design requirements  Example layout effervescents factory Figure: The picure shows humidity controlled areas. Typically, exposed humiditysensitive products require humidity control to 30,0 to 50,0 %, but different values are not uncommen (e.g. effervescence products). Process range can also range to 10,0 % to 20,0 % rel. humidity depending on process and mixture of components (acid / alkaline gradient). 8
  • 9. HVAC construction requirements  In case of humidity sensitiveness a dehumidification unit has to be integrated / installed.  Such a unit selected should not adversely contaminate the product. Cooling coils generate large quantities of condensate which must drained properly to avoid microbial contamination. Provisions should also be made that no condensate droplets can be entrained into the air stream passing throug the cooling coils.  Liquid and dry type desiccant systems should be evaluated for potential carry-over of dessicant into the supply air stream and the effect of such carry-over on the exposed product. 9 Figure: Simplified picture of a small dehumidification unit (cooling coils).
  • 10. HVAC construction requirements  General structure of a HVAC system used in sterile manufacturing of parenterals. Critical process steps are covered by laminar air flow units. Figure: In general the HVAC system includes several basic units such as fresh / exhaust air, and air conditioning units with their fans, filters, and measurement and control instrumentation  10
  • 11. HVAC construction requirements  Dehumidification method by adsorptive separation Figures: The exchange of humidity happens in the slow rotating adsorption-rotor (charched with silica gel).The humidity load will be desorbed by a countercurrent heated air flow. The loaded air can be exhaust. There are different types available (heat recovery unit or with integrated condenser). The adsorption process is frequently reversal and continuous. Pictures authorized by Munters GmbH  11
  • 12. HVAC construction requirements  Dehumidification by adsorption:  Continuous working dehumidification (adsorbed layer / adsorbent made of silica or zeolites). Simultaneous adsorption and regeneration.  Supply with dry air flow ranges from 50 m3h-1 to 80.000 m3h-1.  Adsorption as well as desorption results are a function of  temperature of air to dehumidification unit,  stable pressure conditions inside dehumidification unit,  humidity load of inlet air (fresh air / recirculated air rate),  angle velocity / revolutions per minute (adsorbed layer / rotor)  and contact time with adsorbent as a function of air flow rate.  Additional requirements are the proper insulation of the conditioned rooms, and measures to eliminate electrostatic differential potential.  12
  • 13. General HVAC qualification activities (DQ, IQ, OQ, PQ)  General acceptance criteria DQ: The design and its documentation comply with user and GMP requirements. Chronology and trace ability are covered. The main contents of the concept, basic, and detail engineering are documented. Figure: The DQ part of Sulzers validation structure matrix for clean rooms and HVAC systems Clean rooms HVAC  13
  • 14. General HVAC qualification activities (DQ, IQ, OQ, PQ)  The IQ will bring the documented evidence that the as it is on site to be installed system with its components, measurement and control units and instrumentation, hardware / software(modules) complies with the specification.  The OQ will bring the documented evidence that the operational functions with its specific parameters, ranges and limits comply with the functional requirements and specifications. Figure: The IQ / OQ part of Sulzers validation structure matrix for clean rooms and HVAC systems Clean rooms HVAC  14
  • 15. Physical / technical OQ and PQ tests for HVAC systems  In addition to these general tests (e.g. power failure and recovery tests, verification of functions and sequences, verification of alarms and interlocks...) typical HVAC specific tests has to be performed. Unidirectional airflow / LAF: Test: Turbulent / mixed airflow: Differential pressure on filters 1 1 Room differential pressure N/A 2, 3 Airflow velocity / uniformity 2, 3 Optional Airflow volume / rate 2 2 Parallelism 2 N/A Air flow patterns Optional Optional Filter leak test / challenge test 2 2 Recovery N/A 2 Room classification (airborne particle) 2 2 Particle fall out Optional Optional Temperature, humidity N/A 2, 3 1 := As built (ideally used to perform IQ); 2:= At rest (ideally used to perform OQ); 3:= Operational (ideally used to perform PQ)  15
