2. 2
CSE POTENTIAL?CSE POTENTIAL?
• Compare Spec. Requirements
• Performance, Size, Weight
• Determine Availability of CSE
• Fleet Availability / Deficits
• PMA 260 Buy - Contract Awarded? (Can we get it
in time?)
• Still in Production? Issue New Contract?
• Investigate R&M of CSE
• Obsolescence issues?
• High Maintenance time / cost?
3. 3
Develop CSE (PSE?) Val/Ver PlanDevelop CSE (PSE?) Val/Ver Plan
• Review VH-71 IETM / EH-101 CIETP
• Who uses SE? (AT, AMH/S, AD)
• What is Function of SE?
• What A/C configuration is required?
• Review PSE data for Trade-off Analysis
• Adequate IPB? Cal Required? Cal Cycle?
• MRC? Training?
• Investigate R&M and Cost of CSE (Trade-off)
• Assign Plan sequential # and submit for Approval
(e.g. 135-SECL#)
4. 4
PSE Val/Ver ExecutionPSE Val/Ver Execution
• Coordinate A/C Availability
• Assemble Required Team Members, mech’s,
Tech Data, PSE, Other Equip.
• Notify Additional Interested Parties
• R&M, QA, HMX, etc.
• Execute Val/Ver Plan
• Complete Report (Blocks 18 – 20)
• Submit Signed Report to LKE
5. 5
PSE/CSE VAL/VERPSE/CSE VAL/VER
• Assemble Required Team Members, mech’s,
Tech Data, CSE, PSE?, Other Equip.
• Notify Additional Interested Parties
• R&M, QA, HMX, etc.
• Execute Val/Ver Plan
• Complete Report (Blocks 18 – 20)
• Submit Signed Report to LKE
7. 7
Develop Val/Ver PlanDevelop Val/Ver Plan
• Review VH-71 IETM / EH-101 CIETP
• Who uses PSE? (AT, AMH/S, AD)
• What is Function of PSE?
• What A/C configuration is required?
• Review PSE data
• Adequate IPB? Cal Required? Cal Cycle?
• MRC? Training?
• Write Val/Ver Plan (Blocks 14 – 17)
• Assign Plan sequential # and submit for
Approval (e.g. 135-SECL#)
8. 8
REPORT PROCESSREPORT PROCESS
• SE inspected & Plan/Report initiated
• P/N, Nomenclature, SECL Ident. No.
• Research CSE potential
• Devise Plan for Val/Ver (blocks 14 – 17)
• Assign sequential No. and submit for
approval
• Enter on Val/Ver Spreadsheet
• Any further changes require Rev.
• Plan executed or put in Queue
9. 9
REPORT PROCESS, cont’dREPORT PROCESS, cont’d
• Val/Ver Completed (PSE & CSE)
• Plan/Report signed by Val/Ver team
• Recommendations identified (PSE/CSE)
• Disagreements identified on Report
• Plan/Report forwarded to SEPO for
concurrence (or not), SERD action, etc.
• If CSE recommended, Report forwarded to
Contractor Team for concurrence (or not)