BASEMENT PLUMBING LAYOUT-SECTOR-2
- 1. N6 N7 N8 N9 N11
N13
S6 S7 S8 S9 S10
S11
N10 N12
?
?
?
?
? ?
? ? ? ? ?
/
FORCONTINUATIONREFERTO
DWGNO:1M21-B1-01
DCW
DCW
BIBTAP
DCW
DCW DCW
BIPTAP
DCWDCW
DCW
DCW
DCWDCW
DCW
DCW TRANSFER PIPE T/A
DCW PRESUURE PIPE F/A
DCW GRAVITY PIPE F/A
TANK DRAIN PIPE F/A
DCW
DCW
DCW
BIBTAP
IRR
IRR
IRR
IRR
BIBTAP
BIBTAP
BIBTAP
GWP
GWP
GWP
GWP
GWP
GWP
ELECTRICAL
CONTROL PANEL
DAF UNIT
2NOS. PUMP
GREY WATER TANK
2NOS. PUMP
GREY WATER TANK
DISC FILTER
CARBON FILTER
IRRIGATION WATER TANK
2NOS. PUMPS
GV
GV
GV
GV GV
GV
GV
GV
SUCTION LINE
DISCHARGE LINE
Project
Manager :
Drawn :
Date :
Drawing Title :
Scale :
Project No :
Key Plan :
North:
Notes :
Stamp:
TrueNorth
DN
Project Name & Location:
Lead Consultant :
Dubai, U.A.E.
info.international@norr.com
Tel : 04-3544439
Fax : 04-3544900
ARCHITECTS ENGINEERS PLANNERS
NORR Group Consultants
International Limited
P.O. Box: 53150
P.O. Box: 44387
Abu Dhabi, U.A.E.
info.international@norr.com
Tel : 02-6763360
Fax : 02-6763361
Owner Name:
Local Consultant (Architect of Record) :
A J D A N R E A L E S T A T E
CIVILIZATION ENGINEERING CONSULTING OFFICE
P.O. BOX 3974 Dammam K.S.A.
Telephone: 03 8336991 FAX: 03 8337441
Website: www.civilization.com.sa
AJDAN WATERFRONT
PARCEL ID : A1
PLAN NO. : 356/2
AL KHOBAR
KINGDOM OF SAUDI ARABIA
Project Description :
AJDAN WATERFRONT
PARCEL-A1 DEVELOPMENT
1303 - PA1 - TD
Drawing No. :
1 : 100
2/28/20164:13:00PMC:RevitLocal
FilesFCDB-140052-AJDANM_FCDB14-0052_AJDAN_WATER_FRONT_KSA_mmahalingam.rvt
M21-B1-02
BASEMENT LEVEL B1 PLUMBING
LAYOUT-SECTOR 2
FCDB150123
Mahendran
B.M.
SCALE - 1 : 100
BASEMENT PLUMBING LAYOUT-
SECTOR 2
1
No. Issued For Date Checked