  • 16. Physical / technical OQ and PQ tests for HVAC systems  Determination of differential pressure on filters  This preliminary test is performed to detect initial defects of filters,  and to verify the pressure differential (for a defined flow) meets the value specified by the vendor,  and finally, where applicable, set the correct value of the alarm as indicated by the vendor for triggering a filter replacement.  Differential pressure between rooms  This measurement consists in measuring with a calibrated manometer the differential pressure existing between the inside of a clean room and the surrounding areas as defined in the specifications.  This determination should be made under various operational conditions such as day mode, night mode, opening of doors, etc. to identify also situations when the pressure differential can not be met and as a consequence the product may be at risk.  16
  • 17. Physical / technical OQ and PQ tests for HVAC systems  Determination of air flow velocity  This verification is used to determine average airflow velocity and uniformity of velocity within a clean room, clean zone or unidirectional flow work zone.  This method is not recommended for non-unidirectional airflow cleanliness zones; in that case the measurement of airflow volumes should be performed instead.  The airflow velocity is measured at a distance of 30 cm from the supply source using an anemometer (therma / vane-type). The number of individual measurements should be at least equal to 3 per m2. The duration of each measurement should not less than 15 s.  The uniformity of air flow velocity is defined as being the relative standard deviation of the velocity, expressed as a percentage of the mean as follows: Uniformity = standard deviation / average velocity * 100.  The relative standard deviation (or uniformity) should not exceed 15 %, except where otherwise specified.  17
  • 18. Physical / technical OQ and PQ tests for HVAC systems  Measurement of air volume and uniformity – air exchange rate  This procedure / verification is used to determine average airflow volume and uniformity of volume wihin a clean room, clean zone or unidirectional flow work zone.  The airflow volume is measured from each terminal filter or supply diffuser by using an electronic microanemometer with an appropriate airflow hood in a manner that includes all of the air issuing from each single source.  The uniformity should not exceed 15 %, except where otherwise specified.  Total air volume will, in turn, be used to determine the air exchange rate (room air volume per hour) for the clean room, as defined: Air exchange rate = total airflow volume / volume of the room.  18
  • 19. Physical / technical OQ and PQ tests for HVAC systems  Airflow parallelism test  The purpose of the test is to verify the parallelism of air flow throuout the work zone of a unidirectional airflow and wether the clean room is capable of limiting the dispersion of internally generated contamination.  The measurement is made using a isokinetic smoke generator and defining the offset distance between the smoke streamline and the theoretical straight line coming from the smoke outlet and parallel to the specified unidirectional airflow.  The number of individual measurements should be equal to 1 / 10 m2.  The angle of the offset should not exceed 14°.  To be valid, such tests must be documented using video techniques.  19
  • 20. Physical / technical OQ and PQ tests for HVAC systems  Determination of airflow patterns  This verification is above all valuable for demonstrating the interactions of airflow and equipment during the OQ phase, and for demonstrating the effectiviness of aerodynamic barriers.  This test should be considered as an alternative to differential pressure between rooms (slide 16) and is particularly recommended for the initial qualification of cleanliness zones (HVAC or clean rooms) where aerodynamic barriers are employed instead of physical barriers and where therefore acceptable differential pressures can not be achieved.  The test consists of a visualisation of the air flow patterns, using a smoke or other visible aerosol and is designed to show evidence that all air flows are as expected.  In addition it is also recommended for the initial qualification in the at rest mode of all types of clean room to demonstrate absence of non desirable dead zones, backflows, leaks or turbulances which may contaminate a critical part of a clean zone. To be valid, such tests must be documented using video techniques.  20
  • 21. Physical / technical OQ and PQ tests for HVAC systems  Filter installation leak test (challange test)  These verifications are performed to confirm that HEPA and ULPA filters are properly installed by verifying the absence of by-pass leakage in the installation (frame, gasket seal, and filter bank framework) and that the filters are free of defects and small leaks in the filter medium and frame seal.  These tests are required for unidirectional airflows, but have only limited value for non-unidirectional airflow systems.  Tests are performed by introducing an aerosol challange upstream of the filters and scanning immediatly downstream of the filters and support frame or sampling in a downstream duct.  In rooms with turbulent airflow, the filter installation leak test can be substituted by in-situ vergification of the integral particle penetration value through the filter. See VDI 2083, Blatt3 for further information.  21
  • 22. Physical / technical OQ and PQ tests for HVAC systems  Determination of the recovery time  This test is not recommended for unidirectional airflows. It is performed to determine whether the clean room or clean zone is capable of returning to its specified cleanliness class within a finite time, after being expoused to a source of airborne particulate challange in form of smoke or aerosol.  The result of this test is an important information for correct operation of the system, because it defines also the minimum „hold“ time which should be taken into account after power failure, start (recovery), mode change. See VDI 2083, Blatt 3 for further infomation.  Determination of room classification (airborne particle count mapping)  This test is performed to determine that the completed clean room can meet the cleanliness class specified.  22
  • 23. Physical / technical OQ and PQ tests for HVAC systems  The test consists in measuring the concentration of particles of a well defined size in the clean room in order to prove with a defined confidence limit, that the clean room complies with the cleanliness class.  In case of unidirectional airflows, the sample points should include test points located immediately upstream of the work activity level.  All sample points must comply with the class limit.  Fore more and detailed information refer US Fed. Std 209E / ISO 14644-1.  If not performed in the operational mode, in the case of cleanliness zones belonging to class A and B, this test must be repeated to take into account generation of particles by operator, equipment or process. The main purpose is then to identify worst case locations which should also be taken into account when installing probes for continuous particle monitoring.  23
  • 24. Physical / technical OQ and PQ tests for HVAC systems  Particle fallout test  These tests are done by allowing a small test surface to collect natural particles that settle out in the clean room area. The particles on the plate are counted with a surface particle detection instrument and a particle-deposition rate is determined.  These verification could also be used in multipurpose / multi-product facilities to support a demonstration of absence of croos contamination.  Temperature level and uniformity test  The purpose is to demonstrate the capability of the clean room / HVAC system to maintain air temperature wihin the specified limits and over a certain period of time.  The result of this test can also be used to support qualification of the location of fixed installed temperature monitoring devices.  24
  • 25. Physical / technical OQ and PQ tests for HVAC systems  Humidity level and uniformity test  The purpose of this test is to demonstrate the capability of the clean room (HVAC system with (de)humidification units) to maintain air humidity levels within the specified limits and over a certain period of time.  The result of these tests can also be used to support qualification of the location of fixed installed humidity monitoring devices.  The function and sequences of dehumidification units must be carefully tested (main functions see slide 12). Figure: Mobile measurement device for the acquisition of humidity data.  25
  • 26. Case studies risk analysis The FMEA is a tool for Quality Management that combines the technology and experience of specialists in identifying failure modes. In the Pharmaceutical Industry the regulatories of Good Manufacturing Practice (GMP) demand a high level on quality assurance system and documentation. Therefore the main intention of the FMEA is to  identify  evaluate  and cover GMP critical functions and process conditions in a systematic, documented, and objective way.  26
  • 27. Case studies risk analysis  Typical applications in the Pharmaceutical Industry are  qualification of technical equipment,  calibration of measurement and control installations,  validation of processes and computerized systems.  In conjunction with an increasing uncertainty  what,  when,  and how to qualify, calibrate and maintain.  27
  • 28. Case studies risk analysis In general, FMEA is the tool  to prevent  to confirm and  to solve problems. Entstehung von 75 % der Fehler Behebung von 80 % der Fehler 60 Fehlerbehebungskurve 55 50 45 Fehlerentstehungkurve 40 35 25 Fehlerquote 30 Failure removal costs 20 15 10 Design incl.. DQ Construction: constructive changes ... Qualification: redesign new construction delay of production ... Production: costs of delay costs maintenance loss of image loss of market shares ... 5 0 Phases of project  28 Planung Konstruktion Qualifizierung Produktion Figures: Most of the failures come into being in a early project phase (design and construction) and must be repaired cost intensive in a late project phase. The FMEA is a usefull tool to identify, evaluate and cover potential failures.
  • 29. Case studies risk analysis A guide for a successfull FMEA used in Pharmaceutical Industry  Systematic way of identification  Objective way of evaluation  Define criteria for evaluation.  Form a team with speacialist‘s competence and the courage to make decisions.  Set a trigger (yes/no) for decision of recommended actions.  Define appropriate protective measures.  Set a high level of documentation (create forms for FMEA-documentation and recommended actions).  29
  • 30. Case studies risk analysis  A potential risk is the hidden, unforeseen occurrence of a failure with considerable consequences.  A potential risk is composed of several factors: D S  the occurence propability (O) that a potential failure occur,  the severity (S) of effects,  the detection propability (D) that a failure will be detected. RPN = f(O, S, D) O  A potential risk is described by the risk priority number (RPN) as the product of O, S, D. Figure: Several factors of a risk potential.  30
  • 31. Case studies risk analysis The FMEA involves four essential steps: Start 1  Identification of the potential failure with its causes and effects. Identify 2/4 (Re-) Evaluate  Evaluation of the potential risk with the several factors O, S, D and calculation of the risk priority number (RPN). no Critical? yes 3 Define corrective actions  Establishing protective measures.  Re-evalution of the improved conditions.  31 Figure: Decision tree of FMEA End
  • 32. Case study risk analysis for measurement and control unsits for HVAC systems  Objective 1: Reducing monitoring activities / costs and cover safty and availability.  Objective 2: Understanding interfaces between HVAC, clean room monitoring. Find a logical / conclusive approach for calibration of HVAC / monitoring instrumentation.  Approach:  The process parameter is leaving the normal prozess range in which the product quantity and quality is covered into alert range. What is the occurance propability and the consequences / sefirity for product quality? How can the detection propability evaluated (e.g. respond other measurement and control unsits?  The process parameter is crossing the limit to the action range. What is the occurance propability and the consequences / sefirity for product quality? How can the detection propability evaluated (e.g. respond other measurement and control unsits?  32
  • 33. Case study risk analysis for measurement and control unsits for HVAC systems Figure: Relation between normal prozess range, alert range, and action range  33
  • 34. Case study risk analysis for measurement and control unsits for HVAC systems a ir in a ir o u t e q u ip m e n t# 5 2 5 4 3 m e a s u rin g & c o n tro l in s t a lla tio n s P L 3 : PD SA 6190, PD SA 6265, M SA6187 2 m e a s u rin g & c o n tro l in s t a lla tio n s P L 2 : T C 6 1 6 3 , T C 6 1 8 5 , M C 6 1 8 6 , P D A 6 1 4 5 , P S A 6 1 6 0 /1 /2 , T C 6 1 6 3 , P D IC 6 1 9 5 , P D A 6 2 6 0 P f r e s h / e x h a u s t a ir u n it e q u ip m e n t# .: 5 2 5 4 T M 1 M 3 2 Figure(s): Evaluated measurement and control units of a HVAC unit P PDI T C le a n r o o m E .2 1 6 C la s s B 1 m e a s u rin g & c o n tro l in s t a lla tio n s P L 3 : M 6516, S 1528, S 1538, S 1548, S 1566, S 1576 m e a s u rin g & c o n tro l in s t a lla tio n s P L 2 : TC 6515, TC 6555, PD 6596, PD 6599, PD I 6571, PD I 6 5 7 2 , P D I 6 5 7 3 ... m e a s u rin g & c o n tro l in s t a lla tio n s P L 1 : T I 1 5 2 0 , T I 1 5 5 7 , T I1 5 5 8 , T I 1 5 6 7 , T I 1 5 6 8 , T I 1 5 7 7 e q u ip m e n t# 5 2 6 0 S Q (L K Z ) Q ( P a r t .) 3 0421 0431 0432 2 p ro c e s s s te p s p ro c e s s s te p s m e a s u rin g & c o n tro l in s t a lla tio n s P L 2 : n o n e , c le a n r o o m m o n ito r in g 1 m e a s u rin g & c o n tro l in s t a lla tio n s P L 1 : n o n e , c le a n r o o m m o n ito r in g P = p r e s s u r e d iffe r e n c e T = te m p e ra tu re p ro c e s s s te p s M = m o is tu r e S = a ir v e lo c ity c r it ic a l ( a s e p t ic ) p r o c e s s s t e p s in E . 2 1 6 ( la m in a r a ir f lo w p r o t e c t e d ) m e a s u rin g & c o n tro l in s t a lla tio n s P L 3 : c l e a n r o o m m o n i t o r i n g s y s t e m ( o b je c t # 5 2 6 1 ) i n c l u d e s Q ( L K Z ) 6 4 2 0 , Q (P a r t.) 6 4 1 0 , Q (P a r t.) 6 4 1 1 , Q ( L K Z ) 6 4 2 1 , Q ( P a rt.)6 4 1 2 , Q ( P a rt.)6 4 1 3 , Q ( P a rt.)6 4 1 4 , P D 6 4 0 1 , PD 6402, PD 6403, PD 6000, T6409 Q ( P a r t. ) = p a r tic le c o u n t in th e a ir Q ( L K Z ) = c o u n t o f m ic r o o r g a n is m s in th e a ir  34 distance to cleanroom class B e q u ip m e n t# 5 2 5 1 T s u b u n it# 0 5 1 0 level of protection (redundance, calibration period...) a ir c o n d it io n in g u n it e q u ip m e n t # 5 2 5 1 P m e a s u rin g & c o n tro l in s t a lla tio n s P L 1 : PD I 6121, PD SA 6155, TS 6175, TC 6225, PD I 6261, TI 1110, TI 1126, TI 1152, TI 1153, TI 1161, TI 1167, TI 1168, P I 1 2 2 9 , P I 1 2 3 1 , P I 1 2 3 3 , P D S A 6 1 3 5 , P D I, 6 1 4 6 , P D S A 6 1 5 5 , P D S A 6 1 7 0 , T S 6 1 7 5 , ...
  • 35. Case study risk analysis for measurement and control unsits for HVAC systems  Result of FMEA case study: Out of nearly 60 Measurement and control units  44 % have only to be adjusted. No calibration activities are required.  26 % have to be adjusted and initial calibrated. No periodic calibration activities are required.  30 % (because of redundant design of clean room monitoring system) have to be adjusted, initial and periodic calibrated.  Reduction in costs: nearly 10.000,00 DM only because of reduced initial calibration.  35
  • 36. Case study risk analysis computerized systems validation for HVAC systems  Approach: Figure: Level of process steps and level of computerized function B D E P (U roze ni ß t O fu pe nkt ra ion tio e ns n ) C C6 C1 B. Geis, xxxBRG_CSVEbenen_1_0  36 C2 C4 C5 F te un r i s kt ie ion r te sS y st C3 em A co m pu  Each essential process step (e.g. A...E) will divided in the functions of the computerized system. Derive from reverse function it is possible to identify potential failures in a systematic way.  Because of that the CSV risk analysis will cover the unit operations as well as the computerized system.
  • 37. Figure: FMEA form used for CSV risk analysis of clean room monitoring system Case study risk analysis computerized systems validation for HVAC systems confidential confidential  37
  • 38. Summary  The key for a successful HVAC qualification are  the understanding of interfaces beween product purity / characteristic, cleanliness zones, HVAC functions and clean rooms requirements,  the knowledge concerning general and HVAC specific tests,  and the structured identification of critical functions and operations, the objective evaluation, and the definition of appropriate measures (design, qualification, calibration, and validation activities) in a documented way.  38